EX-99 5 ex96-1.htm EX-96.1

 

Exhibit 96.1

 

   
Hycroft Mine Project  
   
S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis  
   
Nevada, USA  
   
Effective Date: May 14, 2026  
   
Report Date: May 29, 2026  
   
Prepared for:  
Hycroft Mining Holding Corporation  
PO Box 3030  
Winnemucca, Nevada, United States, 89446  
   
Prepared by:  
Ausenco Engineering USA South Inc.  
595 S Meyer Ave, Tucson, Arizona, United States, 85701  
   
Contributing Authors:  
Ausenco Engineering USA South Inc.  
Independent Mining Consultants Inc.  
WestLand Engineering & Environmental Services, Inc.  
 

 

  

 

Date and Signature Page

 

This technical report summary (“TRS”), entitled “Hycroft Mine Project, S-K 1300 Technical Report Summary and Initial Assessment with Economics Analysis, Nevada, USA” is current as of May 14, 2026, and has been prepared by:

 

Consulting Firm Responsible for the following sections Signature Date

Ausenco Engineering USA South Inc.

1.1, 1.2, 1.8, 1.11, 1.12, 1.13, 1.15, 1.16, 1.17, 1.18, 2.1-2.4.1, 2.5-2.7, 10, 14-16, 18.1-18.2.3, 18.2.4- 18.2.7, 18.2.8.2-18.3.2, 18.3.4, 18.3.5, 19, 22.1, 22.5, 22.7-22.12, 22.13.1.3, 22.13.1.5-22.13.1.7, 22.13.2.2, 22.13.2.4, 22.13.2.5, 23.1, 23.4, 23.6, 24 and 25

“signed”

May 29, 2026

 

Hycroft Mining Holding Corporation

1.3-1.7, 1.15,3-9, 12, 20, 22.2-22.4, 22.13.1.1, 22.13.1.2, 22.13.2.1, 23.1-23.3 and 24

“signed”

 May 29, 2026

Independent Mining Consultants, Inc.

1.9, 1.10, 1.15, 1.18, 2.4.2, 11, 13, 18.2.3, 18.2.8.1, 18.3.1,

18.3.3, 22.6, 22.13.1.4, 22.13.2.3, 23.1, 23.5 and 24

“signed”

May 29, 2026

 

WestLand Engineering &

Environmental Services, Inc.

1.14, 17, 22.1, and 24

“signed”

May 29, 2026

 

Hycroft Mine Project

 

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table of Contents

 

1 Executive Summary 1
  1.1 Introduction 1
  1.2 Terms of Reference 1
  1.3 Mineral Tenure, Surface Rights, Water Rights, and Agreements 2
  1.4 History 2
  1.5 Geology and Mineralization 3
  1.6 Exploration 4
  1.7 Sampling 4
  1.8 Metallurgical Testwork 4
  1.9 Mineral Resource Estimate 5
  1.10 Mining Methods 9
  1.11 Processing and Recovery Methods 9
  1.12 Infrastructure 10
    1.12.4 Tailings Management Facility 11
    1.12.5 Waste Rock Storage Facility (WRSF) 11
    1.12.6 Power, Communications, and Fuel 11
    1.12.7 Water Supply and Management 12
    1.12.8 Hazard Considerations 12
  1.13 Market Studies and Contracts 12
  1.14 Environmental, Permitting and Social Considerations 12
    1.14.1 Environmental Considerations 12
    1.14.2 Permitting Considerations 13
    1.14.3 Social Considerations 14
    1.14.4 Closure and Reclamation Considerations 14
  1.15 Capital and Operating Cost 14
    1.15.1 Capital Cost Estimate 14
    1.15.2 Operating Cost Estimate 15
  1.16 Economic Analysis 15
    1.16.1 Economic Summary 15
    1.16.2 Sensitivity Analysis 18
  1.17 Conclusions 19
  1.18 Recommendations 19

 

Hycroft Mine Project

Page i

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

2 Introduction 20
  2.1 Introduction 20
  2.2 Terms of Reference 20
  2.3 Qualified Persons 21
  2.4 Site Visits and Scope of Personal Inspection 21
    2.4.1 Site inspection for Jonathan Cooper 21
    2.4.2 Site inspection for John Marek 21
  2.5 Effective Dates 21
  2.6 Information Sources and References 21
    2.6.1 General 21
    2.6.2 Previous Technical Reports 22
  2.7 Currency, Units, Abbreviations and Definitions 22
3 Property Description 26
  3.1 Introduction 26
  3.2 Property and Title in Jurisdiction 26
  3.3 Project Ownership 27
  3.4 Property Agreements 29
  3.5 Surface Rights 32
  3.6 Water Rights 32
  3.7 Liabilities and Encumbrances 32
  3.8 Environmental Considerations 32
  3.9 Safety Considerations 33
  3.10 Permitting Considerations 33
    3.10.1 Hycroft Expansion Permitting and Timelines 35
    3.10.2 Crofoot Heap Leach Facility Closure 37
  3.11 Social License Considerations 37
  3.12 Project Risks and Uncertainties 37
4 Accessibility, Climate, Local Resources, Infrastructure and Physiography 38
  4.1 Physiography 38
  4.2 Accessibility 38
  4.3 Climate 38
  4.4 Local Resources and Infrastructure 38
  4.5 Seismicity 41
5 History 42
  5.1 Regional History 42
  5.2 Property Exploration History 42
  5.3 Production 42

 

Hycroft Mine Project

Page ii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

6 Geological Setting, Mineralization, and Deposit 44
  6.1 Geological Setting 44
    6.1.1 Regional Geology 44
    6.1.2 Local Geology 44
  6.2 Mineralization and Alteration 45
    6.2.1 Brimstone 46
    6.2.2 Vortex 47
    6.2.3 Bay 48
    6.2.4 Central 50
    6.2.5 Camel 50
  6.3 Deposit Types 51
7 Exploration 52
  7.1 Exploration 52
  7.2 Geological Mapping 52
  7.3 Geophysics 52
  7.4 Soil Sampling 53
  7.5 Rock-Chip Sampling 53
  7.6 Drilling 53
    7.6.1 Introduction 53
    7.6.2 Exploration Drilling 54
  7.7 Hydrogeology 58
  7.8 Geotechnical 58
  7.9 Exploration Targets 59
8 Sample Preparation, Analyses, and Security 66
  8.1 Introduction 66
  8.2 Sample Preparation 66
  8.3 Assay Methods 66
    8.3.1 Sample Security 70
  8.4 Sample Storage 70
  8.5 Analytical Results 70
  8.6 QP Comment 70
9 Data Verification 71
  9.1 Verification Procedure 71
  9.2 Certificate of Assay Checks 71
  9.3 QA/QC 2005 – 2024 71
    9.3.1 Standards 2005-2013 72
    9.3.2 Blanks 2008 - 2014 74

 

Hycroft Mine Project

Page iii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

    9.3.3 Check Assays 2011-2012 75
    9.3.4 Standards 2021 – 2022 77
    9.3.5 Blank Analysis Results 2021-2022 78
    9.3.6 Duplicate Assays, 2021-2022 79
    9.3.7 Standards 2023 – 2024 80
    9.3.8 Blanks 2023-2024 81
    9.3.9 Duplicate Assays 2023-2024 81
    9.3.10 Check Assays 2023-2024 84
    9.3.11 DDH vs. RC for Post 2000 Samples 85
    9.3.12 Old vs. New Drilling 86
    9.3.13 Downhole Surveys 87
  9.4 QP Comment 87
10 Mineral Processing and Metallurgical Testing 88
  10.1 Introduction 88
  10.2 Metallurgical Testwork 89
    10.2.1 Summary of Metallurgical Testwork Programs 89
    10.2.2 Mineralized Materials and Sampling 89
    10.2.3 Hycroft Mineralization Domains 89
  10.3 Legacy Testwork 91
    10.3.1 Comminution Tests 91
    10.3.2 Flotation 91
    10.3.3 Direct Cyanidation 102
    10.3.4 Concentrate Oxidation Tests 102
    10.3.5 Solid-Liquid Separation Tests 109
    10.3.6 Deleterious Elements 109
    10.3.7 Metallurgical Parameters for Process Design Criteria and Financial Analysis 109
11 Mineral Resource Estimates 111
  11.1 Summary 111
  11.2 Model Location 111
  11.3 Database 111
  11.4 Basic Statistics 113
  11.5 Geology 113
  11.6 Lithology 113
  11.7 Alteration 114
  11.8 Structure 115
  11.9 Domains 117
  11.10 Assay Caps 120

 

Hycroft Mine Project

Page iv

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

  11.11 Bench Height Confirmation 121
  11.12 Composites 122
  11.13 Variography 125
  11.14 Block Grade Estimation 126
    11.14.1 Gold 126
    11.14.2 Silver 126
    11.14.3 Cyanide Ratio 129
    11.14.4 Sulfide Sulfur 130
    11.14.5 Density 132
    11.14.6 Stockpile Grade Estimation 132
    11.14.7 Treatment of 1982 – 1987 Data 133
  11.15 Classification 134
  11.16 Model Verification 135
    11.16.1 Swath Plots 137
    11.16.2 Smear Check 141
  11.17 Mineral Resource Estimate 142
12 Mineral Reserve 149
13 Mining Methods 149
  13.1 Overview 149
  13.2 Geotechnical and Hydrologic Information 153
  13.3 Phase Design 153
  13.4 Production Schedule 157
  13.5 Mining Equipment 171
  13.6 Mine Manpower Requirements 172
14 Processing and Recovery Methods 175
  14.1 Overview 175
  14.2 Process Flowsheet 176
  14.3 Plant Design 178
  14.4 Process Description 180
    14.4.1 Crushing Area 180
    14.4.2 Grinding Circuit 181
    14.4.3 Rougher Flotation 181
    14.4.4 Concentrate Thickening 182
    14.4.5 POX and Neutralization 182
    14.4.6 Gold and Silver Recovery from Flotation Concentrate 185
    14.4.7 CCD Circuit 185
    14.4.8 Merrill-Crowe Precipitation and Refinery (Existing) 186

 

Hycroft Mine Project

Page v

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

    14.4.9 Cyanide Destruction 187
    14.4.10 Final Tailings and Reclaim Water Transport 187
  14.5 Energy, Water, and Process Materials Requirements 187
    14.5.1 Reagent Handling and Storage 187
    14.5.2 Fresh Water, Fire Water and Potable Water 189
    14.5.3 Process Water, and Barren Solution 189
    14.5.4 Oxygen Plant 190
    14.5.5 Electrical Power 190
    14.5.6 High-Pressure and Low-Pressure Air 190
15 Infrastructure 191
  15.1 Introduction 191
  15.2 Site Access 192
    15.2.1 Offsite Access and Security 192
    15.2.2 Onsite Access 193
    15.2.3 Rail Spur 193
  15.3 New Infrastructure 195
    15.3.1 New and Existing Facilities Layout 195
    15.3.2 Upgrades to Existing Facilities 203
    15.3.3 Accommodation 203
  15.4 Stockpiles 204
    15.4.1 Mineralized Stockpiles 204
    15.4.2 Growth Media Stockpile 204
    15.4.3 Limestone Stockpile 204
  15.5 Tailings Management Facilities 204
    15.5.1 Facility Design Basis 205
    15.5.2 TMF Design 208
  15.6 Waste Rock Storage Facility 212
  15.7 Power and Electrical 213
  15.8 Communication 215
  15.9 Fuel 215
  15.10 Water Supply and Management 215
    15.10.1 Fresh Water, Fire Water and Potable Water 216
    15.10.2 Tailings Water Management 217
    15.10.3 WRSF Water Management 218
    15.10.4 Plant Site Stormwater Runoff and Drainage 219
    15.10.5 Site Water Balance 219
    15.10.6 Pit Dewatering 222

 

Hycroft Mine Project

Page vi

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

  15.11 Hazard Considerations 222
  15.12 Comments on Project Infrastructure 222
16 Market Studies and Contracts 224
  16.1 Market Studies 224
  16.2 Commodity Price Projections 224
  16.3 Contracts 224
17 Environmental Studies, Permitting, and Plan, Negotiations, or Agreements with Local Individuals or Groups 225
  17.1 Overview 225
  17.2 Environmental Considerations 225
    17.2.1 Baseline and Supporting Studies 225
    17.2.2 Environmental Monitoring 228
    17.2.3 Water Management 229
  17.3 Permitting Considerations 229
    17.3.1 Federal Permits 230
    17.3.2 State of Nevada Permits 233
    17.3.3 Additional Permits and Authorizations 234
  17.4 Social Considerations 235
    17.4.1 National Register of Historic Places 236
  17.5 Closure and Reclamation Planning 237
    17.5.1 Closure and Reclamation Plans 237
    17.5.2 Closure Cost Estimates 237
  17.6 Comments on Environmental Studies, Permitting and Social or Community Impact 237
18 Capital and Operating Costs 238
  18.1 Introduction 238
  18.2 Capital Costs 238
    18.2.1 Overview 238
    18.2.2 Basis of Estimate 239
    18.2.3 Mine Capital Costs 239
    18.2.4 Process Capital Costs 241
    18.2.5 Infrastructure Capital Costs 242
    18.2.6 Indirect Capital Costs 242
    18.2.7 Owner (Corporate) Capital Costs 243
    18.2.8 Sustaining Capital 243
    18.2.9 Contingency Costs 245
    18.2.10 Closure and Reclamation Planning 245
  18.3 Operating Costs 245
    18.3.1 Overview 245

 

Hycroft Mine Project

Page vii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

    18.3.2 Basis of Estimate 246
    18.3.3 Mine Operating Costs 247
    18.3.4 Process Operating Costs 248
    18.3.5 General and Administrative Operating Costs 252
19 Economic Analysis 253
  19.1 Overview 253
  19.2 Methodologies Used 254
  19.3 Financial Model Parameters 254
    19.3.1 Assumptions 254
    19.3.2 Taxes 254
    19.3.3 Royalties 255
  19.4 Economic Analysis 255
  19.5 Sensitivity Analysis 260
20 Adjacent Properties 264
21 Other Relevant Data and Information 264
22 Interpretation and Conclusions 265
  22.1 Introduction 265
  22.2 Mineral Tenure, Surface Rights, Water Rights, Royalties and Agreements 265
  22.3 Geology and Mineralization 265
  22.4 Exploration 265
  22.5 Metallurgical Testwork 266
  22.6 Mineral Resource Estimate 266
  22.7 Recovery Plan 267
  22.8 Infrastructure 268
    22.8.1 Tailings Management Facility 269
  22.9 Markets and Contracts 269
  22.10 Capital Cost Estimate 269
  22.11 Operating Cost Estimate 269
  22.12 Economic Analysis 270
  22.13 Risks and Opportunities 270
    22.13.1 Risks 270
    22.13.2 Opportunities 272
23 Recommendations 273
  23.1 Estimated Program Costs 273
  23.2 Exploration 273
  23.3 Sample Preparation, Analysis and Security 274

 

Hycroft Mine Project

Page viii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

  23.4 Metallurgical Testing 274
  23.5 Mineral Resource Estimate 275
  23.6 Infrastructure 275
    23.6.1 TMF 275
24 References 277
25 Reliance on Information Provided by the Registrant 281
Appendix A – Patented Claims 282
Appendix B – Unpatented Claims 283

 

List of Tables

 

Table 1-1: Hycroft MRE as of January 21, 2026, US customary Units 6
Table 1-2: Hycroft MRE as of 21 January 2026, Metric Units 7
Table 1-3: High-grade Silver Bearing Domains, Contained Within the MRE at 2 oz/ton Cutoff Grade, US customary Units 8
Table 1-4: High-grade Silver Bearing Domains, Contained Within the MRE at 68.57 g/tonne (2 oz/tonne) Cutoff Grade, Metric Units 8
Table 1-5: Principal Environmental Permits 13
Table 1-6: Other Notifications or Ministerial Permits 13
Table 1-7: Capital Cost Summary 14
Table 1-8: Operating Cost Summary 15
Table 1-9: Economic Analysis Summary 17
Table 2-1: Abbreviations and Acronyms 22
Table 2-2: Units of Measurement 24
Table 3-1: Hycroft Annual Land Holding Costs 29
Table 3-2: Hycroft Operating Permits 33
Table 3-3: Hycroft Miscellaneous Permits 34
Table 3-4: Hycroft Miscellaneous Permits 34
Table 3-5: Right-of-Way Payment and Renewal Schedule 34
Table 4-1: Hycroft Water Wells and Permitted Yearly Consumption 41
Table 7-1: Drilling from 2023 and 2024 Supporting the Updated MRE 56
Table 7-2: Significant Intercepts (2023) 60
Table 7-3: Significant Intercepts (2024) 62
Table 9-1: Nearest Neighbor Sample Comparison of RC vs Diamond Core Gold and Silver Assays 86
Table 9-2: Nearest Neighbor Sample Comparison of 1982-1987 Gold Assays Versus 2005 – 2024 Gold Assays 87

 

Hycroft Mine Project

Page ix

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 10-1: Metallurgical Testwork Summary 89
Table 10-2: Average Sulfur Contents of Oxide, Transition and Sulfide Mineralized Materials 90
Table 10-3: Summary of Test Samples 90
Table 10-4: Grindability Test Summary 91
Table 10-5: G&T Composites 1 through 24 Flotation Test Results 93
Table 10-6: G&T Composites M-1 through M-17 Flotation Test Results 94
Table 10-7: Flotation Reagent Schemes Studied 95
Table 10-8: Estimated Metallurgical Recoveries from 2016 Feasibility Study – Gold and Silver 103
Table 10-9: Hycroft Alkaline POX Testwork Summary 106
Table 10-10: Hycroft Acid POX Testwork Summary 106
Table 10-11: Summary Comparison Table – POX 3 to POX-7 108
Table 10-12: Settling Test Results 109
Table 10-13: Deleterious Element Assay 109
Table 10-14: Process Plant Overall Recovery Prediction 109
Table 11-1: Block Size and Model Size 110
Table 11-2: Data Available for the Assembly of the Resource Model for Au, Ag, AuCn, Sulfide Sulfur 111
Table 11-3: Assay Database (No Stockpile Assays, Inside the Model, and No Drilling from 1982 through 1987) 112
Table 11-4: Population Domains for Grade Estimation 117
Table 11-5: High-grade Silver Vein Domains 118
Table 11-6: Sulfide Domains 118
Table 11-7: Assay Cap Values 120
Table 11-8: Sulfide Cap Values Prior to Compositing 121
Table 11-9: Basic Statistics of Composites, In-Situ Rock, Eliminating Years 1982 to 1987 123
Table 11-10: Basic Statistics of 25 ft Sulfide Composites by Sulfide Domain 125
Table 11-11: Grade Estimation Parameters for Au, Ag 127
Table 11-12: Estimation Parameters for Cyanide Ratio, All Three Domains utilized 1/D3 130
Table 11-13: Sulfide Sulfur Estimation Parameters, All Three Domains Utilized 1/D3 131
Table 11-14: Sulfide Sulfur Default Values if Not Estimated 131
Table 11-15: Density Assigned to the Block Model 132
Table 11-16: Stockpiles Assigned Grades by Inverse Distance Estimation 133
Table 11-17: IMC Smear Check 141
Table 11-18: Economic and Technical Parameters for Hycroft MRE 144
Table 11-19: Hycroft MRE as of January 21, 2026, US customary Units 145
Table 11-20: Hycroft MRE as of 21 January 2026, Metric Units 146
Table 11-21: High-grade Silver Bearing Domains, Contained within the MRE at 2 oz/ton Cutoff Grade, US customary Units 147
Table 11-22: High-grade Silver Bearing Domains, Contained within the MRE at 3 oz/ton Cutoff Grade, US customary Units 147

 

Hycroft Mine Project

Page x

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-23: High-grade Silver Bearing Domains, Contained within the MRE at 4 oz/ton Cutoff Grade, US customary Units 148
Table 11-24: High-grade Silver Bearing Domains, Contained within the MRE at 68.57 g/ton (2 oz/ton) Cutoff Grade, Metric Units 148
Table 11-25: High-grade Silver Bearing Domains, Contained within the MRE at 102.86 g/ton (3 oz/ton) Cutoff Grade, Metric Units 148
Table 11-26: High-grade Silver Bearing Domains, Contained within the MRE at 137.14 g/t (4 oz/ton) Cutoff Grade, Metric Units 148
Table 13-1: Hycroft Initial Assessment Mine Production Schedule, Measured and Indicated Mineralization 151
Table 13-2: Summary of Lerch-Grossman Computer Pit Generation 154
Table 13-3: Contained Tonnage by Internal Cutoff Grade 155
Table 13-4: Major Mine Equipment 172
Table 13-5: Mine Hourly Personnel 173
Table 13-6: Mine Salaried Staff 174
Table 14-1: Process Design Criteria 178
Table 14-2: Major Process Equipment 179
Table 14-3: Summary of Reagent Used in the Process Plant 188
Table 14-4: Annual Consumption for Major Reagents 189
Table 15-1: Existing Hycroft Buildings 196
Table 15-2: New Ancillary Facilities Planned over the LOM 203
Table 15-3: Proposed Upgrades for Existing Facilities 203
Table 15-4: Minimum Pre-feasibility Seismic Design Criteria for Stability for Very High Dam Classification 206
Table 15-5: Minimum Pre-feasibility Hydrologic Design Criteria for Very High Dam Classification 206
Table 15-6: Selected Ground Motions and Associated Seismic Coefficients 211
Table 15-7: Weather Station Summary 216
Table 15-8: Summary of Storm Event with Associated Rainfall Intensity 216
Table 15-9: Monthly Maximum Flows Demand 221
Table 17-1: Current Major Environmental Permits and Permits Necessary to Operate the Mine 230
Table 17-2: Ministerial Permits, Plans and Notifications 234
Table 18-1: Capital Cost Summary 238
Table 18-2: Baseline Mine Capital Cost (without Accuracy or Contingency adjustment) 240
Table 18-3: Process Plant Capital Cost Breakdown 241
Table 18-4: On-Site Infrastructure Capital Cost Breakdown 242
Table 18-5: Off-Site Infrastructure Capital Cost Breakdown 242
Table 18-6: Indirect Capital Cost Breakdown 243
Table 18-7: Mining Sustaining Capital Costs 244
Table 18-8: Operating Cost Summary 246
Table 18-9: Mine Operating Cost per Ton of Total Material Moved, US$/ton (Mine Costs) 248
Table 18-10: Process Plant Operating Cost Summary 248
Table 18-11: Process Plant Labor Cost Summary 249

 

Hycroft Mine Project

Page xi

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 18-12: Reagent Consumption Summary 250
Table 18-13: Process Plant Consumable Consumption Summary 251
Table 19-1: Economic Analysis Summary Table 256
Table 19-2: Life of Mine Economics 257
Table 19-3: Pre-Tax NPV (US$M) and IRR (%) Sensitivity Analysis 260
Table 19-4: Post-Tax NPV (US$M) and IRR (%) Sensitivity Analysis 261
Table 22-1: Hycroft Mineral Resources as of 21 January 2026, US customary Units 267
Table 22-2: High-grade Silver Bearing Domains, Contained within the Mineral Resource at 2 oz/ton Cutoff Grade, US customary Units 267
Table 23-1: Estimated Program Costs 273
Table 25-1: Information Provided by Hycroft 281

 

List of Figures

 

Figure 1-1: Post-Tax Sensitivity Analysis Results 18
Figure 3-1: Hycroft Mine Location Map 27
Figure 3-2: Claim Map 30
Figure 3-3: Current Property and Facilities Layout (2025) 31
Figure 4-1: Onsite Lab, Admin, Maintenance, Truck Shop, and Warehouse 39
Figure 4-2: Crusher and Conveyor Belt Circuit 39
Figure 4-3: North Merrill-Crowe Facility 40
Figure 4-4: Stage 1 Heap Leach Pad and Ponds Along Jungo Road 40
Figure 6-1: Stratigraphic Column for Hycroft Deposit Area 45
Figure 6-2: Simplified East–West Cross Section Through the Hycroft Mine – Section 40600 N 45
Figure 6-3: Vortex Alteration Cross-Section – 40600 N 48
Figure 6-4: Bay Geologic Cross-Section at 50300-N 49
Figure 6-5: Generalized Epithermal Diagram 51
Figure 7-1: Drill Collar Location Plan 55
Figure 9-1: Results of Submitted Gold Standards 2005 - 2013 73
Figure 9-2: Results of Submitted Silver Standards 2005-2013 74
Figure 9-3: Results of Blank Submissions 75
Figure 9-4: Check Assay Results, Fire Assay Gold 2011 - 2012 76
Figure 9-5: Check Assay Results, Fire Assay Silver 2011 – 2011 77
Figure 9-6: Standards Results, 2021 – 2022 78
Figure 9-7: Blank Results, 2021 – 2022 79
Figure 9-8: Duplicate Assay Results, 2021 – 2022 79

 

Hycroft Mine Project

Page xii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-9: Gold Standards 2023 – 2024 80
Figure 9-10: Blank Insertions 2004 81
Figure 9-11: Gold Duplicates, 2023-2024 82
Figure 9-12: Silver Duplicates, 2023-2024 83
Figure 9-13: Gold Check Assays 2023 – 2024 84
Figure 9-14: Silver Check Assays, 2023-2024 85
Figure 10-1: Recovery Vs. Time Plot, G&T Kamloops Tests, M Composites 96
Figure 10-2: Gold Grade Distribution Chart 97
Figure 10-3: Silver Grade Distribution Chart 97
Figure 10-4: Total Sulfur Grade Distribution 98
Figure 10-5: Sulfide Sulfur Grade Distribution 98
Figure 10-6: FLS Variability Flotation Recoveries under Optimal Conditions (137 Test Samples) 100
Figure 10-7: FLS Variability Flotation Gold Recoveries Based on Gold Head Grade Groups 101
Figure 10-8: FLS Variability Flotation Silver Recoveries Based on Head Grade Groups 101
Figure 10-9: Oxidation of Central Flotation Concentrate: Sulfate Spike Test 104
Figure 10-10: Demonstration Plant Cyanide Leach Recovery of Au and Ag 104
Figure 11-1: East–West Cross-Section 44000-N Looking North, Showing Lithology Types 114
Figure 11-2: East–West Cross-Section 44000-N Looking North, Showing Alterations 115
Figure 11-3: Structure and Domain Interpretation (Plan View) 116
Figure 11-4: Structure and Domain Interpretation with Silver Wireframes (plan view) 119
Figure 11-5: Bench Height Analysis 122
Figure 11-6: Gold Variograms for Silicic Material Between the Central Fault and East Fault 125
Figure 11-7: Gold Variograms for Silicic Material Between the Range Fault and Central Fault 125
Figure 11-8: E-W Cross-section at 41000-N, Showing Confidence Codes 135
Figure 11-9: E-W Cross-section at 41000-N, Visual Check of Gold Grades in Drillholes and Block Model 136
Figure 11-10: E-W Cross-section at 41000-N, Visual Check of Silver Grades in Drillholes and Block Model 137
Figure 11-11: Swath Plots for Gold, X = East and Y = North Slices, 160 ft Wide Slices 138
Figure 11-12: Swath Plots for Silver, X = East and Y = North Slices, 160 ft Slices 139
Figure 11-13: Swath Plots for Sulfide Sulfur, X = East and Y = North Slices, 160 ft Slices 140
Figure 13-1: Hycroft Initial Assessment Mine Plan Schedule 150
Figure 13-2: Summary of Lerch-Grossman Computer Pit Generation 155
Figure 13-3: Phase Schematic and Extraction Sequence 156
Figure 13-4: Approximate Recovered Gold by Year 158
Figure 13-5: Approximate Recovered Silver by Year 158
Figure 13-6: Approximate Recovered Equivalent Gold Ounces by Year Based on $3,100/oz Au and $36/oz Ag 159
Figure 13-7: Mine and Waste Storage Plan – Pre-production 160
Figure 13-8: Mine and Waste Storage Plan - End of Year 1 161
Figure 13-9: Mine and Waste Storage Plan – End of Year 2 162
Figure 13-10: Mine and Waste Storage Plan - End of Year 3 163

 

Hycroft Mine Project

Page xiii

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-11: Mine and Waste Storage Plan - End of Year 4 164
Figure 13-12: Mine and Waste Storage Plan – End of Year 5 165
Figure 13-13: Mine and Waste Storage Plan – End of Year 10 166
Figure 13-14: Mine and Waste Storage Plan – End of Year 20 167
Figure 13-15: Mine and Waste Storage Plan – End of Year 30 168
Figure 13-16: Mine and Waste Storage Plan – End of Year 40 169
Figure 13-17: Mine and Waste Storage Plan – End of Year 51 170
Figure 14-1: Sulfide Sulfur Process Plant Flowsheet 176
Figure 15-1: Site Layout 191
Figure 15-2: Site Access and Major Towns Near Hycroft Mine 192
Figure 15-3: Rail Spur Design 194
Figure 15-4: Overall Site Layout 197
Figure 15-5: Existing Crushing Facility and Surrounding Infrastructure 198
Figure 15-6: The Proposed Process Plant Generic Site Plan 199
Figure 15-7: Proposed Limestone Plant and Rail Spur 200
Figure 15-8: North Merrill-Crowe Plant 201
Figure 15-9: Existing Mine Ancillary Buildings 202
Figure 15-10: TMF Facility Layout 207
Figure 15-11: TMF Main Dam Section 208
Figure 15-12: TMF North Dam Section 209
Figure 15-13: TMF Closure Plan 212
Figure 15-14 Waste Rock Storage Facilities 213
Figure 15-15: Proposed Power Line from Imlay Relay Station (Nevada Historical Marker 49) to Jungo Road (49 Road) - NTS 214
Figure 15-16: Proposed Power Line along Jungo Road (Road 49) to Hycroft Mine Site (in total approximately 57 miles) - NTS 215
Figure 15-17: Hycroft Water Balance Schematic 220
Figure 15-18: Total Fresh Water Demand 221
Figure 19-1: Project Post-Tax Unlevered Cashflow 255
Figure 19-2: Pre-Tax Sensitivity Analysis Results 262
Figure 19-3: Post-Tax Sensitivity Analysis Results 263
Figure 20-1: Location of Rosebud Property 264

 

Hycroft Mine Project

Page xiv

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1Executive Summary

 

1.1Introduction

 

This technical report summary (TRS) has been prepared by Ausenco Engineering USA South Inc. (Ausenco), Independent Mining Consultants, Inc. (IMC), and WestLand Engineering & Environmental Services, Inc. (WestLand) for Hycroft Mining Holding Corporation (Hycroft), following the reporting requirements of the United States (US) Securities and Exchange Commission’s (SEC) Modernization of Property Disclosures of Mining Registrants under subpart 1300 and item 601 (96)(B)(iii) of Regulation S-K for an initial assessment (IA).

 

This TRS is an initial assessment with an economic analysis (IA-EA) and, filed on Electronic Data Gathering, Analysis, and Retrieval (EDGAR). The IA-EA is based on heap leaching the oxide material, while sulfide material is milled and processed using the pressure oxidation (POX) process. Transition material will be controlled by Hycroft grade control and may be processed with the sulfide material or heap leached with the oxide material. This TRS includes drill results received through March 17, 2025, which formed the basis of the Mineral Resource Estimate (MRE) model.

 

The Hycroft mine (the Mine) is situated on the western flank of the Kamma Mountains on the eastern edge of the Black Rock Desert approximately 54 miles west of Winnemucca in Humboldt and Pershing Counties, Nevada. The Mine property straddles Townships 34, 35, 35½ and 36 north and Ranges 28, 29 and 30 east (MDB&M) with its central coordinates at approximately latitude 40°52’ north and longitude 118°41’ west.

 

The Mine is accessible via Nevada State Route 49 (Jungo Road), an unpaved road maintained by Humboldt County and Pershing County and Hycroft. The Union Pacific railway, a major east–west railway, runs immediately adjacent to the property.

 

Hycroft, a past producer, has existing facilities on site including two administration buildings, a mobile maintenance shop, a light vehicle maintenance shop, a warehouse, multiple leach pads, primary, secondary and tertiary crushing systems, an assay lab, one Merrill-Crowe process plant, and a refinery.

 

1.2Terms of Reference

 

The firms and consultants who are providing Qualified Persons (QPs) responsible for the content of the TRS are, in alphabetical order, Ausenco, Hycroft, IMC and WestLand.

 

The TRS presents the IA-EA for the mine based on the POX and Heap Leach processes.

 

All units of measurement in the TRS are US customary, unless otherwise stated.

 

The monetary units are in US dollars, unless otherwise stated.

 

Mineral resources are reported in accordance with the US Securities and Exchange Commission Code of Federal Regulations, Subpart 229.1300 – Disclosure by Registrants Engaged in Mining operations (S-K 1300).

 

Hycroft Mine Project

Page 1

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.3Mineral Tenure, Surface Rights, Water Rights, and Agreements

 

The Mine property consists of 25 private parcels with patented claims totaling approximately 1,855 acres, along with 3,249 unpatented mining claims covering approximately 62,298 acres, for a combined total of approximately 64,000 acres. On May 15, 2023, Hycroft expanded its holdings by acquiring a 50% undivided interest in three additional patented mining claims, adding approximately 61 acres at one location in Northern Nevada. Some mining claims overlap other Hycroft Mining claims to ensure there are no fractional gaps in mining claim coverage.

 

These claims are contiguous or proximate to the original Crofoot and Lewis claims.

 

Payment of annual claim maintenance and holding fees to the Bureau of Land Management (BLM) and Humboldt and Pershing Counties and payment of annual real property taxes for patented claims in Humboldt and Pershing Counties are made every third quarter (Q3). Payments are current through the 2025–2026 claim years, with US$724,095 paid for 2025–2026. Payment of annual claim maintenance and holding fees and real property taxes are required to hold the Hycroft property in good standing. BLM annual maintenance fees for claims are due not later than September 1 of each year. Humboldt and Pershing County State annual holding fees beginning September 1 of each year are due no later than November 1 of each year. Annual real property taxes for patented claims in Humboldt and Pershing Counties are due August 31 of the following year.

 

Hycroft controls all surface and mineral rights within the Hycroft MRE area. No further land acquisition is required for the operation of the mine and contemplated processing facilities.

 

1.4History

 

The Mine location is in the Nevada Sulfur District, where mining for native sulfur began in the late 1800’s. In the early part of the 20th century high-grade Ag was mined as were veins of nearly pure alunite (hydroxylated aluminum potassium sulfate mineral) in the southern part of the district. From 1941 to 1943, cinnabar (a mercury sulfide mineral) was also mined. Exploration for native sulfur commenced again in 1966 with the Duval Corporation (Duval) reporting elevated Au and Ag values but finding no significant evidence of a sulfur deposit at depth (Wallace, 1980).

 

In 1977, the Cordex Syndicate mapped and rock-chip sampled the Hycroft property, recognizing the potential for a bulk tonnage, low-grade precious metal deposit. Homestake then took interest in the property and completed surface sampling and exploration drilling during 1981-1982. Mining officially began as a small heap leach operation in 1983 at what was then known as the Lewis Mine. In 1985, Vista gained control of the original Hycroft property. They also acquired the Lewis Mine in early 1987 from F. W. Lewis, Inc., and the Crofoot Mine in April 1988. From 1985 to 1999, they drilled 3,212 exploration holes, totaling 965,552 feet (ft) with the bulk of this drilling focused on oxide gold mineralization at Central, Bay and Brimstone. Production from the Brimstone pit commenced in 1985 and continued until December 1998.

 

From 1983 to 1998, the Mine produced approximately 1.2 million ounces (Moz) of Au and 2.5 Moz of Ag. An additional 58,700 ounce (oz) of Au was produced from the leaching operations from 1999 through 2004. The remaining leasehold interest in the Lewis property was purchased by Vista in December 2005. Production followed at the former Crofoot property in the Bay, South Central, Boneyard, Gap, and Historic Cut-4 pits along the Central Zone. The Mine was placed on a care and maintenance program through 2007. In May 2007, the Nevada-based holdings of Vista were spun out into Allied Nevada Gold Corp. (Allied Nevada). The Mine was included as part of the transfer of ownership allowing Allied Nevada to explore, expand, and develop the resources. The Mine was reactivated in September 2007 and achieved planned ore production by the end of 2009. With the construction of the North leach pad in 2013, the total leach pad space was increased to more than 20 million square ft (ft2). In 2010, the Mine began an expansion program that included construction of a 21,000 gallon per minute (gal/min.) Merrill-Crowe processing plant and a three-stage crushing facility as well as solution pumping capacity upgrades. Active mining was stopped again at the Mine in June 2015 due to low metal prices, but active leaching of previously mined ore continued through 2018. During this time, Allied Nevada emerged from its financial restructuring to become Hycroft Mining Corporation.

 

Hycroft Mine Project

Page 2

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

In late 2018, Hycroft began construction of new leach pads. In April 2019, active mining began with a focus on transition and sulfide minerals but were set aside for future processing. Active mining ceased in 2021, but gold and silver production continued through 2022.

 

From September 2007 through July 2019 metal sales totaled approximately 900,000 oz of Au and 5.0 Moz of Ag. Active mining ceased and production at the Mine was terminated on November 11, 2021. Annual sales in ounces of Au and Ag produced from the Mine’s heap leach operations over years 2019 through 2022 total approximately 107,258 ounces of Au and 615,000 ounces of Ag.

 

1.5Geology and Mineralization

 

The Hycroft deposit is a low-sulfidation, epithermal, hot springs system that contains gold and silver mineralization. Radiometric dating indicates that the main phase of gold and silver mineralization was formed four million years ago, when hydrothermal fluids were fed upward along high angle, normal faults.

 

Low-grade gold and silver mineralization were co-deposited with silica and potassium feldspar throughout porous rock types.

 

A subsequent drop in permeability, due to sealing of the system, led to over pressuring and subsequent repeated hydrothermal brecciation. Additional precious metal mineralization was deposited during this event as breccia zones, veins, and sulfide flooding.

 

Gold and silver mineralization was followed by an intense event of high sulfidation acid leaching of the mineralized volcanic rocks coincident with a regional water table drop. This allowed steam heated sulfur gases to condense into sulfuric acid and leach the upper portion of the mineralized rocks.

 

Oxidation of sulfide mineralization occurs to variable depths over the deposit, depending upon proximity to faults, extent of acid leaching, and depth to water table. Sulfide content through the deposit is variable from 0% to 20%.

 

A total of six major north-northeast trending, west dipping, normal fault zones appear to broadly control the distribution of alteration. From west to east, these fault zones are referred to as the Range, West Splay, Central, Break, Albert, and East Faults. These major structures down-drop stratigraphy and affect the distribution of alteration and mineralization.

 

A post-mineral basin bounding fault appears to border the Camel Conglomerate and the adjacent Pleistocene Lahontan Lake sediments in the Black Rock Desert. Based on geophysics, this structure is approximately one to two miles west of the Mine site. There are several east–west trending structures that appear to provide post-mineral offset to the deposit. These form a series of horst and grabens within the deposit footprint.

 

Hycroft Mine Project

Page 3

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.6Exploration

 

The Hycroft property drill history covers the period from 1982 through 2024. Within the block model there are 5,813 drillholes, with 516,901 drill intervals amounting to 2,668,616 ft of drilling.

 

During 2021 through 2024, Hycroft drilled 260 holes, 105 in 2021, 85 in 2022, 49 in 2023 and 21 in 2024. Most of the 2021 drilling was diamond core that was used for metallurgical testing and assay. The 2022 and 2023 drilling focused on extending mineralization and upgrading areas from inferred to measured and indicated classification. Since 2024, drilling has focused on high-grade mineralization in Brimstone and Vortex.

 

1.7Sampling

 

Hycroft provided IMC with the database which contained drilling information from 1982 through 2024. Assay data was received through March 2025.

 

The current sample preparation analysis and security follow best practices and are acceptable for application to mineral resource reporting.

 

The historic data collection is unknown. Components of the historic data have been found to be reliable. Some components are not reliable and have been removed or modified prior to incorporation into the MRE.

 

After the noted adjustments, John Marek, the QP, finds the data applicable to the determination of the MRE.

 

1.8Metallurgical Testwork

 

Metallurgical testwork supporting the Hycroft process flowsheet has been conducted by several laboratories, including G&T Metallurgical Services Ltd. (G&T), SGS Mineral Services (SGS), Hazen Research Inc. (Hazen), FLSmidth Minerals Testing & Research Center (FLSmidth MTRC), and Kappes, Cassiday & Associates (KCA). The process design and metallurgical assumptions used in this study are primarily based on the most recent testwork completed by FLSmidth - MTRC and Hazen Research, with historical testwork from the other laboratories reviewed to support the interpretation of metallurgical performance and flowsheet development. 

 

Comminution testwork indicates that Hycroft mineralization is very high and requires relatively high grinding energy in ball mill grinding.

 

Hycroft Mine Project

Page 4

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

In 2021, Hycroft initiated a new metallurgical variability study to evaluate mineralized material characteristics within the current mine plan, validate the metallurgical performance across the deposit; and identify potential variations in processing conditions required to recover gold and silver. The objective of the study was to support development of a Hycroft process flowsheet, including definition of key process control points in crushing, grinding, capable of consistently achieving gold and silver recoveries across anticipated metallurgical variability.

 

Key outcomes of this study included the development of the flotation process with significantly improved recoveries. The following key process controls parameters were identified during the flotation process development program:

 

Optimal grind size is a P80 of less than 85 micrometers (µm).
  
Flotation time is 24 minutes.
  
Adjusted pH level is 4.7.
  
Flotation mass pull is 20 to 25% with 22% being the target.

 

A total of 137 samples were tested under these selected conditions to achieve higher gold and silver recoveries to flotation concentrate. The results show that gold recovery exhibits a broader distribution, with values ranging from approximately 72 to 98% and a statistical median near 88%, indicating greater sensitivity across the tested samples. In contrast, silver recovery is generally higher, with recoveries spanning approximately 76 to 100% and a statistical median exceeding 92%. This is a significant improvement from the gold flotation recovery and silver flotation recovery values reported in a TRS prepared for Hycroft and filed in 2023 (the 2023 TRS).

 

In 2025, Hycroft completed a series of POX tests demonstrating that POX at 225°C with oxygen overpressure, followed by hot cure, lime boil, and cyanide leaching, is a technically viable and repeatable processing route for the pyrite concentrate. Gold and silver recoveries of approximately 93% and 86%, respectively, were consistent with past performance. Overall, considering the full flowsheet involving flotation, POX, and leaching, gold recovery has improved to approximately 83% and silver recovery has improved to approximately 78%. Overall recovery for both gold and silver are exceeding the values assumed in the 2023 TRS.

 

Hycroft existing heap leaching was discontinued in 2022. Heap leach operations are expected to restart once new oxide and transition material becomes available.

 

1.9Mineral Resource Estimate

 

The MRE on the Hycroft property is currently envisioned to be mined by way of a conventional hard rock open pit mine feeding two process facilities:

 

1.Run-of-mine (ROM) oxide material will be directed to cyanide heap leaching, producing a gold and silver doré.
  
2.Sulfide material will be directed to a crushing, flotation milling followed by POX of the concentrate to make a gold and silver doré.

 

Transitional material will be directed to either (ROM) cyanide heap leaching or flotation milling followed by POX depending on the sulfide sulfur levels of the individual blocks, total sulfur content, and gold grade.

 

The terms of reference for this MRE are mineralization in-place. The procedures described in the following paragraphs establish that the stated MRE has reasonable prospects for economic extraction of mineral resources.

 

Mineral resources were developed using a computer-based block model for mineralization and pit optimization software to determine mineralization with reasonable prospectus for economic extraction.

 

Hycroft Mine Project

Page 5

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The cutoff grade that is reported for this statement of mineral resources is based on mining and processing costs estimated by IMC and Ausenco combined with reasonable metal prices. The internal or marginal cutoff is applied and reported where the benefits of selling the recovered metal will pay for the processing and fixed general and administrative (G&A) costs. The cutoff is presented in terms of net of refining (NSR).

 

Metal prices for the MRE were US$3,100/oz Au and US$36.00/oz Ag. Spot prices for gold and silver in 2025 ranged from US$2,798 to US$4,323/oz Au and US$31.34 to US$71.63/oz Ag. The spot prices for gold and silver on January 21, 2026, were US$4,726/oz Au and US$93.50/oz Ag. The prices selected for determination of the MRE are 35% below the spot gold price and 62% below the spot silver price on January 21, 2026.

 

The risks to the MRE are project costs and project recoveries as well as metal prices that can have a substantial impact on the mineral resource both positively and negatively. The Hycroft MRE is sensitive to estimated parameters of operating costs, recoveries, and metal prices. That sensitivity may result in future variation in the mineral resource as costs and recoveries are refined.

 

Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.

 

Table 1-1: Hycroft MRE as of January 21, 2026, US customary Units

 

Classification

Cutoff Grade

$ Net

of Refining

Approximate

Cutoff, AuEq oz/ton

Ktons

Gold

oz/ton

Silver

oz/ton

Sulfide

Sulfur %

Contained Ounces

Gold

Oz x 1000

Silver

Oz x 1000

Heap Leach Resource
Measured $1.88 - $3.63 0.001 - 0.002 92,994 0.005 0.11 1.83 446 10,322
Indicated $1.88 - $3.63 0.001 - 0.002 110,374 0.004 0.09 1.54 475 9,492
Meas + Ind $1.88 - $3.63 0.001 - 0.002 203,368 0.005 0.10 1.67 921 19,814
Inferred $1.88 - $3.63 0.001 - 0.002 110,018 0.005 0.09 1.41 528 10,122
Flotation Mill + Concentrate Treatment by Pressure Oxidation and Cyanide Leach
Measured $16.73 0.007 734,571 0.011 0.43 2.03 8,154 316,600
Indicated $16.73 0.007 748,876 0.010 0.30 1.84 7,339 226,161
Meas + Ind $16.73 0.007 1,483,447 0.010 0.37 1.93 15,493 542,761
Inferred $16.73 0.007 459,646 0.010 0.27 1.76 4,505 122,725
Combined Mineral Resources Leach Plus Mill
Measured $1.88 - $16.73 0.001 - 0.007 827,565 0.010 0.40 2.01 8,600 326,922
Indicated $1.88 - $16.73 0.001 - 0.007 859,250 0.009 0.27 1.80 7,814 235,653
Meas + Ind $1.88 - $16.73 0.001 - 0.007 1,686,815 0.010 0.33 1.90 16,414 562,575
Inferred $1.88 - $16.73 0.001 - 0.007 569,664 0.009 0.23 1.69 5,033 132,847

 

Notes:

 

1.Mineral resources based on metal prices of $3,100/troy oz Au and $36.00/troy oz Ag.
2.Cutoffs are Income – Refining Cost = NSR.
3.Gold Equivalent (AuEq) for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay, or at average gold leach recovery AuEq = Fire Gold + 0.0035 Total Silver Assay.
4.Gold Equivalent for Mill + Pressure Oxidation = Fire Gold + 0.0107 x Total Silver Assay.
5.Numbers may not match exactly due to rounding.
6.Mineral resources are contained within a computer-generated optimized pit.
7.Total material in that pit is 5.42 billion tons.

 

Hycroft Mine Project

Page 6

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

8.Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.
9.Modifying factors for mine and process design have not been applied.
10.All units are US customary. Ktons means 1,000 short tons. Au and Ag grades are in troy ounces per short ton (oz/ton).

 

Table 1-2: Hycroft MRE as of 21 January 2026, Metric Units

 

Classification

Cutoff Grade

$ Net

of Refining

Approximate

Cutoff, AuEq g/tonne

Ktonnes Gold Silver Sulfide Sulfur Contained Ounces
Gold Silver
g/tonne g/tonne % Oz x 1000 Oz x 1000
Heap Leach Resource
Measured $2.07 - $4.00 0.027 - 0.055 84,364 0.164 3.80 1.83 446 10,322
Indicated $2.07 - $4.00 0.027 - 0.055 100,131 0.147 2.95 1.54 475 9,492
Meas + Ind $2.07 - $4.00 0.027 - 0.055 184,495 0.155 3.34 1.67 921 19,814
Inferred $2.07 - $4.00 0.027 - 0.055 99,808 0.164 3.15 1.41 528 10,122
Flotation Mill + Concentrate Treatment by Pressure Oxidation and Cyanide Leach
Measured $18.44 0.206 666,403 0.380 14.76 2.03 8,154 316,600
Indicated $18.44 0.206 679,380 0.336 10.34 1.84 7,339 226,161
Meas + Ind $18.44 0.206 1,345,783 0.358 12.53 1.93 15,493 542,761
Inferred $18.44 0.206 416,991 0.336 9.14 1.76 4,505 122,725
Combined Mineral Resources, Leach Plus Mill
Measured $2.07 - $18.44 0.027 - 0.206 750,767 0.356 13.53 2.01 8,600 326,922
Indicated $2.07 - $18.44 0.027 - 0.206 779,512 0.311 9.39 1.80 7,814 235,653
Meas + Ind $2.07 - $18.44 0.027 - 0.206 1,530,279 0.333 11.42 1.90 16,414 562,575
Inferred $2.07 - $18.44 0.027 - 0.206 516,799 0.303 7.99 1.69 5,033 132,847

 

Notes:

 

1.Mineral resources based on metal prices of $3,100/ oz Au and $36.00/ oz Ag.
2.Cutoffs are Income – Refining Cost = NSR.
3.Gold Equivalent for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay.
4.Gold Equivalent for Mill + Pressure Oxidation = Fire Gold + 0.0107 x Total Silver Assay.
5.Numbers may not match exactly due to rounding.
6.Mineral resources are contained within a computer-generated optimized pit.
7.Total material in that pit is 4.92 billion tonnes.
8.All units on this table are metric: Ktonnes means 1,000 tonnes. Au and Ag grades are in grams per tonne (g/tonne).
9.Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.
10.Modifying factors for mine and process design have not been applied.

 

Contained within the MRE at Hycroft are a series of high-grade silver veins at Brimstone and zones of higher silver concentrations in Vortex that are associated with a low angle breccia body. Table 1-3 and Table 1-4 are the tabulation of gold and silver within the domain volumes that are contained within the MRE at 2 oz/tonne cutoff grade in US customary and 68.57 g/tonne cutoff grade in metric.

 

Hycroft Mine Project

Page 7

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 1-3: High-grade Silver Bearing Domains, Contained Within the MRE at 2 oz/ton Cutoff Grade, US customary Units

 

Classification Cutoff Grade Silver (oz/ton) Ktons

Gold

(oz/ton)

Silver
(oz/ton)
Sulfide Sulfur (%) Gold Contained
oz x 1000
Silver Contained
oz x 1000
Brimstone
Measured 2.00 3,195 0.011 8.35 1.33 35 26,686
Indicated 2.00 330 0.010 3.11 1.87 3 1,025
Meas + Ind 2.00 3,525 0.011 7.86 1.38 38 27,711
Inferred 2.00 15 0.008 3.52 1.13 0 52
Vortex
Measured 2.00 9,126 0.018 3.81 1.49 160 34,781
Indicated 2.00 7,342 0.014 3.78 1.24 100 27,726
Meas + Ind 2.00 16,468 0.016 3.80 1.38 261 62,507
Inferred 2.00 3,644 0.014 3.65 1.27 50 13,307
Brimstone + Vortex
Measured 2.00 12,322 0.016 4.99 1.45 195 61,467
Indicated 2.00 7,671 0.013 3.75 1.26 104 28,750
Meas + Ind 2.00 19,993 0.015 4.51 1.38 299 90,218
Inferred 2.00 3,659 0.014 3.65 1.27 51 13,359

 

Table 1-4: High-grade Silver Bearing Domains, Contained Within the MRE at 68.57 g/tonne (2 oz/tonne) Cutoff Grade, Metric Units

 

Classification Cutoff Grade Silver (g/tonne) Ktonnes Gold
(g/tonne)
Silver
(g/tonne)
Sulfide Sulfur (%) Contained Ounces
Gold
Oz x 1000
Silver
Oz x 1000
Brimstone
Measured 68.57 2,899 0.372 286.35 1.33 35 26,686
Indicated 68.57 299 0.332 106.62 1.87 3 1,025
Meas + Ind 68.57 3,198 0.368 269.54 1.38 38 27,711
Inferred 68.57 13 0.289 120.74 1.13 0 52
Vortex
Measured 68.57 8,279 0.603 130.67 1.49 160 34,781
Indicated 68.57 6,660 0.469 129.48 1.24 100 27,726
Meas + Ind 68.57 14,940 0.543 130.14 1.38 261 62,507
Inferred 68.57 3,306 0.475 125.20 1.27 50 13,307
Brimstone + Vortex
Measured 68.57 11,178 0.543 171.04 1.45 195 61,467
Indicated 68.57 6,959 0.463 128.49 1.26 104 28,750
Meas + Ind 68.57 18,137 0.512 154.71 1.38 299 90,218
Inferred 68.57 3,319 0.474 125.18 1.27 51 13,359

 

Hycroft Mine Project

Page 8

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.10Mining Methods

 

Hycroft is planned as a conventional hard rock open pit operation. IMC developed a mine plan that produces the required process feed and moves sufficient mine waste to assure continued release of the mineralization. The mine plan is based on measured and indicated mineralization that was estimated in the mineral resource block model described in Section 11.

Inferred mineralization was not included within this initial assessment for two reasons: (1) there is sufficient measured and indicated mineralization to feed the process plant for over 50 years, and (2) to reduce the changes in the mine schedule and potentially minable material as the project moves toward a pre-feasibility study in the future.

The mine will feed two processing facilities:

 

1.A flotation mill followed by pressure oxidation and leaching of the concentrate.

 

2.A ROM heap leach for mineralization that is amenable to direct cyanide leaching.

 

The mine production schedule is summarized in Figure 13-1 with tabular detail in Table 13-1.

 

1.11Processing and Recovery Methods

 

Hycroft property is currently envisioned to be mined by way of a conventional hard rock open pit mine feeding two process facilities:

 

1.Oxide Material – ROM oxide material will be directed to cyanide heap leaching, producing gold and silver doré.

 

2.Sulfide Material – Sulfide material will be directed to a crushing and flotation milling circuit, followed by pressure oxidation (POX) of the concentrate to produce a gold and silver doré.

 

Transitional material will be routed to either ROM cyanide heap leaching or flotation milling followed by POX, depending on the sulfide sulfur levels of the individual blocks, total sulfide sulfur content, and gold grade. The process route will be determined based on grade control

 

The existing Heap Leach facilities (Brimstone Heap Leach Pad and North Heap Leach Pad) will be expanded to accommodate additional capacity. These facilities have existing collection ponds and pumping systems. The leach solution distribution network will be expanded as required to support increased throughput.

 

Hycroft Mine Project

Page 9

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

For sulfide processing, the plant will utilize the existing crushing plant. Consisting of three stages of crushing, reducing the mineralized material from a nominal top size of approximately 35 inches (“) to about ⅜”. The crushed material is fed to a two-stage ball milling circuit operating in closed circuit with hydrocyclones, producing a grind suitable for downstream processing. Cyclone overflow will be directed to rougher flotation for recovery of gold and silver into a flotation concentrate.

 

Rougher flotation tailings will be thickened prior to transfer to the final tailings pumping system. The flotation concentrate will be processed through POX to oxidize sulfide minerals and liberate gold and silver for downstream recovery.

 

Following oxidation, the oxidized slurry will undergo counter-current decantation (CCD) washing to recover dissolved metal values and remove acidic process solutions. The washed solids are then conditioned through lime boil and hot curing prior to cyanide leaching.

 

The conditioned solids will be leached in cyanide leach tanks to dissolve gold and silver. Precious metals will be recovered from the leach solution using the existing Merrill-Crowe zinc precipitation circuit, producing gold-silver doré.

 

Residual cyanide in the leach tailings will be destroyed using a sulfur dioxide–oxygen detoxification process, after which the detoxified tailings will be combined with flotation tailings and pumped to the tailings management facility (TMF) for disposal.

 

1.12Infrastructure

 

The Hycroft Mine infrastructure scope represents a brownfield development within an established mining complex. The proposed sulfide ore processing plant will be integrated into existing site infrastructure via tie-ins to current crushing facilities, utilities, and site services. Most existing access roads, haul roads, and ancillary structures will remain in service or be selectively upgraded.

 

1.12.1Site Access and Haulage

 

New road infrastructure includes 0.6 miles of plant access roads, a 5.6-mile TMF access road parallel to the tailings delivery pipeline corridor, and a 3.4-mile TMF construction haul road connecting the North WRSF to the TMF embankment. All roads are designed as dirt roads with a maximum 10% grade and 25 miles per hour (mph) speed limit. A rail spur extension from the adjacent Union Pacific line will receive reagents, consumables, and fuel, and facilitate export of salable metals. The spur design by Mountain States Contracting Inc. includes turnouts, derails, signals, ballast, bridges, civil works, and a bottom-dump hopper car loadout facility.

 

1.12.2New Infrastructure

 

New process plant facilities will tie into the existing crushing circuit and North Merrill-Crowe facility. New onsite infrastructure includes utility tie-ins, power distribution upgrades, substations, a process control system and control room, and reagent handling facilities including an oxygen plant and limestone offloading and slaking system. Six new ancillary facilities are planned over the LOM including a covered crushed ore stockpile dome (313 ft diameter × 104 ft height), new assay lab, fuel station, technical services building, maintenance shop, and crusher maintenance building. Ten existing structures will be upgraded, relocated, or repurposed. Workforce accommodation will be drawn primarily from Winnemucca (~54 miles east), with personnel transported via contracted bus service.

 

Hycroft Mine Project

Page 10

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.12.3Stockpiles

 

Coarse ore stockpile capacity is 56,000 tons live and 175,400 tons total; crushed ore stockpile capacity is 34,000 tons live and 113,000 tons total, covered by a round dome structure. These stockpiles support crushing circuit availability of 31.3% for primary and 65.1% for combined secondary and tertiary crushing. Growth medium stripped during TMF construction will be stockpiled for reclamation use. Limestone will be delivered by rail to a dedicated onsite stockpile.

 

1.12.4Tailings Management Facility

 

The TMF uses conventional designs and will be constructed in a total of eight stages and zero discharge of process solutions. The TMF will fill the broad valley immediately northeast of the mill site and require the main and the north embankments to impound an ultimate tailings storage capacity of 1.05 billion tons (Btons) at an average settled dry density for the ultimate facility of 92 pounds per cubic ft (pcf). The main embankment will cross the natural drainage on the west side of the TMF, and the secondary embankment will be constructed along the northern ridge. The facility will provide continuous containment of process solutions through the installation of a vertical chimney drain and engineered geomembrane liner systems, extending across the impoundment basin and below a portion of the main embankment and the upstream slope of the north embankment. The design is capable of storing runoff from the basin and direct precipitation on the facility, resulting from the 5,000-year, 24-hour storm event during operation and the 10,000-year, 24-hour storm event for post-closure.

 

1.12.5Waste Rock Storage Facility

 

Two initial waste rock storage facility (WRSF) locations — west and south of the pit — will merge into a single facility on the southwest perimeter by Mine Year 10. The dump is designed with an overall slope of 2.7H:1V and inter-bench geometry of 1.5H:1V slopes with 50 ft high and 60 ft wide benches, constructed over previously disturbed ground. Water management consists of upstream diversion channels for non-contact water and a seepage collection system for contact water, comprising double-walled HDPE pipes (300 mm main, 100 mm secondary) sized for the 100-year, 24-hour event. Seepage is conveyed to double-lined GCL and HDPE collection ponds for reuse at the process plant. Surface water diversion channels are sized for the 100-year, 24-hour event with a minimum 2% slope and riprap lining. Physical stability will be monitored via survey markers, vibrating wire piezometers, hydraulic piezometers, and inclinometers throughout the LOM. Topsoil and growth media will be harvested from areas adjacent to the WRSF during closure to support reclamation.

 

1.12.6Power, Communications, and Fuel

 

Two 120 kV powerlines will supply the site via the Nevada Power Imlay Substation. Installed load is 160 MW with an operating load of 124 MW; total load including the oxygen plant is 170 MW, requiring additional transmission capacity. Site communications are currently served by microwave, fiber optic, and cellular systems and will be upgraded as required during execution. Diesel fuel is priced at $3.76/gallon; supply contracts are in place on an annual or bi-annual basis. Fuel will be delivered by rail once the spur is operational. The existing fuel island will be replaced with a high-efficiency system in mine years 3 and 4.

 

Hycroft Mine Project

Page 11

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.12.7Water Supply and Management

 

Hycroft holds 16 water-right permits sufficient to support all planned facilities and process demands. Plant freshwater demand is estimated at 7,260 gal/min, supplied via four existing wells with four additional production wells to be drilled. Tailings will be transported as slurry at 48% solids through an HDPE-lined pipeline, distributed via a 36” manifold system. Return water will initially be managed via the Underdrain Collection Pond, transitioning to barge-mounted pumps in the TMF supernatant pool in later years. GoldSim Monte Carlo water balance modeling over 250 simulations indicates average make-up water demand starting at 6,500 gal/min in year 1, declining to 3,200 gal/min by years 14–15. Pit dewatering will be managed by four depressurization wells with groundwater at approximately 700 ft below ground surface (bgs), with water conveyed to the process plant. Plant site stormwater is managed via perimeter ditches and a 9,850 yd³ HDPE-lined sedimentation pond sized for the 100-year, 24-hour event.

 

1.12.8Hazard Considerations

 

The site climate is arid at 7.7 in/a average precipitation with winter temperatures between 20 °F and 40 °F, introducing freeze-thaw cycling risk in near-surface soils. Seismicity is assessed as low to moderate with no active or capable faults identified. Principal pit slope stability controls are the argillically altered Camel Conglomerate, Auld Lang Syne Formation siltstones, and the East Fault.

 

1.13Market Studies and Contracts

 

No formal marketing studies have been completed. Gold and silver doré will be sold on the spot market under terms typical of comparable doré contracts. Both metals are globally liquid commodities supporting reliable price discovery throughout the LOM. The economic analysis assumes base case prices of US$3,600/oz gold and US$48.00/oz silver, based on long-term consensus forecasts from numerous financial institutions as of April 2026. No refining, transportation, or hedging contracts are currently in place, though these are considered readily obtainable. Refining and transportation costs are estimated at US$5.00/oz gold and US$0.50/oz silver based on comparable project terms.

 

1.14Environmental, Permitting and Social Considerations

 

1.14.1Environmental Considerations

 

The Mine has conducted numerous environmental baseline studies as part of their previous permitting efforts and continues to collect certain environmental baseline data. The Mine area has been surveyed for surface water resources, including Waters of the United States (WOTUS), biological resources, cultural resources, and groundwater resources. In addition, the Mine has developed a series of environmental management and monitoring plans which are required to guide the development and operation of the Project to limit environmental impacts. These plans are developed to address legal requirements and committed Environmental Protection Measures (EPMs) made by the Mine during Project permitting and recent Plan of Operations amendments.

 

Hycroft Mine Project

Page 12

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.14.2Permitting Considerations

 

The Mine operates under a series of permits, which are issued by both federal and state regulators. The following table lists the principal environmental permits necessary to operate the Mine and the applicable issuing agency.

 

Table 1-5: Principal Environmental Permits

 

Operating Permits Issuing Agency
Plan of Operations BLM
Mercury Operating Permit to Construct NDEP Bureau of Air Pollution Control
Class I Air Quality Operating Permit to Construct NDEP Bureau of Air Pollution Control
Class II Air Quality Permit NDEP Bureau of Air Pollution Control
Permit to Operate a Public Water System NDEP Bureau of Safe Drinking Water
Water Pollution Control Permit-Crofoot Project NDEP Bureau of Mining Regulation & Reclamation
Water Pollution Control Permit-Hycroft Mine NDEP Bureau of Mining Regulation & Reclamation
Reclamation Permit NDEP Bureau of Mining Regulation & Reclamation
Mining General Stormwater Pollution Prevention Permit NDEP Bureau of Water Pollution Control
Class III Landfill Waiver NDEP Bureau of Waste Management
Artificial Pond Permit (Brimstone Process Ponds) NV Department of Wildlife
Artificial Pond Permit (Crofoot Process Ponds) NV Department of Wildlife
Artificial Pond Permit (North Process Ponds) NV Department of Wildlife
Septic Onsite Disposal NDEP Bureau of Water Pollution Control
Dam Safety Permits NV Division of Water Resources
Hazardous Materials Storage Permit NV State Fire Marshal
Special Use Permit Pershing County
Special Use Permit Humboldt County
Golden Eagle Take Permit US Fish & Wildlife Service

 

In addition to the principal environmental permits outlined above, the following table lists other notifications or ministerial permits that may likely be necessary to operate the Project, as well as the applicable agency.

 

Table 1-6: Other Notifications or Ministerial Permits

 

Notification/Permit Agency
Above Ground Storage Tank Permit Nevada Bureau of Corrective Actions
Agreement for Road Maintenance Humboldt and Pershing Counties
Explosives Permit Bureau of Alcohol, Tobacco, Firearms, and Explosives
Explosives User’s License (User’s Clearance) Bureau of Alcohol, Tobacco, Firearms, and Explosives
Fire and Life Safety Nevada State Fire Marshal
Hazardous Materials Permit Nevada State Fire Marshal
Industrial Artificial Pond Permit Nevada Department of Wildlife
Leach Pad Commencement Nevada Bureau of Mining Regulation and Reclamation
Leach Pad As-Built Report Nevada Bureau of Mining Regulation and Reclamation
Process Plant As-Built Report Nevada Bureau of Mining Regulation and Reclamation
Dam Safety Permit Nevada Division of Water Resources
Mine ID Number Mine Safety & Health Administration
Mine Opening Notification Nevada Division of Minerals
Mine Registry Nevada Division of Minerals
Notification of Commencement of Operations Mine Safety & Health Administration
Production/Dewatering Wells - Proof of Completion Nevada Division of Water Resources
Radio License Federal Communications Commission
RCRA Waste Mgt. ID - Mine Nevada Bureau of Sustainable Materials Management/U.S. Environmental Protection Agency
Well Drilling Permit (Notice of Intent to Drill) Nevada Division of Water Resources
Potable Water System Nevada Bureau of Safe Drinking Water
Septic System Nevada Bureau of Water Pollution Control

 

Hycroft Mine Project

Page 13

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.14.3Social Considerations

 

Social and community impacts are considered and evaluated for the revision to the Plan Application and would be used in the NEPA process. Potentially affected Native American tribes, tribal organizations, and/or individuals are consulted during the preparation of all plan amendments to advise on the proposed projects that may affect cultural sites, resources, and traditional activities.

 

1.14.4Closure and Reclamation Considerations

 

A Tentative Plan for Permanent Closure (TPPC) for the Mine is in place and is currently being updated for future submission to the BMRR with the application to modify the WPCP (NEV0094114). In the TPPC, the proposed TMF closure approach would consist of fluid management through evaporation, covering the TMF with a geosynthetic cover and growth media, and then revegetation. The design of the process components is not sufficiently advanced to determine the closure costs. Any residual TMF drainage will be managed with evaporation cells. Surface management surety bonds currently total US$58.7 million with US$58.3 million securing financial assurance requirements for the Mine and US$0.4 million securing financial assurance requirements for the water supply well field and exploration within the Project boundary. Future increases in reclamation bonding will either be through surety bonds supported by restricted cash balances or by letters of credit issued by banks.

 

1.15Capital and Operating Cost

 

The capital cost (CAPEX) and operating cost (OPEX) estimates were developed in Q1 2026 in U.S. dollars (US$). The estimates are based on budgetary quotations, supplemented with Ausenco’s in-house database, and informed by Ausenco’s experience from similar operations in North America.

 

1.15.1 Capital Cost Estimate

 

The capital cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The CAPEX estimate includes the following:

 

Initial capital cost to design, construct, and commission the mine, process plants, and supporting facilities and infrastructure.
  
Sustaining capital to construct and commission equipment replacement and other major capital expenses expected after commercial production commences.
  
Closure costs associated with reclaimation of the project site after operations have ceased.

 

The initial, sustaining, and total costs of the project are summarized by major areas in Table 1-7.

 

Table 1-7: Capital Cost Summary

 

WBS Description Capital Cost (US$M) Sustaining Cost (US$M) Total Cost1 (US$M)
1000 Mining 194 1,171 1,365
2000 Crushing 48 60 109
3000 Sulfide Process 915 776 1,692
4000 Oxide Process 16 46 63
5000 Waste Rock Storage & TMF 208 515 723
6000 Onsite Infrastructure 139 9 148
7000 Offsite Infrastructure 43 366 409
Total Direct Costs 1,563 2,944 4,507
8000 Indirects 382 27 409
9000 Provisions 448 136 584
10000 Owner’s Costs 41 - 41
Total Capital Cost 2,434 3,107 5,541

 

Note:

 

1.Totals may not match due to rounding

 

Hycroft Mine Project

Page 14

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.15.2Operating Cost Estimate

 

The operating cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The OPEX estimate for the project includes expenses incurred by the mine, process plant, and administration of the operation (G&A costs). A summary of the mining, processing, and G&A operational costs by LOM total cost and unit cost (US$/ton) is in Table 1-8.

 

Table 1-8: Operating Cost Summary

 

Cost Area LOM Total (US$M)1 US$/ton milled % of Total
Mining 8,6832 6.91 31.5
Process 18,245 14.52 66.1
G&A 664 0.53 2.4
Total 27,592 21.96 100

 

Note:

 

1.Totals may not match due to rounding
2.Includes 10% contingency

 

1.16Economic Analysis

 

1.16.1Economic Summary

 

The results of the economic analysis discussed in this section represent forward-looking information as defined under U.S. securities law. The results depend on inputs that are subject to a number of known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those presented here.

 

Information that is forward-looking includes:

 

mineral resource estimates
  
assumed commodity prices and exchange rates
  
proposed mine production plan
  
projected mining and process recovery rates
  
assumptions as to mining dilution
  
capital and operating cost estimates and working capital requirements
  
assumptions as to closure costs and closure requirements
  
assumptions as to environmental, permitting and social consideration and risks.

 

Hycroft Mine Project

Page 15

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Additional risks to the forward-looking information includes:

 

changes to costs of production from what is assumed
  
unrecognized environmental risks
  
unanticipated reclamation expenses
  
unexpected variations in quantity of mineralized material, grade or recovery rates
  
geotechnical or hydrogeological considerations differing from what was assumed
  
failure of mining methods to operate as anticipated
  
failure of plant, equipment or processes to operate as anticipated
  
changes to assumptions as to the availability of electrical power, and the power rates used in the operating cost estimates and financial analysis
  
ability to maintain the social license to operate
  
accidents, labor disputes and other risks of the mining industry
  
changes to interest rates
  
changes to tax rates and availability of allowances for depreciation and amortization.

 

The economic analysis was completed assuming a 5% discount rate. The pre-tax NPV discounted at 5% is US$5,437 million; the IRR is 18.9%, and payback period is 4.3 years. On a post-tax basis, the NPV discounted at 5% is US$4,344 million, the IRR is 16.9%, and the payback period is 4.7 years. A summary of project economics is listed in Table 1-9.

 

Readers are cautioned that the assessment is preliminary in nature and there is no certainty that the economic assessment will be realized. However, it does not include any inferred mineral resources.

 

Hycroft Mine Project

Page 16

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 1-9: Economic Analysis Summary

 

  Unit Value
General Inputs
Gold Price US$/oz 3,600
Silver Price US$/oz 48.00
Discount Rate % 5.0
LOM Production
Total Mineralized Material Mined kst 1,496,134
Total Waste Mined kst 2,320,719
Average Strip Ratio w:o 1.55
Life of Mine years 50.5
Total Mill Feed Processed kst 1,046,284
Average Mill Feed Grade (Au) oz/st 0.012
Average Mill Feed Grade (Ag) oz/st 0.43
Total Leach Material Processed kst 210,010
Average Leach Feed Grade (Au) oz/st 0.005
Average Leach Feed Grade (Ag) oz/st 0.12
Total Recovered Gold koz 10,476
Total Recovered Silver koz 349,208
Average Mill Feed Gold Recovery % 82.8
Average Mill Feed Silver Recovery % 77.5
Average Leach Gold Recovery % 40.0
Average Leach Silver Recovery % 12.0
Life of Mine Payable Gold Production koz 10,424
Life of Mine Payable Silver Production koz 347,462
Life of Mine Payable Gold Equivalent Production koz 15,057
Refining, Royalties
Gold Payable % 99.5
Silver Payable % 99.5
NSR Royalty % NSR 2.14
Refining Costs - Au US$/oz 5.00
Refining Costs - Ag US$/oz 0.50
LOM Operating Costs
Mining Cost US$/st mined 2.28
Mining Cost US$/st processed 6.91
Processing Cost US$/st processed 14.52
G&A Cost US$/st processed 0.53
Total Operating Cost US$/st processed 21.96
Cash Costs1 US$/oz AuEq 1,924
All-In Sustaining Cost2 US$/oz AuEq 2,147
Capital Costs
Initial Capital US$M 2,434
Sustaining Capital US$M 3,107
Closure Costs US$M 243
Financials
Pre-Tax NPV (5%) US$M 5,437
Pre-Tax IRR % 18.9
Pre-Tax Payback years 4.3
Post-Tax NPV (5%) US$M 4,344
Post-Tax IRR % 16.9
Post-Tax Payback years 4.7

 

Notes:

 

1.Cash costs consist of mining costs, processing costs, mine-level G&A and refining charges and royalties
2.AISC includes cash costs plus sustaining capital and closure costs

 

Hycroft Mine Project

Page 17

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.16.2Sensitivity Analysis

 

A sensitivity analysis was conducted on the base case NPV and IRR of the project using the following variables: discount rate, head grade, recovery, total operating cost, initial capital cost, as well as silver and gold prices, which were encompassed in a single variable, metal price.

 

As shown in Figure 1-1, the sensitivity analysis revealed that the project is most sensitive to changes in metal price, head grade, and recovery.

 

Figure 1-1: Post-Tax Sensitivity Analysis Results

 

 

 

Note: Metal price, head grade, and recovery series overlap on the above figure. Source: Ausenco, 2026

 

Hycroft Mine Project

Page 18

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

1.17Conclusions

 

Hycroft, in conjunction with IMC, developed the Hycroft deposit block model based on 5,813 drillholes with 516,901 drill intervals amounting to 2,668,616 ft of drilling. The model was assembled by Ryan Rodney, C.P.G. of Hycroft. IMC worked with Hycroft and reviewed the final model. IMC is the qualified firm for the statement of mineral resources with John Marek, P.E., acting as the Engineer of Record.

 

Previous metallurgical testwork programs conducted on the Hycroft sulfide deposit consisted of a series of comminution, flotation, concentrate oxidation, and cyanide leaching tests on mineralized materials, flotation tailings, and oxidized sulfide concentrates.

 

Comminution testwork indicates that the Hycroft mineralization exhibits very high rock competency. Flotation testwork, conducted at a grind sizes of P80 of 85 µm, under acidic conditions (pH of 4.7) using strong non-selective sulfide collectors, demonstrated improved flotation performance. Flotation residence time was identified as a key parameter, and optimized test conditions targeted a mass pull of approximately 22% to 25%, resulting in favorable Au and Ag recoveries.

 

Metallurgical testwork conducted between 2021 and 2025 indicates that the Hycroft sulfide mineralization can be processed using a flotation and POX flowsheet. Flotation optimization resulted in improved gold and silver recoveries, and POX test results support the application of POX followed by hot cure, lime boil, and cyanide leaching for treatment of the pyrite concentrate.

 

The MRE statement was developed using a conventional computer-based block model. Each block was evaluated to determine the net return from the following two processes:

 

ROM cyanide heap leaching and Merrill-Crowe of oxide and some transition materials.
Milling, Flotation, POX, Hot Cure, and Lime Boil followed by Cyanide Leach and Merrill-Crowe of sulfide and some transition materials.

 

The Initial Assessment indicates that the selected development has the potential to support economic extraction of the Hycroft mineral resources based on the study adopted for mining, processing, infrastructure, capital and operating costs, and commodity prices. The economic analysis demonstrates positive project economics. However, project value remains sensitive to key factors including metal prices, metallurgical performance, capital cost estimates, and operating assumptions. Additional metallurgical testwork, engineering refinement, and economic optimization are recommended in the next study phase to reduce uncertainty and improve confidence in project outcomes.

 

1.18Recommendations

 

Recommendations cover the discipline areas of exploration and resource model refinement, mineral processing and metallurgical testing, and overall project configuration to support the evaluation at the PFS level. The total recommended budget estimate to complete the programs is $22,050,000.

 

Hycroft Mine Project

Page 19

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

2Introduction

 

2.1Introduction

 

This technical report summary (TRS) summarizes the results of an initial assessment with an economic analysis (IA-EA) for the Mine located in northwestern Nevada. The work has been prepared at the request of Hycroft Mining Holding Corporation (Hycroft). The TRS follows the requirements and outline as described in the. US Securities and Exchange Commission Code of Federal Regulations, Subpart 229.1300 – Disclosure by Registrants Engaged in Mining operations (S-K 1300). This TRS has been completed by Ausenco Engineering South USA (Ausenco), Hycroft, Independent Mining Consultants, Inc. (IMC) and WestLand Engineering & Environmental Services (WestLand) (collectively, the Report Authors).

 

The updated statement of mineral resources reflects information developed through 2025.

 

This TRS supersedes all previous technical studies, including the TRS filed on EDGAR under Form 8-K on January 21, 2026.

 

The MRE is based on information provided by Hycroft which has been checked and validated wherever possible by IMC. The MRE is based on information provided by Hycroft. IMC, an independent third party with necessary relevant experience, has checked and validated the MRE wherever possible, and is assuming responsibility for the published MRE.

 

2.2Terms of Reference

 

Some sections of this report were published previously as part of a previous technical report summary filed in January 2026 (the 2026 TRS) and are listed below in Section 2.6.2. The sections of these reports which were utilized have been reviewed by both IMC and Ausenco in sufficient detail so that the Qualified Persons (QPs) at IMC and Ausenco have assumed responsibility for this work.

 

Hycroft staff have provided all requested information and have worked with Ausenco, IMC and Westland Engineering in an open and transparent manner throughout the Project period.

 

All units of measurement in this report are in US customary units and currencies are expressed in United States dollars (symbol: US$ or currency: USD), unless otherwise stated. Precious metal grades are presented in units of troy ounces per short ton (oz/ton). The occasional use of non-US customary units will be clearly noted and explained in text when they occur. Tons mean short tons of 2,000 lbs, Ktons means 1,000 short tons.

 

This TRS presents the MRE for the Hycroft Mine (the Mine), and an economic analysis based on pressure oxidation (POX) for sulfide material and Heap Leaching for oxide material. Transitional material may be processed by either process.

 

Hycroft Mine Project

Page 20

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Mineral resources are reported in accordance with SK-1300.

 

2.3Qualified Persons

 

Below is a list of the firms that acted as QPs in the preparation of this TRS:

 

Ausenco Engineering USA South Inc. is responsible for sections 1.1, 1.2, 1.8, 1.11, 1.12, 1.13, 1.15, 1.16, 1.17, 1.18, 2.1-2.4.1, 2.5-2.7, 10, 14-16, 18.1-18.2.3, 18.2.4- 18.2.7, 18.2.8.2-18.3.2, 18.3.4, 18.3.5, 19, 22.1, 22.5, 22.7-22.12, 22.13.1.3, 22.13.1.5-22.13.1.7, 22.13.2.2, 22.13.2.4, 22.13.2.5, 23.1, 23.4, 23.6, 24 and 25.

 

Hycroft is responsible for sections 1.3-1.7, 1.15,3-9, 12, 20, 22.2-22.4, 22.13.1.1, 22.13.1.2, 22.13.2.1, 23.1-23.3, and 24.

 

Independent Mining Consultants, Inc. is responsible for sections 1.9, 1.10, 1.15, 1.18, 2.4.2, 11, 13, 18.2.3, 18.2.8.1, 18.3.1, 18.3.3, 22.6, 22.13.1.4, 22.13.2.3, 23.1, 23.5 and 24.

 

WestLand Engineering & Environmental Services, Inc., is responsible for Section 1.14, 17 and 24.

 

2.4Site Visits and Scope of Personal Inspection

 

2.4.1Site inspection for Jonathan Cooper

 

Ausenco’s QP, Jonathan Cooper, P.Eng., completed a site visit of the Hycroft property from April 8 to 11, 2024 to inspect the existing infrastructure.

 

2.4.2Site inspection for John Marek

 

IMC’s QP, John Marek, P.E., completed a site visit on August 5, 2021, to review the existing core and logs.

 

2.5Effective Dates

 

The overall effective date of this report is May 14, 2026.

 

2.6Information Sources and References

 

2.6.1General

 

The authors sourced information from documents listed in the References section of this report (Section 24).

 

The reports and documents listed in Section 2.6.2 and Section 25 of this Report were also used to support preparation of the TRS.

 

Hycroft Mine Project

Page 21

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

2.6.2Previous Technical Reports

 

Hycroft previously filed the following technical reports:

 

Hycroft Technical Report Summary and Initial Assessment, Nevada, USA. Prepared by Ausenco Engineering South USA Inc for Hycroft Mining Holding Corporation. Effective date: January 21, 2026.

 

Initial Assessment Technical Report Summary; Humboldt and Pershing Counties. Prepared by Ausenco Engineering USA South Inc for Hycroft Mining Holding Corporation. Effective date: March 27, 2023.

 

Technical Report Summary of Initial Assessment on the Hycroft Mine, Nevada, United States of America. Prepared by Ausenco Engineering USA South Inc for Hycroft Mining Holding Corporation, Effective date: February 18, 2022.

 

Hycroft Project Technical Report Summary: Heap Leaching Feasibility Study, Winnemucca, Nevada, USA. Prepared by M3 Engineering & Technology Corp for Hycroft Mining Corporation. Effective date: July 31, 2019.

 

Hycroft completed the following technical report in accordance Canada’s National Instrument 43-101 Standards of Disclosure for Mineral Projects and which are available on the SEDAR website (www.SEDARplus.ca)

 

Hycroft Project NI 43-101 Technical Report: Mill Expansion Feasibility Study, Winnemucca, Nevada, USA. Prepared by M3 Engineering & Technology Corp. for Allied Nevada Gold Corp. Effective date: November 03, 2014.

 

2.7Currency, Units, Abbreviations and Definitions

 

All units of measurement in this report are US customary, and all currencies are expressed in US dollars (symbol: US$; currency: USD) unless otherwise stated. Contained gold metal is expressed as troy ounces (oz), where 1 oz = 31.1035 g. All material tons are expressed as dry tons unless stated otherwise. A list of abbreviations and acronyms is provided in Table 2-1, and units of measurement are listed in Table 2-2.

 

Table 2-1: Abbreviations and Acronyms

 

Abbreviation Description
AAL American Assay Laboratories
AAO atmospheric alkaline oxidation
AAS atomic absorption spectroscopy
AES atomic emission spectrometry
Allied Nevada Allied Nevada Gold Corp.
AR aqua regia
Ag Silver
ALS Auld Lang Syne formation
Au Gold
Ausenco Ausenco Engineering USA South Inc.
Az Azimuth
BLM Bureau of Land Management
BWi bond ball mill work index
CCD counter-current decantation

 

Hycroft Mine Project

Page 22

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Abbreviation Description
CNI Call & Nicholas, Inc.
CWi bond crusher work index
DDH diamond drill hole
DSHA deterministic seismic hazard assessment
EA Environmental Assessment
EDGAR Electronic Data Gathering, Analysis, and Retrieval
FA fire assay
FPCP Final Permanent Closure Plan
G&A general and administration
HLF Heap leach facility
Hycroft Hycroft Mining Holding Corporation
IA initial assessment
ICP inductively coupled plasma
ID2 inverse distance squared
ID3 inverse distance cubed
IMC Independent Mining Consultants, Inc.
IA-EA Initial assessment with economic analysis
IP induced polarization
ISO International Organization for Standardization
LECO Laboratory Equipment Corporation
LOM life of mine
LWIR Longwave Infrared
LTI lost time incident
M3 M3 Engineering and Technology Corp
MRE mineral resource estimate
MS mass spectrometry
MWWAI Michael W. West and Associates Inc.
NDEP Nevada Division of Environmental Protection
NDOW Nevada Department of Wildlife
NDWR Nevada Division of Water Resources
NEPA National Environmental Policy Act
NN nearest neighbor
NSR net smelter return
OES optical emission spectrometry
POX pressure oxidation
QA/QC quality assurance/quality control
QP qualified person (as defined in National Instrument 43-101)
RC reverse circulation drilling

 

Hycroft Mine Project

Page 23

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Abbreviation Description
ROM run-of-mine
RPEE reasonable prospects for economic extraction
RQD rock quality designation
SD standard deviation
SEC Securities and Exchange Commission
SHLF South Heap Leach Facility
S-K 1300 US Securities and Exchange Commission Ruling S-K Subpart 1300
SRK SRK Consulting (US) Inc.
SS sulfide sulfur
SWIR Shortwave Infrared
the Mine Hycroft Mine
TMF tailings management facility
TRIFR Total Recordable Incident Frequency Rate
TRS technical report summary
TSG Tertiary Sulfur Group
USGS United States Geological Survey
USFWS US Fish and Wildlife Service
Westland WestLand Engineering & Environmental Services, Inc.
WSP WSP Global Inc.

 

Table 2-2: Units of Measurement

 

Unit Description
µm micrometer
Ac acre
Asl above sea level
Axb hardness of ore in term of impact breakage, unitless
B billion
Bgs below ground surface
Bton billion short tons
°C Celsius
Cfs cubic feet per second
D day
°F fahrenheit
ft feet
ft/a feet per year
GWh/a gigawatt-hours per year

 

Hycroft Mine Project

Page 24

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unit Description
g gram (unit of weight)
gal gallon
gal/a gallons per year
gal/min gallons per minute
g/ton, gm/ton grams per short ton
Hp horsepower
hr hour
in inch
in/a inches per year
kg kilogram
km kilometer
Km2 Square kilometer
kt kilotonne (1,000 metric tonnes)
ktons kilo short tons
kV kilovolt
kWh/ton kilowatt-hours per ton
lb pound
M million
masl Meters above sea level
mi mile
mi2 square mile
mm millimeters
mph miles per hour
Mt million tonnes
Mtons million short tons
Mtons/a million short tons per year
min. minute
Moz million troy ounces
MW megawatt
oz troy ounce
oz/ton troy ounces per short ton
pcf pounds per cubic foot
ppm parts per million
ppt parts per trillion
psig pressure per square inch
shifts/a shifts per year
t metric tonne (1,000 kg)
t/d tonnes per day
ton short ton (2,000 pounds)
ton/a short tons per year
ton/d short tons per day
tn short ton
TSS total suspended solids
units/a units per year
US$, USD United States dollars (symbol; currency)
US$/a United States dollars per year
US$/ton United States dollars per short ton
wt/wt weight percent
% percent

 

Hycroft Mine Project

Page 25

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

3Property Description

 

3.1Introduction

 

The Mine is an existing gold and silver operation located 54 miles west of Winnemucca in Humboldt County and Pershing County, Nevada, as shown in Figure 3-1. The Site is accessible via Nevada State Route 49 (Jungo Road), an all-weather, unpaved road that is maintained by Humboldt County and Hycroft. A major east–west railway runs immediately adjacent to the property.

 

The Mine property straddles Townships 34, 35, 35½ and 36 north and Ranges 28, 29 and 30 east (MDB&M) with an approximate latitude 40°52’ north and longitude 118°41’ west. The mine is situated on the western flank of the Kamma Mountains on the eastern edge of the Black Rock Desert.

 

The Mine property was consolidated through multiple transactions over several years and is described below. Some unpatented mining claims overlap other Hycroft patented and unpatented mining claims to ensure there are no fractional claim gaps. Existing facilities on site include two administration buildings, a mobile maintenance shop, a light vehicle maintenance shop, a warehouse, an assay laboratory, three heap leach pads – Crofoot, North, and Brimstone, primary, secondary and tertiary crushing systems, two Merrill-Crowe process plants and a refinery. It is considered that existing components of the mine property would be utilized for future development. The Mine operates under permit authorization from the Bureau of Land Management (BLM), Nevada Division of Environmental Protection (NDEP), Nevada Department of Wildlife (NDOW), Nevada Division of Water Resources (NDWR) and County agencies. As of the effective date of this report, Hycroft has approximately 52 employees.

 

3.2Property and Title in Jurisdiction

 

The Mine is owned and managed by Hycroft Resources and Development, LLC, a wholly owned subsidiary of Hycroft Mining Holding Corporation.

 

Hycroft Mine Project

Page 26

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 3-1: Hycroft Mine Location Map

 

 

Source: Nevada Bureau of Mines, 2023

 

3.3Project Ownership

 

The property containing the Mine property consists of 25 private parcels with patented claims totaling approximately 1,855 acres, along with 3,249 unpatented mining claims covering approximately 62,298 acres, for a combined total of approximately 64,000 acres. Some mining claims overlap other Hycroft Mining claims to ensure there are no fractional gaps in mining claim coverage.

 

Hycroft Mine Project

Page 27

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

There are 30 unpatented placer claims, and 3,219 unpatented lode claims are in Humboldt County and Pershing County, Nevada as follows:

 

T36N, R29E, Sections: 28, 32, 33

 

T36N, R30E, Sections: 19, 28-34

 

T35 1/2N, R29E, Sections: 25, 26, 35, 36

 

T35N, R29E, Sections: 1-3, 10-15, 21-28, 31-36

 

T35N, R30E, Sections: 2-10, 15-23, 25-36

 

T34N, R28E, Sections: 1, 2, 11, 12, 13

 

T34N, R29E, Sections: 1-28, 33

 

T34N, R30E, Sections: 2-11, 17-20, 29, 30

 

The 25 private patented claims are located in Humboldt County and Pershing County, Nevada as follows:

 

T35N, R29E, Sections: 24, 25, 35, 36

 

T35N, R30E, Sections: 19, 30, 31

 

T34N, R29E, Sections: 1, 2

 

The mining claim package is depicted in Figure 3-2. Individual mining claims for each township range and section are presented in Appendix A – Patented Claims and Appendix B – Unpatented Claims. The project centroid is defined in the following mine grid coordinates: 51500 N and 20500 E.

 

This point is located central to all mine facilities. The project centroid shall be used to reference all other locations within one mile.

 

Much of the project area is located on un-surveyed public and private land for which the sections, ranges, and townships listed above have been interpolated. Patented claims have been surveyed (Wilson, 2008; Prenn, 2006). The following is a list of land acquisitions/transactions made over the years which constitute the entire Hycroft land claim package and has been assembled through a series of transactions.

 

The Crofoot property and approximately 3,500 acres of claims were acquired by Vista in 1985. The Crofoot property, originally held under lease, is owned by Hycroft. The Crofoot royalty was terminated January 7, 2026. The Lewis property and approximately 8,700 acres of claims were acquired by Vista in early 1987. In 2006, approximately 13,100 acres of additional claims were staked by Vista. These claims are contiguous or proximate to the original Crofoot and Lewis claims.

 

From 2007 through 2015, Hycroft staked additional lode mining claims contiguous to existing Hycroft claims that cover approximately 37,373 acres. Some of these lode claims overlap existing placer claims.

 

Hycroft Mine Project

Page 28

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Payment of annual claim maintenance and holding fees to the BLM and Humboldt and Pershing Counties and payment of annual real property taxes for patented claims in Humboldt and Pershing Counties are made every third quarter (Q3). Payments are current through the 2025–2026 claim years, with US$724,095 paid for 2025–2026. Payment of annual claim maintenance and holding fees and real property taxes are required to continue to hold the Hycroft property in good standing from. BLM annual maintenance fees for claims are due not later than September 1 of each year. Humboldt and Pershing County State annual holding fees beginning September 1 of each year are due no later than November 1 of each year. Annual real property taxes for patented claims in Humboldt and Pershing Counties are due August 31 of the following year.

 

Hycroft controls all surface and mineral rights within the Hycroft MRE area. No further land acquisition is required for the operation of the mine and contemplated processing facilities.

 

Figure 3-3 shows the property layout including site facilities, mine workings, leach pads and waste dumps.

 

3.4Property Agreements

 

Table 3-1 shows the royalty amount and other annual land holding costs.

 

Table 3-1: Hycroft Annual Land Holding Costs

 

Month Due Lessor Type Amount
Monthly Sprott Royalty1 Net Smelter Return Royalty 1.5% NSR
August-October US BLM, Humboldt & Pershing Counties Claim Fees US$724,095

 

Note:

 

1.The Sprott royalty is equal to 1.5% of Net Smelter Returns (NSR) free and clear of withholding taxes or similar taxes.

 

Hycroft Mine Project

Page 29

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 3-2: Claim Map

 

 

Source: Hycroft, 2026

 

Hycroft Mine Project

Page 30

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 3-3: Current Property and Facilities Layout (2025)

 

 

Source: Hycroft, 2026

 

Hycroft Mine Project

Page 31

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

3.5Surface Rights

 

Hycroft controls all surface and mineral rights within the Hycroft MRE area. No further land acquisition is required for the operation of the mine and contemplated processing facilities.

 

3.6Water Rights

 

Hycroft controls 16 separate water-right permits administered by the NDWR. These permits are held in ownership either by Hycroft, or by other private parties and leased to Hycroft. Water resources to support the Mine are controlled under 14 permits in the Black Rock Desert Basin totaling 20,414.9 acre-ft/a (6.65 billion gal/a). Two of these water permits are outside the Black Rock Desert Hydrographic Basin and used to support construction maintenance of Jungo Road with Humboldt County.

 

3.7Liabilities and Encumbrances

 

The consolidated financial statements of Hycroft Mining Holding Corporation set forth its material liabilities as of the date of such financial statements. The assets of Hycroft Mining Holding Corporation and its subsidiaries (collectively, the Company) are subject to encumbrances and obligations, including encumbrances and obligations under and associated with the Sprott Royalty Agreement dated May 29, 2020, by and between the Company and Sprott Private Resource Lending II (Co) Inc.

 

3.8Environmental Considerations

 

Gold production began on the property in 1983 and continued through 1985 when Standard Slag opened the Lewis Mine. There was a brief gap in mining until Hycroft acquired the Lewis Mine and the Crofoot claims and recommenced mining in 1988. Mining operations continued until 1998 when mining was placed on standby due to low metal prices. Process operations continued until 2004 when the property was placed on care and maintenance.

 

Efforts began in 2003 to update the Reclamation Plan, associated cost estimate, and related amount of surety bond posted with the BLM. During the years 2011 and 2012, Hycroft increased collateral account balances to support additional surety bonds for the benefit of the BLM. These additional surety bonds allowed Hycroft to continue operations at the Mine and to expand exploration activities outside of the Mine. In 2011, Hycroft received a reimbursement of US$0.5 million related to reclamation costs that had been paid out.

 

In January 2014, the BLM approved an updated reclamation cost estimate allowing for the phased bonding of the expansion activities. The required bond amount was lowered from US$63 million to US$58.3 million. Hycroft has Surface Management Surety Bonds with insurance companies that meet the financial requirements of the BLM to comply with the total requirement of US$58.3 million as detailed in the September 2013 reclamation cost estimate that requested the phasing of the mill expansion activities. Additionally, Hycroft has posted a bond with the BLM in the amount of US$0.6 million for the adjacent water supply well field, well field monitoring and exploration within the project boundary. Hycroft has US$14.4 million in restricted cash for collateral for these bonds.

 

Hycroft Mine Project

Page 32

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The Hycroft area has been surveyed for surface water resources, including Waters of the United States, biological resources, cultural resources, and groundwater resources. The Golden Eagle (Aquila chrysaetos) is known to occur adjacent to the Hycroft Project. Hycroft is working with the BLM and the US Fish and Wildlife Service (USFWS) in the management of this species.

 

3.9Safety Considerations

 

The operation of the Mine is subject to regulation by the Federal Mine Safety and Health Administration (MSHA) under the Federal Mine Safety and Health Act of 1977 (the Mine Act). MSHA inspects the Mine on a regular basis and issues various citations and orders when it believes a violation has occurred under the Mine Act. In years ending 2024 and 2025, after multiple inspections, MSHA has issued no (0) citations and no (0) “Significant and Substantial” Violations under section 104(a) of the Mine Act. There have been no fines including citations and orders issued to contractors for the year ending May 1, 2026.

 

Hycroft mandated mine safety and health programs include employee and contractor training, risk management, workplace inspection, emergency response, accident investigation, and program auditing with a goal to have zero workplace injuries and occupational illness. In 2023, Hycroft implemented multifunctional workplace inspections and monthly employee engagement sessions. As a result, Hycroft has now operated for three consecutive years at a 0.0 Total Recordable Incident Frequency Rate (TRIFR) and achieved over 1.4 million hours without a Lost Time Incident (LTI). The Mine’s TRIFR per 200,000 man-hours worked including contractors was 0.0 on May 1, 2026.

 

3.10Permitting Considerations

 

The Mine operates under permit authorizations from the BLM, NDEP, NDOW, and NDWR. All operating and environmental permits, approved by the BLM, NDEP, NDOW and NDWR, are in good standing for mining operations. Table 3-2 summarizes the operating permits while Table 3-3 shows the miscellaneous permits for the property.

 

Table 3-2: Hycroft Operating Permits

 

Operating Permits Issuing Agency Number Status
Plan of Operations BLM NVN-064641 Current
Eagle Take Permit USFWS MB90099B-0 Current
Mercury Operating Permit to Construct NDEP - BAPC AP1041-2255 Current
Class I Air Quality Operating Permit to Construct NDEP - BAPC AP1041-2974 Incorporated into the Class II AQOP
Class I Air Quality Operating Permit to Construct NDEP - BAPC AP1041-3344 Incorporated into the Class II AQOP
Class I Air Quality Operating Permit NDEP - BAPC AP1041-2964 Current
Permit to Operate a Public Water System NDEP - BSDW HU-0864-12NTNC Current
Class II Air Quality Permit NDEP - BAPC AP1041-0334.05 Current
Water Pollution Control Permit-Crofoot Project NDEP - BMRR NEV60013 Current
Water Pollution Control Permit-Brimstone Project NDEP - BMRR NEV94114 Current (Application Shield)
Bioremediation Facility Permit NDEP - BMRR GNV041995-HGP15 Superseded by Water Pollution Control Permit
Reclamation Permit NDEP - BMRR 134 In Renewal
Mining General Stormwater Pollution Prevention Permit NDEP - BWPC R300000: MSW-177 Current
Class III Landfill Waiver NDEP - BSMM SWW-346 Current
Artificial Pond Permit (Brimstone Process Ponds) NDOW HU019 – S503626 Current
Artificial Pond Permit (Crofoot Process Ponds) NDOW HU009 – 39469 Current
Artificial Pond Permit (North Process Ponds) NDOW HU022-39468 Current
Artificial Pond Permit (Stage 1 Ponds) NDOW HU022-40377 Current
General Onsite Sewage Disposal System NDEP - BWPC GNEVOSDS09 Current
Dam Safety Permit (Crofoot Process Ponds) NDWR J-273 Current
Dam Safety Permit (Brimstone Leach Event Pond) NDWR J-683 Current
Dam Safety Permit (North Leach Event Ponds) NDWR J-687 Current
Dam Safety Permit (Stage 1 Event Ponds) NDWR   Pending
Hazardous Materials Storage Permit NV State Fire Marshal 8250 Current
Special Use Permit Pershing County SUP 12-04 Current
Special Use Permit Humboldt County UH-12-04 Current

 

Hycroft Mine Project

Page 33

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 3-3: Hycroft Miscellaneous Permits

 

Operating Permits Issuing Agency Number Status
Microwave Repeater; Sec. 29, 30 BLM NVN46292 Current
ROW Wells/Pipeline/Power Line; Sec. 3 BLM NVN46564 Current
ROW 2 Wells/Pipeline/Power Line BLM NVN46959 Current
ROW Road and Waterline (Old Man camp to Lewis) BLM NVN39119 Current
ROW Crofoot pipeline BLM NVN44999 Current
ROW 24 kV Aerial Powerline, Lewis/Floka BLM NVN54893 Current
Kamma Peak Station FCC WNER344 Current
Sulfur Mine Station FCC WNER345 Current
Winnemucca Mountain Station FCC WNER346 Current
Base Station and 45 Mobile Units FCC WNKK336 Current

 

Operating and miscellaneous permits that require annual maintenance fees are shown in Table 3-4. Fixed annual fees are required for storm water and public drinking water system permits based upon the current Nevada regulatory structure. The other annual fees are based on annual mining production, quantities and types of chemicals stored on site, existing and permitted surface disturbance, and the level of actual and permitted air emissions. The variable fees shown are based upon the 2025 operational conditions.

 

Table 3-4: Hycroft Miscellaneous Permits

 

Permit and Fee Description Annual Amount (US$)
Air Quality Operating Permit AP1041-0334.05 Fees are incorporated into title V permit.
Air Quality Operating Permit AP1041-2255 $16,958
Air Quality Operating Permit AP1041-2964 $47,448
Reclamation Permit $37,811
Nevada Radioactive Material License $2,000
Stormwater Permit $1,000
Artificial Pond Permit $31,625
Water Pollution Control Permit NEV94114 $66,000
Water Pollution Control Permit NEV60013 $60,000
State Fire Marshal $210
Public Drinking Water System $391
Septic System Permits $750
Toxic Release Inventory Annual Fee $5,500
Nevada LP-Gas License $795
Total $270,488

 

Hycroft currently holds six Right-of-Way (ROW) leases with two exploration notices with the BLM, as described in Table 3-5 along with fees and renewals.

 

Table 3-5: Right-of-Way Payment and Renewal Schedule

 

ROW Number Annual Payment Amount (estimated) Payment Date Expiration Date
NVN46292 $125 01/01/2025 12/31/2048
NVN46564 $100 01/01/2025 12/31/2046
NVN46959 $610 01/01/2025 In Renewal
NVN39119 $427 01/01/2025 In Renewal
NVN44999 $279 01/01/2025 In Renewal
NVN54893 $200 01/01/2025 In Renewal

 

Hycroft Mine Project

Page 34

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

3.10.1Hycroft Expansion Permitting and Timelines

 

Hycroft submitted a Plan of Operations for an expansion of its heap leach facilities, open pits and waste rock facilities to the BLM in April 2010. A major modification to the State Water Pollution Control Permit was submitted in 2011 for the process components that included engineering design reports from Golder Associates Inc. (Golder). The permit modification was issued in August 2012. An amended Plan of Operations that included a rail spur, open pit expansion and processing complex was submitted to the BLM in August 2012. The BLM determined that an Environmental Assessment (EA) was required, deemed the Plan of Operations complete, and initiated public scoping in December 2012. In March 2013, NV Energy submitted a ROW application for the power line associated with the Hycroft Mill. The BLM determined that this action should be analyzed with the Hycroft EA. Approval was received in December 2014. The permits required to construct and operate the crushing system and to begin mill construction were received in 2012. The air quality permit for operation of a mill was submitted in December 2012, and issuance was received in late 2013.

 

The Plan of Operations for a rail spur, open pit expansion and processing complex, that included a tailings management facility (TMF) and expanded Heap Leach Facility (HLF), was completed in December 2014, with the BLM issuance of the Record of Decision authorizing the proposed action received in January 2015. A major modification to the State Water Pollution Control Permit was submitted in 2011 for the process components that included engineering design reports from Golder. The permit modification was issued in August 2012. All other permits required for the heap leach expansion have been received.

 

A Plan of Operations for an alternate TMF, mining below the water table and expanded facilities was submitted to the BLM in April 2014. The BLM determined that a Supplemental Environmental Impact Statement (SEIS) was required. In October 2019, the BLM issued a record of decision on the SEIS permitting the new TMF location, expanded facilities and deeper pit depths.

 

In December 2010, Hycroft submitted a minor modification to the NDEP which proposed increasing the permitted processing rate from 10 to 12 Mtons/a. This modification was approved in February 2011. In May 2011, Hycroft proposed a major modification to build a new heap leach pad on the site of the closed Lewis pad and to increase the processing rate to 30 Mtons/a. This modification was approved by the NDEP in December 2011. In January of 2012, Hycroft submitted another major modification to construct a heap leach facility on the south extent of the property. The facility was referred to as the South Heap Leach Facility (SHLF). Around the same time, Hycroft submitted a modification proposing to add both a north and south processing area, increasing the Brimstone and Lewis heap leach pads permitted height to 400 ft, and increasing the permitted processing rate to 36 Mtons/a of ore. Both modifications were approved by the NDEP in September 2012. Later, in December 2012, Hycroft submitted a minor modification proposing to add a Merrill-Crowe facility at the North Process Area. NDEP approved this modification in May 2013. In March of 2013, Hycroft submitted another modification to construct a combined heap leach and tailings storage facility (TMF), referred to as the South Processing Complex (SPC), in the same location as the previously permitted SHLF. The SPC uses the new SHLF, constructed in a horseshoe shape, to provide the embankment for the Southwest TMF located in the central portion of the new SHLF. Also, as part of this modification, Hycroft proposed the construction of a mill and related facilities for processing high-grade ore at an approximate throughput of 65,000 tons per day (ton/d) during Phase 1 to a final phase capacity of 132,000 ton/d. Tailings were proposed to be pumped to the TMF at the SPC. These 2013 major modifications were approved by NDEP in August 2017.

 

Hycroft Mine Project

Page 35

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

In September 2014, Hycroft submitted a minor modification to expand the Brimstone-North HLF to the southeast by approximately 80 acres including an additional Event Pond at the existing North Area Merrill-Crowe facility. NDEP approved these minor modifications in March 2015.

 

In April 2019, Hycroft submitted a major modification to construct a new heap leach facility named Hycroft Heap Leach Facility Stage 1 (Stage 1 HLF) north of the North Processing Facility. The Stage 1 HLF will have a storage volume of 29 Mtons and is the first stage of the larger facility (Hycroft HLF) with a storage capacity of 550 Mtons. The ultimate footprint of the Hycroft HLF will cover approximately 925 acres, with the Stage 1 footprint covering approximately 390 acres that includes ponds, channels, and roads. Of this area, 234 acres will be lined with geomembrane along with the HLF pad comprising 204 of these acres. Pregnant solution collected from the pad will be pumped to the existing North Merrill-Crowe process facility for precious metals recovery. The barren solution from the North Merrill-Crowe facility will then be returned to the top of each lift and applied over a designated cell area using a drip and sprinkler system. The major modification was approved by NDEP in July 2020.

 

Currently, Hycroft has all permits required to restart the Mine and recently received the Federal Record of Decision for the Phase II Environmental Impact Statement supporting the life of mine (LOM) pit development.

 

Received Record of Decision from BLM for Environmental Impact Statement (EIS) (10-22-19):

 

Current operating plan is fully permitted

 

Existing operating permits will be amended as new facilities/infrastructure are required

 

EIS allows flexibility:

 

Expanded pits

 

Construction of a TMF to the south of the property, if needed

 

Phase 1 of the new leach pad is permitted

 

Phase 1A of the new leach pad has completed earthwork and high-density polyethylene (HDPE) liner installation. A media cover has been added to protect the porous multimedia protective layer. Collection ponds are in place. Electrical switch gear, instrumentation, and pumps are in storage and will be added during construction restart. No mineralized ore has been added to the pad. Phase 1B of the new leach pad and future phases will be planned for construction from cash flows when needed.

 

Any future expansion activities recommended in this TRS will require multiple federal, state and local permits. The USFWS will require modification to the Golden Eagle Take Permit for the NE TMF and extensions of the South (Vortex) Dump.

 

Hycroft Mine Project

Page 36

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

3.10.2Crofoot Heap Leach Facility Closure

 

In 2023, NDEP asked Hycroft to update the 2017 Final Permanent Closure Plan (FPPC). Hycroft complied with this request and a new FPPC was submitted. The updated plan includes schedule of compliance (SOC) items and incorporates current regulations. There are six items in this plan. SOC Items 1 (Stormwater Controls), 2 (Heap Leach Drain-Down Channel), 3 (Update Monitoring Plan), 4 (Water Quality Evaluation Report), SOC Item 5 (updating FPCP), and 6 (Investigation of trend for Wells SP-23, SP-24, and SP-25). NDEP has accepted and approved SOC Items 2 (Heap Leach Drain-Down Channel) and Item 3 (Update Monitoring Plan). The other items are still under review.

 

Construction of a drain-down collection system was completed in 2012. In 2024 and 2025, Hycroft completed steps to regrade the pad in preparation for closure. Hycroft will continue to re-contour the pad, as necessary for surface water management; apply medium, where required; and reseed the pad to complete the closure process. Hycroft is working in conjunction with NDEP, who will issue the final closure approval letter once these activities are reviewed and accepted.

 

3.11Social License Considerations

 

Social and community impacts have been considered and evaluated in the National Environmental Policy Act (NEPA) process. Potentially affected Native American tribes, tribal organizations, and/or individuals are consulted during the preparation of all plan amendments to advise on proposed projects that may influence cultural sites, resources, and traditional activities. Potential community impacts on the existing population and demographics, income, employment, economy, public finance, housing, community facilities, and community services are also evaluated during NEPA review processes. There are currently no social or community issues that materially impact Hycroft’s ability to extract mineral resources.

 

3.12Project Risks and Uncertainties

 

Timely filings and payments are required to maintain title and rights to claims, water rights and permits. Hycroft maintains processes and controls to ensure timely filings and payments. Changing regulations or failure to make timely filings and payments are significant risks to maintaining environmental access or ability to perform the permitted and authorized work on the property.

 

Hycroft Mine Project

Page 37

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

4Accessibility, Climate, Local Resources, Infrastructure and Physiography

 

4.1Physiography

 

Hycroft is situated on the eastern edge of the Black Rock Desert and on the western flank of the Kamma Mountains between Winnemucca and Gerlach, Nevada. The site is characterized by flat, prehistoric lakebed and well-dissected topography with moderately steep slopes. Topographic relief within the project area is 1,900 feet (ft). The elevation ranges from 4,100 ft above sea level on the western side to 6,000 ft above sea level on the eastern side. The climate in the mine area is arid. Vegetation consists mostly of sagebrush, rabbit brush, and surface grass. Scattered pinon and juniper trees occur along slopes in the higher parts of the property.

 

4.2Accessibility

 

Hycroft and its related facilities are located 54 miles west of Winnemucca, Nevada along State Road No. 49 (Jungo Road), a good quality, unpaved road. Access is also possible from Gerlach via Jungo Road, Imlay or Lovelock by dirt roads intersecting Interstate 80. Winnemucca is a commercial community on Interstate 80 where most of the Mine’s employees are likely to reside. Winnemucca is 164 miles northeast of Reno, Nevada. The town is served by a transcontinental railroad and has a small public airport and there are adequate boarding rooms and dining facilities.

 

4.3Climate

 

The climate at the Mine is classified as arid, with an average precipitation of 7.7 inches per year (in/a), which occurs during the winter and spring months. Winds are generally light with occasional dust or sandstorms, particularly in the spring.

 

Temperatures are moderate during the summer, ranging from 50 °F at night to above 90 °F, and averaging 85 °F to 95 °F during the day. Winter temperatures average 20 °F at night and 40 °F during the day. The average range between the highest and lowest daily temperatures is 30 to 35 °F with strong surface heating during the day and rapid nighttime cooling due to the dry air. Winter nights can drop well below freezing, but daytime highs are usually above freezing. Winter snowpack is light, and snow does not normally present logistical problems. Hycroft has not reported experiencing major delays in production due to inclement weather and is accessible year-round.

 

4.4Local Resources and Infrastructure

 

Existing infrastructure at the Mine consists of the following: a truck shop, a maintenance building, a laboratory, ore crushing facilities, an administration building, and other service-related structures. Power is supplied to the site from nearby power lines that are fed directly from the main power grid and there is a modern communications system including cellular connections. Potable water is sourced from a well located approximately one mile south of the Crofoot Heap. A major east–west railway passes adjacent to the Hycroft property.

 

Hycroft Mine Project

Page 38

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 4-1: Onsite Lab, Admin, Maintenance, Truck Shop, and Warehouse

 

 

Source: Hycroft, 2025

 

Figure 4-2: Crusher and Conveyor Belt Circuit

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 39

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 4-3: North Merrill-Crowe Facility

 

 

Source: Hycroft, 2025

 

Figure 4-4: Stage 1 Heap Leach Pad and Ponds Along Jungo Road

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 40

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The Mine is in a well-known mining jurisdiction near several towns including Winnemucca, Gerlach and Lovelock. The Mine’s workforce primarily lives in Winnemucca (Humboldt County) and Lovelock (Pershing County).

 

Initial surveys indicated that the town of Winnemucca has the required infrastructure (short- and long-term rooming and boarding facilities, dining establishments, shopping, emergency services, schools, etc.) to support the maximum workforce and dependents. The Mine has always been successful in filling positions with qualified mining personnel from all over the country.

 

Currently, the Mine operates three water wells that are located four to five miles west of the mine, and a single potable well. These four production wells are the main sources of water for the mine site. All water rights are within the Black Rock Desert Hydrographic Basin, a recently designated basin. Water rights are shown in Table 4-1.

 

Hycroft controls sufficient land position and water rights to support its planned facilities and process water demands.

 

Table 4-1: Hycroft Water Wells and Permitted Yearly Consumption

 

Application No. Permit Diversion Limit (cfs) Annual Appropriation Limit (acre-ft) Point of Division
81228 0.4 14.83 T34N R29E S3
81226 3.2 724.79 T35N R29E S31
81225 3.2 303.43 T35N R29E S31
81227 2.0 1,448 T35N R29E S31
81224 2.0 1,448 T34N R28E S1
81408 5.4 3,890 T35N R29E S31
81409 5.4 3,890 T35N R29E S31
84477 0.3 177.9 T35N R29E S31
82274 10 4,096 T35N R29E S31
82355 3.3 2,050 T35N R29E S31
82356 5.6 3,415 T34N R28E S1
Total 40.8 21,457.95 -

 

A fully developed project will include plans to develop access and haul roads to new processing facilities, a TMF, and additional waste rock storage dumps. Furthermore, the development of a rail spur is recommended off the existing rail line for the receipt of grinding media, fuel, reagents, and other supplies.

 

A power study needs to be conducted to upgrade the existing power at the site to support a fully developed processing plant.

 

4.5Seismicity

 

In 2012, Michael W. West and Associates Inc. (MWWAI) completed a review of the Hycroft deterministic seismic hazard assessment (DSHA). MWWAI concluded that historical seismicity in the vicinity of the site is low to moderate with no relation to mapped faults. No faults in the project area are classified as “active/capable” based on an unequivocal association of instrumentally recorded earthquakes in the last approximately 50 years. MWWAI stated that a comparison of the United States Geological Survey (USGS) national probabilistic seismic hazard model to deterministic and probabilistic floating earthquake peak ground accelerations (PGAs) show reasonable agreement. MWWAI recommends the use of the deterministic and probabilistic PGAs presented in the DSHA.

 

Hycroft Mine Project

Page 41

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

5History

 

5.1Regional History

 

The earliest recorded mining in the Sulfur District, where the Mine is located, began in the late 1800s following the discovery of significant native sulfur deposits (Couch and Carpenter, 1943; Wilden, 1964). Mining of native sulfur was sporadic from 1900 to 1950 with over 181,488 tons of sulfur ore, grading approximately 20-35% sulfur, mined and milled (McLean, 1991).

 

In addition to sulfur, high-grade Ag mineralization, consisting of nearly pure seams of cerargyrite (AgCl), was discovered in 1908 at Camel Hill (Vandenburg, 1938). Assays up to 3,439 oz/ton Ag and 0.362 oz/ton Au were reported (Jones, 1921). Ag mining ceased in 1912 with an estimated 165,375 Ag ounces produced. Minor Ag mining also occurred along the East Fault at the Snyder Adit, and Ag samples as high as 66 oz/ton (Friberg, 1980) and 29 oz/ton (Bates, 2001) were reported.

 

During the First World War (1914 to 1918), three 6 to 8 ft wide veins of nearly pure alunite were mined in the southern part of the Sulfur District (Clark, 1918). In 1931, several hundred tons of alunite were mined as a soil additive (Fulton & Smith, 1932). Vandenburg estimated that 454 tons of alunite was shipped to the west coast to be used as fertilizer (Vandenburg, 1938). From 1941 to 1943, cinnabar was mined from small pits in the exposed acid leach zone (Bailey, 1944). Total mercury production during this period is estimated at 1,900 lbs. (McLean, 1991).

 

5.2Property Exploration History

 

In 1966, the Great American Minerals Company began extensive exploration for native sulfur in the regional area of the Mine. Approximately 200 shallow holes were drilled, and numerous trenches were dug (Friberg, 1980). In 1974, Duval drilled 20 holes on the property in search of a Frasch-type sulfur deposit (Wallace, 1980). Duval found no evidence of a sulfur deposit at depth but did report elevated Au and Ag values. Duval drilled two core holes (DC-1 and DC-2) and 18 rotary holes (DR-3 through 20) (Ware, 1989).

 

In 1977, the Cordex Syndicate mapped and rock-chip sampled the property. They concluded that there was potential for bulk tonnage as a low-grade precious metal deposit. In 1978, Homestake became interested in the property, recognizing similarities with the McLaughlin hot springs deposit in California. Homestake completed surface sampling and exploration drilling during 1981-1982, and although successful in defining an oxide gold/silver mineral deposit, they forfeited the property in 1982.

 

5.3Production

 

Mining at the Mine began in 1983 with a small heap leach operation known as the Lewis Mine. In 1987, Vista acquired the Lewis Mine and in 1988, they acquired the Crofoot Mine. The Mine was comprised of various open pits on the property (e.g., the Bay, South Central, Boneyard, Gap and Historic Cut-4 pits along the Central Zone and Brimstone) and produced approximately 1.2 million ounces (Moz) of Au and 2.5 Moz of Ag from 1983 to December 1998 when the operations were suspended due to low Au prices at the time (<$300/oz). An additional 58,700 ounces of Au were produced from the leaching and rinsing of the heap leach pads from 1999 through 2004, after the mine had been placed on a care and maintenance program. The remaining leasehold interest in the Lewis property was purchased by Vista in December 2005, in consideration of the US$5.1 M payment, resulting in the elimination of the 5% NSR royalty on Au and 7.5% NSR royalty on Ag.

 

Hycroft Mine Project

Page 42

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Further information on the production history of the Mine comes from Hycroft’s internal documents. Ore from the Lewis Mine was crushed and stacked on the Lewis leach pads in the north-central part of the Sulfur District. Approximately 259.2 Mtons of ore with a gold grade averaging 0.014 oz/ton was mined from 1983 to 2019, beginning with ore mined from the Lewis Mine, followed by ore mined from the Bay, South Central, Boneyard, Gap and Historic Cut-4 pits, and finally the north end of the Brimstone pit, producing over 2.082 Moz of Au.

 

The Crofoot leach pad (Pads 1 and 2) were constructed in 1987, and Pad 3 in 1992. Ore was placed on Pad 1 from 1988 to 1997, on Pad 2 from 1989 to 1997, and on Pad 3 from 1993 to 1997. Solutions from these pads were treated in the Crofoot Merrill-Crowe plant located on the northeast side of Pad 1.

 

Production from the Brimstone pit was placed on the Brimstone pad (Pads 4 and 5) as run-of-mine (ROM). Pad 4, constructed just south of the old Lewis pad, was completed in 1996. Loading of Pads 4 and 5 commenced in October 1996 and July 1997, respectively. A 2,800 gallon per minute (gal/min) Merrill-Crowe leach solution plant (the Brimstone Plant) was completed and put into operation in February 1997. The plant treated solutions from Pad 4. Pad 5 solutions were treated in the older Crofoot plant.

 

In May 2007, the Nevada-based holdings of Vista were spun out into Allied Nevada Gold Corp. The Mine was included as part of the transfer of ownership allowing Allied Nevada to explore, expand, and develop the resources at Hycroft.

 

In September 2007, Allied Nevada’s Board of Directors approved the reactivation of the Mine, and a year later in December 2008, the Mine had produced its first doré which was shipped to an offsite refinery for final processing, yielding Au and Ag bullion. Allied Nevada received a construction permit for the Brimstone Refinery in 2008, and construction was completed in June of 2009. By the end of 2009, the Mine was achieving the forecasted ore production capacity. In 2010, the mine began an expansion program which included the construction of a 21,000 gal/min Merrill-Crowe processing plant, a three-stage crushing facility and upgrades to their solution pumping capacity. With the construction of the North leach pad complete in 2013, the total leach pad surface area at the Mine site had increased to over 20 million ft2 including the Brimstone and Lewis leach pads. Allied Nevada filed for bankruptcy on March 10, 2015, and active mining ceased in June 2015 due to low metal prices. Leaching of the mined ore continuing through 2018.

 

On October 22, 2015, Allied Nevada emerged from its financial restructuring and changed its name to Hycroft Mining Corporation. On May 29, 2020, Hycroft Mining Corporation completed a business combination with a publicly trade special purpose acquisition company (SPAC). Following the closing of the transaction, the SPAC changed its name to Hycroft Mining Holding Corporation.

 

In late 2018, Hycroft began construction of Phase 1 of the Jungo Leach Pad to expand process capacity for anticipated heap leach material. Additionally, Hycroft began preparing the mine for a restart. Active mining began again in April 2019 to November 10, 2021, transition ore was placed on the existing leach pads. Sulfide materials, when encountered during active mining, were set aside for future processing.

 

In November 2021, Hycroft suspended mining operations to refocus resources on metallurgical test work and exploration. Final construction of Phase 1 of the Jungo Leach Pad was suspended, and protective media cover material was placed on the multimedia liner. Electrical, instrumentation, and pumping equipment were placed in covered storage for a future restart.

 

The annual sales produced from the Mine’s heap leach operations over years 2019 through 2022 were 107,258 oz Au and 629,904 oz Ag. There have been no gold or silver commodity sales since 2022.

 

Hycroft Mine Project

Page 43

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

6Geological Setting, Mineralization, and Deposit

 

6.1Geological Setting

 

Section 6 has been written and updated by Alex Davidson, Vice-President of Exploration of Hycroft Resources and Development LLC and approved by IMC (Independent Mining Consultants). IMC is a third-party consulting firm with people who can act as a qualified person for this section.

 

The Hycroft deposit is a low-sulfidation, epithermal, hot springs system that contains Au and Ag mineralization. Radiometric dating of adularia (potassium feldspar) indicate that the main phase of Au and Ag mineralization formed approximately four million years ago (Ebert, S.W., & Rye, R.O. (1997)) when hydrothermal fluids were fed upward along high angle, normal faults. Low-grade Au and Ag mineralization was co-deposited with silica and potassium feldspar throughout porous rock types.

 

A subsequent drop in permeability, due to sealing of the system, led to over pressuring and subsequent repeated hydrothermal brecciation. Additional precious metal mineralization was deposited during this event as breccia zones, veins, and sulfide flooding.

 

Au and Ag mineralization was followed (0.7 to 4.0 million years ago, (Ebert, S.W., & Rye, R.O. (1997)) by an intense event of high sulfidation acid leaching of the mineralized volcanic rocks coincident with a regional water table drop. This allowed steam heated sulfur gases to condense into sulfuric acid and leach the upper portion of the mineralized rocks.

 

Oxidation of sulfide mineralization occurs to variable depths over the deposit, depending upon proximity to faults, extent of acid leaching, and depth to water table. Sulfide content through the deposit is variable from 0 to 20%.

 

6.1.1Regional Geology

 

The Mine is located on the western flank of the Kamma Mountains in the Basin and Range physiographic province of northwestern Nevada. The Kamma Mountains were formed during Miocene to Quaternary Epoch from the uplift of Jurassic basement rock and emplacement of Tertiary volcanic and sedimentary rocks. The stratigraphy along the western flank of the range is down dropped to the west, along a series of north to northeast striking normal faults. These faults served as conduits of hydrothermal fluids that deposited the Hycroft mineralization.

 

6.1.2Local Geology

 

The Hycroft property consists of Tertiary to recent age, fault-controlled, low-sulfidation Au zones that occur over an area measuring approximately three miles in a north–south direction by two miles in an east–west direction. The zones are hosted in volcanic rock eruptive breccias, flows and conglomerates associated with the Tertiary Kamma Volcanics and sand to conglomeratic debris flows associated with the Tertiary Sulfur Group (TSG).

 

Hycroft Mine Project

Page 44

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Younger rocks at the mine are Tertiary conglomerate, siltstone and fanglomerate of the Sulfur Group (locally termed Camel Conglomerate). These rocks are comprised of sediment eroded from the underlying Kamma Volcanics and Jurassic Auld Lang Syne (ALS) Formation. The Sulfur Group is divided into three main units: a clast-supported coarse conglomerate, a matrix-supported conglomerate, and an underlying tuffaceous lake sediment. This unit outcrops throughout the mine site with increasing thickness to the west.

 

The older Kamma Group is exposed throughout the Kamma Mountains east of the Central Fault. It underlies the Camel Conglomerate (TCM). The volcanic package is comprised of siliceous to intermediate tuffs, coarse grained volcanic clastics, fanglomerates, eruption breccias and massive to flow banded rhyolites.

 

The Jurassic ALS Formation underlies the Kamma volcanic package. This formation consists of a thin bedded to laminated siltstone, with calcite cementing. ALS is exposed approximately three miles east of the deposit and is encountered only at depth in drilling at Hycroft. A generalized stratigraphic column for the Hycroft deposit area is presented in Figure 6-1. This stratigraphic column illustrates the formations of volcanic origin that host the deposit with notations for lithologies in each formation. The TCM of the TSG has been broken out as a separate rock, in addition to those shown in Figure 6-1. The sub-group of the TSG references lakebed sediments that are distinct from the TCM.

 

Figure 6-1: Stratigraphic Column for Hycroft Deposit Area

 

 

Source: SRK, 2019

 

Six major north-northeast trending, west dipping, normal fault zones appear to broadly control the distribution of alteration as shown in Figure 6-2. From west to east, these fault zones are referred to as the Range, West Splay, Central, Break, Albert, and East Faults. These major structures down-drop stratigraphy and affect the distribution of alteration and mineralization. A post-mineral basin bounding fault (not pictured) appears to border TCM and the adjacent Pleistocene Lahontan Lake sediments in the Black Rock Desert. Based on geophysics, this structure is approximately one to two miles west of the mine site. There are several east–west trending structures that appear to provide post-mineral offset to the deposit. These form a series of horst and grabens within the deposit footprint.

 

Figure 6-2 is a mine grid north-looking section through the Mine showing structures and volcanic rock stratigraphy. There are also several other parallel fault zones that may have a significant impact on the localization of mineralization. The depth of oxide and mixed sulfide/oxide Au and Ag mineralization vary considerably throughout the area. Alteration at the deposit is dominated by acid leaching, silicification, argilization, and propylitization.

 

Figure 6-2: Simplified East–West Cross Section Through the Hycroft Mine – Section 40600 N

 

 

Source: Hycroft, 2025

 

6.2Mineralization and Alteration

 

The Hycroft deposit is broken into five major zones based on geology, mineralization, and alteration. These include Brimstone, Vortex, Central, Bay, and Camel. The boundaries are typically major faults, namely Break, East, and Ramp Faults. Continuity is structurally controlled and disseminated in each of these areas.

 

Hycroft Mine Project

Page 45

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Detailed geologic work by previous owners at Hycroft identified several hydrothermal alteration events. However, for resource estimation purposes, the following four alteration types have been interpreted and assigned to the block model:

 

Acid Leach – Associated with the upper portion of the epithermal vent. Native Sulfur is common in this area and the original protolith has been obliterated with a white clay alteration.

 

Propylitic – Propylitic altered material is generally found in the volcanic rocks of the Kamma Mountains. Although it is occasionally interpreted within the mineralized zone of the deposit.

 

Argillic – A pervasive alteration of both TCMs and the Kamma Volcanics clay minerals have replaced the original potassium feldspars and other minerals.

 

Silicic – Silica flooding is associated with the mineralization processes at Hycroft.

 

Propylitic is generally barren or nearly so. It has been lumped with the argillic alteration units for grade estimation and assignment.

 

Silicic alteration generally has better grade than the surrounding argillic and is mechanically more robust.

 

Oxidation has occurred across the deposit to variable depth depending on the structural preparation and available acidic ground water. The oxidized material has been the historical ore for heap leaching at Hycroft. This study includes ROM leaching of low-grade mineralization and flotation of mineralization with sufficient pyrite and other sulfides to generate a gold and silver rich concentrate for further processing.

 

6.2.1Brimstone

 

Brimstone is approximately ¾ mile wide (E-W) and approximately 1 mile long (N-S) and sits between the East Fault and Albert Fault. The stratigraphy (depth) at Brimstone includes up to 100 ft of alluvium, underlain by Camel Conglomerate rocks (0 ft to 400 ft), and Kamma volcanic rocks. ALS has been drilled at depth and is in fault contact (East Fault) as well as unconformably with the overlying Kamma Volcanics. The Brimstone deposit is hosted primarily by Kamma volcanic rocks in the hanging wall of the East Fault. The volcanic rocks are principally eruption breccias, tuffs, rhyolites, and volcanic rocks proximal to vents, and overlie deformed and metamorphosed shale, sandstone, and siltstone of the ALS group.

 

At Brimstone, the East Fault is a north-northeast striking, west dipping, normal fault with repeated episodes of movement, including approximately 150 to 200 ft of alluvial offset. Where exposed in the Brimstone pit, the fault clearly shows steep normal movement, with slickensides that plunge 80° to 85°. At depth the fault shallows to 45° to 60° and may merge with the Central and Break Faults. The fault may have originally served as a conduit to hydrothermal fluids.

 

North of the Brimstone deposit, the east–west trending Ramp Fault appears to down-drop favorable stratigraphy. Condemnation drilling of the leach pad to the north has shown only local zones of weak Au and Ag mineralization. To the south, the Brimstone Zone transitions to the Vortex Zone, with no apparent change in stratigraphy, but changes to alteration zonation.

 

Hycroft Mine Project

Page 46

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Host rocks were highly altered by at least four phases of alteration. The relatively porous conglomerate and breccias were preferentially acid leached by late stage steaming hydrothermal acid vapors. Acid leach alteration extends to depths of 700 ft in some areas of the Brimstone deposit indicating that the water table was present below the base of the acid leached zone. A siliceous layer (basal acid leach), up to tens of feet thick, occurs at the base of the acid leach material. Underlying the acid leaching is a layer of hydrothermal clay alteration, followed by silica potassium feldspar alteration. Pervasive silicification, veining and hydrothermal brecciation are generally found in the rhyolites and breccias.

 

Zones of silicification of varying thickness, oriented parallel to the East Fault, are present in the footwall zone. Alteration extends approximately 1,000 ft from the fault into the footwall, with pervasive silicification and quartz veining dominant.

 

Au and Ag are spatially associated with fracture and breccia-controlled chalcedony sulfide mineralization. A subsequent acid alteration event produced the current distribution of oxidized and transition sulfide/oxide ore. The lower acid leach material hosts Au and Ag mineralization, as does the underlying silicified and veined volcanics.

 

Drilling through 2024 has shown that high-grade silver mineralization hosted in quartz/clay veins extends to a depth of over 1,800 ft in the Brimstone Zone. The high-grade silver veins have little to no association with gold, indicating gold and silver were deposited at different times. Petrography with support from geochemistry indicates some of the high-grade silver mineralization is potentially related to an intermediate sulfidation system and proximal to a magmatic fluid source. Mineralization thickness of the high-grade is highly variable but generally less than 100 ft thick (true width) and the broader overall Brimstone mineralization is 200 to 1,500 ft thick, and both mineralization styles remain open to the west toward the Break Fault. The main phase of mineralization in the high-grade silver is naumannite and argentotetrahedrite with inclusions of chalcopyrite, clausthite, and galena.

 

6.2.2Vortex

 

Vortex area is approximately ¾ mile wide (E-W) and approximately 1 mile long (N-S) and sits east of the Albert Fault. The stratigraphy (depth) in the Vortex Zone is correlative with those at the Brimstone Zone immediately to the north. Camel Conglomerate is underlain by tuffs, volcanic clastics, fanglomerates, and rhyolites of the Kamma Volcanics. The ALS is present in the footwall of the East Fault and appears to be in stratigraphic contact with the Kamma Volcanics.

 

The upper elevation at Vortex is hydrothermally clay (kaolinite) altered. Acid leaching is less prominent than in Brimstone and is focused primarily along the East Fault. Strong silicification has been observed to depths greater than 1,500 ft. At least four hydrothermal mineralizing events are present, as evidenced by crosscutting vein and breccia relationships. Propylitic and/or clay alteration extends outboard of the silicification. The alteration within the Brimstone pit is depicted in Figure 6-3.

 

The mineralization at Vortex is of both vein and disseminated types, with brecciated and altered rhyolite rocks and volcanic clastics acting as favorable hosts. In addition to Au mineralization, high-grade Ag has been encountered at Vortex; with values ranging from 10 to 647 oz/ton. The predominant Ag minerals are miargyrite, and selenostephanite with inclusions of argentotetrahedrite, naumannite occurring both in veins, disseminated and coarse grains along fractures. Petrography and geochemistry support the low-sulfidation epithermal style of mineralization.

 

Hycroft Mine Project

Page 47

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Oxide mineralization is present at a depth of approximately 500 ft bgs, with sulfide mineralization extending to 2,500 ft bgs. Mineralization thickness (true width) is 1,000 to 1,800 ft thick. Banded quartz veins with both high- grade Ag and Au have been noted in core. Drilling to date indicates that the high-grade zones are both high angle banded quartz veins and a more extensive flat lying, massive quartz zone containing visible pyrargyrite and miargyrite.

 

Figure 6-3: Vortex Alteration Cross-Section – 40600 N

 

 

Source: Hycroft, 2025

 

6.2.3Bay

 

Bay area is approximately ¾ mile wide (E-W) and approximately 1.5 miles long (N-S) and sits north of the Camel Pit. Mineralization in Bay is hosted by gentle, west dipping Camel Conglomerate. Both clast-supported and matrix-supported conglomerate rocks host mineralization. The basal rock type is tuffaceous lake sediments, composed of fine-grained clay with minor layers of gravel and conglomerate extending to a depth greater than 1,100 ft. Mineralization is primarily bedding controlled, with the Range and Central Faults as the main feeders. The Break Fault may also have zoning controls but is poorly drilled in this zone. Mineralized siliceous hot spring sinters have been historically mined indicating that this deposit represents the upper-most levels of a hot spring hydrothermal system.

 

Hycroft Mine Project

Page 48

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The predominant alteration type at Bay is silicification. Acid leach alteration in the area is relatively minor and occurs along high angle structures as seen in Figure 6-4. Clay alteration of the underlying lacustrine sediments is also noted in limited drillholes and is Illite-smectite dominated. Strong oxidation is present in the upper portion of the silicified zone.

 

Au and Ag mineralization is associated with flat lying Camel Conglomerate, above the lacustrine lake sediments. Mineralization thickness (true width) is 20 to 250 ft thick at Bay and 50 to 300 ft thick at Boneyard. This zone transitions into the upper zone of mineralization at Central. Bay and Boneyard remain open to the north and east.

 

Figure 6-4: Bay Geologic Cross-Section at 50300-N

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 49

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

6.2.4Central

 

Central area is approximately ½ mile wide (E-W) and approximately 1 mile long (N-S) and sits between Central Fault and West Splay Fault. Central geology is similar in nature to that of Bay, with mineralization and alteration fed by high angle faults and fractures, with dominant lateral fluid flow through the porous conglomerate rocks of the Sulfur Group. Camel Conglomerate units are underlain by lacustrine sediments. However, the lacustrine units thin dramatically to the south, with less than 50 ft of the material noted south of Historic Cut-4 Pit.

 

The Central fault movement is unknown, but extends at least 2,000 ft, with recent reactivation in the quaternary (50 to 150 ft), as demonstrated by offset in the alluvium. The Range Fault to the west may provide an additional boundary, although drill data is limited at this time. Alteration along the Central Zone is consistent with the alteration found at Bay. Acid leach alteration is stronger and more widespread than at Bay and is extensive in the southern portion of the zone. The acid leaching overlies silicified conglomerate rocks, except along the immediate trace of the Central Fault where silicification dominates as the alteration type as seen in Figure 6-4. Acid leach material has mostly been mined through and very little still exists in this area. Oxidation extends downward approximately 400 ft. Underlying the silicification and acid leaching are illite-smectite clay altered and clay dominant lacustrine sediments. Hot spring sinter deposits have not been observed.

 

Au and Ag mineralization is associated with favorable stratigraphic horizons in the Camel Conglomerate, with an upper and lower zone noted in drilling, separated by a north–south striking, east dipping clay layer. Mineralization remains open to the west, past the Range Fault, and at depth (>1,400 ft). Mineralization thickness (true width) in the upper zone is 50 to 300 ft thick, while the lower zone ranges from 300 to 1,200 ft thick and remains open at depth. The mineralization zone is contiguous to the Vortex and Brimstone Zones to the east, and the Camel Hill/ Historic Cut-5 Pit zones to the south.

 

6.2.5Camel

 

Camel area is approximately ¾ mile wide (E-W) and approximately ½ mile long (N-S). Conglomerate is the dominant lithology at Camel. The conglomerates appear to extend to depth in this zone, with only thin lake sediments drilled to date. The lack of lake sediments can be attributed to either the Camel Fault or facies changes along a shoreline. The Camel Fault is an east–west trending fault, with down-drop to the south, which is presently poorly defined by drilling.

 

Alteration in the Camel area is predominantly comprised of silicification and clay alteration. Hydrothermal clays, overlying silicified conglomerate rocks, and basal illite-smectite clay altered rocks are present. Acid leaching in the area is relatively minor, especially with respect to the intensity and amount in the Central Zone area immediately to the northeast.

 

Mineralization in Camel is hosted by conglomerate rocks and occurs as both disseminated Au and Ag associated with pyrite and marcasite, and higher-grade veins, including Ag bearing pyrargyrite veins. Mineralization thickness (true width) is 200–1,100 ft thick, extends to depths greater than 1,400 ft, and remains open at depth. Oxidation extends to depths greater than 200 ft and an area of intense oxidized mordenite alteration is present between the Historic Cut-5 Pit and Camel. Mineralization remains open to the south, west and at depth. Mineralization is also open to the west of Camel and to the south towards Hades Fault.

 

Hycroft Mine Project

Page 50

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

6.3Deposit Types

 

The Hycroft deposit is generally an epithermal, low-sulfidation hot springs deposit (Figure 6-5). Au and Ag mineralization are noted as both disseminated and vein controlled.

 

Figure 6-5: Generalized Epithermal Diagram

 

 

Source: Buchanan, 1981 and modified by Corbett Greg and Leach, Terry, 1998

 

Hycroft Mine Project

Page 51

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

7Exploration

 

7.1Exploration

 

Section 7 has been written and updated by Alex Davidson, Vice President of Exploration of Hycroft and approved by IMC. IMC is a third-party consulting firm with people who can act as a qualified person for this section. Hycroft has conducted geophysical surveys, soil and rock-chip sampling programs, field mapping, historical data compilation, and regional reconnaissance at the site. These efforts are designed to improve the understanding of known mineralization, as well as provide data for further exploration of the greater property position.

 

7.2Geological Mapping

 

Field mapping was historically and is currently carried out in all active mine areas. Mapping focuses on structure, bedding, joints, lithology, and alteration. The near mine data is incorporated into the three-dimensional geology model, while the regional work is focused on defining exploration targets for future drilling. A regional geology map covering the land position was compiled in 2012. Regional exploration data from Homestake, LAC Minerals, USX, HRDI, and others has been compiled from both in-house and public data sources. Approximately 250 drillholes, various soil and rock chip locations and results, and various field maps have been identified at present.

 

7.3Geophysics

 

The land position has been surveyed with both gravity and induced polarity (IP) geophysical techniques by Hycroft. The current ground-based gravity survey covers approximately 130 square miles, centered on the mine site. Gravity indicates several structural features and density changes that offer potential exploration targets.

 

Ground induced polarization (IP) surveys were run over the mine site and Vortex in 2007 and extended outward in 2011 to cover approximately 24 square miles. The survey results focus on chargeability anomalies, that potentially identify sulfide material (> approximately 1.5%) at depth, and resistivity anomalies, that potentially identify silicification at depth. Results have identified and confirm additional exploration targets suggested by the other geophysical methods.

 

An additional 56-line kilometers of IP were collected in four phases during the 2023 and 2024 exploration seasons which extended several of the lines from the previous surveys. The data from the new IP lines were incorporated into Voxel models which included historical IP data. The results from the survey focused on both chargeability and resistivity anomalies.

 

In 2022 a hyperspectral imaging flyover of the Hycroft was conducted by SpecTIR Advanced Hyperspectral Solutions. Both longwave infrared (LWIR) and shortwave infrared (SWIR) imaging were collected with the intent of helping identify key minerals on the surface to focus reconnaissance mapping and soils programs. Total flyover grid was 1,200 km2.

 

Hycroft Mine Project

Page 52

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

7.4Soil Sampling

 

A soil sampling grid was conducted over the Vortex and Brimstone areas historically (1,797 samples) and was extended approximately 5,200 ft north and 29,600 ft south of the mine in 2011–2012 (1,834 samples). The soil sampling program was conducted primarily along the East Fault exposure, which is a primary ore-controlling feature at Vortex and Brimstone. Results, using Au, Ag, arsenic, and antimony, indicate potential exploration targets to the south of the Vortex area. At present this work has identified several target areas. Au values range from 0 to 0.027 oz/ton, while Ag values range from 0 to 3.7 oz/ton. Soil samples are taken on an evenly spaced grid (approximate 100-meter grid spacing), and screened for coarse material and wind-blown material, resulting in a fraction between 2 mm and 180 µm being prepped for analysis. These samples are considered representative of local soil geochemistry and are used to guide the regional exploration effort.

 

7.5Rock-Chip Sampling

 

Rock-chip sampling has been conducted both historically in the active mine area, and on a regional basis (2007–present). A database of 2,416 samples has been compiled, covering the greater land position. Using Au, Ag, arsenic, and other elements, exploration targets have been developed both north and south of the current mine. Rock-chip samples have been taken on most outcrops, with a focus on alteration and potential mineralization. These samples are used as a guide to exploration and are point samples only.

 

An additional 206 rock-chip samples were collected in the 2023 and 2024 exploration season within the mine area and immediately east of the mine area. The gold values include 22 samples greater than 0.03 oz/ton Au, and two samples greater than 0.23 oz/ton Au. These samples were collected in mineralized structures in the Bay Pit highwall. Silver values include 16 samples greater than 0.58 oz/ton Ag and two samples greater than 5.9 oz/ton Ag (maximum 15.2 oz/ton Ag). These samples were collected in mineralized structures in the Brimstone pit highwall and were not collected on a grid.

 

7.6Drilling

 

7.6.1Introduction

 

The Hycroft drill history covers the period from 1982 through 2024 and includes 6,024 holes, representing 2,814,546 ft of drilling. Some of those holes are water wells or are outside the resource model area and were not applied to MRE. The drillhole collar locations are shown in Figure 7-1. At this time, there are 5,813 drillholes in the resource model area of which 188 have been drilled to define stockpiles or the Crofoot leach pad. Section 11 provides a more detailed breakdown of the amount of drilling and assaying used in the mineral resource modeling.

 

Hycroft Mine Project

Page 53

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

7.6.2Exploration Drilling

 

Exploration drilling was started in 1974 by Duval Corporation, which was evaluating the property for a Frasch-type sulfur deposit and the copper potential. Although native sulfur appeared to be limited to the acid leach zone, Au and Ag mineralization was discovered at depth, with the deepest hole completed to 2,000 ft. Duval concluded that the property did not have large scale sulfur potential. Twenty drillholes (9,726 ft) were completed on the project. Hycroft does not have access to the Duval Corporation drilling data and therefore is not a part of the Hycroft database.

 

Homestake (1982), using their McLaughlin deposit as a model, completed 96 RC drillholes totaling 16,537 ft, primarily in the Bay and Boneyard areas. Shallow oxide Au mineralization was discovered, but Homestake declined the opportunity. Crofoot and American Slag then proceeded to acquire the property rights and initiated small-scale oxide heap leach mining at Central and Bay in 1983. Homestake also completed 8 core holes during this timeframe, but collar location data has not been located.

 

Hycroft gained control of the district in 1985 and drilled 3,212 exploration holes, totaling 965,552 ft, between 1985 and 1999. The bulk of this drilling was shallow and focused on oxide Au mineralization at Central, Bay and Brimstone.

 

In 2005, Canyon Resources completed 33 drillholes totaling 13,275 ft of RC drilling. These were completed primarily in the Brimstone pit area.

 

Hycroft commenced systematic exploration and resource development drilling starting in 2006. Drilling was focused on oxide resource delineation, sulfide resource definition, sulfide exploration, condemnation drilling for facilities, Ag data and both geotechnical and metallurgical core samples. Between late-2006 and August 31, 2016, Hycroft completed 1,970 exploration holes, totaling approximately 1.45 million ft.

 

A combination of rotary, RC and core drilling techniques has been utilized to verify the nature and extent of mineralization. Most samples have been collected using RC drilling methods on 5 ft sample intervals. RC drilling utilizes 4.5- to 5.5” tooling. Deeper drilling is conducted with diamond drilling, using PQ, HQ and NQ tooling. This practice continued through 2013. Since 2013, an RC drilling program was completed in 2014, and a metallurgical core program with six drillholes was completed in 2017. Various protocols applied to drilling by Hycroft are consistent with industry standards and the resulting data is of good quality for use in the Hycroft model. Shallow drillholes to sample heap material were completed with sonic coring. The 2018 sonic drilling program was limited to 56 vertical holes in sulfide stockpiles and did not include in-situ alluvium or bedrock material. While these were not used for interpolation of in-situ rock, they were applied to estimate grades in fill material.

 

During 2021 through 2024, Hycroft drilled 260 holes, 105 in 2021, 85 in 2022, 49 in 2023 and 21 in 2024. Most of the 2021 drilling was diamond core that was used for metallurgical testing and assay. The 2022 and 2023 drilling focused on extending mineralization and upgrading areas from inferred to measured and indicated classification. The 2024 drilling focused on high-grade mineralization in Brimstone and Vortex.

 

Hycroft Mine Project

Page 54

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 7-1: Drill Collar Location Plan

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 55

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 7-1: Drilling from 2023 and 2024 Supporting the Updated MRE

 

Hole ID Northing Easting Elevation
(masl)
Hole length (ft) Inclination (deg) Azimuth
(deg)
H23C-5767 23022.532 39788.972 5050.094 1000 -57.98 243
H23C-5768 23097.466 39986.601 5048.798 1020 -57.98 243
H23C-5769 19563.12 40199.23 4458.06 1750 -57.98 243
H23C-5770 19024.77 40418.99 4239.71 1887 -57.98 243
H23C-5776 18426.95 40800.25 4361.54 1629.5 -57.98 243
H23C-5778 25545.11 36956.82 5616.41 1000 -57.98 243
H23C-5780 25984.36 36976.45 5575.68 605 -57.98 243
H23C-5781 25980.93 36976.25 5575.86 753 -57.98 243
H23R-5747 22189.79 39295.821 5001.41 1300 -70 90
H23R-5748 17122 38400.01 4606.39 1300 -70 90
H23R-5749 17178.57 38589.8 4598.47 1300 -70 90
H23R-5750 17078.89 38776.26 4598.543 1400 -70 90
H23R-5751 17039.71 38669.56 4599.205 1760 -70 90
H23R-5752 17039.97 38669.7 4599.259 1400 -70 90
H23R-5753 22119.91 42749.64 4479.94 1200 -70 90
H23R-5754 21510.24 41418.17 4501.49 1250 -70 90
H23R-5755 16516.25 37642.36 4406.38 800 -70 90
H23R-5756 16369.51 38282.53 4302.76 1100 -70 90
H23R-5757 16902.9 38592.574 4597.643 1200 -70 90
H23R-5758 16916.07 38779.44 4599.196 1400 -70 90
H23R-5759 17064.069 38765.321 4599.206 1300 -70 90
H23R-5760 22545.27 42526.38 4617.74 1500 -70 90
H23R-5761 22540.37 42621.83 4619.23 1500 -70 90
H23R-5762 16878.68 40805.17 4439.201 1510 -70 90
H23R-5763 17117.9 40800.38 4448.28 1700 -70 90
H23R-5764 17366.39 40800.14 4433.93 1720 -70 90
H23R-5765 21362.57 41350.61 4508.29 1250 -70 90
H23R-5766 21642.38 40908.35 4653.27 1500 -70 90
H23R-5771 22375.51 42362.41 4619.92 1210.4 -70 90
H23R-5773 22579.05 44400.47 4834.02 1380 -70 90
H23R-5774 22577.06 44400.39 4834.09 1500 -70 90
H23R-5784 16389.27 37693.98 4375.49 950 -70 90
H23R-5785 16130.29 37479.09 4343.28 750 -70 90
H23R-5786 16212.63 37860.99 4357.13 800 -70 90
H23C-5787 25261.92 36571.14 5560.73 800 -57.98 243
H23C-5777 26047.99 37510.26 5710.02 659 -57.98 243

 

Hycroft Mine Project

Page 56

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hole ID Northing Easting Elevation
(masl)
Hole length (ft) Inclination (deg) Azimuth
(deg)
H23C-5779 25048.82 36226.86 5511.94 610 -57.98 243
H23C-5790 22137.378 42732.949 4481.43 1222 -57.98 243
H23C-5794 26978.764 38048.934 5725.895 1625.5 -70 90
H23C-5795 22368.307 42211.245 4615.752 1205 -70 90
H23R-5775 22107.49 41546.68 4597.67 1378 -70 90
H23R-5782 22417.57 41989.33 4611.14 1200 -70 90
H23R-5792 19737.808 47981.098 4592.636 450 -70 90
H23C-5788 22124 42755 4480 785 -57.98 243
H23C-5789 21501.12 41405.63 4501.13 1260 -57.98 243
H23C-5796 14219.804 30051.704 5258.447 564 -70 90
H23C-5797 14216.243 30054.634 5258.395 421 -70 90
H23C-5791 19202.43 50349.998 4466.932 556 -62.53 91.39
H23C-5798 21842.82 42721.378 4480.006 1306 -70 90
H24D-6000 18456.79 41109.25 4358.82 1288.1 -51.55 139.51
H24D-6001 20279.43 40613.29 4845.23 1897 -81.79 225.4
H24D-6002 19532.83 39871.49 4497.08 1936.6 -72.19 28.04
H24D-6003 21617.07 42344.04 4522.26 1603 -57.96 74.93
H24D-6004 21632.9 42668.16 4480.78 1491 -53.29 85.89
H24D-6005 20430.43 39723.11 4874.35 1978 -80.04 37.12
H24D-6007 18467.86 39384.38 4603.13 1764.3 -65.42 19.17
H24D-6009 21596.98 42343.93 4522.13 1439 -60.25 96.83
H24D-6010 22075.19 42771.26 4480.41 1270 -58.27 121.77
H24D-6008 21414.42 42576.31 4525.28 1589.3 -65.42 19.17
H24D-6011 22083.7 42463.77 4520 1128.9 -58.27 118.96
H24D-6012 21577.37 42129.56 4563.03 1480 -77.5 16.35
H24E-6013 19581.635 52769.501 4459.163 662 -49.93 81.98
H24E-6014 19438.89 51895.48 4426.114 600 -49.93 81.98
H24E-6015 23464.19 39901.24 5307.52 785 -49.93 81.98
H24D-6006 18702.71 40106.39 4419.27 1319.8 -80.04 37.12
H24D-6016 18394.08 39005.45 4671.78 2107 -63.53 20.92
H24D-6017 22075.42 42769.46 4479 1235.4 -63.53 20.92
H24D-6018 22084.57 42462.56 4520.41 1186 -63.53 20.92
H24D-6019 21733.69 42244 4521.2 1701 -63.53 20.92
H24D-6020 21876.02 42083.76 4559.42 1254.7 -49.93 81.98

 

Hycroft Mine Project

Page 57

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

7.6.2.1Drilling Methods

 

Drilling at Hycroft has been a mix of diamond core holes, reverse circulation (RC), and sonic drilling. A total of 6,024 drill holes representing 2,814,546 ft of drilling has been performed throughout the history of the project. A total of 35,647 down-hole surveys exist in the database.

 

7.6.2.2Logging Procedures

 

Core is loaded into cardboard boxes in approximately ten-foot intervals and are transported to the core processing facility. Geology data is logged directly into acQuire by the staff geologists where they log formation, lithology, structure, vein, mineralization, and alteration, and geotechnical data. RC chips are collected from the RC rejects and the rig and stored in chip trays for logging by similar methods as applied to core.

 

7.6.2.3Recovery

 

The average sample recovery within the ore at Hycroft is 82% and the average sample recovery within the waste is 75%.

 

7.6.2.4Sample Length/True Thickness

 

Sample length is generally 5 ft intervals sampled down the drill hole but broken in smaller intervals based on local geologic variation. The true thickness of mineralization is several feet to more than, 2,000 ft.

 

7.7Hydrogeology

 

An extensive program of hydrologic data collection was implemented by SRK Consulting (US) Inc. (SRK) for a previous owner of the property. That work is summarized in a report titled “Summary of Field Investigations and Conceptual Hydrogeology – Hycroft Mine Expansion Project, Nevada”, August 2013. SRK collected data from 43 drill holes including monitor wells, piezometers, slug tests, packer tests, long-term pumping tests, and ground water level monitoring. Eighty-one ground water samples were collected and analyzed over a period of a year and a quarter. The SRK work was utilized during the preliminary geotechnical analysis of the Hycroft pit slopes.

 

IMC holds the opinion that hydrologic data collection and analysis are appropriate to determine mineral resources and an initial assessment with an economic analysis.

 

7.8Geotechnical

 

Call & Nicholas, Inc. (CNI) has completed geotechnical data collection and analysis. CNI has prepared two reports titled: “Hycroft Geotechnical Slope Stability Study,” February 2022, and “2023 Camel Pit Geotechnical Logging and Laboratory Testing Report,” October 2023. Geotechnical laboratory testing was completed by CNI during 2010, 2011, 2021, and 2023.

 

Hycroft Mine Project

Page 58

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Two geotechnical holes were drilled in 2022 using diamond core methods (H22D-5726 and H22D-5729). These holes were sampled and logged for rock quality designation (RQD) and other geotechnical parameters by CNI engineers on site at Hycroft. Hole H22D-5729 was also televiewer logged.

 

CNI has provided slope angle recommendations that have been utilized to establish the MRE presented in this document.

 

IMC holds the opinion that geotechnical work is appropriate for development of mineral resources and initial assessment with economic analysis. Additional work will be required as the project progresses, and more detail is required.

 

7.9Exploration Targets

 

In mid-2022 Hycroft restarted exploration drilling with the primary goal of converting waste material and inferred resources into measured and indicated resources. The drilling was dominantly RC, and RC with core tails occurring on the deeper (<1,800 ft) holes (See Table 7-2). In the second half of 2023 the program was re-aligned due to the recognition of significant silver grades both within subvertical thin veining in Brimstone and within a low angle breccia body at Vortex. Subsequently, the drilling method was switched to core to better understand and define structural complexities at Brimstone and Vortex.

 

The drilling in Brimstone indicates the zone of veining is related to a structural dilation zone between East Fault related structures. The geometry of the high-grade Brimstone deposit has not been fully defined and remains open at depth and along strike.

 

The drilling in Vortex along with additional mapping east on the trend of the Vortex mineralization, indicates the Vortex deposit is related to a pre-mineral detachment fault.

 

Exploration targets were also identified outside the resource area to the east (Manganese and Wildrose) and south (Oscar), with work on these areas including detailed field mapping, soil and rock-chip geochemistry, IP geophysics, and core drilling. Additional exploration work was completed at Bay to start defining vein geometry extending below the current resource. These targets are still conceptual and may require significant work before a resource can be determined. Hycroft will continue to develop these high value targets in future exploration programs. The exploration program continued through 2024 with one core drill program completing 21 holes totaling approximately 30,000 ft, which was exclusively focused on high-grade silver zones within Brimstone and Vortex.

 

Hycroft Mine Project

Page 59

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 7-2: Significant Intercepts (2023)

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H23R-5748 Camel 105.16 134.11 28.96 0.41 8.82
  204.22 251.46 47.24 0.53 5.71
Including 205.74 219.46 13.72 0.61 10.84
H23R-5749 Camel 195.07 240.79 45.72 0.53 4.86
Including 204.22 222.50 18.29 0.64 3.75
  288.04 304.80 16.76 0.39 5.39
  368.81 377.95 9.14 0.39 3.42
H23R-5750 Camel 156.97 184.40 27.43 0.45 4.08
  210.31 245.36 35.05 0.50 4.18
  278.89 297.18 18.29 0.33 3.59
  377.95 387.10 9.14 0.44 4.17
H23R-5751 Camel 112.78 211.84 99.06 0.46 6.88
Including 192.02 204.22 12.19 0.63 13.91
  393.19 429.77 36.58 0.41 3.24
H23R-5752 Camel 152.40 219.46 67.06 0.41 4.91
  333.76 371.86 38.10 0.37 29.32
Including 338.33 345.95 7.62 0.33 85.36
H23R-5757 Camel 45.72 111.25 65.53 0.51 10.38
Including 45.72 56.39 10.67 0.50 36.37
  126.49 259.08 132.59 0.54 1.37
Including 138.68 184.40 45.72 0.69 8.78
  350.52 365.76 15.24 0.47 7.67
H23R-5758 Camel 129.54 234.70 105.16 0.44 4.97
  298.70 329.18 30.48 0.41 2.31
H23R-5759 Camel 27.43 231.65 204.22 0.53 20.70
Including 27.43 68.58 41.15 0.49 75.81
Including 80.77 128.02 47.24 0.78 8.19
  281.94 359.66 77.72 0.35 3.48
H23R-5784 Camel 105.16 158.50 53.34 0.47 11.86
  237.74 289.56 51.82 0.42 12.26
H23R-5786 Camel 60.96 135.64 74.68 0.36 41.20
Including 60.96 86.87 25.91 0.29 106.01
  173.74 225.55 51.82 0.43 44.99
Including 173.74 181.36 7.62 0.49 266.72
H23R-5756 Camel 12.19 68.58 56.39 0.40 4.58
  141.73 204.22 62.48 0.36 4.76
  224.03 240.79 16.76 0.43 2.31

 

Hycroft Mine Project

Page 60

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H23R-5785 Camel 164.59 213.36 48.77 0.50 43.60
Including 172.21 184.40 12.19 0.59 161.16
H23R-5762 Camel 4.57 13.72 9.14 0.41 6.42
  48.77 455.68 406.91 0.39 4.90
Including 137.16 202.69 65.53 0.59 6.14
H23R-5763 Camel 190.50 236.22 45.72 0.51 5.36
  254.51 445.01 190.50 0.42 4.99
Including 367.28 445.01 77.72 0.53 3.76
H23R-5764 Camel 275.84 300.23 24.38 0.57 4.32
  396.24 519.68 123.44 0.47 7.00
H23C-5769 Vortex 357.62 417.15 59.53 0.36 75.91
Including 399.32 417.15 17.83 0.55 211.89
H23C-5770 Vortex 0.00 29.57 29.57 0.45 7.42
  224.27 328.00 103.72 0.37 6.62
  347.38 398.07 50.69 0.50 139.87
Including 350.58 368.72 18.14 0.31 288.82
Including 387.16 398.07 10.91 1.29 138.48
H23R-5773 Brimstone 88.39 141.73 53.34 0.24 24.41
Including 121.92 134.11 12.19 0.32 56.84
  310.90 342.90 32.00 0.51 4.87
  359.66 411.48 51.82 0.38 3.98
H23R-5774 Brimstone 108.20 111.25 3.05 0.36 57.00
  129.54 132.59 3.05 0.59 30.85
  275.84 278.89 3.05 0.69 34.45
  315.47 326.14 10.67 0.44 26.83
  393.19 396.24 3.05 0.54 5.00
H23C-5768 Brimstone 61.87 67.97 6.10 0.39 210.50

 

Hycroft Mine Project

Page 61

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 7-3: Significant Intercepts (2024)

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H24D-6000 Vortex 71.7 102.3 30.5 0.64 13.80
  272.0 318.8 46.8 0.69 18.12
H24D-6001 Vortex 189.3 224.6 35.3 0.66 6.32
Including 220.0 223.5 3.5 1.07 16.76
  383.2 507.5 124.4 0.95 102.59
Including 385.4 388.2 2.8 7.38 40.85
Including 385.4 386.3 0.9 19.65 80.60
Including 410.7 424.8 14.2 2.13 77.34
Including 449.4 488.0 38.6 0.71 134.25
Including 451.7 452.0 0.3 0.03 4,170.00
Including 458.5 462.1 3.6 2.99 40.94
Including 470.2 478.9 8.7 0.32 207.33
  498.2 507.0 8.9 0.31 475.56
Including 498.2 498.8 0.7 0.42 1,700.00
Including 504.6 506.0 1.4 0.34 1,538.78
H24D-6002 Vortex 357.3 458.2 100.9 0.38 100.65
Including 357.3 359.3 2.1 2.86 4.53
  428.4 448.8 20.4 0.83 357.01
Including 428.4 429.4 1.0 1.38 300.12
Including 435.9 439.5 3.6 0.66 397.04
Including 440.4 445.0 4.6 1.59 1,066.47
Including 441.9 442.4 0.5 5.90 3,310.00
  452.2 454.2 2.0 0.32 225.49
H24D-6005 Vortex 111.2 119.1 8.0 0.79 176.54
  207.4 234.5 27.1 0.40 6.33
  254.4 476.9 222.4 0.45 32.38
Including 385.2 395.2 10.0 0.34 328.25
Including 385.2 386.9 1.7 0.94 1,155.27
Including 408.2 419.0 10.8 0.24 107.02
  537.1 556.1 19.0 0.37 142.14
Including 537.4 537.6 0.3 0.06 6,260.00
H24D-6006 Vortex 20.9 25.6 4.7 2.81 56.97
  19.6 31.3 11.7 1.38 31.50
  74.5 96.1 21.6 1.11 10.99
Including 74.5 79.2 4.8 0.91 8.60
Including 82.2 86.1 3.9 0.56 6.19
  279.7 280.1 0.4 0.15 581.00
  346.2 400.9 54.7 0.68 12.86
Including 351.8 355.1 3.3 2.19 9.29
Including 365.0 367.4 2.5 4.23 16.71
Including 373.3 375.3 2.0 1.05 16.13

 

Hycroft Mine Project

Page 62

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H24D-6007 Vortex 46.1 93.6 47.4 0.35 22.51
Including 47.7 50.2 2.6 0.12 307.40
Including 64.0 64.6 0.5 3.10 54.40
  113.4 125.0 11.6 0.98 16.56
  371.3 399.5 28.2 0.44 11.98
  468.4 537.8 69.4 0.57 108.38
Including 468.4 474.7 6.4 0.63 213.71
Including 497.1 537.8 40.7 0.73 144.25
Including 497.1 500.9 3.8 0.23 193.57
Including 512.4 514.9 2.5 0.72 645.25
Including 513.2 513.7 0.5 1.19 1,430.00
Including 536.3 537.8 1.5 4.78 960.00
H24D-6016 Vortex 405.4 456.3 50.9 0.42 19.38
  472.3 518.0 45.7 0.49 15.57
  535.3 557.2 21.9 0.40 53.80
H24D-6003 Brimstone 0.0 23.8 23.8 0.29 10.80
  42.4 47.8 5.5 0.20 119.54
  250.7 278.3 27.6 0.38 4.13
  351.4 440.0 88.5 0.23 34.70
Including 386.7 386.8 0.2 0.12 1,835.00
Including 397.7 397.9 0.2 0.62 8,410.00
Including 418.8 421.1 2.3 0.08 130.87
H24D-6004 Brimstone 0.0 18.6 18.6 0.63 24.59
  341.4 361.6 20.2 0.34 5.48
  413.8 442.1 28.3 0.31 14.19
Including 429.3 441.4 12.0 0.52 11.73
H24D-6008 Brimstone 458.6 474.0 15.4 0.45 12.81
Including 464.5 467.9 3.5 0.82 20.54
Including 470.2 474.0 3.8 0.46 19.83
H24D-6009 Brimstone 0.0 16.2 16.2 0.38 54.89
Including 4.8 6.4 1.5 1.05 353.24
  333.2 358.7 25.5 0.35 5.46
  417.9 423.5 5.6 0.10 150.80
Including 417.9 421.1 3.3 0.10 199.20
Also Including 420.3 420.6 0.2 0.10 652.00

 

Hycroft Mine Project

Page 63

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H24D-6010 Brimstone 328.4 346.6 18.2 0.35 1,987.35
Including 331.0 332.8 1.8 0.11 2,612.33
Including 333.4 335.8 2.5 0.33 4,683.70
Also Including 333.4 333.7 0.3 0.41 20,280.00
Including 340.2 342.7 2.5 0.50 5,513.43
Also Including 340.2 341.1 0.9 0.72 10,289.00
Also Including 341.1 341.4 0.3 0.64 15,211.00
H24D-6011 Brimstone 109.3 119.0 9.8 0.81 8.14
  168.2 174.7 6.4 0.56 29.76
  246.3 260.2 13.9 0.31 311.41
Including 249.9 252.8 2.9 0.27 1,211.32
  273.2 326.5 53.3 0.26 218.92
Including 289.0 314.4 25.3 0.28 401.50
Also Including 298.5 300.7 2.3 0.29 2,210.81
Also Including 306.5 311.4 4.9 0.33 610.65
H24D-6012 Brimstone 37.3 37.8 0.4 0.49 4,540.00
  65.8 66.8 0.9 0.52 4,040.00
  284.0 325.2 41.2 0.39 7.28
Including 297.4 307.5 10.1 0.84 4.67
  354.6 405.4 50.7 0.28 101.82
Including 354.6 357.7 3.1 0.58 36.37
Including 366.3 372.6 6.2 0.23 282.25
Also Including 370.1 370.8 0.7 0.12 1,185.00
Including 385.0 386.6 1.6 0.09 1,156.86
Including 400.8 405.4 4.6 0.12 202.67
  419.1 421.5 2.4 0.24 103.52
Including 420.7 421.5 0.8 0.13 176.30
H24D-6017 Brimstone 312.6 332.5 20.0 0.45 70.02
Including 314.7 321.6 6.9 0.14 151.39
H24D-6018 Brimstone 306.6 327.9 21.2 0.38 2359.68
Including 317.4 324.7 7.3 0.59 6,278.23
Also Including 317.4 317.6 0.2 1.62 80,017.00

 

Hycroft Mine Project

Page 64

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hole ID Area From (m) To (m) Interval (m) Grade
Au (g/t) Ag (g/t)
H24D-6019 Brimstone 148.0 155.0 6.9 0.98 9.76
  379.1 392.4 13.3 0.16 314.05
Including 379.1 385.1 6.0 0.15 591.73
H24D-6020 Brimstone 262.8 274.7 11.9 0.34 25.86
  320.4 349.2 28.8 0.32 320.7
Including 328.7 332.0 3.3 0.36 775.1
Including 335.6 341.3 5.7 0.48 642.40
Including 343.6 346.2 2.6 0.24 465.16
H24E-6013 Bay 0.0 55.5 55.5 0.45 3.00
Including 13.6 15.0 1.4 3.84 40.00
H24E-6014 Bay 9.0 14.7 5.7 2.68 4.10
Including 12.5 14.7 2.2 4.91 4.74
H24E-6015 Manganese 33.6 41.2 7.6 0.81 293.51
Including 33.6 37.9 4.3 1.18 454.21
  55.4 55.9 0.6 7.91 117.00
  115.5 125.8 10.3 0.61 86.08
Including 117.1 123.6 6.5 0.72 131.15
  168.0 173.9 5.9 0.46 6.03

 

Hycroft Mine Project

Page 65

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

8Sample Preparation, Analyses, and Security

 

8.1Introduction

 

This section describes the sample collection, preparation, analysis, and security that has been used by Hycroft or their predecessors. Drilling and sampling at the Mine have been ongoing from 1982 through 2024. Hycroft provided IMC with the database which contained assay information for drilling from 1982 through 2024. IMC is the qualified organization for the section.

 

Most of the current staff at Hycroft have been at site for less than five years. As a result, much of the information that is reported here regarding historical sample preparation, analysis, and security was previously reported in the 2023 TRS.

 

Discussion of quality assurance and quality control (QA/QC) regarding the database is presented in Section 9.

 

8.2Sample Preparation

 

The sample preparation procedures prior to 1999 were not documented. Starting in 2005, preparation procedures were well documented with standard methods. The comparison of the pre-2005 data with post-2005 drilling will be presented in Section 9 to provide some confidence in the application of some of the pre-2005 data.

 

Post-2005 sample collection consisted of both diamond core and RC drilling. Core samples are currently split at the mine site, tagged, and the split core is sent to commercial laboratories for further preparation. RC samples are currently collected at the rig with a rotary splitter. Bags of RC cutting splits are tagged and sent to commercial laboratories for further preparation and assaying.

 

Once at the commercial labs, the samples are crushed to 10 mesh and a 0.55-lb (0.25 kg) split is taken and pulverized to 85% passing 200 mesh prior to assay analysis.

 

8.3Assay Methods

 

Prior to 1992, most samples were sent to Barringer Laboratories, Inc., in Golden, Colorado. Fire assays (FA) were routinely performed on cyanide soluble assays for selected intervals.

 

From 1992 to 1999, samples were processed at the Hycroft laboratory at the mine site.

 

The Hycroft laboratory assays consisted of Au FA followed by cyanide soluble Au and cyanide soluble Ag on all intervals. The Mine cyanide soluble assay methods are reported to have been non-standard and were developed to provide a prediction of recoverable Au and Ag from heap leaching.

 

There are no samples in the database from 2000 through 2004. Starting in 2005, all samples were sent out to commercial labs for analysis that are independent of Hycroft. During 2012, there were 10 drillholes that were an exception to this rule and were assayed by the Hycroft lab. Those holes have reportedly been compared with assays from commercial labs and are still maintained in the database.

 

Hycroft Mine Project

Page 66

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The external labs that have been used by Hycroft prior to 2021 are all in the Reno/Sparks, Nevada area and are listed below with their accreditations:

 

ALS Minerals ISO9001:2000 and ISO17025
    
American Assay Laboratories ISO/IEC17025, PTP-MAL Canada
    
Inspectorate ISO9001:2008
    
McClelland ISO/IEC17025

 

During 2021 and 2022, Hycroft utilized the following laboratories in the Reno/Sparks area:

 

Bureau Veritas Mineral Laboratories USA ISO-9001 ISO-14001 ISO-45001 OHSAS-18001
    
Paragon Geochemical ISO/IEC 17025:2017

 

During 2023, Hycroft utilized the following laboratories in the Reno/Sparks area:

 

Paragon Geochemical ISO/IEC 17025:2017
     
ALS Minerals ISO/IEC 17025:2017 and ISO 9001:2015

 

During 2024, Hycroft utilized the following laboratories in the Reno/Sparks area:

 
ALS Minerals ISO/IEC 17025:2017 and ISO 9001:2015
     
American Assay Laboratories ISO/IEC 17025:2017

 

All intervals were assayed using conventional FA with Atomic Absorption (AA) or gravimetric finish for Au. Fire silver assays were not regularly completed by previous project operators. After 2013, aqua regia (AR) digestion was used for total silver assays and replaced the previous gravimetric treatment of silver. The lower detection limit on the AR method was the reason for the change.

 

The FA method for gold with an AA finish was the primary assay method at all the labs. Cyanide soluble methods were alternatively hot or cold depending on the lab.

 

As noted previously, cyanide silver was much more consistently assayed than fire silver. Starting in 2014, total silver was consistently assayed along with fire gold.

 

Hycroft Mine Project

Page 67

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Cyanide soluble assays for gold and silver were highly prevalent in the pre-2000 drilling. As drilling began to target the deeper sulfide mineralization after 2005, the cyanide soluble assays were selectively run on the upper, oxidized portion of the deposit and not applied to the deeper sulfide mineralization.

 

During 2007 and 2008, Hycroft also applied the 35-element inductively coupled plasma (ICP) analysis to 90% of the assay intervals. That data results in 53,624 sample intervals that can be used to track trace elements.

 

During 2011, 127 drillholes were selected for ICP and Laboratory Equipment Corporation (LECO) analysis at American Assay. These holes were generally 500 x 200-foot centers across the estimated sulfide pit target at the time. Most were assayed on 25-foot intervals from top to bottom for total sulfur, sulfide sulfur and carbon. During 2014, additional sample intervals were selected from the 2012 to 2014 drilling for LECO and ICP.

 

During 2022, analysis for LECO was conducted on site by Hycroft on some drillholes.

 

During 2023, some drillholes were selected for ICP (4-acid digestion) and LECO analysis at ALS Minerals. ICP was analyzed on a sample-by-sample basis while LECO was analyzed on 25-foot composites. Some drillholes were analyzed for LECO on site by Hycroft.

 

During 2024, all drillholes were sent out for ICP (4-acid digestion) and LECO analysis at ALS Minerals. In addition, a portion of the 2022 and 2023 drillholes were also sent out for ICP and LECO analysis to ALS. ICP was analyzed on a sample-by-sample basis while LECO was analyzed on 25-foot composites.

 

The sulfide sulfur results from this work have been used to assign sulfide sulfur values to the block model for process metallurgical input. It should be noted that the sulfide sulfur procedures also report elemental sulfur along with the sulfide component.

 

Assay submittals have included blanks and standards since 2007. Check assays and duplicate assays were submitted in 2012 and 2014. The results of the analysis of those samples will be reported in Section 9.

 

Assay procedures requested of ALS laboratories Reno and ALS Laboratories in Vancouver include:

 

ALS Au-AA23 testing:

 

FA gold with an atomic absorption spectroscopy (AAS) finish

 

FA Fusion with AAS finish for Au

 

30 g nominal sample weight

 

0.005/10 g/t lower/upper limit

 

>10 g/t over limit testing by gravimetric by Au-GRA21

 

ALS Au-AA13 testing: cyanide leach capacity

 

Cyanide leach; AAS finish for Au

 

Hycroft Mine Project

Page 68

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

30 g nominal sample weight

 

0.03/50 g/t lower/upper limit

 

ALS ME-ICP41 testing

 

AR digestion with an atomic emission spectrometry (AES) or AAS

 

AR digestion with AES or AAS finish

 

0.5 g nominal sample weight

 

0.2/100 g/t lower/upper limit.

 

100 g/t over limit testing by AR digestion and AES or AAS finish by Ag-OG46

 

1,500 g/t over limit gravimetric testing by Ag-GRA21

 

10,000 g/t overlimit gravimetric testing by Ag-CON01

 

ALS Ag-AA13 testing: cyanide leach capacity:

 

Cyanide leach with AAS finish

 

30 g nominal sample weight 0.03/350 g/t lower/upper limit

 

ALS ME-MS61m testing: multi-element trace elements:

 

Four acid digestion with ICP atomic emission mass spectrometry (MS)

 

0.75 g nominal sample weight

 

49-element suite with automatic ore-grade testing on over-limits

 

Over-limits were set-up specific to each element

 

ALS S-GRA06a testing: sulfur speciation for autoclave blending:

 

Total sulfur by LECO furnace analysis

 

HCI (15%) leach of sulfates with LECO furnace analysis for sulfide sulfur (SS). Sulfide values are reported as calculated values

 

1 g nominal sample weight

 

0.01/50% lower/upper limit by weight

 

Assay procedures requested of American Assay Laboratories (AAL) Reno:

 

AAL IO-FAAu30 testing: fire assay (FA) with an optical emission spectrometry (OES) finish:

 

Hycroft Mine Project

Page 69

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

FA with an OES finish for Au

 

30 g nominal sample weight

 

0.003/10 g/t lower/upper limit

 

>10 g/t over limit gravimetric testing by G-FA Au

 

AAL IO-2AAg testing: AR with an optical emission spectrometry (OES) finish:

 

AR digestion with an OES finish

 

30 g nominal sample weight

 

0.3/100 g/t lower/upper limit

 

>100 g/t over limit AR digestion testing by IO-2AOR-AG1000

 

>1,000 g/t over limit gravimetric testing by G-FAAg

 

8.3.1Sample Security

 

Samples were delivered to the analytical laboratories in numbered bags along with transmittal sheets that list the sample numbers, the total sample count, and codes for sample type (RC or Core). The lab confirmed the receipt of shipment against the transmittal sheets to account for all samples issued.

 

It is reported that no officers, directors, or associates of Hycroft or their predecessors were operationally involved in the sample collection, preparation, or assay transmittal.

 

Sample security relies on the samples being in custody of Hycroft personnel or stored in a secure area prior to shipment to ALS. Chain-of-custody procedures consist of unique and independent sample numbers used for each sample with dispatch-submittal sheets and database entries used to track the progress of samples and to ensure that all samples are received by the laboratory.

 

Unique and independent sample numbers and sample tags are used in all cases. Sample Dispatch and Submittal sheets are used to check and track samples through the system. Sample information is entered into the computer database to track the samples and record results.

 

8.4Sample Storage

 

Split core and chip trays are stored on site in an enclosed warehouse, Conex containers, or wrapped outside, located near the core shed. Generally, since 2021, the remaining half of split core is retained. However, core from 2021 was mostly consumed for metallurgical purposes, and core prior to 2021 no longer exists.

 

Sample rejections are retained but stored outside where they degrade after three to four years.

 

All core boxes, chip trays, and pulps are coded to facilitate easy retrieval when required.

 

8.5Analytical Results

 

Following analysis, results are posted to a digital laboratory database for which Hycroft has secure permission privileges. Managers download data where the sample results are cross-referenced to sample numbers. Each drillhole carries a unique self-identifying sample number, simplifying cross-referencing. The completed digital file for each drillhole is emailed to Hycroft by the lab, and a follow-up, hard copy certificate is mailed to Company offices.

 

Data is checked by geologists visually and loaded into the secure acQuire database. The acQuire database is further checked using electronic methods and then calculated into ounce per ton values and loaded to the modeling database for display and further visual QA/QC checking.

 

Database security and integrity are accomplished by restricting access and user level permissions that are set by the Database Administrator. Once data entry and validation are completed for a drill hole, access is locked. There are procedures for version control on any updates that may happen over time, so that the database will retain all original information and prioritize use of any updates.

 

8.6QP Comment

 

The sample preparation, analysis and security practices are typical for the US mining industry and are acceptable for application to mineral resource determination.

 

The QP considers that current sampling, sample preparation, analytical methods and security are acceptable, are in line with industry-standard practices, and are adequate for mineral resource estimation.

 

Hycroft Mine Project

Page 70

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

9Data Verification

 

9.1Verification Procedure

 

This section will address the QA/QC and data verification procedures that were used to confirm that the Hycroft database was acceptable for estimation of mineral resources. Multiple tasks have been completed to verify the data since the completion of previous TRS’s in Feb 2022 and Feb 2023.

 

The data verification steps were as follows:

 

1.Detailed comparison of certificates of assay versus the assay database which resulted in substantial update and correction to the database.

 

2.Analysis of the QA/QC data used by Hycroft and previous owners from 2005 to 2024. This work was done in three stages representing different time periods.

 

3.Analysis of diamond drilling hole (DDH) versus RC Drilling with the 2005-2024 drilling to confirm that the two methods can be comingled and utilized for the estimation of mineral resources.

 

4.Comparison of pre-2005 drilling versus 2005-2024 drilling to verify the application of the older data. The pre-2005 data has no QA/QC information that can be used to verify its reliability.

 

The IMC approach to data verification was to establish the reliability of the post-2005 drilling based on the available QA/QC data and the comparison between DDH and RC. Once the 2005-2024 data was established as reliable, it was used to check the historic pre-2000 drilling by a nearest neighbor sample comparison.

 

9.2Certificate of Assay Checks

 

The team at the Mine site completed an extensive check and verification of the data base with interval-by-interval checks against the available certificates of assay. After completion of that work, IMC completed a spot check of 95 of the drill hole certificates of assay to confirm the edits and corrections completed by Hycroft.

 

9.3QA/QC 2005 – 2024

 

The 2005 to 2024 drilling data had the following QA/QC information collected:

 

Standards

 

Blanks

 

Duplicate Assays

 

Check Assays from 2011 through 2013 and again in 2024.

 

Hycroft Mine Project

Page 71

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

That information will be analyzed in three parts to understand the relative reliability of the post-2005 drilling: (1) the data collected from 2005 to 2014, (2) the data collected from 2021 through 2022, and finally (3) the 2023 to 2024 data.

 

9.3.1Standards 2005-2013

 

Blind standards are inserted into the assay sample submissions for analysis at the assay lab. The lab obviously knows the sample is a standard, but they do not know which standard.

 

The early standards database provided to IMC did not include dates of insertion. It is presumed that the insertion of standards started in 2005 with the modern drilling program. However, the earliest example of standard acquisition that IMC could find was mid-2007. There are indications of sample insertion though the 2013-time frame.

 

In most exploration environments, standards results are reviewed as they arrive from the lab to confirm that the measured result is within the error tolerance reported for the standard. IMC takes a different approach and compares the accepted value of the standard against the multiple assays of the standard on an XY plot to identify any potential bias in the assay process.

 

Figure 9-1 illustrates the results of the standards submissions for gold for 2005-2013.

 

The comparison of the accepted value of the standard and the tested standards results does not indicate consistent bias. The points that are scattered off-line reflect swapped samples meaning that the wrong standard was recorded or submitted to the lab compared to the tabular results. There are 22 apparent sample swaps out of 7,154 tested standards or about 0.3% of the original samples.

 

Figure 9-2 summarizes the results of the total silver standards submissions. There is substantially more variation in the silver standards results as one would expect in this grade range. In addition, most of the original assays are gravimetric finish which have a detection limit of 5 ppm or 0.15 oz/ton. There are only five standards below 0.15 oz/ton out of 6,498 Ag standards analyzed. With some standards values as low as 0.20 oz/ton it would not be out of line to see an indication of subtle bias if the lowest value that can be reported is 0.15 oz/ton.

 

Hycroft Mine Project

Page 72

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-1: Results of Submitted Gold Standards 2005 - 2013

 

 

Source: IMC, 2021

 

Hycroft Mine Project

Page 73

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-2: Results of Submitted Silver Standards 2005-2013

 

 

Source: IMC, 2021

 

9.3.2Blanks 2008 - 2014

 

Blank samples are inserted periodically to confirm that metal is not carried over from one sample to the subsequent sample in the sample stream. Figure 9-3 summarizes the results of the blank submissions for gold from 2008 to 2014. The figure indicates that most samples reported back as trace or small values.

 

Hycroft Mine Project

Page 74

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

However occasional samples have been reported near or above heap leach feed grade. Of the 2,260 standards in Figure 9-3, 5.9% reported higher than 0.005 oz/ton and 5.6% reported higher than 0.010 oz/ton. Although these represent small percentages, there is room for improvement.

 

One expects that some of the samples were not blanks but were mistakenly inserted standards. The statistical average above 0.005 oz/ton is about 0.019 oz/ton, which is quite close to the standard value of the Cove 2 standard.

 

Figure 9-3: Results of Blank Submissions

 

 

Source: IMC, 2021

 

9.3.3Check Assays 2011-2012

 

Assay pulps were submitted to a second lab as check assays during 2011–2012. The primary lab was ALS, and the check lab was AAL. The results are summarized in Figure 9-4 and Figure 9-5 as XY plots.

 

The variability in the results is more than one would expect from pulp submissions, but there does not appear to be an observable bias in the laboratory comparisons. The line on the graphs illustrates a 1:1 relationship as a comparison.

 

Hycroft Mine Project

Page 75

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-4: Check Assay Results, Fire Assay Gold 2011 - 2012

 

 

Source: IMC, 2021

 

Hycroft Mine Project

Page 76

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-5: Check Assay Results, Fire Assay Silver 2011 – 2011

 

 

Source: IMC, 2021

 

9.3.4Standards 2021 – 2022

 

All recent drilling completed by Hycroft utilizes standards, blanks, and duplicate assays for QA/QC confirmation of the database. Hycroft analyzes the data as it is received to confirm that the results are within appropriate acceptance ranges.

 

Diamond drilling was the primary method used during 2021, and RC drilling was the primary method during 2022. An analysis of RC to DDH during 2021 and 2022 indicates that both can be used for mineral resource estimation. In addition, two assay laboratories were used in 2021 and 2022. Bureau Veritas, Mineral Laboratories, USA (Sparks, Nevada) and Paragon Geochemical Laboratories, (Sparks, Nevada) were both used to assay Hycroft samples during this period.

 

Paragon and Bureau Veritas’ results have been analyzed separately and both provide similar results. The figures presented for the 2021 through 2022 QA/QC show both laboratories combined as a summary of the overall results. Most of the silver QA/QC was applied to cyanide silver assays. Since those are not used in this estimate, the gold QA/QC information is shown.

 

Hycroft Mine Project

Page 77

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The standards that do not check well amount to about 2.4% of the submitted standards. Those out-of-range results tend to line up with other standards or blank values. This implies swaps in standards submissions or in data recording rather than outright errors in the assay.

 

Figure 9-6 illustrates the standards results for the 495 submitted gold standards during 2021 and 2022.

 

Figure 9-6: Standards Results, 2021 – 2022

 

 

Source: IMC, 2023

 

9.3.5Blank Analysis Results 2021-2022

 

Blanks are inserted and analyzed to confirm that there is no sample-to-sample contamination. Figure 9-7 illustrates the results of blank submissions during 2021 – 2022. The results indicate only one value reported with a potentially economic gold grade out of 495 blank submissions.

 

Hycroft Mine Project

Page 78

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-7: Blank Results, 2021 – 2022

 

 

Source: IMC, 2022

 

9.3.6Duplicate Assays, 2021-2022

 

Duplicate pulps were assayed to confirm the repeatability of results from the assay lab. During 2021-2022, 314 duplicates were re-assayed. Figure 9-8 summarizes the results of the duplicate checks. There are two results that are higher than expected. Those reflect an error rate of about 0.64%.

 

Figure 9-8: Duplicate Assay Results, 2021 – 2022

 

 

Source: IMC, 2023

 

Hycroft Mine Project

Page 79

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

9.3.7Standards 2023 – 2024

 

During 2023 and 2024, 70 drill holes were completed. Of that total, 44 were diamond drilling, the rest were RC drilling. The next few sections address the QA/QC completed by Hycroft during the period of 2023 through 2024.

 

During this period, 1,501 gold standards were inserted out of 18,893 gold assays, amounting to almost 8% of the assay count. However, only 36 silver standards were inserted during this period and all of those were during 2024. The explanation is that silver standards were inserted if there was observable high-grade silver mineralization. This procedure is inappropriate and should be corrected going forward so that the silver standards insertion rate is 5% of the total assay number.

 

The average grade of all silver assays during 2024 was 1.46 oz/ton. In the future, as silver values and volumes increase at Hycroft, silver bearing material will receive the same QA/QC diligence as gold.

 

Figure 9-9 illustrates the comparison of assayed gold values versus the standard value inserted into the assay stream.

 

Figure 9-9: Gold Standards 2023 – 2024

 

 

Source: IMC, 2025

 

Hycroft Mine Project

Page 80

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The results of this overview are consistent with previous work where the incorrect standard was inserted, or the wrong standard was recorded. The number of these occurrences is extremely small, and the gold standard results are acceptable for 2023-2024.

 

The 36 silver standards did not illustrate any bias, but the graph is not shown due to the insignificant number of silver standards.

 

9.3.8Blanks 2023-2024

 

Figure 9-10 summarizes the results of 1,013 blank insertions during 2023 and 2024 (6%). The results are positive with only one value at 0.045 g/t.

 

Figure 9-10: Blank Insertions 2004

 

 

Source: IMC, 2025

 

9.3.9Duplicate Assays 2023-2024

 

Three different types of duplicates samples were applied in 2023. The naming convention and the source of the duplicates is summarized below:

 

FDUP: Field duplicate, these were ¼ core for DDH holes and a second split from the rotary splitter for RC samples. IMC check procedure is to combine field duplicates with the core and RC field duplicates.
  
PDUP: Pulp duplicate, a second aliquot from the pulp is inserted into the sample stream to check the repeatability of the assay process.
  
CDUP: Coarse duplicate, a second split from the coarse rejects is taken during the sample preparation process. The coarse duplicate is meant to check on the repeatability of the pulp preparation and assaying combined.

 

The above duplicates were assayed for both gold and silver and compared to the original values of gold and silver to confirm the overall process repeatability (precision). The results of all three duplicate types for both gold and silver produced similar statistical mean and standard deviation results for all tests. All tests comfortably passed the Student’s T test illustrating that they represent the same population with a high degree of confidence.

 

Figure 9-11 and Figure 9-12 illustrate the results for the gold and silver duplicate checks during 2023-2024 respectively.

 

Hycroft Mine Project

Page 81

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-11: Gold Duplicates, 2023-2024

 

 

Source: IMC, 2025

 

Hycroft Mine Project

Page 82

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-12: Silver Duplicates, 2023-2024

 

 

Source: IMC, 2025

 

Hycroft Mine Project

Page 83

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

9.3.10Check Assays 2023-2024

 

During 2023 – 2024, 668 sample pulps were sent to an outside laboratory for independent checks on the primary assay lab. The primary lab changed from Paragon to ALS Chemex between 2023 and 2024. However, the check assays were all completed at AAL. The check assay rate is about 3.5% out of the total number of over 18,800 assays during 2023 through 2024.

 

Basic statistical analysis of the original versus check assays indicate that the check data report the same population as the primary lab with better than 95% confidence. Figure 9-13 and Figure 9-14 illustrate X-Y plots of the original assays versus check assays for 2023-2024.

 

Figure 9-13: Gold Check Assays 2023 – 2024

 

 

Source: IMC, 2025

 

Hycroft Mine Project

Page 84

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 9-14: Silver Check Assays, 2023-2024

 

 

Source: IMC, 2025

 

9.3.11DDH vs. RC for Post 2000 Samples

 

The drillhole database at Hycroft is predominately based on RC drilling with some DDH. Prior to 2000, the database does not provide a record regarding the type of drilling applied, although it was reported to be largely RC.

 

Since 2000, the database records whether the drilling was RC, DDH, or sonic. All the DDH drilling was completed after 2006. The sonic drilling was applied in stockpiles which are a minor component of the MRE.

 

The RC data was compared to DDH drilling using the nearest neighbor method that was described in the previous sub-section. Table 9-1 summarizes the results of that comparison.

 

Hycroft Mine Project

Page 85

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 9-1: Nearest Neighbor Sample Comparison of RC vs Diamond Core Gold and Silver Assays

 

Maximum Separation Distance (ft) Number of Sample Pairs

RC Mean

(oz/ton)

DDH Mean

(oz/ton)

Ratio of the Means T-Statistic1
Gold
10 1114 0.006 0.005 0.903 0.976
20 3207 0.006 0.006 0.965 0.681
Silver
10 1042 0.197 0.281 1.428 0.971
20 3005 0.296 0.224 0.757 1.512

 

Note:

1.T-Statistics is the Smith-Satterthwaite T for large populations

 

The results indicate that the RC and DDH drilling information provide similar results for the post-2006 drilling and that they can be combined for estimation of mineral resources.

 

9.3.12Old vs. New Drilling

 

Early technical reports regarding Hycroft mineral resources had reported that all gold assays prior to 2000 were factored upward. Those in acid leach alteration were factored upward by 1.32 and all others upward by 1.19 (Hycroft Project Mill Expansion Feasibility Study Technical Report, October 31, 2016, and Technical Report, Allied Nevada Gold Corp, Hycroft Mine, October 2011).

 

Detailed checks on the certificates of assay indicate that the gold assay information used by Hycroft and provided to IMC for use in this MRE has not been factored in any way and the database matches the original certificate of assay.

 

A comparison of pre-2000 drilling and gold assay results versus the 2005-2024 gold assay results indicates that the old data averages higher grade than the new data when compared on a nearest neighbor basis. To identify the source of this bias, the pre-2000 data was analyzed on a year-by-year basis against the 2005-2024 drilling assay data. The 2005-2024 data set has been illustrated to be reliable based on the QA/QC analysis reported on previous pages and on the DDH-RC comparisons reported in the previous sub-section.

 

A nearest neighbor analysis was completed comparing 1999 drilling versus 2005-2024. That was followed by analysis of 1998 versus 2006-2024. This process was completed annually for all years prior to 2000. The results for years 1988 through 1999 were stable and compare acceptably with the 2005-2024 data. However, once 1987 and earlier years were compared against the 2005-2024 data, an obvious high bias was identified in the 1982 to 1987 data.

 

To summarize the results, the 1982-1987 data is compared to the 2005-2024 data on a nearest sample basis. These results were completed for sample distances as close as 5 ft for assay data.

 

Hycroft Mine Project

Page 86

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 9-2: Nearest Neighbor Sample Comparison of 1982-1987 Gold Assays Versus 2005 – 2024 Gold Assays

 

Maximum Separation Distance (ft)

Number of Sample

Pairs

1982-1987 Mean

(oz/ton)

2006-2024 Mean

(oz/ton)

Ratio of the Means T-Statistic1
5 164 0.020 0.012 1.67 3.98
10 300 0.025 0.017 1.47 4.24
20 803 0.020 0.011 1.82 8.41
30 1,635 0.018 0.010 1.80 10.43
40 2,746 0.017 0.010 1.70 12.47

 

Note:

1.T-Statistics is the Smith-Satterthwaite T for large populations

 

The above data excludes the stockpile drilling and includes all hard rock data that is located within the block model area.

 

The results of Table 9-2 indicate that the 1982-1987 gold assays are between 1.47 and 1.80 times higher than the 2005-2024 gold assays. The T-Statistic reported on the right side of the table is comfortably above the value of 2.0 for the sample separation distances. If the T-Statistic is greater than 2.0 one should reject that the two data sets are similar.

 

The above analysis indicates that the 1982-1987 data is biased high and unreliable relative to the more modern 2005-2024 drilling and assaying. The 1982-1987 drilling is reported to be RC drilling completed by an early predecessor of the current Hycroft management. Hycroft and IMC have not found any record regarding the RC sampling methods that were applied during that time that would shed light on the cause or source of this bias.

 

Half of the 1982 to 1987 database has been mined out. Discussion with retired Hycroft staff has indicated that production reconciliation was difficult during that period. However, the 1982-1987 data set does indicate the presence of mineralization. To capture that mineralization in the potential resource, IMC and Hycroft have completed the following steps:

 

1.The 1982-1987 gold data (composites) were multiplied by 0.56 to remove the observed high bias. There are no fire silver assays recorded during that period.
  
2.Block gold grades were estimated without the 1982-1987 data and were frozen so that they could not be changed.
  
3.Block grade estimation for gold was repeated including the bias corrected 1982-1987 data.
  
4.If a block received a gold grade in this process that was not previously assigned, it was added to the model and coded as “Inferred” class mineralization.
  
5.The resource floating cone was regenerated with the additional 1982-1987 inferred resource blocks.

 

In summary, a bias corrected version of the 1982-1987 data was incorporated so that any component of the resource based on that data is coded as “Inferred.”

 

9.3.13Downhole Surveys

 

The Mine operates on a local mine survey grid that is rotated 15.85 degrees from the Nevada state plane coordinate system. Down-hole survey data from the drill rigs reports directly in true north coordinates, requiring all holes to be rotated into the Hycroft grid.

 

Hycroft personnel have spent substantial amount of time checking the downhole survey bearings against the original downhole survey logs. The data is stored in both state planes, and the Hycroft grid in the Hycroft system. Hycroft and IMC have confirmed that the down-hole surveys used for the MRE are in the mine grid, consistent with the resource model and historic and potentially future mine planning.

 

9.4QP Comment

 

The work outlined in this section is a summary of over a year’s worth of data verification and checking by Hycroft and IMC personnel. As a result, the Hycroft and IMC teams have gained significant confidence in this data set. IMC holds the opinion that the database as utilized in this statement of mineral resources inclusive of the edits and corrections outlined is appropriate for the estimation of mineral resources. The 1982-1987 data set has been incorporated so that it only contributes to inferred category mineral resource after correction for the high bias of that data.

 

In the future, IMC recommends that complete QA/QC procedures be applied to silver and sulfide sulfur assaying and sampling. Regular sampling for QA/QC should be applied to those values in the same way as they have been recently applied to gold.

 

Hycroft Mine Project

Page 87

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10Mineral Processing and Metallurgical Testing

 

10.1Introduction

 

Hycroft has been operating the Mine as an open pit mine with a ROM heap leach facility (HLF) treating oxide ores to produce gold and silver since 2008. Prior to that, Vista Gold operated the Mine in a similar manner. As a result, the cumulative performance statistics and metallurgical test data gathered for the direct cyanidation of high-grade ROM oxide ore via heap leach are extensive and are not the focus of this report.

 

No metallurgical testwork has been completed on transition material for heap leach processing. As a result, heap leach recovery, leach kinetics, reagent consumption, and permeability characteristics remain uncertain. To reduce this technical uncertainty and improve confidence in the process design and economic evaluation, a dedicated transition material heap leach metallurgical testwork program is recommended during the next study phase.

 

The following subsections focus on metallurgical testwork conducted by Hycroft on extraction of Au and Ag from refractory sulfide mineralization.

 

The metallurgical test programs conducted on the Hycroft sulfide mineral deposits over the years have consisted of comminution, flotation, concentrate oxidation, and cyanide leaching tests on mineralized materials, flotation tailings, and oxidized sulfide concentrate samples. The samples were mostly derived from drill cores. Most of the flotation testwork were conducted at G&T Metallurgical Services (G&T) and SGS Canada Mineral Lakefield (SGS), both located in Canada, as well as by Hazen Research Inc. (Hazen) in Colorado. Oxidation testing was primarily conducted by Hazen, SGS and Kappes, Cassiday & Associates (KCA). G&T (ISO – 9001:2008) and SGS (ISO – 17025:2017) both have ISO accreditation. All laboratories are independent of Hycroft.

 

In general, core samples for metallurgical testing were selected to be representative of the mineralized materials, drawing from five mineralization domains, as they were classified at the time. The primary sources included the Brimstone and Vortex domains.

 

The metallurgical testwork programs were carried out by independent, third-party, ISO accredited laboratories using established and widely accepted industry standard analytical and metallurgical procedures. These include conventional methods for comminution, flotation, oxidation, and cyanide leaching applicable to the mineralization types under evaluation.

 

In the opinion of the Qualified Person, the analytical procedures and resulting data are appropriate for the level of study and are sufficient to support the conclusions and technical disclosures presented in this report. No non-conventional or experimental procedures requiring additional justification have been identified.

 

Hycroft Mine Project

Page 88

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.2Metallurgical Testwork

 

10.2.1Summary of Metallurgical Testwork Programs

 

Table 10-1 summarizes the metallurgical testwork programs completed to date for the Hycroft sulfide mineralization, including the testing laboratory/location and the primary testwork performed. These third party, industry recognized laboratories are independent of Hycroft. All data and information have been generated in accordance with their respective quality assurance and quality control (QA/QC) policies and procedures and were reviewed and approved by qualified laboratory personnel prior to being used in this Technical Report.

 

Table 10-1: Metallurgical Testwork Summary

 

Year Laboratory/Location Testwork performed
2009-2014 SGS Minerals Services (Lakefield, Canada) Flotation testwork
2011 Kappes, Cassiday & Associates (Reno, USA) Flotation, batch and locked-cycle testing
2011 G&T Metallurgical Services Ltd. (Kamloops, Canada) Flotation testing
2011-2016 Hazen Research, Inc. (USA) Flotation variability testing; concentrate oxidation tests
2013 SGS Minerals Services (Lakefield Canada and South Africa) BIOX testing
2014 Hazen Research, Inc (USA) Pilot plant flotation testing
2021-2025 FLSmidth Minerals Testing (Salt Lake City, USA) Flotation variability testing
2024-2025 Hazen Research, Inc (USA) Concentrate oxidation testing

 

10.2.2Mineralized Materials and Sampling

 

Hycroft mineralized materials are classified as oxide, transition, or sulfide based on the cyanide solubility of its gold, which is used as an indicator of refractoriness. Materials with cyanide soluble gold of 70% or greater are classified as oxide, while material with cyanide soluble gold of less than 30% is classified as sulfide. Material with a cyanide soluble ratio between 30% and 70% is classified as transition. The classification has been shown to have no strong correlation with sulfide sulfur content.

 

10.2.3Hycroft Mineralization Domains

 

The Hycroft mineral deposit consists of five process domains, namely Bay, Boneyard, Brimstone, Central, and Vortex.

 

Table 10-2 is a summary of the data for average total sulfur, sulfide sulfur, and the ratio of sulfide sulfur to total sulfur from 95 oxide, 158 transition, and 417 sulfide samples collected from the Brimstone, Central, and Vortex domains. It shows that the classification of mineralized material as oxide, transition, or sulfide is essentially a measure of refractoriness and shows little correlation with sulfide-sulfur content of the minerals. The sulfide-sulfur to total sulfur ratio averages slightly over 80% across the entire dataset, indicating that degree of sulfur oxidation is similar among oxide, transition, and sulfide classifications.

 

Hycroft Mine Project

Page 89

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 10-2: Average Sulfur Contents of Oxide, Transition and Sulfide Mineralized Materials

 

Total S (ST), % Oxide (%) Transition (%) Sulfide (%)
Brimstone 2.55 2.41 2.25
Central 2.94 2.82 2.48
Vortex 2.47 2.66 2.33
Unclassified 4.28 2.92 2.61
All 3.00 2.74 2.43
Sulfide S (S=), % Oxide (%) Transition (%) Sulfide (%)
Brimstone 2.19 2.06 1.87
Central 2.36 2.26 1.80
Vortex 2.09 2.23 1.91
Unclassified 3.29 2.23 2.09
All 2.45 2.23 1.93
S=:ST Ratio Oxide (%) Transition (%) Sulfide (%)
Brimstone 0.839 0.839 0.820
Central 0.810 0.806 0.797
Vortex 0.880 0.827 0.833
Unclassified 0.840 0.823 0.843
All 0.849 0.819 0.824

 

10.3Legacy Testwork

 

Table 10-3 below lists the number of samples selected to span three historically defined main domains and their distribution within the Hycroft mineral deposit.

 

Information on the individual core samples selected for testing can be found in the metallurgical test reports referenced in this study.

 

Table 10- 3: Summary of Test Samples

 

Tests Number of Samples per Domain
Central Brimstone Vortex Composite
Crushing (CWi) 1 1 5 7
Axb (Drop Wt & SMC) 13 6 9 32
Bond BWi 24 6 16 58
Bond RWi 2 1 0 5
Bond Abrasion 3 1 5 12
Flotation 11 13 24 48

 

Hycroft Mine Project

Page 90

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.1Comminution Tests

 

The Hycroft mineralized material has been extensively characterized for its comminution properties in previous studies. Comminution tests were conducted at the laboratories of SGS, G&T, Hazen, and Phillips, and included crushing and grinding work indices, JKSimMet parameters, and abrasion indices.

 

A summary of the 80th-percentile comminution test results is presented in Table 10-4 below. For the Axb parameter, material competence increases as Axb decreases, therefore, the 80th-percentile in material competence corresponds to the 20th-percentile of Axb value. The results indicate that the Hycroft mineralized material is very competent.

 

Table 10-4: Grindability Test Summary

 

Parameter Unit Value
CWi kWh/ton 18.6
RWi kWh/ton 21.2
BWi kWh/ton 20.1
Axb Unitless 34.2
SPI min 102.4
Ai g 0.623

 

10.3.2Flotation

 

Refractory gold in Hycroft’s sulfide mineralized materials is believed to be associated with iron sulfides, primarily pyrite and marcasite. The objectives of the flotation testwork were to evaluate the floatability of the sulfide minerals and the recovery of gold and silver into a sulfide concentrate. Recovering gold and silver into a sulfide concentrate reduces the volume of material requiring downstream processing.

 

Initial flotation testwork was performed by SGS in March 2009 and continued at several laboratories through April 2014. Over this period, the testing program progressed from bench-scale flotation tests to pilot plant flotation testing conducted at G&T and Hazen.

 

Hycroft Mine Project

Page 91

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.2.1SGS Minerals Services (Lakefield) – March 2009

 

Six drums containing samples representative of the Hycroft Project were shipped to SGS Minerals Services (Lakefield) on September 5, 2008.

 

The initial flotation test development program consisted of three bench-scale rougher kinetics tests to evaluate the effect of primary grind size on flotation response. A standard bulk sulfide collectors suite, comprising potassium amyl xanthate (PAX) and dithiophosphate (Cytec AF 208), was used in conjunction with Dowfroth 250 as the frother. An additional five bench-scale tests were conducted to investigate alternative reagent schemes and grind sizes.

 

Flotation testwork was conducted on the Master Composite sample. The flotation investigation consisted of the following:

 

Two-stage cleaner flotation applying the flowsheet developed during phase 1 testing (program 12012-001).
  
Cyanide leaching of the second cleaner flotation concentrate.
  
Cyanide leaching of the recombined rougher and first cleaner scavenger tailings.

 

SGS stated “In terms of sulfide flotation, it appears that beyond about 10% mass pull, recoveries were on the same grade vs. recovery curve regardless of grind fineness.”

 

10.3.2.2SGS Minerals Services (Lakefield) – Nov 2010

 

Batch tests were completed on 33 sulfide zone composites representing the Vortex (18), Cut 5 (four), Bay Area (10), and Bone Yard (one) deposits of the Mine sulfide resource. Multiple rock types were represented in the composites. The testwork evaluated metallurgical variability in response to the flotation (and cyanidation) flowsheet previously developed for the Master Composite under program 12012-001.

 

Metallurgical variability testing consisted of rougher flotation followed by concentrate regrinding and two-stage cleaning. In the initial set of tests, the second cleaner concentrate was cyanide leached. Based on review of those results, cyanide leaching was subsequently refocused on the combined rougher and first cleaner scavenger tailings.

 

From these tests, gold recovery in rougher flotation ranged from ~62% at a mass pull of ~15% (Test F-2, P80 of ~103 μm) to ~69% at a mass pull of ~17% (Test F-1, P80 of ~128 μm). At comparable mass pulls, silver recovery ranged from 74% (Test F-2) to 85% (Test F-1). The addition of a dithiophosphate collector (Cytec A208) in Test F-5 further improved Au recoveries to 80.1% at a mass pull of 14.6%.

 

10.3.2.3KCA Batch Tests – Jan 2011

 

In December 2010, KCA received material from the Hycroft project at its laboratory facility in Reno, Nevada. Portions of the received material were composited, as directed, to generate six composite samples for metallurgical testing. Initial testwork was conducted by KCA and reported in the study titled “PAX, pH, and Grind Flotation Kinetics Study” (January 2011). Additional flotation testing was subsequently completed, including cyanide leach testing of flotation products.

 

10.3.2.4KCA Locked-Cycle Tests – May 2011

 

Portions of the six composites were combined to generate two master composites, a Sulfide Master Composite and a Mixed Master Composite. Additional flotation testing was conducted using material from these composites, including cyanide leach testing of the flotation tailings.

 

10.3.2.5G&T Metallurgical Services Ltd. – Feb 2011

 

Five separate shipments of samples were received at G&T between August 31 and December 3, 2010. The samples consisted of half HQ drill core, with a total estimated mass of approximately 2.9 tons. These samples were used to construct 39 composite samples for flotation and cyanidation testing.

 

For the first set of 24 composites, a single stage batch cleaner flotation test was performed. For the second set of samples (M1 to M17), a simplified flotation flowsheet was applied, using a reduced reagent scheme consisting of PAX and MIBC only. Under this simplified flowsheet, the flotation froth was more stable and more representative of a typical sulfide flotation froth compared to the original flowsheet. Overall, the samples responded well to flotation. Across all 39 composite samples, average flotation recoveries to the rougher concentrate were about 78% for Au and 67% for Ag.

 

Using this revised flowsheet applied to samples M1 to M17, average rougher recoveries were 78% for Au and 83% for Ag. These recoveries generally correlated with sulfide sulfur recovery to the rougher concentrate. Table 10-5 and Table 10-6 show the results of this testwork.

 

Hycroft Mine Project

Page 92

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 10-5: G&T Composites 1 through 24 Flotation Test Results

 

Sample ID

ST

(%)

S=

(%)

Au (oz/ton) Ag (oz/ton) Rougher Conc
Mass Pull, (%)
Au Recovery
to conc, (%)
Ag Recovery
to conc, (%)
Type
G&T Composite 1 0.70 0.62 0.009 3.968 13.3 80.1 77.3 Sulfide
G&T Composite 2 2.48 2.49 0.145 11.136 13.2 79.6 63.2 Transition
G&T Composite 3 2.29 2.28 0.076 11.872 12.2 82.7 61.9 Transition
G&T Composite 4 1.25 1.22 0.008 18.016 9.1 60.4 27.7 Sulfide
G&T Composite 5 1.50 1.40 0.045 0.496 12.9 83.1 83.6 Sulfide
G&T Composite 6 1.64 1.51 0.027 23.136 15.0 88.3 72.6 Sulfide
G&T Composite 7 1.36 1.29 0.010 9.504 15.7 94.5 37.8 Sulfide
G&T Composite 8 1.33 1.26 0.027 4.000 13.1 89.4 50.5 Sulfide
G&T Composite 9 4.30 3.81 0.021 0.602 16.5 86.5 88.5 Sulfide
G&T Composite 10 2.23 2.04 0.014 1.946 11.6 80.5 60.1 Sulfide
G&T Composite 11 2.80 2.72 0.027 8.064 17.8 88.1 53.9 Transition
G&T Composite 12 1.57 1.25 0.113 1.680 8.3 73.6 44.8 Oxide
G&T Composite 13 2.32 2.02 0.065 1.472 11.6 56.1 68.2 Transition
G&T Composite 14 2.08 1.34 0.004 1.818 7.8 89.5 30.2 Sulfide
G&T Composite 15 1.78 1.71 0.043 5.376 10.8 94.0 63.2 Transition
G&T Composite 16 2.64 2.27 0.022 0.627 14.9 77.2 76.9 Sulfide
G&T Composite 17 0.45 0.34 0.093 0.198 5.2 28.1 27.5 Oxide
G&T Composite 18 1.33 1.08 0.014 0.074 11.8 58.7 61.2 Sulfide
G&T Composite 19 2.00 1.76 0.012 0.266 15.7 69.9 50.3 Sulfide
G&T Composite 20 13.70 11.80 0.045 0.992 31.2 93.7 87.1 Sulfide
G&T Composite 21 2.06 1.97 0.019 0.598 13.1 85.6 74.9 Sulfide
G&T Composite 22 1.73 1.70 0.025 0.464 13.1 61.2 60.7 Sulfide
G&T Composite 23 1.72 1.31 0.016 2.099 11.1 87.5 53.7 Sulfide
G&T Composite 24 2.00 1.92 0.024 3.584 15.5 85.4 38.9 Sulfide
Average Sulfides 2.56 2.25 0.020 4.246 14.2 80.7 60.7  
Average All 2.39 2.13 0.037 4.666 13.4 78.1 58.9  

 

Hycroft Mine Project

Page 93

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 10-6: G&T Composites M-1 through M-17 Flotation Test Results

 

Sample ID

ST

(%)

S=

(%)

Au (oz/ton) Ag (oz/ton) Rougher Conc
Mass Pull, (%)
Au Recovery
to conc, (%)
Ag Recovery
to conc, (%)
Type
G&T Composite M-1 1.98 1.81 0.038 0.378 13.4 86.4 82.4 Sulfide
G&T Composite M-2 2.62 1.75 0.013 1.082 14.2 82.1 85.9 Sulfide
G&T Composite M-3 1.20 1.12 0.014 0.272 12.7 73.6 83.2 Sulfide
G&T Composite M-4 1.62 1.55 0.020 0.150 18.1 79.7 76.8 Sulfide
G&T Composite M-5 1.81 1.70 0.013 0.128 18.8 76.9 72.7 Sulfide
G&T Composite M-6 1.92 1.79 0.016 0.253 20.8 79.1 76.4 Sulfide
G&T Composite M-7 No Data - - - - - - -
G&T Composite M-8 No Data - - - - - - -
G&T Composite M-9 2.25 2.06 0.011 0.586 10.9 89.7 92.7 Sulfide
G&T Composite M-10 2.50 2.00 0.012 2.454 11.6 76.7 96.0 Sulfide
G&T Composite M-11 1.55 1.49 0.016 1.475 8.3 80.4 96.4 Sulfide
G&T Composite M-12 1.86 1.30 0.016 3.840 10.4 80.4 97.3 Sulfide
G&T Composite M-13 6.34 2.99 0.046 1.043 13.0 85.7 86.8 Sulfide
G&T Composite M-14 5.53 2.32 0.020 0.288 16.0 88.2 84.1 Transition
G&T Composite M-15 2.32 1.15 0.024 1.584 7.0 44.9 61.3 Oxide
G&T Composite M-16 2.51 2.43 0.017 0.486 14.3 74.6 87.8 Transition
G&T Composite M-17 1.52 1.39 0.017 0.259 16.1 65.1 62.8 Sulfide
Average Sulfides 2.26 1.75 0.019 0.993 14.0 79.7 84.1  
Average All 2.50 1.79 0.020 0.943 13.7 77.6 82.8  

 

10.3.2.6Hazen Research, Inc. – August 2011

 

For this investigation, 38 drillhole composite samples representing five mineralized material types were evaluated. Initial flotation testing was conducted using sodium hydrosulfide (NaHS) and copper sulfate (CuSO4). In subsequent tests, the NaHS and CuSO4 were eliminated, and lead nitrate (Pb(NO3)2) was introduced as a modifying agent. Following the addition of modifying agents, flotation pH ranged from neutral to 10.5, and redox potential was monitored throughout the testing program.

 

A series of 91 small-scale flotation tests were performed on 4.4-lbs splits from the 38 composite samples. The objective of this testwork was to evaluate variability in flotation response among the composite samples.

 

An additional 41 small-scale flotation tests were subsequently performed on Composites 1 through 38, excluding Composites 6, 8, 9, and 10, using rougher flotations conditions based on G&T Metallurgical conditions and conditions recommended by Hazen. Rougher concentrate mass pulls ranged from 4.9% to 30.7%, with corresponding Au recoveries ranging from 26.9% to 97.6% and Ag recoveries ranging from 17.1% to 98.7%.

 

The rougher concentrate assays ranged from 0.032 oz/ton Au (Test 3346-82) to 1.536 oz/ton Au (Test 3346-40), and from 0.224 oz/ton Ag (Test 3346-82) to 73.601 oz/ton Ag (Test 3346-68). The recoveries of Au and Ag to the rougher concentrates ranged from 27% (Test 3346-52) to 91% (Test 3346-68) and from 17% (Test 3346-52) to 99% (Test 3346-68), respectively.

 

Hycroft Mine Project

Page 94

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.2.7Effect of Grind Size on Flotation Performance

 

Most flotation tests on Hycroft samples were performed on materials ground to 80% passing 100 µm. Additional tests were conducted at both finer and coarser grind sizes. Overall, the results indicate that flotation achieves favorable recoveries at grinds ranging from 100 to 150 µm. Gold and silver recoveries generally decreased with grind sizes finer than 100 µm or coarser than 150 µm.

 

10.3.2.8Reagent Suite

 

Both G&T and Hazen concluded that flotation tests using NaHS as a sulfurizing agent, as well as tests conducted at alkaline pH, generally resulted in poor flotation performance.

 

The exploratory and variability flotation test results discussed above demonstrate that sulfide mineralized materials can be floated to recover gold and silver. The reagents schemes employed relied on strong, non-selective sulfide collectors, with frothing achieved using methyl isobutyl carbinol (MIBC), Dowfroth 250 (DF250), or a combination of both. Table 10-7 summarizes the reagent schemes applied by G&T, SGS, and Hazen. In all laboratory test programs, the reagent dosages were relatively high.

 

Table 10-7: Flotation Reagent Schemes Studied

 

Reagent (lb/ton) G&T Laboratory Hazen SGS
NaHS - 0, 2.56 2.1
PAX 0.552 0.546, 0.416 0.21
3418A - 0, 0.064 - 0.124 0.055
MIBC 0.05 - 0.128, 0.192 0.02 - 0.064 -
DF250 - 0.02 - 0.064 0.095

 

Based on the test results from the three laboratories, particularly G&T, the simplified reagent scheme can be further developed. Several tests indicate that Cytec’s AEROPHINE® 3418A Promoter (sodium diisobutyldithiophosphinate) may improve Au and Ag recoveries.

 

10.3.2.9Flotation Time

 

Flotation kinetics were not systematically evaluated during the flotation test programs. However, flotation data generated from the G&T testwork on the M Composites included recoveries from froth collected at 4, 8, 12, and 16 minutes. A total of 15 rougher flotation tests were performed. Kinetics plots for Au and Ag derived from this work are shown in Figure 10-1. To avoid visual clutter, only selected data points are shown, along with asymptotic recovery curves fitted to the data.

 

Hycroft Mine Project

Page 95

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

For each of the 15 datasets, the maximum recovery, Rmax and the kinetics constant, K were derived from the fitted asymptotic curves.

 

The results indicate that the average laboratory flotation time required to achieve 95% of the maximum recovery is 19 minutes for gold and 17 minutes for silver.

 

Figure 10-1: Recovery Vs. Time Plot, G&T Kamloops Tests, M Composites

 

 

Source: M3, 2016

 

10.3.2.10FLSmidth 2021

 

In 2021, Hycroft initiated a new metallurgical variability study to evaluate mineralized material characteristics within the current mine plan validate the metallurgical behavior of material across the mine site; and identify potential variations in processing conditions required to recover gold and silver. The objective of the study was to support development of a robust Hycroft process flowsheet, including definition of key process control points in crushing, grinding, capable of consistently achieving gold and silver recovery across anticipated metallurgical variability. Hycroft selected 243 Samples from 65 different drill holes, all within the current resource, representing the three primary metallurgical domains – Brimstone, Vortex, and Camel. The drill holes encompassed material ranging from near surface elevations to approximately 1,235 ft below current elevations (3,040 ft above mean sea level). Two primary lithologies were represented, corresponding to material located east and west of the Central Fault. The sample suite covered a broad range of alteration and mineralization characteristics, including four silicification intensities - Strong quartz-K-feldspar, strong quartz, moderate, and weak; two alunite styles based on vein width and frequency (used to estimate volume percent and validated by sulfide sulfur content; and gold grades ranging from slightly below the cutoff grade of 0.2 g/t to values exceeding above 2.0 g/t. oxide and transition ore types were not included in this study; it is envisioned that in the future, these materials will be processed in the heap leach pads.

 

Figure 10-2 to Figure 10-5 present the head grade distribution plots for gold, silver, total sulfur, and sulfide sulfur, based on the full set of 243 variability study samples.

 

Hycroft Mine Project

Page 96

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 10-2: Gold Grade Distribution Chart

 

 

Source: Hycroft, 2025

 

Figure 10-3: Silver Grade Distribution Chart

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 97

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 10-4: Total Sulfur Grade Distribution

 

 

Source: Hycroft, 2025

 

Figure 10-5: Sulfide Sulfur Grade Distribution

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 98

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The head grade distributions for gold, silver, total sulfur, and sulfide sulfur across the 243 variability study samples indicate a broad but well-represented range of metallurgical conditions within the current resource. Gold head grades exhibit a right-skewed distribution with an average of approximately 0.56 g/t and a standard deviation of 0.64 g/t, reflecting the inclusion of material spanning from near cutoff grades to higher-grade mineralization. Silver grades show a wider distribution, with an average of approximately 12.4 g/t and a higher standard deviation (14.3 g/t), indicating greater variability in silver tenor relative to gold.

 

Total sulfur and sulfide sulfur distributions demonstrate moderate variability, with average grades of approximately 2.60% total sulfur and 2.17% sulfide sulfur, and standard deviations of 2.00% and 1.64%, respectively. The close correspondence between total sulfur and sulfide sulfur indicates that sulfur is predominantly present as sulfide minerals, consistent with the refractory nature of the ore. Collectively, these distributions confirm that the variability study sample set adequately captures the range of grade and mineralogical conditions expected within the mine plan, providing a sound basis for evaluating metallurgical response and defining robust process design criteria.

 

Important results of this study included the development of the flotation process with significantly improved recoveries. There were four key process controls parameters identified during the flotation process development program.

 

1.Optimal grind size is a P80 of less than 85 µm.
  
2.Flotation time is 24 minutes.
  
3.Adjusted pH level is 4.7.
  
4.Mass Pull is 20 to 25% with 22% being the target.

 

A total of 137 samples were tested under these selected conditions to achieve higher gold and silver recoveries. Figure 10-6 summarizes the distribution of gold and silver flotation recoveries achieved under the selected key process control conditions, based on 137 variability test samples. The results show that gold recovery exhibits a broader distribution, with values ranging from approximately 72% to 98% and a statistical median near 88%, indicating greater sensitivity to operating conditions. In contrast, silver recovery is generally higher and more consistent, with recoveries spanning approximately 76 to 100% and a statistical median exceeding 92%. Overall, the figures highlight the comparatively more robust flotation response of silver relative to gold under the selected operating conditions.

 

Hycroft Mine Project

Page 99

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 10- 6: FLS Variability Flotation Recoveries under Optimal Conditions (137 Test Samples)

 

 

Source: Hycroft, 2025

 

Figure 10-7 and Figure 10-8 show that flotation recovery is only weakly correlated with head grade for both metals. Gold recoveries display greater variability within grade groups, particularly at lower head grades, indicating sensitivity to mineralogical and metallurgical factors beyond grade alone. In contrast, silver recoveries are consistently higher and more uniform across head grade groups, demonstrating a more robust and less grade-dependent flotation response.

 

Hycroft Mine Project

Page 100

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 10- 7: FLS Variability Flotation Gold Recoveries Based on Gold Head Grade Groups

 

 

Source: Hycroft, 2025

 

Figure 10- 8: FLS Variability Flotation Silver Recoveries Based on Head Grade Groups

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 101

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.3Direct Cyanidation

 

Direct cyanidation testwork on bulk concentrate samples (P80 = 325 mesh, or 44 µm) collected from all zones of the deposit was conducted in early 2010. The results indicated generally poor metallurgical performance. Gold recoveries for the Brimstone and Vortex samples were in the mid-20% range, with silver recoveries of approximately 80%. The remaining samples yielded gold recoveries ranging from 45% to 50% and silver recoveries ranging from 55% to 83%.

 

A useful indicator of direct cyanidation amenability is the ratio of cyanide soluble metal to total metal assay, expressed as AuCN/AuFA for gold and AgCN/AgFA for silver. These ratios have been determined for many exploration samples and have been included in the resource database. The cyanide soluble gold ratio has been applied during resource estimation to assist in mineral classification and routing, with mineralized domains exhibiting higher cyanide soluble gold preferentially directed to heap leach processing.

 

10.3.4Concentrate Oxidation Tests

 

Oxidation testwork on Hycroft flotation concentrates evaluated POX, roasting, atmospheric oxidation, and other oxidation methods, all of which demonstrated technical viability with varying recoveries. The results of these tests are summarized below.

 

Beginning in 2007, Hycroft investigated milling and flotation of refractory sulfide mineralized material followed by oxide treatment, focusing primarily on POX, and roasting technologies commonly applied in the gold industry.

 

In 2012, additional testwork assessed alternative, low capital oxidation methods, including chlorination, atmospheric alkaline oxidation, and fine grinding with intensive cyanidation. These tests showed that the Hycroft rougher concentrates were amenable to oxidation under atmospheric conditions, leading to pilot scale testing on three main metallurgical domains at Hazen.

 

In 2016, Hycroft developed an oxidation demonstration plant at the mine site to process flotation concentrates and produce doré onsite. Based on historical and current oxide heap leach performance, combined with oxide heap leach metallurgical testwork and bench-, pilot-, and demonstration-scale metallurgical test results, individual gold and silver recoveries for each processing stream were calculated and are presented in Table 10-8. This recovery assumption formed the basis of the 2016 NI 43-101 Feasibility Study Technical Report published in 2016 (Ibrado, A. et al, 2016).

 

Table 10- 8: Estimated Metallurgical Recoveries from 2016 Feasibility Study – Gold and Silver

 

  Gold Silver
Contained (koz) Recovered (koz)

Recovery

(%)

Contained

(koz)

Recovered (koz)

Recovery

(%)

Heap Leach 3,875 1,933 49.9 21,242 21,242 15.5
Mill-AAO Sulfide 7,797 5,696 73.0 287,693 287,693 81.6
Total 11,672 7,629 65.4 489,447 308,935 63.1

 

Hycroft Mine Project

Page 102

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.4.1Atmospheric Oxidation – Batch Tests

 

From 2013 through 2016, metallurgical testing focused on developing a process to oxidize sulfide flotation concentrates under atmospheric conditions. The process concept involved oxidation in an agitated slurry at elevated temperatures, using oxygen as the oxidant. Batch oxidation tests were conducted at Hazen under various conditions on concentrates derived from Central, Brimstone, and Vortex composites.

 

The results demonstrated that complete oxidation is not required to achieve high precious metal recoveries during subsequent cyanide leaching, consistent with earlier oxidation studies. Cyanidation recoveries of approximately 85% for gold and 92% for silver were achieved when about 60% of the sulfide-sulfur content in the concentrate was oxidized.

 

Oxidation reaction kinetics improved with increasing temperatures up to 75 °C. Tests conducted at higher temperatures (around 90 °C) resulted in slower oxidation rates, due to reduced oxygen solubility under bench-scale laboratory conditions.

 

10.3.4.2Pilot Plant Oxidation Tests

 

Continuous pilot testing was conducted at Hazen using 10-liter reactors on concentrates from three metallurgical domains. The pilot results confirmed the batch test findings. Testing was performed at 75°C a grind size of 25 µm, 20% solids, and a total residence time of 48 hours. Oxidation rates varied by material type, with Vortex oxidizing most rapidly, followed by Central and then Brimstone. The Master Composite exhibited oxidation behavior comparable to Brimstone.

 

Key outcomes from the pilot testing include:

 

gold recovery versus sulfide oxidation was higher than indicated by bench-scale testing
  
approximately 80% gold recovery was achieved at 50% sulfide oxidation for all material types
  
approximately 87% gold recovery was achieved at 60% sulfide oxidation for all material types.

 

10.3.4.3Hycroft Mill Demonstration Plant

 

Hycroft Mining constructed and operated a demonstration plant with a nominal capacity of 10 tons/d at the Mine site. The integrated flowsheet comprised of a ball mill, rougher flotation bank, concentrate and tailings thickeners, a regrind mill, oxidation and neutralization tanks, an oxidized concentrate thickener, cyanide leach tanks, CCD thickeners, and a Merrill-Crowe precipitation circuit. The plant was operated continuously, with concentrate surge capacity upstream of oxidation and pregnant solution storage upstream of Merrill-Crowe.

 

The demonstration plant processed Central and Brimstone materials mined from exposed mineralization at the surface of the current open pit.

 

Key demonstration plant results for Central material are presented in Figure 10-9. For clarity, only data from Tank 1 (TK1) and Tank 5 (TK5) are shown. Sulfide oxidation levels of 60% or greater were consistently achieved when steady-state operating conditions were maintained.

 

Hycroft Mine Project

Page 103

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 10-9: Oxidation of Central Flotation Concentrate: Sulfate Spike Test

 

 

Source: M3, 2019

 

Oxidation of the flotation concentrates resulted in a significant improvement in gold and silver recoveries compared to direct cyanidation. Cyanide leach recoveries of oxidized concentrates during demonstration plant operation are presented in Figure 10-10. The graph initially reflected Central concentrate processing and transition to Brimstone concentrates on June 11, 2016. Gold and silver recoveries for Central concentrate peaked at approximately 85%. For Brimstone concentrate, gold recovery reached approximately 80%, while silver recovery peaked at 90%. Overall recovery trends closely tracked the degree of concentrate oxidation.

 

Figure 10-10: Demonstration Plant Cyanide Leach Recovery of Au and Ag

 

 

Source: M3, 2019

 

Hycroft Mine Project

Page 104

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

10.3.4.4Pressure Oxidation

 

Previous POX testwork was conducted primarily by Hazen and SGS on various flotation concentrates derived from Hycroft sulfide mineralized material, including individual samples, composites samples, and two transition material samples. POX testwork was performed under both alkaline and acidic conditions.

 

The following is a list of all POX testwork reports provided to Ausenco:

 

Hazen Project 11232 Report and Appendices A-F, POX-CIL Evaluation of Hycroft Flotation Concentrates.

 

Hazen Project 11243-01 Report and Appendix, Evaluation of Hycroft Blend Flotation Concentrate.

 

Hazen Project 11307 Report and Appendix, Evaluation of Kappes, Cassiday & Associates Flotation Concentrate.

 

SGS Project 13224-001/003 Final Report, An Investigation into Oxidative Pre-treatment of Hycroft Flotation Concentrates.

 

SGS Hycroft Project – 12012-001 Report 3, The Recovery of Au and Ag from Hycroft Project Sulfide Samples, Allied Nevada Gold Corporation.

 

Kappes, Cassidy & Associates Project No. 189 C, Hycroft Pressure Oxidation and Leach Testwork.

 

Previous acid POX testwork was conducted on flotation concentrates to establish suitable operating criteria. Table 10-9 summarizes the alkaline POX testwork result, indicating that longer AC retention times still resulted in lower gold recovery, suggesting limited benefit from extended durations.

 

Table 10-10 summarizes the acid POX test results completed by Hazen, SGS and KCA.

 

The results indicate that the highest gold and silver cyanide amenability was achieved under conditions of an operating temperature between 374 °F to 437 °F, an oxygen overpressure of approximately 100 psi, and a residence time of 60 minutes. The POX test results also suggest that the concentrates may be prone to jarosites formation, which can inhibit silver recovery. Evidence for potential jarosite formation includes:

 

the acidic autoclave discharge pulp exhibited a yellow coloration, transitioning to reddish brown following lime boil conditioning

 

silver recovery was higher when the pulp was subjected to a lime boil, which exposed the hot pulp to alkaline conditions for several hours.

 

Hycroft Mine Project

Page 105

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 10-9: Hycroft Alkaline POX Testwork Summary

 

Flotation Concentrates Samples Sulfide (Stotal) (wt%)

Gold

(ppm)

Silver

(ppm)

AC Temp

(°F)

Solids

(wt%)

AC Retention Time

(min)

Oxygen Over-pressure

(Psig)

Caustic Consumption

(lbs/ton)

Cyanide Conc. (wt%) Gold recovery
(%)
Silver recovery
(%)
Brimstone 40.1 11.6 418 437 20 256 40 5.41 2 98.5 72.9
40.1 11.6 418 212 40 360 40 6.05 2 54.3 71.2
Hycroft Blend Float Concentrate 38.5 18.1 2,103 437 26 240 40 0.15 1 64.3 35.8
38.5 18.1 2,103 437 26 240 40 1.45 2 63.8 52.0
38.5 18.1 2,103 4,37 26 240 40 2.95 5 63.8 82.1

 

The gold and silver recoveries from rougher flotation concentrate subjected to acid POX, followed by lime boil conditioning and cyanide leaching were in the mid-90% range for gold and approximately the mid-80% range for silver (Table 10-10).

 

Acid POX followed by lime boil was evaluated during development of the MRE primarily due to its ability to consistently achieve high sulfide oxidation. Sulfide oxidation exceeding 95% is expected with POX, whereas AAO did not consistently achieve the target of 60%. As a result, gold and silver recoveries from POX residue are expected to be higher and more stable than those achieved using AAO. Additional factors for supporting the evaluation of POX included the following:

 

Limestone is a more cost-effective reagent for acid neutralization.

 

Cyanide consumption following pressure oxidation is lower than for AAO.

 

Soda ash was considered as an alternative to trona but was found to be less cost effective than limestone.

 

Table 10-10: Hycroft Acid POX Testwork Summary

 

Sulfide Concentrate
Samples Tested

Sulfide (S=)

(wt%)

Au (ppm) Ag1
(ppm)
Temp (°F)

Cyan. Conc.6

(ppt)

Sulfide Oxidation (%) Au recovery (%) Ag recovery (%) Test Lab
Brimstone 40.1 11.60 418 374 1 - 97.5 89.0 Hazen
Cut 4 36.9 11.40 168 374 1 - 94.0 94.1 Hazen
Camel 37.7 9.33 152 374 1 - 97.7 89.9 Hazen
Bay 22.1 6.03 52.3 374 1 - 97.5 75.3 Hazen
Bone Yard 31.9 5.97 95.3 374 1 - 96.0 86.0 Hazen
Hycroft Blend 38.5 18.10 2103 401 1 - 100.0 77.1 Hazen
Sulfide Master Ro 18.9 4.90 432 401 1 - 87.0 65.8 Hazen
Mixed Master Ro 9.3 8.50 193 401 1 - 82.8 86.4 Hazen
Central Blk Sul Ro 8.4 2.47 26 374 1 98.8 93.6 90.5 SGS
Central Blk Sul Cl 35.6 10.10 131 374 1 99.8 94.0 94.2 SGS
Vortex Blk Sul Ro 9.1 2.93 276 374 1 98.6 97.7 73.5 SGS
Vortex Blk Sul Cl 32.3 10.80 976 374 1 99.8 96.0 72.2 SGS

 

Hycroft Mine Project

Page 106

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Sulfide Concentrate
Samples Tested

Sulfide (S=)

(wt%)

Au (ppm) Ag1
(ppm)
Temp (°F)

Cyan. Conc.6

(ppt)

Sulfide Oxidation (%) Au recovery (%) Ag recovery (%) Test Lab
Central Sul Cl 30.7 10.30 750 374 1 98.1 93.5 81.9 SGS
Brimstone Sul Cl 34.7 7.93 392 374 1 83.6 53.6 49.5 SGS
Vortex Sul Cl 35.4 8.03 350 374 1 94.2 94.5 89.2 SGS
POX 1 Cl con F-162 31.1 5.93 158 437 1 98.8 71.8 5.5 SGS
POX 2 Cl con F-253 33.9 9.38 155 437 1 98.6 64.3 19.1 SGS
POX 3 Cl con F-264 24.2 4.95 165 435 1 97.6 72.7 72.7 SGS
Brimstone Sul Cl5 33.9 7.13 383 428 2 99.9 94.0 97.0 KCA

 

Note:

 

1.Fire Assay
2.No lime boil, no NaCl
3.No lime boil, 1.34 oz/g NaCl
4.No lime boil, 2.67 oz/g NaCl
5.H2SO4 added to autoclave feed
6.ppt = parts per trillion

 

10.3.4.5Concentrate Oxidation Tests – Hazen 2025

 

During 2022 to 2025, Hycroft repeated flotation testing in preparation of concentrate for the POX Process Development program and achieved higher recovery rates with tighter controls on particle size, pH adjustment to 4.7, 24-minute flotation time and 20% to 25% Mass Pull with a target of 22%.

 

A series of POX tests (POX-3 through POX-7) were conducted at Hazen Research, Inc. on pyrite flotation concentrate to evaluate oxidation performance and downstream precious metal recovery following hot cure, lime boil, and cyanide leaching. The objective of this test program was to establish repeatability, assess sensitivity to operating conditions, and confirm the effectiveness of the integrated POX–hot cure–lime boil–cyanidation flowsheet.

 

All POX tests were conducted in a 2-L titanium autoclave at a nominal temperature of 225 °C, with oxygen overpressure of approximately 100 psig, and a total residence time of 90 minutes. The starting solution contained approximately 10 g/L H₂SO₄. Agitation speeds ranged from 1,000 to 1,020 rpm, and off-gas bleed rates were maintained at approximately 100 cm³/min.

 

Across POX-3 through POX-7, oxidation conditions were consistent and reproducible. No evidence of excessive passivation or runaway reactions was observed. The POX discharge slurries were subsequently subjected to hot cure to decompose basic iron sulfate phases prior to lime boiling and cyanide leaching.

 

10.3.4.6Hot Cure – Hazen 2025

 

Hot cure tests were conducted on pressure-oxidized slurry at 90 to 95 °C for 12 hours with agitation. The purpose of this step was to decompose basic iron sulfate species formed during pressure oxidation and to condition the solids for effective jarosite breakdown during lime boiling.

 

Hycroft Mine Project

Page 107

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Across POX-3 to POX-7, hot cure performance was stable, with temperature control maintained within ±1 °C of target. Filtration following hot cure produced well-behaved filter cakes suitable for downstream processing. No washing was conducted after hot cure, consistent with the intended flowsheet configuration.

 

10.3.4.7Lime Boil – Hazen 2025

 

Lime boil tests were performed on hot-cured residues at 90 to 95 °C under alkaline conditions (target pH approximately 11 to 11.5) to promote decomposition of jarosite and related basic iron sulfate phases. Residence times ranged from four hours to overnight, depending on the specific test objective.

 

Calcium hydroxide consumption varied across tests, reflecting differences in sulfate loading and the extent of iron sulfate formation during POX. Later tests (POX-6 and POX-7) incorporated extended lime boil durations and tighter pH control to ensure complete jarosite decomposition prior to cyanidation.

 

10.3.4.8Cyanide Leaching – Hazen 2025

 

Cyanide bottle roll leach tests were conducted on lime-boiled residues at ambient temperature using sodium cyanide concentrations ranging from 2.5 to 5.0 g/L, with activated carbon addition where indicated. Leach durations were typically 48 hours.

 

In several cases, a second lime boil and/or second cyanide leach was performed where the initial cyanidation indicated incomplete precious metal extraction, particularly for silver. This staged approach demonstrated that additional gold and silver recovery could be achieved when jarosite decomposition was completed prior to cyanidation.

 

Overall, the combined results confirm that the integrated POX–hot cure–lime boil–cyanidation flowsheet is effective for achieving high gold and silver recoveries from the pyrite concentrate. Table 10-11 summarizes the POX 3 through POX 7 test results.

 

Table 10-11: Summary Comparison Table – POX 3 to POX-7

 

Test POX Temp
(°C)
O₂ Overpressure (psig)

Hot Cure

(°C/h)

Lime Boil

(°C/h)

NaCN

(g/L)

Au Extraction (%) Ag Extraction (%)
POX-3 225 100 90–93 / 12 90–95 / 4 5.0 ~91 ~95
POX-4 225 100 90–95 / 12 90–95 / overnight 5.0 >92 ~95
POX-5 225 100 90–95 / 12 90–95 / overnight 5.0 ~92 ~93
POX-6 225 100 90–93 / 12 90–95 / 4 5.0 ~93 ~88–90
POX-7 225 100 95 / 12 95 / 24+ 2.5–5.0 ~93 ~92

 

Note: Gold and silver extractions shown are combined values based on feed and final residues. Minor balance deviations are attributed to analytical uncertainty and low residual grades

 

Hycroft Mine Project

Page 108

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The POX-3 through POX-7 test series demonstrates that pressure oxidation at 225 °C with oxygen overpressure, followed by hot cure, lime boil, and cyanide leaching, is a robust and repeatable processing route for the pyrite concentrate. Variability in silver recovery was primarily associated with the completeness of jarosite decomposition, which was successfully addressed through extended lime boiling and staged cyanidation.

 

These results provide a defensible metallurgical basis for flowsheet development and recovery assumptions.

 

10.3.5Solid-Liquid Separation Tests

 

Several thickeners are included in the Hycroft flowsheet. Updated settling tests for these thickeners were conducted by Pocock Industrial, Inc. using samples generated during hydrometallurgical process development studies performed by Hazen Research, Inc.

 

Tested sample streams included:

 

rougher flotation concentrate

 

neutralized AAO circuit product (pre-leach)

 

cyanide-leached slurry (CCD feed)

 

rougher flotation tailings.

 

A summary of the settling test results is presented in Table 10-12 below.

 

Table 10-12: Settling Test Results

 

Sample

Tested Feed Solids

(%)

Design Basis Net Feed Loading (ft2/gal/min.) Flocculant Dosage (lb/ton)

Predicted U’flow Density

(% solids)

Overflow Clarity, (ppm) TSS
Rougher Concentrate 7.47 – 14.79 0.87 – 1.37 0.12 – 0.13 40.6 – 49.1 150 – 318
Pre-Leach Oxidized Concentrate 7.52 – 7.75 0.68 – 0.92 0.11 – 0.17 35.0 – 41.0 150 – 329
CCD Feed 7.41 – 8.00 0.92 – 1.11 0.15 – 0.17 33.0 – 37.0 150 – 349
Rough Tailings 14.10 – 15.80 0.84 – 0.88 0.07 – 0.13 59.5 – 65.0 150 – 250

 

10.3.6Deleterious Elements

 

The deleterious element assay results for five bulk samples analyzed by Hazen are presented in Table 10-13 below.

 

Table 10-13: Deleterious Element Assay

 

Sample ID Hg (ppm)
Cut 4 Bin-03, -08, and -18 4.19
Brimstone Bin-14 and -20 2.68
Camel Conglomerate Bin -26, -27, and -28 2.35
Boneyard Bin-9, -16, and -23 15.70
Bay Bulk Bin-7, -11, and -24 9.96

 

Mercury is present in the mineralized material at moderate to high levels and is a deleterious element that can negatively impact gold recovery. Mercury is managed through zinc precipitation, followed by retorting to capture and remove the mercury.

 

10.3.7Metallurgical Parameters for Process Design Criteria and Financial Analysis

 

Overall plant recovery is calculated by multiplying the flotation recoveries by the recoveries achieved in POX, cyanide leaching, and counter current decantation (CCD), by the refining recovery in Merrill-Crowe precipitation. The proposed process plant overall recoveries are presented in Table10-14.

 

For oxide and transition materials processed by heap leaching, the estimated gold and silver recoveries are 40% and 12%, respectively.

 

Table 10-14: Process Plant Overall Recovery Prediction

 

Element

Flotation Recovery

(%)

Cyanide Extraction

(%)

Refining Recovery

(%)

Overall Recovery

(%)

2023 Tech Report Overall Recovery (%)
Au 89.5 93.5 99.0 82.8 76.0
Ag 92.9 86.0 97.0 77.5 76.0

 

Note: Overall Recovery = (Flotation Recovery) x (POX and Cyanide Leach Recovery) x (Refining Recovery)

 

Hycroft Mine Project

Page 109

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11Mineral Resource Estimates

 

11.1Summary

 

Mineral resources for the Hycroft deposit were developed using conventional block modeling methods and open pit optimization software to estimate the component of mineralization that has reasonable prospects for economic extraction (RPEE) for the mineral resource. The mineral resource estimation (MRE) was developed in accordance with the US Securities and Exchange Commission Rule SK-1300 for Mineral Projects. The estimate of the MRE reflects in-place mineralization as the point of reference. The effective date of the MRE is January 1, 2026. The MRE presented here supersedes any previously stated mineral resources for the Hycroft property.

 

The model was assembled by Ryan Rodney, C.P.G. of Hycroft. IMC worked with Hycroft and reviewed the final model. IMC is an independent third party with people who meet the definition of a QP under S-K 1300, and who have checked and validated the mineral resource wherever possible, and are assuming responsibility for the published MRE, with John Marek, P.E., acting as the QP.

 

11.2Model Location

 

The block model is assembled in the existing local mine grid. That grid is rotated 15.85 degrees (left rotation looking down) compared to true north. Table 11-1 summarizes the block size and block limits.

 

Table 11-1: Block Size and Model Size

 

Model Location From Coordinates To Coordinates Number of Blocks
Easting Limit 13000 26000 325
Northing Limit 35440 54800 484
Elevation Limits 2200 6600 110
Block Size Parent, subblock 40 x 40 x 40 ft

 

The drillhole database and the block model are all in the mine grid. To the user, there does not appear to be a rotation because the mine grid is treated as if there were no rotation. The block size selection will be discussed in a later sub-section.

 

11.3Database

 

The drillhole database has been assembled over many years by multiple companies using at least four different drill methods. That history and the verification of the historical information have been discussed in previous sections. Additional drilling has been completed since the MRE published March 2023, with additional checking and corrections completed on the historic database. The cutoff date for the drilling database is March 17, 2025, which represents the last data received from the 2024 drilling campaign.

 

Hycroft Mine Project

Page 110

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

There are stockpiles and historical leach pads at the Mine that are within the block model area. Many of those have been drilled after the original excavation by sonic or rotary methods. The stockpile holes have been used to estimate the stockpile and leach pad areas, only; they have not been used to estimate in-situ rock. In total, the Hycroft database contains 6,023 drillholes with 534,881 sample intervals amounting to 2,814,546 ft of drilling. Within the area of the block model, there are 5,813 drillholes with 516,901 drill intervals amounting to 2,668,616 ft of drilling. There has been 87,383 ft of drilling in 70 drill holes that have been added due to drilling or database correction since the previous MRE in March 2023. Table 11-2 summarizes the amount of drilling and assay information that was used to assemble the block model.

 

Table 11-2: Data Available for the Assembly of the Resource Model for Au, Ag, AuCn, Sulfide Sulfur

 

Number of Total in Model Stockpile Drilling Assays for Estimation After Removal of 1982-1987 Drilling
Holes 5,813 188 4,221
Assay Intervals 516,901 3,268 460,131
Au Fire Assays 488,222 2,354 433,422
Au Cn Assays 380,400 1,952 325,962
Ag Fire Assays 330,110 2,336 327,774
Ag Cn Assays 327,125 1,972 309,137
Sulfide Assays 39,058 2,450 39,058

 

The “Assays for Estimation After Removal of 1982-1987 Drilling” column indicates how much of the information was used to estimate measured and indicated class mineralization.

 

Sulfide sulfur levels have been estimated from a combination of three data sources. A set of sample composites were established by weighing pulp material from the drillholes to represent 25 ft composites from selected holes during 2011 and 2014. Specific holes were selected to provide coverage over the zone of the deposit being considered for flotation mill treatment. Those 25 ft samples were analyzed by LECO methods to determine sulfide sulfur percent by weight. In addition, all recent drilling in 2021 through mid-way through 2023 were assayed for sulfide sulfur using the LECO method on each 5 ft interval. Starting in the 2023 drilling campaign, LECO analyses were reverted to the 25 ft samples created from pulp samples. The three data sets were combined and then numerically distributed to 25 ft down-hole intervals. The combined sulfide sulfur LECO database inside the model contains 13,523 composites that are 25 ft long, averaging 1.66% sulfide sulfur.

 

There is additional multi-element ICP data available that was not used in the development of this resource model.

 

Hycroft Mine Project

Page 111

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.4Basic Statistics

 

The assay values of economic interest are gold, silver, and sulfide sulfur. This PFS is based on sulfide material being processed as a flotation concentrate and then utilizing pressure oxidation (POX) to generate a cyanide leachable slurry. The POX process is planned for flotation concentrate treatment. Sulfide sulfur content is a key measurable indicator in the POX process with potential operating cost impacts. There is a direct correlation of sulfide sulfur content to lime and limestone consumption during the Hot Cure and Lime Boil steps after POX and prior to cyanide leaching.

 

In addition, the cyanide soluble assays of gold are of interest because they provide a basis to establish the best metallurgical process based on the ability of the gold to dissolve into cyanide solution.

 

Table 11-3 presents the basic statistics of the assay database used to assemble the model. The stockpile assays are not included in the table and the assay data from 1982 through 1987 have been removed. The entire database listed in Table 11-3 was used for block grade estimation even though some of the assay values are located above current post mining topography. Drilling data from 1982 through 1987 was bias corrected and used to contribute to inferred class mineralization only. The cyanide data is represented as the ratio of cyanide gold divided by fire gold where the cyanide gold value exists and when fire gold is greater than or equal to 0.001 oz/ton.

 

Table 11-3: Assay Database (No Stockpile Assays, Inside the Model, and No Drilling from 1982 through 1987)

 

Commodity Number of Assays Mean Grade Standard Deviation Minimum Value Maximum Value
Fire Au 433,422 0.0063 oz/t 0.0145 0 oz/t 3.15 oz/t
CnAu/FaAu (ratio) 251,475 0.3431 ratio 0.3156 0 ratio 1.00 ratio
Ag 327,774 0.25 oz/t 5.20 0 oz/t 2,334 oz/t
Sulfide Sulfur in %, 25 ft Composites 13,486 1.65% 1.39% 0% 42.86%

 

Table 11-3 also illustrates that Au cyanide soluble ratio (CnAu/FaAu) data exists on 58% of the database. Total silver assays exist on 76% of the database. During later historic leach operations, cyanide Ag assays were generally completed; however, fire Ag assays were not common. Estimation of total or fire Ag will consequently be limited by the smaller number of available assays. Cyanide Ag assays were not used for block grade estimation due to uncertainty in that data identified during checks of the certificates of assay.

 

Cyanide soluble gold assays were completed on approximately 75% of the intervals where there are gold fire assays. The ratio of cyanide soluble Au to fire assay Au (CnAu/FaAu) ratio has been used to estimate the intensity of oxidation within the deposit. Although not statistically optimum, the process is necessary and common in the industry. The ratio of cyanide soluble Au to fire assay Au is used in mine planning to allocate material to the proper treatment process. When the CnAu/FaAu is calculated, values over 1.0 are set back to 1.0. The basic statistics of CnAu/FaAu are also summarized on Table 11-3. In simple terms, the cyanide to fire ratio reflects the degree of oxidation in the rock mass.

 

The apparent loss of cyanide ratio data (75% assay to 58% ratio) is because a gold fire value of 0.001 oz/ton or greater was required to calculate a meaningful ratio. In many cases, cyanide and/or fire assays are reported as trace values. In those cases, the resulting cyanide ratio was either 0.0, 0.5, or 1.0. Those values are meaningless when determining the level of oxidation and the relative cyanide amenability of the fire gold assay and were removed from the estimation process.

 

Hycroft Mine Project

Page 112

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.5Geology

 

The geology of the Hycroft deposit has been presented in previous report sections. The primary occurrences which have control on the grade distribution at Hycroft are Lithology, Alteration, and Structure. Each has an impact on mineralization.

 

11.6Lithology

 

The following are the main lithology or rock types in the Hycroft deposit:

 

Alluvium

 

Tuffaceous Lake Bed Sediment, part of the TSG

 

Camel Conglomerate, part of the TSG, and eroded from the Kamma Volcanics

 

Kamma Volcanics, Tertiary, but older than the sulfur group conglomerates and sediments

 

Auld Lang Syne (ALS), Jurassic laminated siltstone, the basement of the deposit.

 

The lithology interpretation was updated by Hycroft since the 2023 TRS. The primary change was a reduction in size of the TSG unit due to detailed review of the original geologic logging by Hycroft geologists. New wire frame solids were developed and used to code the model blocks to the nearest whole block. The main mineral hosts are the Camel and Kamma units; however, mineralization is found in all the lithologic units.

 

Interpreted solids representing the above rock types were provided by Hycroft and checked against logging by IMC. IMC found them appropriate for use in the development of the resource model. Figure 11-1 is an east–west cross-section illustrating the major rock types looking north.

 

Hycroft Mine Project

Page 113

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-1: East–West Cross-Section 44000-N Looking North, Showing Lithology Types

 

 

Source: Hycroft, 2025

 

11.7Alteration

 

Alteration consists of:

 

acid leach

 

argillic

 

silicic

 

propylitic

 

unaltered.

 

Hycroft provided alteration solids to IMC that have not been updated since the 2023 TRS. IMC checked those solids against the logged database and found them to be acceptable for use in development of the resource model. In summary, when propylitic alteration was encountered, boundary analysis and basic statistics indicated that it was statistically similar to the argillic altered material, and it was combined with argillic during block grade estimation.

 

Silicic alteration is common and tends to be deeper and generally more prevalent in the eastern portion of the deposit. Boundary and statistical analysis indicate that the silicic altered material is generally higher grade than the argillic-propylitic altered rock. Figure 11-2 is an east–west cross-section through the interpreted alterations, looking north.

 

Hycroft Mine Project

Page 114

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-2: East–West Cross-Section 44000-N Looking North, Showing Alterations

 

 

Source: Hycroft, 2025

 

11.8Structure

 

Several north–south striking basin and range faults cut through the Hycroft deposit. In addition to those faults, the deposit is cut by the Ramp Fault and the west dipping East Fault. The East Fault is interpreted to be a thick shear zone and appears to be the orientation and probably the conduit of mineralization in the eastern portion of the deposit. The footwall of the East Fault has minor low-grade mineralization in the Kamma formation.

 

Figure 11-3 is a map view of the faults and the numbering system assigned to the fault blocks between the faults. The fault block numbers will be used to define the domains and search parameters for block grade estimation.

 

There are additional interpreted faults through the deposit, but after review by the Hycroft geology and modeling team, the faults and fault blocks on Figure 11-3 were selected as those that had impact or control on the mineralization.

 

Hycroft Mine Project

Page 115

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-3: Structure and Domain Interpretation (Plan View)

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 116

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.9Domains

 

Domains for grade estimation are a combination of structure, alteration, and lithology. The domain boundaries were developed by studying the basic statistics by Hycroft and by boundary analysis completed by IMC to confirm the domain interpretation.

 

Boundary analysis selects the assay (or composite) information from both sides of the boundary being tested at several different separation distances. IMC then completes a series of statistical hypothesis tests to confirm if the data on either side of the boundary could have come from the same or different statistical populations.

 

As a result of the work described above, the selected 22 domains are summarized on Table 11-4. In addition to the domains created from boundary analysis, Hycroft identified and created 16 additional discrete domains to represent high-grade (greater than or equal to 4 oz/ton) silver veins. The silver domains create additional boundaries which isolate the higher-grade veins from the lower grade disseminated silver to prevent too much smearing during estimation. The domains are identified in Table 11-5, where 6,000 series represent the Vortex area, and 7,000 series represent the Brimstone area. Figure 11-4 shows the location of the high-grade silver domains. These domains are treated as hard boundaries where composites outside the boundary do not influence the inside, and the composites inside do not influence outside the boundary.

 

Sulfide sulfur utilized a different set of domains based on similar analysis as applied to gold and silver. There are three domains for sulfide sulfur illustrated on Table 11-6.

 

Table 11-4: Population Domains for Grade Estimation

 

Domain Name Structure Block Lithology Alteration Description
Alluvium All Alluvium All Alluvium
TSG_seds All TSG All Tertiary Lake Bed Sediments (TSG)
auld lang syne All ALS All ALS formation
acid leach All All Acid Leach Acid Leach Alteration
domain_1_arg_prop 1 Kamma+Camel Argillic+Propylitic West of the Range Fault, North of the Camel Fault
domain_1_silicic 1 Kamma+Camel Silicic West of the Range Fault, North of the Camel Fault
domain_1_unaltered 1 Kamma+Camel Unaltered West of the Range Fault, North of the Camel Fault
Domain_2_arg_prop 2 Kamma+Camel Argillic+Propylitic Between Range and Central Faults, North of the Camel Fault
domain_2_silicic 2 Kamma+Camel Silicic Between Range and Central Faults, North of the Camel Fault
domain_2_unaltered 2 Kamma+Camel Unaltered Between Range and Central Faults, North of the Camel Fault
domain_3_arg_prop 3 Kamma+Camel Argillic+Propylitic Between Central and East, Albert Fault, North of the Camel Fault
domain_3_silicic 3 Kamma+Camel Silicic Between Central and East, Albert Fault, North of the Camel Fault
domain_3_unaltered 3 Kamma+Camel Unaltered Between Central and East, Albert Fault, North of the Camel Fault
domain_4_arg_prop 4 Kamma+Camel Argillic+Propylitic East of East Fault, South of the Ramp Fault
domain_4_silicic 4 Kamma+Camel Silicic East of East Fault, South of the Ramp fault
domain_4_unaltered 4 Kamma+Camel Unaltered East of East Fault, South of the Ramp fault
domain_5_arg_prop 5 Kamma+Camel Argillic+Propylitic South of the Camel Fault, West of the East Fault
domain_5_silicic 5 Kamma+Camel Silicic South of the Camel Fault, West of the East Fault
domain_5_unaltered 5 Kamma+Camel Unaltered South of the Camel Fault, West of the East Fault
domain_6_arg_prop 6 Kamma+Camel Argillic+Propylitic East of Albert Fault, North of Ramp fault
domain_6_silicic 6 Kamma+Camel Silicic East of Albert Fault, North of Ramp fault
domain_6_unaltered 6 Kamma+Camel Unaltered East of Albert Fault, North of Ramp fault

 

Hycroft Mine Project

Page 117

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-5: High-grade Silver Vein Domains

 

Domain Name Structure Block Lithology Alteration Description
ag_6001 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6002 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6003 3,4 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6004 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6005 3,4 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6006 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6007 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6008 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6009 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6010 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6011 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_6012 3 Kamma Argillic+Propylitic+Silicic Vortex High-grade silver vein
ag_7001 3 Kamma Argillic+Propylitic+Silicic Brimstone High-grade silver vein
ag_7002 3 Kamma Argillic+Propylitic+Silicic Brimstone High-grade silver vein
ag_7004 3 Kamma Argillic+Propylitic+Silicic Brimstone High-grade silver vein
ag_7005 3 Kamma Argillic+Propylitic+Silicic Brimstone High-grade silver vein

 

Table 11-6: Sulfide Domains

 

Sulfide Domain Number Structure Block Lithology Alteration Description
1 All All Acid Leach Alluvium
2 3,4,6 All All East of the Central fault
4 1,2,5 All All West of the Central fault flat dipping

 

Hycroft Mine Project

Page 118

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-4: Structure and Domain Interpretation with Silver Wireframes (plan view)

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 119

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.10Assay Caps

 

Prior to grade estimation, high-grade outliers were capped to limit undue impact on block grade estimation. Histograms were studied by Hycroft within each of the domains to set cap values. IMC spot checked the cap values using cumulative frequency plots. In all cases, only a small percentage of high valued samples were capped, generally less than 0.5% of the database. Table 11-7 summarizes the cap values that were applied to assays prior to calculating composites.

 

Table 11-7: Assay Cap Values

 

Domain Gold Cap Value (oz/ton) Silver Cap Value (oz/ton)
Alluvium 0.10 3
TSG_Seds 0.06 7
Auld Lang Syne 0.07 4
Acid Leach 0.25 5
domain_1_arg_prop 0.07 5
domain_1_silicic 0.09 15
domain_1_unaltered 0.06 3
Domain_2_arg_prop 0.36 12
domain_2_silicic 0.55 34
domain_2_unaltered 0.04 2.5
domain_3_arg_prop 0.35 30
domain_3_silicic 0.65 55
domain_3_unaltered 0.05 10
domain_4_arg_prop 0.07 6
domain_4_silicic 0.15 15
domain_4_unaltered 0.07 2
domain_5_arg_prop 0.03 0.5
domain_5_silicic 0.04 3.5
domain_5_unaltered 0.03 1
domain_6_arg_prop 0.06 1.5
domain_6_silicic 0.12 30
domain_6_unaltered 0.07 4
ag_6001 n/a 12
ag_6002 n/a 14
ag_6003 n/a 35
ag_6004 n/a 15
ag_6005 n/a 8
ag_6006 n/a 20
ag_6007 n/a 12
ag_6008 n/a 14
ag_6009 n/a 25
ag_6010 n/a 20
ag_6011 n/a 8
ag_6012 n/a 20
ag_7001 n/a 300
ag_7002 n/a 15
ag_7004 n/a 60
ag_7005 n/a 9

 

Hycroft Mine Project

Page 120

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The gold cyanide to fire assay ratio was capped at 1.0 to assure that there were no values with cyanide assay greater than fire assay when estimating the model.

 

In all cases above, the stockpile drilling and the drilling in the Crofoot leach pad were excluded from the analysis as they do not represent in-situ mineralization.

 

Sulfide cap values were applied to the original sulfide data prior to compositing. The cap levels by sulfide domain are summarized on Table 11-8.

 

Table 11-8: Sulfide Cap Values Prior to Compositing

 

Alteration Structure Blocks Lithology Sulfide Cap Level % Sulfide
Acid Leach All All 12.00%
Argilic All All 17.00%
Propylitic All All n/a
Silicic All All 28.00%
Unaltered All All 12.00%

 

11.11Bench Height Confirmation

 

A test was completed to confirm the selection of bench height for the model. The assay database was composited into alternative bench height intervals of 20 to 50 ft in 5-ft intervals. For each set of composites, the number of composites above cutoff and the average grade of those composites above cutoff were calculated. The number of composites multiplied by the average grade is used as an approximation of contained metal above cutoff. Multiple cutoffs of 0.001 through 0.007 oz/ton Au were tested at each of the bench heights. The stockpile and leach pad drilling were not included in the analysis.

 

Figure 11-5 indicates that the gold grade is not particularly sensitive to bench height and the selected bench height of 40 ft is a reasonable value considering the relatively high ore production rate being considered at Hycroft (nearly 60,000 t/d).

 

Future work could consider increasing the bench height to 50 ft, but 50 ft is only about a 1.2% improvement over the contained metal at 40 ft.

 

Hycroft Mine Project

Page 121

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-5: Bench Height Analysis

 

 

Source: IMC, 2025

 

11.12Composites

 

Downhole (length) composites were created from the capped, raw assay values for input to block grade estimation. Composite lengths of 40 ft were used for gold and silver estimation outside of the silver veins. Within the silver veins, the composite length was set to 10 ft due to the narrow width of the interpreted veins.

 

The capped assays were composited at 40 ft down-hole intervals, respecting the alteration and mineral domain boundaries described above. A minimum of 20 ft was required for a composite and anything less than 20 ft was applied to the previous interval. Table 11-9 summarizes the basic statistics of the composited assay data.

 

Table 11-10 summarizes the basic statistics of the composited sulfide-sulfur data as 25 ft composites.

 

Hycroft Mine Project

Page 122

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-9: Basic Statistics of Composites, In-Situ Rock, Eliminating Years 1982 to 1987

 

Domain Number Structure Block Code Lithology Alteration Statistics Summary for Composites
Statistic Au oz/ton Ag oz/ton CnAu/ AuFa Ratio
alluvium All Alluvium All N = 2,644 1,849 1,058
Mean = 0.0028 0.0873 0.5370
Max = 0.0508 1.6595 1
Std = 0.0039 0.1134 0.26
TSG_seds All TSG All N = 1,465 1,254 363
Mean = 0.0025 0.0882 0.2380
Max = 0.0336 4.2323 1
Std = 0.0042 0.1814 0.214
auld lang syne All ALS All N = 49 51 9
Mean = 0.0014 0.0410 0.2700
Max = 0.0105 0.2061 0.45
Std = 0.0019 0.0428 0.132
acid leach All All Acid Leach N = 5,401 1,621 3,486
Mean = 0.0048 0.0888 0.6070
Max = 0.1245 1.9186 1
Std = 0.0076 0.1645 0.252
domain_1_arg_prop 1 Kamma+Camel Argillic+Propylitic N = 373 352 80
Mean = 0.0020 0.0745 0.1950
Max = 0.0198 1.0011 0.688
Std = 0.0032 0.0858 0.17
domain_1_silicic 1 Kamma+Camel Silicic N = 824 795 513
Mean = 0.0071 0.1983 0.1210
Max = 0.0476 6.4177 1
Std = 0.0065 0.4468 0.167
domain_1_unaltered 1 Kamma+Camel Unaltered N = 305 306 44
Mean = 0.0017 0.0918 0.4180
Max = 0.0205 1.1522 0.863
Std = 0.003 0.1271 0.258
Domain_2_arg_prop 2 Kamma+Camel Argillic+Propylitic N = 4,461 3,169 1,941
Mean = 0.0040 0.0932 0.4100
Max = 0.1091 4.8678 1
Std = 0.0066 0.2059 0.287
domain_2_silicic 2 Kamma+Camel Silicic N = 10,458 7,120 8,503
Mean = 0.0100 0.1895 0.3220
Max = 0.3368 11.5751 1
Std = 0.0101 0.4312 0.27
domain_2_unaltered 2 Kamma+Camel Unaltered N = 151 128 49
Mean = 0.0030 0.0800 0.3330
Max = 0.0328 0.8482 1
Std = 0.0046 0.132 0.274
domain_3_arg_prop 3 Kamma+Camel Argillic+Propylitic N = 7,101 5,944 2,386
Mean = 0.0033 0.1091 0.3090
Max = 0.1395 5.9384 1
Std = 0.0062 0.2488 0.253
domain_3_silicic 3 Kamma+Camel Silicic N = 16,860 13,688 12,995
Mean = 0.0085 0.3065 0.2780
Max = 0.251 36.5706 1
Std = 0.0094 0.6761 0.247
domain_3_unaltered 3 Kamma+Camel Unaltered N = 723 384 363
Mean = 0.0023 0.1048 0.5680
Max = 0.0349 3.5645 1
Std = 0.0034 0.2502 0.294
domain_4_arg_prop 4 Kamma+Camel Argillic+Propylitic N = 1,203 1,146 224
Mean = 0.0017 0.0738 0.3990
Max = 0.0338 1.932 1
Std = 0.0028 0.1335 0.275
domain_4_silicic 4 Kamma+Camel Silicic N = 1,232 995 563
Mean = 0.0040 0.1787 0.3980
Max = 0.0604 3.9584 1
Std = 0.0051 0.3188 0.29
domain_4_unaltered 4 Kamma+Camel Unaltered N = 283 259 55
Mean = 0.0012 0.0290 0.3850
Max = 0.0323 0.6248 0.935
Std = 0.003 0.0558 0.186
domain_5_arg_prop 5 Kamma+Camel Argillic+Propylitic N = 107 100 11
Mean = 0.0008 0.0830 0.3170
Max = 0.0193 0.2503 0.7
Std = 0.0025 0.0349 0.25
domain_5_silicic 5 Kamma+Camel Silicic N = 207 198 50
Mean = 0.0021 0.0914 0.1760
Max = 0.0214 0.7186 0.863
Std = 0.0039 0.0958 0.203
domain_5_unaltered 5 Kamma+Camel Unaltered N = 94 93 -
Mean = 0.0004 0.0797 -
Max = 0.003 0.2559 -
Std = 0.0005 0.0381 -

 

Hycroft Mine Project

Page 123

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Domain Number Structure Block Code Lithology Alteration Statistics Summary for Composites
Statistic Au oz/ton Ag oz/ton CnAu/ AuFa Ratio
domain_6_arg_prop 6 Kamma+Camel Argillic+Propylitic N = 896 774 83
Mean = 0.0009 0.0696 0.4590
Max = 0.0298 0.3795 1
Std = 0.0018 0.0529 0.311
domain_6_silicic 6 Kamma+Camel Silicic N = 583 496 225
Mean = 0.0041 0.1869 0.2690
Max = 0.0382 10.7052 1
Std = 0.0051 0.5849 0.241
domain_6_unaltered 6 Kamma+Camel Unaltered N = 161 136 97
Mean = 0.0037 0.1936 0.5050
Max = 0.0199 1.175 0.906
Std = 0.0039 0.2161 0.177
ag_6001 3 Kamma Argillic+Propylitic+Silicic N = n/a 41 n/a
Mean = n/a 4.2624 n/a
Max = n/a 12 n/a
Std = n/a 3.4599 n/a
ag_6002 3 Kamma Argillic+Propylitic+Silicic N = n/a 18 n/a
Mean = n/a 5.3505 n/a
Max = n/a 11.8884 n/a
Std = n/a 2.9268 n/a
ag_6003 3,4 Kamma Argillic+Propylitic+Silicic N = n/a 18 n/a
Mean = n/a 8.8920 n/a
Max = n/a 26.8903 n/a
Std = n/a 9.1648 n/a
ag_6004 3 Kamma Argillic+Propylitic+Silicic N = n/a 12 n/a
Mean = n/a 6.6931 n/a
Max = n/a 15 n/a
Std = n/a 4.9057 n/a
ag_6005 3,4 Kamma Argillic+Propylitic+Silicic N = n/a 12 n/a
Mean = n/a 4.2462 n/a
Max = n/a 8 n/a
Std = n/a 2.4865 n/a
ag_6006 3 Kamma Argillic+Propylitic+Silicic N = n/a 15 n/a
Mean = n/a 7.7032 n/a
Max = n/a 18.3126 n/a
Std = n/a 5.1522 n/a
ag_6007 3 Kamma Argillic+Propylitic+Silicic N = n/a 25 n/a
Mean = n/a 5.3803 n/a
Max = n/a 11.1771 n/a
Std = n/a 3.2084 n/a
ag_6008 3 Kamma Argillic+Propylitic+Silicic N = n/a 23 n/a
Mean = n/a 4.5142 n/a
Max = n/a 13.0085 n/a
Std = n/a 3.5674 n/a
ag_6009 3 Kamma Argillic+Propylitic+Silicic N = n/a 34 n/a
Mean = n/a 8.9273 n/a
Max = n/a 25 n/a
Std = n/a 6.6283 n/a
ag_6010 3 Kamma Argillic+Propylitic+Silicic N = n/a 40 n/a
Mean = n/a 6.0614 n/a
Max = n/a 20 n/a
Std = n/a 5.3179 n/a
ag_6011 3 Kamma Argillic+Propylitic+Silicic N = n/a 22 n/a
Mean = n/a 4.3523 n/a
Max = n/a 8 n/a
Std = n/a 1.656 n/a
ag_6012 3 Kamma Argillic+Propylitic+Silicic N = n/a 29 n/a
Mean = n/a 5.9920 n/a
Max = n/a 18.645 n/a
Std = n/a 5.5774 n/a
ag_7001 3 Kamma Argillic+Propylitic+Silicic N = n/a 79 n/a
Mean = n/a 25.4563 n/a
Max = n/a 157.5105 n/a
Std = n/a 36.8384 n/a
ag_7002 3 Kamma Argillic+Propylitic+Silicic N = n/a 14 n/a
Mean = n/a 4.8935 n/a
Max = n/a 15 n/a
Std = n/a 4.3965 n/a
ag_7004 3 Kamma Argillic+Propylitic+Silicic N = n/a 11 n/a
Mean = n/a 11.0018 n/a
Max = n/a 52.5782 n/a
Std = n/a 18.7548 n/a
ag_7005 3 Kamma Argillic+Propylitic+Silicic N = n/a 8 n/a
Mean = n/a 4.5161 n/a
Max = n/a 6.2646 n/a
Std = n/a 1.4602 n/a

 

Hycroft Mine Project

Page 124

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-10: Basic Statistics of 25 ft Sulfide Composites by Sulfide Domain

 

Sulfide Domain Number Structure Blocks Lithology Alteration Basic Statistics of 25ft Composites
1 All All Acid Leach N = 319
Mean = 1.94
Max = 12.00
Std = 2.36
2 3,4,5,6 All All N = 8,544
Mean = 1.54
Max = 28.00
Std = 1.45
4 1,2,5 All All N = 4,623
Mean = 1.82
Max = 26.20
Std = 1.14

 

11.13Variography

 

Variograms were prepared and analyzed by mineralized domain during earlier work on the MRE. The guidance for search orientation and distance that was developed from that work has been applied to the grade assignment techniques applied to this model. A few illustrative variograms have been prepared using the database and domain boundaries applied to this model to provide support to the selected search parameters.

 

Figure 11-6: Gold Variograms for Silicic Material Between the Central Fault and East Fault

 

Down Dip to West

North-South

 

Source: IMC, 2023

 

Figure 11-7: Gold Variograms for Silicic Material Between the Range Fault and Central Fault

 

East-West North

 

Source: IMC, 2023

 

Hycroft Mine Project

Page 125

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.14Block Grade Estimation

 

Block grade estimation was broken into four groups of estimates: gold, silver, gold cyanide ratio (cnratau), sulfide-sulfur. The boundaries and controls on each of the four were different as might be expected with the differences in geologic occurrence in each case.

 

11.14.1Gold

 

Gold estimations utilized the 22 domains defined previously. Those domain boundaries were treated as “hard” boundaries during estimation. The estimation used the 40 ft composites noted earlier and inverse distance cubed (1/d3) as the estimation method. Search parameters are provided on Table 11-11.

 

The grade estimation used a maximum of ten composites with a maximum of three composites from one hole. A single composite could be used to assign a block grade, but that grade would be considered as inferred category (Class is discussed later in this section).

 

Test runs of ordinary kriging have been applied in previous models. The intent of selecting the inverse distance method was to develop a better planning model with less smoothing during block estimation and to provide an estimate of block values that would be predictive of actual mine head grades once appropriate mining cutoffs were applied.

 

Block gold grade estimation was done in two estimation passes:

 

1.Block grades were estimated without the 1982 to 1987 drilling, applying the methods described here in text.

 

2.The mineral resource classes of measured, indicated, and inferred were established without the use of the 1982-1987 data.

 

A second pass of gold block grade estimation was made incorporating the 1982 to 1987 data after the bias correction of 0.56 was applied. Any blocks that were added in addition to those in Step 1 above were coded as Inferred.

 

11.14.2Silver

 

Silver utilized the 38 domains defined previously. Those domain boundaries were treated as “hard” boundaries during estimation. As discussed earlier, silver composites were broken by domain boundaries where high-grade silver mineralization occurs, the composites are set to 10 ft length inside the high-grade domains and 40 ft outside of the high-grade domain. Silver was estimated using 1/d3 methodology.

 

The estimation strategy within the high-grade domains used a three-pass approach incorporating a small ellipse in the first pass and a larger ellipse in the subsequent passes. Outside of the high-grade domains, the estimation used a one pass approach. Search parameters are provided on Table 11-11.

 

Two domains that are not inside the high-grade structures, incorporated a high-grade search limit where composites above a certain grade were capped again beyond a specified search distance. This process includes the high-grade values but limits their extent to minimize high-grade smearing over neighboring low-grade values.

 

Hycroft Mine Project

Page 126

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-11: Grade Estimation Parameters for Au, Ag

 

Domain Variable

Ellipsoid Ranges

(ft)

Ellipsoid Directions

(°)

Composite Counts Drill Hole Limit HG Restrictions
Max Interm Min Dip Dip Azimuth Pitch Min Max Max per oz/ton Search Limit (ft)
Alluvium Au 150 150 25 0 270 0 1 10 3 n/a n/a
Ag 150 150 25 0 270 0 1 10 3 n/a n/a
TSG_seds Au 270 270 50 0 270 0 1 10 3 n/a n/a
Ag 270 270 50 0 270 0 1 10 3 n/a n/a
auld lang syne Au 150 150 50 40 285 0 1 10 3 n/a n/a
Ag 150 150 50 40 285 0 1 10 3 n/a n/a
acid leach Au 270 270 50 0 270 0 1 10 3 n/a n/a
Ag 270 270 50 0 270 0 1 10 3 n/a n/a
domain_1_arg_prop Au 150 150 50 0 270 0 1 10 3 n/a n/a
Ag 150 150 50 0 270 0 1 10 3 n/a n/a
domain_1_silicic Au 300 300 50 0 270 0 1 10 3 n/a n/a
Ag 300 300 50 0 270 0 1 10 3 n/a n/a
domain_1_unaltered Au 150 150 50 0 270 0 1 10 3 n/a n/a
Ag 150 150 50 0 270 0 1 10 3 n/a n/a
Domain_2_arg_prop Au 250 250 50 0 270 0 1 10 3 n/a n/a
Ag 250 250 50 0 270 0 1 10 3 n/a n/a
domain_2_silicic Au 300 300 50 0 270 0 1 10 3 n/a n/a
Ag 300 300 50 0 270 0 1 10 3 n/a n/a
domain_2_unaltered Au 150 150 50 0 270 0 1 10 3 n/a n/a
Ag 150 150 50 0 270 0 1 10 3 n/a n/a
domain_3_arg_prop Au 300 300 50 40 285 0 1 10 3 n/a n/a
Ag 300 300 50 40 285 0 1 10 3 20 50
domain_3_silicic Au 300 300 50 40 285 0 1 10 3 n/a n/a
Ag 300 300 50 40 285 0 1 10 3 20 50
domain_3_unaltered Au 150 150 50 40 285 0 1 10 3 n/a n/a
Ag 150 150 50 40 285 0 1 10 3 n/a n/a
domain_4_arg_prop Au 250 250 50 40 285 0 1 10 3 n/a n/a
Ag 250 250 50 40 285 0 1 10 3 n/a n/a
domain_4_silicic Au 300 300 50 40 285 0 1 10 3 n/a n/a
Ag 300 300 50 40 285 0 1 10 3 n/a n/a
domain_4_unaltered Au 150 150 50 40 285 0 1 10 3 n/a n/a
Ag 150 150 50 40 285 0 1 10 3 n/a n/a
domain_5_arg_prop Au 250 250 50 0 270 0 1 10 3 n/a n/a
Ag 250 250 50 0 270 0 1 10 3 n/a n/a

 

Hycroft Mine Project

Page 127

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Domain Variable

Ellipsoid Ranges

(ft)

Ellipsoid Directions

(°)

Composite Counts Drill Hole Limit HG Restrictions
Max Interm Min Dip Dip Azimuth Pitch Min Max Max per oz/ton Search Limit (ft)
domain_5_silicic Au 300 300 50 0 270 0 1 10 3 n/a n/a
Ag 300 300 50 0 270 0 1 10 3 n/a n/a
domain_5_unaltered Au 150 150 50 0 270 0 1 10 3 n/a n/a
Ag 150 150 50 0 270 0 1 10 3 n/a n/a
domain_6_arg_prop Au 250 250 50 40 285 0 1 10 3 n/a n/a
Ag 250 250 50 40 285 0 1 10 3 n/a n/a
domain_6_silicic Au 300 300 50 40 285 0 1 10 3 n/a n/a
Ag 300 300 50 40 285 0 1 10 3 n/a n/a
domain_6_unaltered Au 150 150 50 40 285 0 1 10 3 n/a n/a
Ag 150 150 50 40 285 0 1 10 3 n/a n/a
ag_6001 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6002 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6003 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6004 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6005 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6006 pass 1 120 60 30 50 300 90 2 12 2 n/a n/a
pass 2 180 90 45 50 300 90 2 12 2 n/a n/a
pass 3 240 120 60 50 300 90 1 12 n/a n/a n/a
ag_6007 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6008 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6009 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a

 

Hycroft Mine Project

Page 128

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Domain Variable

Ellipsoid Ranges

(ft)

Ellipsoid Directions

(°)

Composite Counts Drill Hole Limit HG Restrictions
Max Interm Min Dip Dip Azimuth Pitch Min Max Max per oz/ton Search Limit (ft)
ag_6010 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6011 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_6012 pass 1 120 60 30 20 270 90 2 12 2 n/a n/a
pass 2 180 90 45 20 270 90 2 12 2 n/a n/a
pass 3 240 120 60 20 270 90 1 12 n/a n/a n/a
ag_7001 pass 1 120 60 30 50 300 90 2 12 2 n/a n/a
pass 2 180 90 45 50 300 90 2 12 2 n/a n/a
pass 3 240 120 60 50 300 90 1 12 n/a n/a n/a
ag_7002 pass 1 120 60 30 50 300 90 2 12 2 n/a n/a
pass 2 180 90 45 50 300 90 2 12 2 n/a n/a
pass 3 240 120 60 50 300 90 1 12 n/a n/a n/a
ag_7004 pass 1 120 60 30 50 300 90 2 12 2 n/a n/a
pass 2 180 90 45 50 300 90 2 12 2 n/a n/a
pass 3 240 120 60 50 300 90 1 12 n/a n/a n/a
ag_7005 pass 1 120 60 30 50 300 90 2 12 2 n/a n/a
pass 2 180 90 45 50 300 90 2 12 2 n/a n/a
pass 3 240 120 60 50 300 90 1 12 n/a n/a n/a

 

11.14.3Cyanide Ratio

 

About 75% of the assay database for fire gold was also assayed for cyanide soluble gold. The cyanide soluble assay is a direct indication of the cyanide amenability of the mineralized material to gold and silver recovery by cyanidation. Much of the upper portion of the deposit received cyanide soluble assays for gold and silver.

 

CnAu/FaAu was used to indicate cyanide amenability. The ratio, where it is available, can be interpreted as an indication of oxidation that has occurred in the rock mass.

 

The domains selected for gold and silver mineralization (previously shown in Table 11-4) reflect the original hydrothermal mineralization. The cyanide ratio however reflects the oxidation process as a secondary impact.

 

Hycroft Mine Project

Page 129

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

A review of cross-sections of the cyanide ratio data indicated two populations of cnratau:

 

1.A generally horizontal band near topography reflecting surface water and oxidation that looks like a conventional oxidation blanket.

 

2.Isolated values at depth that likely reflect oxidation downward along structure with limited later extent.

 

To estimate cnratau, a boundary was developed between the upper oxide blanket and the lower structural controlled oxidation. This was completed by visual analysis of cnratau cross-sections.

 

The boundary surface was defined as a horizontal plane on the 4,000 ft. elevation from the eastern edge of the model to the 19,000 East line. From there the surface trends upward to the 4,400 ft. elevation at the 21,000 East line. From 21,000 east to the east edge of the model, the 4,400 ft. elevation is applied. Blocks above the surface were coded with a value of 1 in a variable called “Contrat”. Blocks below the surface were coded with a Contrat value of 2.

 

Table 11-12 summarizes the parameters used to estimate the cnratau within each block. Once the ratio was assigned, block values of cyanide soluble Au could be calculated where required. Composite requirements: max =10, min =1, max per hole =3.

 

Table 11-12: Estimation Parameters for Cyanide Ratio, All Three Domains utilized 1/D3

 

Cn Ratio Domain “Contrat” Structure Block Code Description Parameters Applied to 40 ft Composites
Variable Orientation, Degrees Search Radii, (ft) Maximum Composites per Drillhole
Dip Dir Plunge Rotation Prim Second Perpend
1 All Near Surface Oxidation cnratau 0 0 0 700 700 50 3
2 3,4,6 Structural Oxidation, East of Central Fault cnratau 285 -40 0 150 150 50 3
3 1,2,3,5 Structural Oxidation, West of Central Fault cnratau 270 -90 0 150 150 50 3

 

11.14.4Sulfide Sulfur

 

Sulfide sulfur was estimated to provide an improved localized cost for concentrate processing. The cost of concentrate processing is dependent on the amount of sulfide sulfur in the mill feed. The current POX process has been adjusted to match the full range of sulfide sulfur found in the flotation concentrate. Most of the sulfide sulfur is in the form of pyrite. Pyrite exists everywhere throughout the deposit, including in the oxidized portion. In particular, the acid leach alteration type contains native sulfur which also reports to the LECO assay method for sulfide sulfur.

 

The presence of sulfide sulfur is not impacted by the oxidation state or rock type. Population tests indicate that the only independent population is the acid leach alteration. The dip orientation for the estimation parameters was, however, adjusted based on structure.

 

Hycroft Mine Project

Page 130

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The sulfide sulfur LECO data was performed on selected drillholes. The sulfide sulfur block grades were estimated from the 25 ft composite LECO data as described in previous sections. Composite counts were a maximum of 10, minimum of one with a maximum of three composites per drill hole.

 

Table 11-13 summarizes the estimation parameters used to assign sulfide sulfur to the model blocks.

 

Table 11-13: Sulfide Sulfur Estimation Parameters, All Three Domains Utilized 1/D3

 

Structure Block Code Description Variable Orientation, Degrees Search Radii, (ft)
Dip Dir Plunge Rotation Prim Second Perpend
All Acid Leach Alteration Sulfd 0 0 0 650 650 200
3,4,6 East of Central Fault Sulfd 285 -40 0 650 650 200
1,2,3,5 West of Central Fault Sulfd 0 0 0 650 650 200

 

Due to the low number of sulfide sulfur composites, default values were assigned based on alteration type to those blocks without estimated sulfide sulfur. Sulfide sulfur can be an input to project cost so leaving blocks un-estimated would underestimate project costs.

 

The default values were assigned as follows in Table 11-14. Default values were assigned to blocks that did not receive a sulfide sulfur value from the estimation process.

 

In the development of the POX process, reagent consumption and power costs were consistent across the range of sulfide sulfur levels identified. Therefore, a fixed value could be applied to the operating costs.

 

Table 11-14: Sulfide Sulfur Default Values if Not Estimated

 

Description Default Sulfide Sulfur %
Acid Leach 1.7167
Argillic 1.5226
Silicic 1.8335
Propylitic 1.1057
Unaltered 0.782

 

Hycroft Mine Project

Page 131

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.14.5Density

 

Bulk density was assigned to in-situ rock based on density data collected by Hycroft and their predecessors. Average density values were set based on alteration type within the hard or in-situ units. The exception was the ALS rock type which was assigned a single value not impacted by alteration.

 

Alluvium, back fill, and stockpiles were guided by the few test values available but were generally based on the density values assigned to an earlier block model completed in 2019. Table 11-15 summarizes the densities assigned to the model.

 

Table 11-15: Density Assigned to the Block Model

 

Description Specific Gravity lbs/ft Cu Ktons per Model Block
Acid Leach 2.2654 141.424 4.5256
Argillic 2.2094 137.928 4.4137
Silicic 2.5055 156.413 5.0052
Propylitic 2.3193 144.789 4.6333
Alluvium 1.7808 111.172 3.5575
Auld Lang Syne 2.652 165.559 5.2979
Unassigned Blocks 2.3193 144.789 4.6333
Stockpile Specific Gravity lbs/ft Cu Ktons per Block
100 1.6026 100.047 3.2015
101, 102, 103, 104, 105, 106 1.7049 106.433 3.4059
120 (Crofoot Leach Pad) 2.0000 124.856 3.9954

 

11.14.6Stockpile Grade Estimation

 

The Hycroft pits have incurred both backfilling and in-pit stockpiling. Potential sulfide mill feed that has been incurred during the mining of oxide heap leach ores have been stockpiled. That material is a potential future mill feed to a sulfide processing facility.

 

Hycroft developed interpreted solids based on survey data of the stockpiles.

 

Some of the stockpiles at Hycroft have been drilled by Sonic drilling and RC sampling methods. The grade of those stockpiles that contained stockpile drilling were assigned with the assays from those holes. Stockpiles that were estimated all used a search of 600 x 600 x 200 ft and 1/D1 methods to estimate Au, Ag, Sulfide Sulfur and cnratau. Densities were assigned as summarized in the previous sub-section. Where there were no stockpile drilling assays, average tonnage and grade of each stockpile based on the blast hole grade control information was used.

 

Hycroft Mine Project

Page 132

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Blocks were assigned stockpile codes as summarized in Table 11-16.

 

Table 11-16: Stockpiles Assigned Grades by Inverse Distance Estimation

 

Stockpile Codes Location Variables Estimated by 1/D1
Au, Ag, Sulfide Sulfur, CnAu/FaAu Ratio
Dip Dir Plunge Rotation Prim (ft) Second (ft) Perpend (ft)
101 Brimstone Stockpile 1 0 90 0 600 600 200
102 Brimstone Stockpile 2 0 90 0 600 600 200
104 Central Stockpile 1 0 90 0 600 600 200
120 Crofoot Leach Pad 0 90 0 600 600 200
Stockpile Grades Assigned by Hycroft Production History
Stockpile Codes Location Au oz/ton Ag oz/ton Sulfide Sulfur % CnAu/FaAu Ratio
100 General Fill 0 0 0 0
103 Brimstone Stockpile 3 0.0148 0.6514 2.51 0.2
105 Central Stockpile 2 0.0131 0.2308 1.89 0.25
106 Gyro Stockpile 0.019 0.848 2.97 0.18
120 Crofoot Leach Pad - - 1.74 -

 

Note: No sulfide sulfur data exists for the Crofoot Leach Pad (120) so a default value was assigned for processing costs

 

The Crofoot leach pad (code 120) was assigned an inferred confidence classification. All other graded stockpiles were assigned an Indicated confidence classification.

 

11.14.7Treatment of 1982 – 1987 Data

 

The observed high bias with the 1982 – 1987 data was discussed and illustrated in Section 9. Half of the 1982-1987 data have been historically mined out. The 1982-1987 drill data was included using the following steps:

 

1.The procedures described in the previous sub-sections and in Section 11.15 regarding classification were first completed using the drill hole composites that had excluded the 1982 to 1987 drill data.
  
2.Once completed, the block gold grades and the block class codes were stored in separate variables.
  
3.The 1982-1987 composite data was corrected for potential high bias by multiplying each composite by a factor of 0.56, based on the nearest neighbor comparison to post 2005 data described in Section 9.
  
4.The gold estimation procedure was repeated using the identical parameters as described in the previous sub-sections and in item 1 above.
  
5.Any additional blocks that were estimated in pass 2 were added to the gold grade and coded as “Inferred.”

 

The procedure outlined above did not change the gold block grade of the blocks estimated in pass 1 without the 1982-1987 data. It was not necessary to update the silver because there were no silver assays within the 1982-1987 data.

 

Hycroft Mine Project

Page 133

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.15Classification

 

Individual blocks in the model were assigned classification codes as defined within S-K 1300. As noted earlier, the stockpiles were assigned classification codes of 2 for Indicated class and the Crofoot leach pad was assigned a code of 3 for inferred.

 

The in-situ rock values were assigned classification codes based on the inverse distance estimation of Au. During that estimation process, the number of composites that were used to estimate the block was stored along with the distance between the block and the closest composite. Those two parameters were used to assign classification code in the following manner to blocks estimated without the 1982-1987 data.

 

If closest distance <= 125 ft and number of composites = 10, Class = 1 Measured

 

Else

 

If closest distance <=225 ft and number of composites >=4, Class = 2 Indicated

 

Otherwise

 

Remaining Estimated Blocks                                                  Class = 3 Inferred

 

After the above coding was complete, the additional blocks that resulted from inclusion of the bias corrected 1982-1987 data were coded as inferred.

 

As noted in Section 11.14.4, sulfide sulfur information is limited in number compared to gold and silver assays. The confidence procedures that are described in the previous paragraph are to be applied to metallurgical processes that utilize sulfide sulfur to estimated process cost such as POX. Default assignments of sulfide sulfur to blocks with estimated gold and silver are appropriate for cost estimation.

 

The previous paragraphs discuss several items of uncertainty in the database that have caused components of the mineralization to be classified as inferred. There is indication that those inferred components are mineralized, but the uncertainty in the data or lack of data contributes to an inferred level of grade estimation.

 

Measured mineralization has a sound level of reliability due to the close spacing (125 ft) and large number of samples contributing to the grade estimates. Indicated level is slightly more uncertain than measured due to the wider spacing of the data and fewer number of samples used for estimation. The definitions of measured, indicated, and inferred are consistent with the definitions within SK-1300.

 

Figure 11-8 is a cross-section showing the classification for Hycroft resources.

 

Hycroft Mine Project

Page 134

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-8: E-W Cross-section at 41000-N, Showing Confidence Codes

 

 

 

Note: Red (1) = Measured, Green (2) = Indicated, Blue (3) = Inferred. Source: Hycroft, 2025

 

11.16Model Verification

 

The block model was verified by several methods before being used to determine mineral resources:

 

Detailed Visual Checks of Drilling versus Block Estimates.
  
A Bias Check for Each Domain.
  
Swath Plots.
  
IMC Smear Check.

 

Hycroft Mine Project

Page 135

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The visual check of the block model is one of the most useful and informative processes that was used to confirm the practicality of the block model. IMC completed visual checks on plan and sections for all the estimated variables in the model. In addition to IMC visual checks, the Hycroft engineering and geology team on site have also reviewed the model.

 

Figure 11-9 and Figure 11-10 are cross sections through the block model with drilling as visual checks.

 

Figure 11-9: E-W Cross-section at 41000-N, Visual Check of Gold Grades in Drillholes and Block Model

 

 

Note: Warmer Colors are Higher Grade. Source: Hycroft, 2025

 

Hycroft Mine Project

Page 136

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-10: E-W Cross-section at 41000-N, Visual Check of Silver Grades in Drillholes and Block Model

 

 

Note: Warmer Colors are Higher Grade. Source: Hycroft, 2025

 

11.16.1Swath Plots

 

Hycroft produced comparative statistics, including inverse distance cubed (ID3), nearest neighbor (NN) and inverse distance squared (ID2) estimations, and swath plots for all deposits. Swath plots provide a visual indication if the block model follows the grade trends indicated by the supporting data and if there is any observable local bias in the block grade estimation. The swath plots produced generally demonstrated good correlation, with block grades being somewhat smoothed relative to composite grades, as expected.

 

Figure 11-11 is an example for the swath plots in the X and Y (model east and north) directions across the deposit for the gold estimation. Figure 11-12 and Figure 11-13 illustrate the same swath plots for silver and sulfide sulfur respectively.

 

The green histogram represents the volume of estimated blocks within the resource pit for each 160 ft slice of the model.

 

Hycroft Mine Project

Page 137

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-11: Swath Plots for Gold, X = East and Y = North Slices, 160 ft Wide Slices

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 138

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-12: Swath Plots for Silver, X = East and Y = North Slices, 160 ft Slices

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 139

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 11-13: Swath Plots for Sulfide Sulfur, X = East and Y = North Slices, 160 ft Slices

 

 

Source: Hycroft, 2025

 

Hycroft Mine Project

Page 140

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

11.16.2Smear Check

 

IMC used a simple test to understand the amount of grade smoothing within the block model and to confirm that the model grades are not high biased. The test is referred to internally as the “smear check.”

 

The procedure is as follows:

 

A range of cutoff grades are selected for the check process. Typically, they bracket the potential planning cutoff grades.

 

For each cutoff grade being tested, the blocks above cutoff are identified.

 

All composites contained within those blocks are identified.

 

Average grade of the composites and blocks are tabulated.

 

Percentage of the contained composites less than cutoff are calculated.

 

Table 11-17 summarizes the results for both Au and Ag in-situ rock. Stockpiles and stockpile drillholes have been removed from this analysis. In all cases, the model mean grade is less than or equal to the mean grade of the contained composites. This is because the block estimate also draws from composites that are outside of the test shape.

 

Less than cutoff, is indicative of the amount of averaging or “smearing” of grade that has occurred in the estimation process. Ideally this value should be less than about 10 to 15% in the range of cutoff grades. The gold and sulfide sulfur responses meet these criteria over a range of the deposit grades.

 

Table 11-17: IMC Smear Check

 

Cutoff Grade % Comps Less than Cutoff Number of Comps in Shape Composite Grade (oz/ton) Number of Blocks in Shape

Model Grade

(oz/ton)

Au Composites vs Model Au
0.002 6.24 24,464 0.009 673,328 0.008
0.003 7.31 22,073 0.010 585,073 0.009
0.004 9.10 20,000 0.010 511,894 0.009
0.005 11.54 17,758 0.011 445,637 0.010
0.006 13.39 15,577 0.012 380,290 0.011
0.007 15.08 13,349 0.013 318,446 0.012
0.008 15.84 11,331 0.014 262,200 0.013
0.009 18.36 9,446 0.015 213,726 0.014
0.010 20.04 7,830 0.016 171,559 0.015
Ag Composites vs Model Ag
0.100 15.52 16,074 0.353 500,629 0.302
0.200 21.81 8,259 0.531 221,681 0.505
0.300 25.83 4,916 0.729 122,015 0.720

 

Hycroft Mine Project

Page 141

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Cutoff Grade % Comps Less than Cutoff Number of Comps in Shape Composite Grade (oz/ton) Number of Blocks in Shape

Model Grade

(oz/ton)

0.400 27.16 3,328 0.934 80,459 0.914
0.500 28.17 2,446 1.076 57,512 1.100
0.600 29.70 1,943 1.217 43,761 1.274
Sulfide Sulfur Composites vs Model, Default Values Removed from Analysis
0.25 4.73 11,813 1.86 792,323 1.78
0.50 3.28 10,887 1.98 758,989 1.85
1.00 4.99 9,547 2.15 670,013 1.99
1.50 8.07 7,773 2.34 532,655 2.18
2.00 13.61 4,181 2.87 272,917 2.56

 

Note: Below End 2021 Topography, Without stockpile blocks or drilling, and without data from 1982 through 1987 Drilling. The silver check does not include the vein domains

 

Silver grade responses at 0.20 oz/ton and above indicate a modeled mineralized zone will have 22 to 29% of the composite values inside the modeled shape that are less than the cutoff shape. Although not ideal, the result for silver is acceptable.

 

As an additional test on silver, the blocks within the MRE pit with positive economic value were averaged to determine their average silver grade. The average of all composites was identified within the same envelope. The statistical mean of the resource containing silver composites is 0.55 oz/ton after capping. The average silver grade of the resource blocks is 0.32 oz/ton. The result indicates that the observed grade smearing in silver is not overestimating the contained silver in the MRE.

 

11.17Mineral Resource Estimate

 

The MRE at the Hycroft property is currently envisioned to be produced from a conventional hard rock open pit mine feeding two process facilities:

 

1.Oxide material will be routed to ROM cyanide heap leach, producing gold and silver doré.
  
2.Sulfide material will be allocated to a Flotation milling process followed by POX of the concentrate to make a gold and silver doré.

 

The terms of reference for this MRE are mineralization in-place. The procedures described in the following paragraphs establish that the stated mineral resources have RPEE.

 

Mineral resources were developed using the block model and pit optimization software to determine mineralization with reasonable prospects for economic extraction of the mineral resource as defined by S-K 1300. The optimization software compares the cost of production versus the benefit of metal sales to develop an estimated open pit geometry. The pit walls of the resulting pit are at breakeven economics where costs equal benefits.

 

Hycroft Mine Project

Page 142

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The cutoff grade that is reported for this statement of mineral resources is based on the estimated costs and metal prices on Table 11-18. The internal or marginal cutoff is applied and reported where the benefits of selling the recovered metal will pay for the processing and fixed general and administrative (G&A) costs.

 

Table 11-18 summarizes the economic and recovery parameters that were used to define the pit that established the MRE. The process costs were developed by Ausenco and Hycroft based on recent cost estimation. Mine operating cost estimates were developed by IMC by scaling from preliminary mine planning and cost estimation completed during early 2022.

 

The cutoff grade is presented as an NSR. A marginal or internal cutoff grade is consequently $0.01/ton. An estimate of the Net of Process value is also provided in terms of Equivalent Gold Grade. Metal prices for the MRE were $3,100 /oz Au, and $36.00/oz Ag. Spot prices for Au and Ag in 2025 ranged from US$2,798 to US$4,323/ oz Au and US$31.34 to US$71.63/ oz Ag respectively. The prices selected for determination of mineral resources are conservative relative to current metal prices and do not include extensive price extrapolation.

 

The MRE is presented on Table 11-19 using US customary units and on Table 11-20 in metric units. Mineral resources are not mineral reserves, and do not have demonstrated economic viability.

 

The risks to the Hycroft MRE are future changes in project costs and project recoveries as well as metal prices that can have a substantial impact on the MRE. Process recoveries in the grade ranges near the cutoff grades may be less than the recoveries presented on Table 11-18. Additional process testing could result in modifications to the recovery and process costs that could result in reductions in the mineral resource.

 

The categories of measured, indicated, and inferred reflect different drill densities as noted in Section 11.15. Uncertainties in the drill database have been minimized by the following two treatment components of the database:

 

1.The 1982 through 1987 drilling and assay data, which appears to be biased, has been corrected for bias and incorporated only in the estimation of inferred mineral resources.
  
2.The cyanide soluble silver assays which measure the cyanide amenable silver content have not been used in the MRE.

 

The slope angles input for the pit optimization software was based on work completed by Call & Nicholas Inc, (CNI) completed in February of 2022 with additional documentation in October of 2023. IMC has reviewed these documents and has accepted the slope angle recommendations for use in the development of the MRE.

 

IMC is a third-party consulting firm with people who can act as a qualified person for the MRE. IMC holds the opinion that all relevant technical and economic factors likely to influence the project or economic extraction could be resolved with further work and that this statement of mineral resources meets the requirements to show RPEE.

 

Hycroft Mine Project

Page 143

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-18: Economic and Technical Parameters for Hycroft MRE

 

Cost Assumptions
Mining Cost, Base $1.65/ton material moved
+ Bench Incremental Cost Below 4660 $0.018/ton per bench of depth

 

Categorization of Oxidation Type based on the AuCn/AuFA Ratio = cnratau
Oxide >=0.7 Transition between 0.3 and 0.7 Sulfide <=0.3

 

Process Cost for Flotation and POX
Total Mill Cost for Sulfide and Transition $16.73/ton of feed to float plant
ROM Leach for Oxide, $1.88/ton of feed to ROM Leach
ROM Leach for Transition Sulfide $3.63/ton of feed to ROM Leach

 

Mill Process Recoveries
Mill Recoveries Flotation POX Extraction Total  
Gold 89.5% 93.5% 99.0% 82.8%  of (AuFA)
Silver 92.9% 86.0% 97.0% 77.5%  of (Total Silver Assay)

 

ROM Heap Leach Recoveries
ROM Leach Recovery Oxide Transition    
Gold   75.0% 75.0% of (AuCn)  
Silver   12.2% 12.2% of (Total Silver Assay)  

 

Refining Recoveries Au Ag
Mill + POX Payable 99.5% 99.5%
Leach Process Payable 99.5% 99.5%

 

Doré Transport and Refining Cost
Gold $5.00/oz
Silver $0.50/oz

 

Metal Price Assumptions Heap Leach AuCN Cutoffs Mill-POX Au Equiv
Gold Silver Internal Cutoff Internal Cutoff
$3,100/oz $36.00/oz Oxide 0.0008 oz/ton 0.0066 oz/t AuEquiv
Transition 0.0016 oz/ton

Gold Equivalent for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay

Or at average gold leach recovery AuEq = Fire Gold + 0.0035 Total Silver Assay

Gold Equivalent for Flotation + Concentration = Fire Assay Gold + Total Silver Assay x 0.0107

 

Hycroft Mine Project

Page 144

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-19: Hycroft MRE as of January 21, 2026, US customary Units

 

Classification

Cutoff Grade

$ Net

of Refining

Approximate

Cutoff, AuEq (oz/ton)

Ktons

Gold

oz/ton

Silver

oz/ton

Sulfide

Sulfur%

Contained Ounces

Gold

Oz x 1000

Silver

Oz x 1000

Heap Leach Resource
Measured $1.88 - $3.63 0.001 - 0.002 92,994 0.005 0.11 1.83 446 10,322
Indicated $1.88 - $3.63 0.001 - 0.002 110,374 0.004 0.09 1.54 475 9,492
Meas + Ind $1.88 - $3.63 0.001 - 0.002 203,368 0.005 0.10 1.67 921 19,814
Inferred $1.88 - $3.63 0.001 - 0.002 110,018 0.005 0.09 1.41 528 10,122
Flotation Mill + Concentrate Treatment by Pressure Oxidation and Cyanide Leach
Measured $16.73 0.007 734,571 0.011 0.43 2.03 8,154 316,600
Indicated $16.73 0.007 748,876 0.010 0.30 1.84 7,339 226,161
Meas + Ind $16.73 0.007 1,483,447 0.010 0.37 1.93 15,493 542,761
Inferred $16.73 0.007 459,646 0.010 0.27 1.76 4,505 122,725
Combined Mineral Resources Leach Plus Mill
Measured $1.88 - $16.73 0.001 - 0.007 827,565 0.010 0.40 2.01 8,600 326,922
Indicated $1.88 - $16.73 0.001 - 0.007 859,250 0.009 0.27 1.80 7,814 235,653
Meas + Ind $1.88 - $16.73 0.001 - 0.007 1,686,815 0.010 0.33 1.90 16,414 562,575
Inferred $1.88 - $16.73 0.001 - 0.007 569,664 0.009 0.23 1.69 5,033 132,847

 

Notes:

 

1.Mineral resources based on metal prices of $3,100/troy oz Au and $36.00/troy oz Ag.
2.Cutoffs are Income – Refining Cost = NSR.
3.Gold Equivalent (AuEq) for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay, or at average gold leach recovery AuEq = Fire Gold + 0.0035 Total Silver Assay.
4.Gold Equivalent for Mill + Pressure Oxidation = Fire Gold + 0.0107 x Total Silver Assay.
5.Numbers may not match exactly due to rounding.
6.Mineral resources are contained within a computer-generated optimized pit.
7.Total material in that pit is 5.42 billion tons.
8.Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.
9.Modifying factors for mine and process design have not been applied.
10.All units are US customary. Ktons means 1,000 short tons of 2,000 lbs Au and Ag grades are in troy ounces per short ton (oz/ton).

 

Hycroft Mine Project

Page 145

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-20: Hycroft MRE as of 21 January 2026, Metric Units

 

Classification

Cutoff Grade

$ Net

of Refining

Approximate

Cutoff, AuEq (g/tonne)

Ktonnes

Gold

(g/tonne)

Silver

(g/tonne)

Sulfide

Sulfur

(%)

Contained Ounces
Gold Silver
Oz x 1000 Oz x 1000
Heap Leach Resource
Measured $2.07 - $4.00 0.027 - 0.055 84,364 0.164 3.80 1.83 446 10,322
Indicated $2.07 - $4.00 0.027 - 0.055 100,131 0.147 2.95 1.54 475 9,492
Meas + Ind $2.07 - $4.00 0.027 - 0.055 184,495 0.155 3.34 1.67 921 19,814
Inferred $2.07 - $4.00 0.027 - 0.055 99,808 0.164 3.15 1.41 528 10,122
Flotation Mill + Concentrate Treatment by Pressure Oxidation and Cyanide Leach
Measured $18.44 0.206 666,403 0.380 14.76 2.03 8,154 316,600
Indicated $18.44 0.206 679,380 0.336 10.34 1.84 7,339 226,161
Meas + Ind $18.44 0.206 1,345,783 0.358 12.53 1.93 15,493 542,761
Inferred $18.44 0.206 416,991 0.336 9.14 1.76 4,505 122,725
Combined Mineral Resources, Leach Plus Mill
Measured $2.07 - $18.44 0.027 - 0.206 750,767 0.356 13.53 2.01 8,600 326,922
Indicated $2.07 - $18.44 0.027 - 0.206 779,512 0.311 9.39 1.80 7,814 235,653
Meas + Ind $2.07 - $18.44 0.027 - 0.206 1,530,279 0.333 11.42 1.90 16,414 562,575
Inferred $2.07 - $18.44 0.027 - 0.206 516,799 0.303 7.99 1.69 5,033 132,847

 

Notes:

 

1.Mineral resources based on metal prices of $3,100/ oz Au and $36.00/ oz Ag.
2.Cutoffs are Income – Refining Cost = NSR.
3.Gold Equivalent for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay.
4.Gold Equivalent for Mill + Pressure Oxidation = Fire Gold + 0.0107 x Total Silver Assay.
5.Numbers may not match exactly due to rounding.
6.Mineral resources are contained within a computer-generated optimized pit.
7.Total material in that pit is 4.92 billion tonnes.
8.All units on this table are metric: Ktonnes means 1,000 tonnes. Au and Ag grades are in grams per tonne (g/tonne).
9.Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.
10.Modifying factors for mine and process design have not been applied.

 

Contained within the MRE at Hycroft are a series of high-grade silver veins at Brimstone and zones of higher silver concentrations in Vortex that are associated with a low angle breccia body. The modeling process of these high-grade silver domains was described earlier in this section. Those domains are contained within the MRE on Table 11-19 and Table 11-20. Table 11-21 to Table 11-23 are the tabulation of the gold and silver within the domain volumes that are contained within the MRE in Table 11-19 and Table 11-20.

 

The domains are in two areas of the deposit referred to as Brimstone and Vortex. The contained metal is illustrated at three different silver cutoff grades. Specific mine plans have not been completed but it is envisioned that these domains could be either mined in an open pit methodology and high-grade material could be comingled with lower-grade material from that specific pit. Or as an alternative, this material could be potentially targeted for an underground mine methodology. Additional metallurgical process development may be required to validate gold and silver recovery values in these specific areas.

 

Hycroft Mine Project

Page 146

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-21: High-grade Silver Bearing Domains, Contained within the MRE at 2 oz/ton Cutoff Grade, US customary Units

 

Classification

Cutoff Grade

Silver

(oz/ton)

Ktons

Gold

(oz/ton)

Silver
(oz/ton)
Sulfide Sulfur (%) Gold Contained
oz x 1000
Silver Contained
oz x 1000
Brimstone
Measured 2.00 3,195 0.011 8.35 1.33 35 26,686
Indicated 2.00 330 0.010 3.11 1.87 3 1,025
Meas + Ind 2.00 3,525 0.011 7.86 1.38 38 27,711
Inferred 2.00 15 0.008 3.52 1.13 0 52
Vortex
Measured 2.00 9,126 0.018 3.81 1.49 160 34,781
Indicated 2.00 7,342 0.014 3.78 1.24 100 27,726
Meas + Ind 2.00 16,468 0.016 3.80 1.38 261 62,507
Inferred 2.00 3,644 0.014 3.65 1.27 50 13,307
Brimstone + Vortex
Measured 2.00 12,322 0.016 4.99 1.45 195 61,467
Indicated 2.00 7,671 0.013 3.75 1.26 104 28,750
Meas + Ind 2.00 19,993 0.015 4.51 1.38 299 90,218
Inferred 2.00 3,659 0.014 3.65 1.27 51 13,359

 

Table 11-22: High-grade Silver Bearing Domains, Contained within the MRE at 3 oz/ton Cutoff Grade, US customary Units

 

Classification

Cutoff Grade Silver

(oz/ton)

Ktons

Gold

(oz/ton)

Silver

(oz/ton)

Sulfide
Sulfur
(%)
Gold Contained
oz x 1000
Silver Contained
oz x 1000
Brimstone
Measured 3.00 1,841 0.010 12.75 1.25 19 23,476
Indicated 3.00 109 0.008 4.55 2.14 1 494
Meas + Ind 3.00 1,949 0.010 12.30 1.30 20 23,970
Inferred 3.00 10 0.009 4.13 1.23 0 40
Vortex
Measured 3.00 4,494 0.017 5.24 1.39 74 23,568
Indicated 3.00 3,899 0.014 4.98 1.16 54 19,416
Meas + Ind 3.00 8,393 0.015 5.12 1.28 128 42,984
Inferred 3.00 2,023 0.010 4.63 1.30 21 9,374
Brimstone + Vortex
Measured 3.00 6,335 0.015 7.43 1.35 93 47,045
Indicated 3.00 4,007 0.014 4.97 1.19 55 19,909
Meas + Ind 3.00 10,342 0.014 6.47 1.29 148 66,954
Inferred 3.00 2,032 0.010 4.63 1.30 21 9,414

 

Hycroft Mine Project

Page 147

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 11-23: High-grade Silver Bearing Domains, Contained within the MRE at 4 oz/ton Cutoff Grade, US customary Units

 

Classification

Cutoff Grade Silver

(oz/ton)

Ktons

Gold

(oz/ton)

Silver

(oz/ton)

Sulfide
Sulfur
(%)
Gold Contained
oz x 1000
Silver Contained
oz x 1000
Brimstone
Measured 4.00 1,386 0.011 15.81 1.23 15 21,912
Indicated 4.00 61 0.007 5.39 2.10 0 331
Meas + Ind 4.00 1,447 0.010 15.37 1.27 15 22,243
Inferred 4.00 10 0.009 4.13 1.23 0 40
Vortex
Measured 4.00 2,679 0.017 6.48 1.37 46 17,350
Indicated 4.00 2,452 0.015 5.88 1.13 36 14,426
Meas + Ind 4.00 5,131 0.016 6.19 1.26 82 31,776
Inferred 4.00 1,326 0.010 5.26 1.26 13 6,969
Brimstone + Vortex
Measured 4.00 4,065 0.015 9.66 1.33 60 39,262
Indicated 4.00 2,513 0.015 5.87 1.15 37 14,757
Meas + Ind 4.00 6,578 0.015 8.21 1.26 97 54,019
Inferred 4.00 1,335 0.010 5.25 1.26 13 7,009

 

Table 11-24: High-grade Silver Bearing Domains, Contained within the MRE at 68.57 g/ton (2 oz/ton) Cutoff Grade, Metric Units

 

Classification Cutoff Grade Silver (g/tonne) Ktonnes Gold
(g/tonne)
Silver
(g/tonne)
Sulfide
Sulfur
(%)
Contained Ounces
Gold
Oz x 1000
Silver
Oz x 1000
Brimstone
Measured 68.57 2,899 0.372 286.35 1.33 35 26,686
Indicated 68.57 299 0.332 106.62 1.87 3 1,025
Meas + Ind 68.57 3,198 0.368 269.54 1.38 38 27,711
Inferred 68.57 13 0.289 120.74 1.13 0 52
Vortex
Measured 68.57 8,279 0.603 130.67 1.49 160 34,781
Indicated 68.57 6,660 0.469 129.48 1.24 100 27,726
Meas + Ind 68.57 14,940 0.543 130.14 1.38 261 62,507
Inferred 68.57 3,306 0.475 125.20 1.27 50 13,307
Brimstone + Vortex
Measured 68.57 11,178 0.543 171.04 1.45 195 61,467
Indicated 68.57 6,959 0.463 128.49 1.26 104 28,750
Meas + Ind 68.57 18,137 0.512 154.71 1.38 299 90,218
Inferred 68.57 3,319 0.474 125.18 1.27 51 13,359

 

Table 11-25: High-grade Silver Bearing Domains, Contained within the MRE at 102.86 g/ton (3 oz/ton) Cutoff Grade, Metric Units

 

Classification

Cutoff Grade Silver

(g/tonne)

Ktonnes Gold
(g/tonne)
Silver
(g/tonne)
Sulfide Sulfur
(%)
Contained Ounces
Gold
Oz x 1000
Silver
Oz x 100
0
Brimstone
Measured 102.86 1,670 0.353 437.24 1.25 19 23,476
Indicated 102.86 98 0.281 155.98 2.14 1 494
Meas + Ind 102.86 1,768 0.349 421.58 1.30 20 23,970
Inferred 102.86 9 0.297 141.73 1.23 0 40
Vortex
Measured 102.86 4,077 0.566 179.80 1.39 74 23,568
Indicated 102.86 3,537 0.477 170.74 1.16 54 19,416
Meas + Ind 102.86 7,614 0.525 175.59 1.28 128 42,984
Inferred 102.86 1,835 0.349 158.91 1.30 21 9,374
Brimstone + Vortex
Measured 102.86 5,747 0.504 254.61 1.35 93 47,045
Indicated 102.86 3,635 0.472 170.34 1.19 55 19,909
Meas + Ind 102.86 9,382 0.492 221.96 1.29 148 66,954
Inferred 102.86 1,844 0.348 158.82 1.30 21 9,414

 

Table 11-26: High-grade Silver Bearing Domains, Contained within the MRE at 137.14 g/t (4 oz/ton) Cutoff Grade, Metric Units

 

Classification

Cutoff Grade Silver

(g/tonne)

Ktonnes Gold
(g/tonne)
Silver
(g/tonne)
Sulfide Sulfur
(%)
Contained Ounces
Gold
Oz x 1000
Silver
Oz x 1000
Brimstone
Measured 137.14 1,257 0.361 542.02 1.23 15 21,912
Indicated 137.14 56 0.244 184.93 2.10 0 331
Meas + Ind 137.14 1,313 0.357 526.88 1.27 15 22,243
Inferred 137.14 9 0.297 141.73 1.23 0 40
Vortex
Measured 137.14 2,430 0.587 222.07 1.37 46 17,350
Indicated 137.14 2,225 0.504 201.70 1.13 36 14,426
Meas + Ind 137.14 4,655 0.548 212.34 1.26 82 31,776
Inferred 137.14 1,203 0.338 180.23 1.26 13 6,969
Brimstone + Vortex
Measured 137.14 3,687 0.510 331.17 1.33 60 39,262
Indicated 137.14 2,280 0.498 201.29 1.15 37 14,757
Meas + Ind 137.14 5,968 0.505 281.55 1.26 97 54,019
Inferred 137.14 1,211 0.338 179.95 1.26 13 7,009

 

Hycroft Mine Project

Page 148

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

12Mineral Reserve

 

This section is not relevant to the technical report summary.

 

13Mining Methods

 

13.1Overview

 

Hycroft is planned as a conventional hard rock open pit operation. IMC developed a mine plan that produces the required process feed and moves sufficient mine waste to assure continued release of the mineralization. The mine plan is based on measured and indicated mineralization that was estimated in the mineral resource block model described in Section 11.

 

Inferred mineralization was not included within this initial assessment for two reasons: (1) there is sufficient measured and indicated mineralization to feed the process plant for over 50 years, and (2) to reduce the changes in the mine schedule and potentially minable material as the project moves toward a pre-feasibility study in the future.

 

The mine will feed two processing facilities:

 

1.A flotation mill followed by pressure oxidation and leaching of the concentrate, and
  
2.A ROM heap leach for mineralization that is amenable to direct cyanide leaching.

 

The mine production schedule is summarized on Figure 13-1 with tabular detail on Table 13-1.

 

The cutoff grade for the schedule is based on income net of process:

 

Income net of process = Net Return after Refining – Process Costs

 

Calculation of the cutoff using net of process allows for the use of a single parameter for cutoff grade across both process facilities. Details of the development of the mine plan and schedule are reported later in this section.

 

Figure 13-1 illustrates the planned mine material movement by year for this initial assessment. Mill process, heap leach, and stockpiled mill process material are shown along with the required waste movement. Total material per year starts with 11.3 Mtons/a in preproduction and increases to 71.2 Mtons/a for years 1 through 3. Additional equipment is acquired later so that total material movement is increased to 81.5 to 82.0 Mtons/a from year 5 to year 27. From year 28 until the end of the mine life, the total material movement reduces to around 70 Mtons/a (See Table 13-1).

 

The material planned for milling and leaching on the production schedule is potentially minable material. They do not constitute mineral reserves at this time.

 

Approximately 240 M tons of low-grade Mill Feed material is stockpiled throughout the mine life. This material is not fed to the mill and is not part of the economic analysis in this report. Further trade-off studies will analyze the opportunity to feed this additional material through the process plant to benefit from the additional revenue.

 

Hycroft Mine Project

Page 149

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13- 1: Hycroft Initial Assessment Mine Plan Schedule

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 150

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 13-1: Hycroft Initial Assessment Mine Production Schedule, Measured and Indicated Mineralization

 

Year Mill Cutoff Mill Oxide Leach, $0.01 Net of Process Cutoff Transition Leach, $0.01 Net of Process Cutoff Low Grd Mill Stkp, $0.01 Net of Process Cutoff Waste Total
Net of Process ($/ton) Ktons Net of Process ($/ton) Fire Gold (oz/t) Silver (oz/ton) Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Cyanide Ratio CnAu/FaAu Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Cyanide Ratio CnAu/FaAu Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Sulfide Sulfur (%) Ktons Ktons
Preprod - - - - - - 861 3.55 0.003 0.11 0.78 2.47 1,601 6.66 0.007 0.14 0.58 3.43 - - - - - 8,871 11,333
1 13.00 14,068 29.53 0.016 0.21 2.11 1,916 5.11 0.004 0.11 0.78 1.82 8,908 4.16 0.007 0.14 0.47 2.26 1,005 6.34 0.008 0.15 2.69 45,302 71,200
2 13.50 20,841 26.01 0.013 0.35 2.45 2,426 1.65 0.002 0.06 0.79 1.48 3,314 3.89 0.007 0.11 0.46 2.11 2,301 9.80 0.009 0.18 2.84 42,318 71,200
3 15.00 20,841 38.31 0.016 0.52 2.31 1,077 6.99 0.005 0.08 0.78 1.88 16,151 3.79 0.007 0.09 0.45 1.65 15,846 6.82 0.008 0.13 2.08 17,285 71,200
4 15.00 20,841 34.59 0.015 0.53 2.32 3,610 5.14 0.004 0.10 0.77 2.16 11,013 3.66 0.006 0.18 0.51 2.41 10,547 7.07 0.007 0.21 2.33 28,335 74,347
5 15.00 20,841 29.24 0.014 0.43 2.87 6,940 6.72 0.005 0.06 0.79 1.65 9,673 4.76 0.006 0.09 0.57 1.85 12,656 8.09 0.007 0.24 2.42 31,389 81,500
6 16.00 20,841 29.73 0.014 0.43 2.22 1,638 7.02 0.005 0.14 0.74 1.20 13,175 4.55 0.006 0.18 0.51 1.43 12,134 9.80 0.009 0.16 2.70 33,712 81,500
7 14.00 20,841 29.74 0.013 0.52 2.03 1,414 5.32 0.004 0.18 0.78 1.25 4,936 2.76 0.005 0.19 0.48 1.51 13,682 7.18 0.007 0.19 2.16 40,627 81,500
8 14.00 20,841 26.17 0.014 0.25 2.06 325 5.33 0.003 0.17 0.86 0.71 3,051 3.07 0.007 0.14 0.41 1.82 14,148 6.76 0.008 0.14 2.14 43,135 81,500
9 7.00 20,841 20.74 0.012 0.23 1.95 13 0.23 0.001 0.05 0.73 0.44 94 1.41 0.004 0.06 0.48 0.67 2,904 3.66 0.007 0.14 2.13 58,149 82,000
10 4.00 20,841 21.08 0.011 0.34 2.00 1,506 2.45 0.002 0.08 0.79 0.96 1,335 1.79 0.004 0.09 0.54 1.38 2,365 2.23 0.006 0.12 1.93 55,954 82,000
11 4.50 20,841 16.39 0.009 0.37 1.97 1,202 4.48 0.003 0.10 0.80 1.74 7,452 1.61 0.004 0.13 0.48 1.77 6,453 2.15 0.006 0.18 1.92 46,052 82,000
12 7.00 20,841 19.93 0.010 0.37 2.04 2,531 2.89 0.003 0.08 0.77 1.02 3,522 2.00 0.005 0.12 0.50 1.64 9,288 3.61 0.006 0.19 2.02 45,818 82,000
13 7.00 20,841 26.32 0.011 0.52 2.16 1,021 5.38 0.004 0.07 0.79 1.29 7,280 2.19 0.005 0.12 0.50 1.52 7,915 3.42 0.006 0.18 2.06 44,943 82,000
14 6.00 20,841 21.20 0.011 0.35 2.26 93 7.34 0.004 0.27 0.98 0.53 419 1.57 0.005 0.16 0.39 1.83 8,696 3.39 0.006 0.18 1.95 51,952 82,000
15 2.00 20,841 19.87 0.011 0.31 1.87 2,772 4.97 0.004 0.05 0.80 1.62 8,284 3.19 0.005 0.09 0.52 1.73 501 1.03 0.006 0.13 2.03 49,602 82,000
16 3.00 20,841 18.83 0.010 0.36 2.07 2,012 2.27 0.002 0.07 0.77 1.24 3,105 2.04 0.005 0.14 0.48 2.67 2,591 1.82 0.005 0.19 2.18 53,451 82,000
17 2.00 20,841 14.36 0.009 0.31 2.43 815 7.24 0.005 0.12 0.76 1.70 4,002 3.13 0.005 0.15 0.53 2.59 1,578 0.98 0.005 0.16 2.23 54,763 82,000
18 8.00 20,841 17.68 0.010 0.32 2.61 1,937 7.10 0.005 0.17 0.76 1.32 2,970 3.57 0.006 0.13 0.51 2.27 13,730 4.37 0.006 0.17 2.41 42,521 82,000
19 4.00 20,841 16.64 0.010 0.26 2.21 718 0.95 0.001 0.09 0.81 1.80 1,483 2.53 0.006 0.12 0.46 2.35 14,391 5.15 0.007 0.18 2.37 44,568 82,000
20 7.00 20,841 14.87 0.010 0.25 1.71 10 3.55 0.003 0.09 0.75 2.00 116 0.99 0.005 0.13 0.38 1.88 11,377 3.76 0.006 0.17 1.94 49,656 82,000
21 7.00 20,841 22.62 0.012 0.34 1.57 30 0.80 0.001 0.02 0.78 1.47 358 0.97 0.005 0.12 0.38 1.64 11,773 3.49 0.006 0.15 1.74 48,997 82,000
22 10.00 20,841 42.57 0.018 0.51 1.45 1,950 5.26 0.004 0.14 0.79 1.09 950 2.57 0.005 0.17 0.51 1.83 9,772 4.62 0.007 0.15 1.77 48,487 82,000
23 8.00 20,841 40.67 0.015 0.72 1.18 3,134 4.07 0.003 0.10 0.77 1.35 1,570 2.20 0.004 0.09 0.59 1.53 3,584 4.03 0.006 0.16 1.79 52,872 82,000
24 6.00 20,841 45.65 0.014 1.04 1.13 5,516 4.92 0.003 0.12 0.79 1.63 3,935 1.88 0.004 0.11 0.57 1.60 1,296 3.19 0.006 0.18 1.57 50,411 82,000
25 9.00 20,841 37.35 0.012 0.83 1.61 4,365 7.79 0.005 0.16 0.78 1.56 7,971 3.21 0.005 0.15 0.55 1.61 2,388 4.98 0.006 0.23 1.68 46,435 82,000
26 9.00 20,841 35.59 0.014 0.58 1.82 1,238 8.04 0.005 0.17 0.83 1.50 3,137 2.89 0.005 0.16 0.49 1.64 2,289 4.85 0.007 0.15 1.77 54,496 82,000
27 8.00 20,841 33.84 0.010 0.90 1.65 1,413 4.51 0.003 0.17 0.80 1.69 2,502 2.50 0.005 0.15 0.53 2.15 7,190 3.96 0.007 0.14 1.55 50,053 82,000
28 4.00 20,841 36.85 0.009 1.13 1.74 581 8.49 0.005 0.13 0.81 1.28 445 1.31 0.005 0.13 0.40 1.91 3,838 2.03 0.006 0.16 1.54 48,295 74,000
29 4.00 20,841 17.78 0.010 0.32 2.02 74 9.49 0.006 0.10 0.78 3.07 1,229 3.02 0.005 0.10 0.56 1.95 3,722 1.96 0.006 0.16 1.93 48,134 74,000
30 2.50 20,841 15.38 0.010 0.20 1.90 5 15.73 0.010 0.26 0.74 1.83 204 1.37 0.004 0.09 0.47 2.51 2,223 1.29 0.006 0.12 1.96 50,727 74,000
31 2.50 20,841 17.31 0.011 0.18 1.92 1,121 6.15 0.004 0.06 0.84 2.01 489 3.73 0.005 0.05 0.59 2.04 1,491 1.28 0.006 0.14 2.09 50,059 74,000

 

Hycroft Mine Project

Page 151

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Year Mill Cutoff Mill Oxide Leach, $0.01 Net of Process Cutoff Transition Leach, $0.01 Net of Process Cutoff Low Grd Mill Stkp, $0.01 Net of Process Cutoff Waste Total
Net of Process ($/ton) Ktons Net of Process ($/ton) Fire Gold (oz/t) Silver (oz/ton) Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Cyanide Ratio CnAu/FaAu Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Cyanide Ratio CnAu/FaAu Sulfide Sulfur (%) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Silver (oz/ton) Sulfide Sulfur (%) Ktons Ktons
32 2.50 20,841 15.24 0.011 0.16 1.89 727 2.96 0.002 0.11 0.88 1.15 149 1.23 0.004 0.14 0.54 0.56 1,061 1.40 0.006 0.12 2.01 53,222 76,000
33 2.50 20,841 14.60 0.011 0.16 1.85 460 1.63 0.002 0.13 0.78 0.39 274 0.83 0.003 0.20 0.55 0.49 801 1.35 0.006 0.11 1.81 53,624 76,000
34 2.50 20,841 16.42 0.011 0.19 1.84 9 5.21 0.004 0.20 0.74 1.09 978 1.25 0.004 0.17 0.48 0.76 677 1.42 0.006 0.11 2.24 53,495 76,000
35 2.50 20,841 16.78 0.011 0.19 1.98 48 7.42 0.005 0.13 0.74 1.80 574 1.52 0.004 0.16 0.47 1.14 593 1.48 0.006 0.14 2.33 53,944 76,000
36 2.50 20,841 15.29 0.009 0.30 1.74 1,228 6.86 0.005 0.06 0.78 1.32 6,408 2.58 0.005 0.13 0.52 1.47 747 1.38 0.006 0.15 1.73 46,775 76,000
37 2.50 20,841 26.91 0.012 0.47 2.36 168 6.08 0.004 0.14 0.91 1.07 238 1.49 0.005 0.13 0.43 1.40 1,560 1.35 0.005 0.17 1.98 51,192 74,000
38 2.50 20,841 24.95 0.011 0.53 2.34 229 12.00 0.007 0.13 0.76 1.20 1,354 3.55 0.006 0.11 0.49 1.62 1,510 1.31 0.005 0.17 1.82 46,566 70,500
39 2.50 20,841 25.43 0.012 0.47 1.82 531 4.33 0.003 0.13 0.74 2.06 454 2.03 0.004 0.15 0.57 1.73 1,503 1.26 0.005 0.16 1.67 47,171 70,500
40 2.50 20,841 26.65 0.010 0.69 1.47 998 4.54 0.003 0.16 0.74 1.70 942 3.56 0.006 0.11 0.53 1.90 2,003 1.24 0.006 0.14 1.71 45,715 70,500
41 2.50 20,841 34.50 0.011 0.85 1.54 675 2.46 0.002 0.14 0.74 1.89 937 2.43 0.004 0.13 0.57 1.81 1,486 1.23 0.005 0.16 1.50 46,561 70,500
42 2.50 20,841 17.02 0.010 0.28 1.78 687 0.65 0.001 0.14 0.95 2.20 862 2.57 0.005 0.12 0.46 2.26 1,643 1.24 0.005 0.17 1.85 46,467 70,500
43 2.50 20,841 15.02 0.011 0.16 1.84 18 4.22 0.003 0.08 0.94 2.40 48 2.63 0.005 0.08 0.51 2.36 1,751 1.35 0.006 0.09 2.05 47,842 70,500
44 2.50 20,841 14.66 0.011 0.16 1.92 192 0.41 0.001 0.06 0.99 2.21 59 2.02 0.005 0.13 0.41 2.00 1,402 1.39 0.006 0.12 1.90 48,006 70,500
45 2.50 20,841 13.15 0.010 0.14 2.21 368 0.52 0.001 0.06 0.99 1.67 211 2.26 0.006 0.05 0.42 2.28 2,141 1.34 0.006 0.09 2.00 47,038 70,600
46 2.50 20,841 12.76 0.010 0.14 1.91 34 3.72 0.002 0.06 0.96 1.79 317 1.89 0.005 0.11 0.50 1.96 1,910 1.34 0.006 0.11 1.84 47,498 70,600
47 2.50 20,841 19.28 0.011 0.29 1.83 117 0.91 0.001 0.08 0.98 1.32 153 2.36 0.005 0.12 0.54 2.00 1,893 1.21 0.006 0.13 1.84 49,370 72,374
48 2.50 20,841 24.54 0.012 0.41 1.78 15 43.38 0.019 0.19 1.00 2.24 309 2.24 0.005 0.10 0.45 2.20 1,030 1.32 0.006 0.13 1.96 33,556 55,750
49 2.50 20,841 23.81 0.011 0.42 1.65 - - - - - - 114 1.13 0.005 0.15 0.36 2.34 749 1.30 0.006 0.14 1.76 33,706 55,409
50 2.50 20,841 35.11 0.011 0.89 1.33 - - - - - - 102 1.81 0.005 0.17 0.40 1.06 737 1.45 0.005 0.18 1.38 19,302 40,982
51 2.50 11,008 42.99 0.011 1.16 1.13 - - - - - - 86 0.55 0.004 0.22 0.33 1.20 964 1.15 0.005 0.22 1.15 12,300 24,358
Total - 1,046,284 24.34 0.012 0.43 1.93 60,768 5.11 0.004 0.12 - 1.55 149,242 3.25 0.006 0.14 - 1.83 239,839 4.76 0.007 0.16 2.08 2,320,719 3,816,853

 

Hycroft Mine Project

Page 152

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

13.2Geotechnical and Hydrologic Information

 

Slope angles for the mine plan were recommended by Call & Nicholas, Inc. (CNI) during February of 2022 with additional documentation in October of 2023. Inter-ramp slope angles range from 25 to 45 degrees depending on the rock type, alteration, and pit geometry. IMC has reviewed this work and has accepted the slope angle recommendations for use in the development of this mine plan.

 

13.3Phase Design

 

The final pit and phase designs were based on computer generated Lerch-Grossman (LG) pits that were generated at a range of metal prices. The input parameters for the LG pits were summarized on Table 11-18. There was one modification to the MRE pit parameters on Table 11-18 when applied to the mine plan. The mine plan LG pits targeted measured and indicated class mineralization only. Inferred was treated as waste in the mine planning process.

 

Multiple nested LG pits were generated to assist in establishing the final pit and the best overall extraction sequence. The metal prices for design were $$3,100/oz gold and $36.00/oz silver. Those prices were reduced in increments by the price ratios shown in Table 13-2. Table 13-2 and Figure 13-2 summarize the results of the nested LG runs in both tabular and graphic form. All cones on the table were tabulated at the design metal prices of $3,100/oz Au, and $36/oz Ag.

 

Table 13-2 and Figure 13-2 indicate that the financial benefit of increasing the pit size beyond the 85% price ratio was marginal. As a result, the 85% pit was used as the target for final pit design. The 85% pit is highlighted on the table and illustrated on the graph. Additional check pits were developed with bench discounting applied. The impact of the bench discounting was minor.

 

Based on the pit geometries of the nested LG pits, a series of 19 phase designs were generated for input into the mine plan. Those phase designs followed the extraction sequence suggested by the LG pit runs. Phase designs utilized the inter-ramp slope designs on combined with the following design parameters:

 

Road Width 125 ft
     
Maximum Road Gradient 10%
     
Minimum Mining Width 300 ft

 

Table 13-3 summarizes the contained tonnage in each phase at the internal cutoff grade.

 

Figure 13-3 illustrates the extraction sequence of the phases.

 

The phases were ranked economically based on the profit per ton ore and the cost per equivalent ounce gold to set the phase extraction sequence. That ranking was adjusted as required to accommodate the practical extraction sequence.

 

At any point in time, the Mine will be a combination of three to four phase designs operating simultaneously.

 

Hycroft Mine Project

Page 153

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 13-2: Summary of Lerch-Grossman Computer Pit Generation

 

Au Price

($)

Price Ratio Mill Process Leach Process

Waste

(Ktons)

Total

(Ktons)

Ktons Net of Process ($/ton) Fire Gold (oz/ton) Total Silver (oz/ton) Ktons Net of Process ($/ton) Fire Gold (oz/ton) Total Silver (oz/ton)
310 10% 1,097 151.36 0.029 3.50 206 8.14 0.008 0.08 334 1,637
465 15% 1,748 126.65 0.025 2.97 434 13.51 0.010 0.08 553 2,735
620 20% 2,573 106.48 0.025 2.20 562 13.34 0.010 0.08 742 3,877
775 25% 4,938 76.85 0.021 1.49 1,298 10.59 0.008 0.08 1,713 7,949
930 30% 8,372 62.48 0.019 1.11 2,027 10.04 0.008 0.10 3,171 13,570
1,085 35% 13,659 52.02 0.018 0.85 4,024 7.59 0.007 0.10 5,490 23,173
1,240 40% 27,258 43.00 0.016 0.67 7,829 6.00 0.006 0.10 13,563 48,650
1,395 45% 85,969 34.89 0.014 0.59 28,356 4.66 0.005 0.11 75,539 189,864
1,550 50% 144,389 30.29 0.013 0.51 38,746 4.39 0.005 0.11 108,094 291,228
1,581 51% 169,775 29.58 0.013 0.50 52,508 4.23 0.005 0.11 140,786 363,070
1,612 52% 175,867 29.33 0.013 0.50 53,945 4.23 0.005 0.11 146,644 376,455
1,643 53% 186,969 28.78 0.013 0.48 55,680 4.22 0.005 0.11 153,832 396,480
1,674 54% 588,778 23.31 0.011 0.43 84,161 3.72 0.004 0.11 673,438 1,346,377
1,705 55% 598,930 23.30 0.011 0.43 85,077 3.72 0.004 0.11 687,143 1,371,150
1,860 60% 776,490 23.03 0.011 0.44 114,870 3.73 0.004 0.11 1,001,378 1,892,739
2,015 65% 906,288 22.30 0.011 0.41 124,912 3.75 0.004 0.11 1,182,421 2,213,621
2,170 70% 1,059,314 21.51 0.011 0.39 141,087 3.93 0.005 0.11 1,446,359 2,646,760
2,325 75% 1,155,463 21.19 0.011 0.39 154,053 3.89 0.005 0.10 1,668,707 2,978,222
2,480 80% 1,252,532 20.91 0.011 0.38 164,321 3.84 0.005 0.10 1,976,220 3,393,073
2,635 85% 1,305,935 20.75 0.011 0.38 170,142 3.81 0.005 0.10 2,180,037 3,656,113
2,790 90% 1,343,023 20.63 0.011 0.38 175,053 3.79 0.005 0.10 2,333,196 3,851,272
2,945 95% 1,368,413 20.47 0.011 0.38 177,864 3.77 0.005 0.10 2,411,860 3,958,138
3,100 100% 1,388,947 20.35 0.011 0.37 180,494 3.75 0.005 0.10 2,492,069 4,061,510

 

Note:

 

1.All Cutoff grades on this table are Internal Cutoff, Net of Process >= $0.01/ton

 

Hycroft Mine Project

Page 154

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-2: Summary of Lerch-Grossman Computer Pit Generation

 

 

Source: IMC, 2026

 

Table 13-3 : Contained Tonnage by Internal Cutoff Grade

 

Extraction

Sequence

Area

Mill Process Material

Heap Leach Process Material

Waste Total
Ktons NPR $/ton Au oz/ton Ag oz/ton Ktons NPR $/ton Au oz/ton Ag oz/ton Ktons Ktons
1 Central 60,039 $22.39 0.012 0.30 4,079 $3.22 0.004 0.09 28,382 92,500
2 Brimstone 42,823 $24.93 0.012 0.43 5,414 $3.36 0.004 0.12 13,300 61,537
3 Bay 18,696 $24.06 0.015 0.13 2,891 $4.51 0.006 0.06 28,538 50,124
4 Brimstone 82,264 $17.71 0.010 0.34 14,222 $2.84 0.004 0.10 83,534 180,019
5 Bay 20,041 $16.31 0.012 0.09 6,700 $3.71 0.006 0.05 10,958 37,700
6 Bay 20,865 $18.98 0.012 0.07 18,176 $5.42 0.005 0.06 44,313 83,354
7 Camel 20,685 $25.19 0.010 0.60 5,956 $3.13 0.004 0.12 28,896 55,537
8 Camel 61,954 $18.62 0.011 0.24 3,445 $3.20 0.004 0.15 48,563 113,962
9 Brimstone/Vortex 75,566 $13.91 0.009 0.32 11,122 $2.15 0.004 0.11 189,237 275,925
10 Brimstone 68,101 $15.53 0.009 0.32 12,788 $2.45 0.004 0.09 118,884 199,773
11 Vortex 226,663 $21.96 0.011 0.43 12,684 $3.23 0.004 0.12 260,253 499,600
12 Central 26,092 $21.62 0.012 0.32 11,040 $3.69 0.005 0.08 82,325 119,457
13 Brimstone 73,941 $32.58 0.011 0.78 27,927 $4.18 0.004 0.12 192,274 294,142
14 Camel 124,473 $15.09 0.011 0.16 7,928 $5.03 0.005 0.12 192,700 325,101
15 Vortex 107,980 $27.15 0.011 0.60 3,594 $1.66 0.003 0.14 297,178 408,753
16 Brimstone 59,873 $15.69 0.009 0.32 5,066 $3.23 0.004 0.14 153,301 218,239
17 Central 14,018 $11.57 0.007 0.36 9,674 $3.76 0.005 0.12 24,596 48,288
18 Camel 118,762 $13.56 0.010 0.17 1,025 $1.31 0.003 0.06 216,108 335,895
19 Vortex 103,387 $25.44 0.011 0.55 5,919 $2.79 0.004 0.12 307,381 416,686

 

Hycroft Mine Project

Page 155

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-3: Phase Schematic and Extraction Sequence

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 156

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

13.4Production Schedule

 

The Mine production schedule was developed after completing a number of iterations. The goals of the production schedule were as follows:

 

1.Assure practical and operational mine geometries.

 

2.Select a total material rate that assured ore release and provided for efficient use of mine capital equipment.

 

3.Maximize the project net present value (NPV) by adjusting mine cutoff grades and total material movement.

 

Table 13-1 presents the mine production schedule for the LOM plan. The cutoff grade to the mill process was adjusted annually to maximize the NPV of the mine production schedule by producing higher grade and consequently more metal in the early years of the mine life. The elevated mill feed cutoff resulted in low grade potential sulfide feed being sent to a low-grade mill stockpile.

 

Each block in the model was evaluated for its net benefit by both heap leach and mill processing. Mill cutoff grades were applied to the mill net of process only. During each year, blocks that were not routed to the mill were evaluated to see if they had sufficient heap leach benefit to provide positive economic benefit on the heap leach pad. Those blocks were re-routed to the heap leach pad. Low grade sulfide mill feed material was stockpiled for eventual re-mining to the mill after the pit was exhausted. Re-mining and processing of the stockpile should consider the potential for loss of process recovery due to exposure to weathering for an extended period of time. Re-mining and processing of the stockpile is not part of the economic model in this study.

 

Figure 13-4 and Figure 13-5 illustrate the approximate recovered metal produced over the life of the open pit. The benefit of the elevated cutoff grades in the initial years can be observed with the higher level of gold production in the early years of the mine life. The relative metal contribution of the heap leach compared to the mill is also evident in the graphs. Figure 13-6 illustrates the approximate recovered equivalent gold based on metal prices of $3,100 oz Au, and $36/oz Ag.

 

Figure 13-7 through Figure 13-17 illustrate the mine and waste storage plan. At any point in time, three to four phases are active to release the process feed, to sustain a consistent total material movement.

 

Waste is delivered to the large storage facility located west and south of the mine. Once areas of the mine are complete, in-pit backfill is utilized for waste storage. The heap leach process material is planned to be delivered to the Brimstone or Jungo heap leach pads located north of the mine. Low grade sulfide stockpile material is hauled to an area west of the Brimstone and Jungo heap leach pads. Mill process material is hauled to the primary crusher located just west of the Brimstone heap leach facility.

 

Hycroft Mine Project

Page 157

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-4: Approximate Recovered Gold by Year

 

 

Source: IMC, 2026

 

Figure 13-5: Approximate Recovered Silver by Year

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 158

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-6: Approximate Recovered Equivalent Gold Ounces by Year Based on $3,100/oz Au and $36/oz Ag

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 159

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-7: Mine and Waste Storage Plan – Pre-production

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 160

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-8: Mine and Waste Storage Plan - End of Year 1

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 161

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-9: Mine and Waste Storage Plan – End of Year 2

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 162

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-10: Mine and Waste Storage Plan - End of Year 3

 

 

Source : IMC, 2026

 

Hycroft Mine Project

Page 163

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-11: Mine and Waste Storage Plan - End of Year 4

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 164

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-12: Mine and Waste Storage Plan – End of Year 5

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 165

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-13: Mine and Waste Storage Plan – End of Year 10

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 166

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-14: Mine and Waste Storage Plan – End of Year 20

 

 

Source: IMC, 2026

 

Hycroft Mine Project

Page 167

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-15: Mine and Waste Storage Plan – End of Year 30

 

 

Source IMC, 2026

 

Hycroft Mine Project

Page 168

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-16: Mine and Waste Storage Plan – End of Year 40

 

 

Source IMC, 2026

 

Hycroft Mine Project

Page 169

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 13-17: Mine and Waste Storage Plan – End of Year 51

 

 

Source IMC, 2026

 

Hycroft Mine Project

Page 170

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

13.5 Mining Equipment

 

Mine equipment was selected for the project under the assumption that Hycroft would own the equipment and operate the mine. Contract mining has not been considered for this initial assessment. Table 13-4 summarizes the major mine equipment list.

 

Mine equipment for this study has been assumed to be diesel powered, negating the requirement for a pit electrical power distribution system. Mechanical availability has been assumed to be 85% with 95% use of that availability. The mine is assumed to operate year-round on a two-shift-per-day, 12-hour shift schedule requiring a four-crew rotation system. IMC has assumed that 10 shifts per year will be lost due to weather or other delays, so that there are 720 planned operating shifts per year. Standard inefficiencies are incorporated into each shift, such that equipment cycles operate for 550 minutes per shift (11 hours at 50 minutes per hour).

 

Mine equipment requirements for drilling and loading equipment were estimated based on typical production rates and Hycroft average material densities. The rock and alternation types at Hycroft cover a broad range of mechanical properties from relatively soft to competent. IMC selected rotary blast hole drills with 70,000 LBF pull down and 10 ⅝ inches (”) bits. Four drills of that type will be required, which matches the typical number of operating pushbacks.

 

Two types of loading equipment have been selected: (1) 44.5 yd3 hydraulic front shovels, and (2) 30 yd3 front end loaders. Two shovels and two loaders are required. The four loading units match the typical number of operating pushbacks, and the front-end loaders provide the flexibility to adjust production rates between pushbacks as required.

 

Haul trucks were sized at 250-ton units to provide a good match to the loading units. Haul profiles were measured for each material type to each destination annually for each of the first 10 years of the mine plan. After year 10, five-year increments were used for haul profile measurements. Truck haul time was calculated over each profile using haul time simulation. Fixed times were added for loading under the shovel or loader and for maneuvering and dumping at the crusher, stockpile, leach pad, or waste storage.

 

In addition to the above units, a substantial fleet of auxiliary equipment is provided to maintain the mine in good working order.

 

A total of five track dozers of the D9 class are provided to complete pioneering, position material on the dumps, leach pads, and stockpiles, and assist with in-pit drop cuts.
A total of four-wheel dozers of the Cat 834 class are provided to help maintain the roads and support the loading equipment. One wheel dozer is matched to each set of drills and loading units.
A total of three graders with 16 ft moldboards is provided for haul road maintenance.
A total of three water trucks on 100-ton truck frames is provided to maintain air quality with dust control.
A 15 yd front loader and three 100-ton trucks are provided as auxiliary support units. They will assist with pioneering, road construction, and other minor material movement tasks around the mine.

 

Hycroft Mine Project

Page 171

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

A support drill is provided for secondary and special blasting, and a backhoe is provided for trenching, drainage, and utility line movement in the mine area.

 

In addition, a significant fleet of minor equipment is provided including blast hole stemmers, flatbed trucks, Ammonium Nitrate Fuel Oil Mix (ANFO) slurry trucks, lube and fuel trucks, crane trucks, tire handler, mechanics trucks, welders trucks, forklifts, man vans, pickup trucks, light plants, and a tractor and lowboy to assist with drill moves. A mine dispatch system is included as are a prill silo and powder magazine.

 

Table 13-4: Major Mine Equipment

 

Mine Major Equipment Fleet on Hand
Equipment Type -1 1 2 3 4 5 6 7 8 9 10 11-15 16-20 21-25 26-30 31-35 36-40 41-45 46-51
70,000 Pull Dn Drill, 10 ⅝” 1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3
Hydralic Shovel, 44.5 yd3 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
30 yd3 Loader (Cat 994) 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
250 Ton Haul Truck 6 18 21 21 21 25 25 25 25 27 27 27 28 32 28 27 26 26 29
Track Dozer, D9 Class 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Wheel Dozer, Cat 834 Class 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3
Grader 16 ft Moldboard 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
100 Ton Water Truck (Cat777 Frame) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Cat 992 Wheel Loader 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
100 Ton Aux Truck 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
Support Rock Drill 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Cat 330 Excavator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 26 46 49 49 49 52 52 52 54 56 56 56 56 61 58 56 56 54 54

 

13.6 Mine Manpower Requirements

 

Mine hourly manpower was estimated to operate and maintain the mine equipment listed in the previous sub-section. The four-crew rotation was incorporated when calculating manpower requirements.

 

Hycroft Mine Project

Page 172

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 13-5 summarizes the mine hourly personnel required to operate and maintain the mine.

 

Table 13-5: Mine Hourly Personnel

 

Job Title Annual Cost Years
Prep 1 2 3 4 5 6 7 8 9 10 11-15 16-20 21-25 26-30 31-35 36-40 41-45 46-51
Mine Operations
Drill Operator 127,738 2 11 11 11 12 13 13 13 13 13 13 13 13 13 12 12 11 11 9
Shovel Operator 136,628 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Loader Operator 136,628 1 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 5 5
Haul Truck Driver 118,638 10 56 65 58 68 79 75 73 80 85 72 86 88 104 86 70 77 82 91
Track Dozer Operator 118,638 5 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 13
Tire Dozer Operator 118,638 4 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 10
Grader Operator 118,638 6 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Service Crew 118,638 16 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21
Blasting Crew 124,705 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Dispatch Operator 124,705 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Laborer 98,418 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Operations Total - 69 163 172 165 178 190 186 184 191 196 183 197 199 215 196 180 185 189 189
Mine Maintenance
Mechanic 136,837 7 22 23 22 24 26 25 25 26 27 25 27 28 30 27 25 26 27 27
Mechanic's Helper 127,772 8 27 28 27 29 31 30 30 31 33 30 33 33 36 33 30 31 32 32
Welder 127,772 3 10 11 10 11 12 12 11 12 12 12 12 13 14 12 12 12 12 12
Electrician 127,772 1 1 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Fuel and Lube Maintenance 118,638 4 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Tire Maintenance 118,638 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Laborer 98,418 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Maintenance Total - 26 74 78 74 80 85 83 82 85 88 83 88 90 96 88 83 85 87 87
VS&A at 10% - 10 24 25 24 26 28 27 27 28 28 27 29 29 31 28 26 27 28 28
Total Labor Requirement - 105 261 275 263 284 303 296 293 304 312 293 314 318 342 312 289 297 304 304
Maintenance/Operations Ratio - 0.38 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.46 0.46 0.46 0.46

 

Note:

 

1. Service Crew operates Rock Drill, Excavators, Water Truck, etc.

 

Hycroft Mine Project

Page 173

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 13-6 summaries the mine salaried staff to provide engineering, supervision, and geology functions. The list includes those salaried personnel directly related to the Mine and does not include overall site wide supervision, processing, or logistics support.

 

Table 13-6: Mine Salaried Staff

 

Job Title Annual Cost (US$) Number
Mine Operations
Mine Superintendent 227,241 1
General Foreman 200,447 1
Mine Shift Supervisor 150,766 4
Drill and Blast Supervisor 150,766 1
Mine Clerk 89,944 1
Mine Trainer 144,712 1
Mine Operations Total - 9
Mine Maintenance
Maint. Superintendent 255,942 1
Maint. General Foreman 189,455 1
Maint. Shift Supervisor 150,766 4
Maintenance Planner 160,353 1
Maintenance Trainer 144,712 1
Maintenance Clerk 89,944 1
Mine Maintenance Total - 9
Mine Engineering
Supervising Mine Engineer 231,620 1
Senior Mining Engineer 178,689 1
Mine Engineer 149,969 1
Sr. Surveyor 154,358 1
Surveyor Helper 109,795 2
Clerk 89,944 1
Mine Engineering Total - 7
Mine Geology
Senior Mine Geologist 202,449 1
Mine Geologist 166,246 1
Sr Geotechnical Engineer 166,246 1
Geotechnical Engineer 101,096 1
Sampler 109,795 8
Mine Geology Total - 12
Total Personnel - 37

 

Note: Annual Cost includes Fringe Benefits

 

Hycroft Mine Project

Page 174

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

14 Processing and Recovery Methods

 

14.1 Overview

 

Hycroft has an established operating history utilizing heap leach processing and has previously produced gold and silver through heap leach operation. The proposed processing strategy continues to build upon this demonstrated operating approach and existing site infrastructure to support project development. Oxide material and transition material will continue to be processed using heap leach and will be stacked on engineering heap leach pads and irrigated with cyanide solution to recover gold and silver. Pregnant leach solution generated from the heap leach operation will be collected and processed through the existing Merrill-Crowe recovery circuit and associated process facilities. Transition material is included in the heap leach processing strategy where supported by the current assumption adopted for the economic assessment. However, uncertainty remains regarding transition material heap leach performance due to limited dedicated metallurgical testwork. Additional transition material heap leach testing is recommended during the next study phase to improve confidence in recovery assumptions, leach kinetics, reagent consumption, and permeability characteristics.

 

As discussed in Section 10, a significant portion of the gold in the Hycroft mineralized material is refractory due to its association with pyrite, marcasite, and other sulfide minerals. A process flowsheet was developed to treat sulfide mineralized material. These materials are ground and floated to produce a concentrate. The concentrate is then oxidized in the POX plant and subsequently cyanide leached to extract gold and silver.

 

The key Project plant design criteria are as follows:

 

Major equipment is designed for a nominal throughput of 57,100 ton/d.
The existing crushing circuit consists of primary, secondary, and tertiary crushing, supported by a coarse ore stockpile and a crushed ore stockpile with dedicated feeders to provide continuous feed to the downstream process plant.
Process flowsheets include three stages of crushing followed by two stages of ball milling, flotation, POX, a cyanide leaching circuit for oxidized flotation concentrate, Merrill-Crowe circuit, and tailings handling facilities, with an overall availability of 92%, given:
design head grades of 0.015 oz/ton Au, 0.41 oz/ton Ag, and 2.41% sulfide sulfur, and
overall process recovery of 82.8% gold and 77.5% silver, given the LOM average grades.

 

Pregnant solution from the cyanide leach circuit will be processed in the existing Merrill-Crowe zinc cementation facilities.

 

Hycroft Mine Project

Page 175

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The recovery rates used in the process plant design and financial model are based on the testwork results provided in Section 10. These results may be updated as further work is done as the project advances.

 

14.2 Process Flowsheet

 

Figure 14-1 presents an overall process flow diagram depicting the proposed major unit operations for the refractory mineralized materials.

 

Figure 14-1: Sulfide Sulfur Process Plant Flowsheet

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 176

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The existing crushing plant will process the ROM material using three stages of crushing to reduce the feed from a nominal top size of 35” to a product size with a P80 of 0.6”. The grinding circuit will consist of a two-stage ball milling configuration. Each stage of ball mills will operate in closed circuits with hydrocyclones. The cyclone overflow from second stage will be directed to a rougher flotation circuit to recover the gold and silver in a flotation concentrate.

 

Rougher flotation tailings will be thickened in a tailings thickener prior to transfer to the final tailings pump box.

 

The flotation concentrate will be oxidized in autoclaves at a temperature of 428 °F and a pressure of 454 psi, with a residence time of 60 minutes. The discharge from each autoclave will pass through two flash vessels, where heat will be released, cooling the slurry to approximately 220 °F. The slurry will then be pumped to the hot cure circuit, where the slurry temperature will be maintained between 195 °F and 220 °F for 10 hours to dissolve basic ferric sulfate (BFS) formed during the pressure oxidation process.

 

Following hot curing, the process will separate the base metal rich acidic liquors from the oxidized solids. This separation will be achieved using a three-stage CCD wash thickener circuit, removing more than 98% of the sulfuric acid and the dissolved metal sulfates. The washed, thickened slurry will then be contacted with steam from the autoclave flash vessels to heat the slurry to approximately 203 °F ahead of a four-stage lime boil circuit. The addition of milk of lime will raise the slurry pH to 10.5, decomposing silver jarosites and enabling silver recovery in the downstream leach circuit. Following the lime boil circuit, the slurry will be cooled to approximately 108 °F in cooling towers and pumped to the leach circuit.

 

The lime addition in the lime boil circuit will provide sufficient protective alkalinity for the leach circuit, and no further lime addition will be required during leaching.

 

The acidic overflow from CCD thickener No. 1 will be pumped to the autoclave plant to quench flash steam. The quench vessel underflow will be treated with limestone slurry in the solution neutralization circuit to remove ferric iron. Neutralization will be carried out in six mechanically agitated neutralization tanks operating in series, with limestone slurry added to the first four neutralization tanks and milk of lime added to the final two neutralization tanks precipitating remaining metal sulfates. The neutralized slurry will be dewatered in a high-rate neutralization thickener. Thickener underflow (sludge) will be pumped to the final tailings pump box and deposited in the TMF, while thickener overflow will be cooled to approximately 108°F in cooling towers and pumped to POX wash and cooling water tank and process water tank.

 

The oxidized flotation concentrate will be leached in stirred tanks using a cyanide solution to dissolve gold and silver. Discharge slurry from the leach circuit will be washed in a four-stage CCD circuit. The overflow from the CCD thickener No. 1 will constitute pregnant solution, which will be deaerated and treated in the existing Merrill- Crowe zinc cementation circuit to precipitate gold and silver. The resulting precious metals precipitate will be filtered and then smelted on site to produce gold–silver doré bars.

 

Hycroft Mine Project

Page 177

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Underflow slurry from the fourth wash thickener will be treated with sulfur dioxide (added as sodium metabisulphite) and oxygen in a series of agitated tanks to detoxify residual cyanide in the leach residue. Following cyanide destruction, the detoxified tailings will be combined with rougher flotation tailings and pumped to the TMF for impoundment.

 

14.3 Plant Design

 

The key process design criteria listed in Table 14-1 form the basis of the process flowsheet design and selection of mechanical equipment. The major process equipment is presented in Table 14-2.

 

Table 14-1: Process Design Criteria

 

Parameter Unit Value
Plant Throughput ton/day 57,100
Head Grade–design oz/ton Au 0.015
oz/ton Ag 0.410
Sulfide sulfur, % 2.41
Overall Recovery (From mineralized material to doré)–Au % 82.8
Overall Recovery (From mineralized material to doré)–Ag % 77.5
Plant Availability % 92
Bond Crusher Work Index–design (75th percentile) kWh/ton 17.9
Bond Ball Mill Work Index–design (75th percentile) kWh/ton 19.0
Abrasion Index (average) g 0.430
Flotation Concentrate Mass Pull – design % 22
Rougher Flotation Residence Time Min 48
POX Sulfide Oxidation % 99
Autoclave Residence Time Min 60
Autoclave Operating Temperature °F 428
Autoclave Operating Pressure Psi 454
Hot Cure Temperature °F 220
Hot Cure Residence Time H 10
Lime Boil Temperature °F 206
Lime Boil Residence Time hr 12
Number of POX CCD Wash Stages  - 3
POX CCD Wash Efficiency % 98
POX CCD Overflow Neutralization Residence Time H 6
Flotation Concentrate Leach Residence Time H 24
Concentrate Leach Slurry Density % solids (wt/wt) 35
Number of CCD Wash Stages  - 4
CCD Wash Efficiency % 98
Metal Recovery Method   Merrill-Crowe
Cyanide Destruction Method   SO2 / Air

 

Hycroft Mine Project

Page 178

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 14-2: Major Process Equipment

 

Equipment Type Quantity/Size
Crushing
Primary crusher (Existing) Gyratory crusher (62 × 113 in) 1 × 1,000 HP
Secondary crusher (Existing) Cone crusher (Raptor XL1300) 2 x 1,300 HP (2 operating)
Tertiary crusher (Existing) Cone crusher (Raptor XL1300) 2 x 1,300 HP (2 operating)
Grinding
Primary grinding ball mill Ball mill 26 ft dia. x 39.5 ft EGL; 2 x 21,500 HP (2 operating)
Secondary grinding ball mill Ball mill 26 ft dia. x 39.5 ft EGL, 2 x 21,500 HP (2 operating)
Flotation
Rougher flotation cell Forced-air tank cells 12 x 17,660 ft3 (2 banks)
Concentrate Thickening
Concentrate thickener High-rate thickener 1 x 157 ft dia.
Pressure Oxidation (POX)
Autoclave Pressure oxidation autoclave

16.2 ft ID x 142.8 ft length

(2 trains)

Flash tanks Pressure flash vessels

22.9 ft ID x 40.6 ft length

(2 tanks per stage, 1 stage per train)

High pressure cyclonic separator Cyclonic separator 2 per train
Pressure scrubber Venturi scrubber 1 per train
Low pressure cyclonic separator Cyclonic separator 1 per train
Oxidized slurry seal leg tank Seal leg tank 8,000 gal, 1 per train
Lime boil preheater Slurry heat exchanger 60,000 gal, 2 units
Autoclave steam quench vessel Quench vessel 42,000 gal, 1 per train
Hot cure tank Agitated tanks 5 x 751,000 gal
Lime boil tank Agitated tanks 4 x 1,145,000 gal
Slurry Neutralization
Slurry washing by CCDs High-rate thickener 3 x 197 ft dia
CCD overflow neutralization Neutralization tanks 6 x 736,000 gal
Neutralization thickener High-rate thickener 1 x 115 ft dia
Cooling towers Cooling towers 7 units (3 slurry cooling, 4 solution cooling)
Leaching
Leach tanks Agitated leach tanks 6 x 1.1 million gal
Leach CCD and Cyanide Destruction
CCD thickener High-rate thickener 4 x 200 ft dia
Cyanide destruction Agitated tanks 2 x 332,000 gal
Rougher Tailings Thickening
Tailing thickener High rate 223 ft dia

 

Hycroft Mine Project

Page 179

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

14.4 Process Description

 

14.4.1 Crushing Area

 

The mill was designed to operate at a nominal capacity of 57,100 ton/day (at 75th percentile mineralized material hardness).

The existing crushing plant includes one primary crusher (60” x 113”), two secondary crushers (XL1300 Standard), and two tertiary crushers (XL1300 Short Head).

 

14.4.1.1 Primary Crushing and Coarse Ore Stockpile

 

ROM mineralized material will be transported by haul trucks from the mine to the existing primary crusher and dumped into a dump pocket. The primary crusher is a 60” x 113” gyratory crusher with an open side setting of 178 mm (7”) and a feed opening of 1,524 mm (60”). The crusher is powered by a 1000-hp motor.

 

The crushed material will be discharged via a surge bin to an apron feeder. The mineralized material will then be transferred by a stacker conveyor and discharged to a coarse ore stockpile. A belt scale will be installed on the stacker conveyor to measure the quantity of crushed mineralized material delivered, and a self-cleaning magnet will be installed upstream of the stockpile to remove any tramp steel.

 

The coarse material stockpile has a live capacity of 75,000 tons and a total capacity of 300,000 tons.

 

The crushed mineralized materials will be reclaimed via two reclaim tunnels located beneath the stockpile. Each reclaim line consists of three reclaim feeders (two operating and one standby) and a reclaim transfer conveyor.

 

Dust suppression systems and baghouses are installed to control dust generated by haul trucks, crushers, and other material handling equipment.

 

14.4.1.2 Secondary and Tertiary Crushing

 

Hycroft has installed four FLS Raptor XL1300 cone crushers – two with standard cavities and two with short head cavities, serving secondary and tertiary crushing duties, respectively. Each crusher is driven by a 1,300-hp motor and is fed from a bin through a feeder and vibrating screen.

 

Coarse mineralized material will be conveyed to the secondary crusher feed bin and distributed to the secondary screens. Oversize from the secondary screens will report to the secondary crushers, while screen undersize will be discharged to screen undersize conveyor. The secondary crusher will operate at a closed side setting (CSS) of 1.2”, producing material with a P80 of 1.3”.

 

Secondary crusher product will be conveyed to the tertiary crusher feed bin and distributed to the tertiary screens, Oversize from the tertiary screens will report to the tertiary crushers, while tertiary screen undersize will be discharged to screen undersize conveyor and transferred to the crushed product conveyor. The tertiary crushers will operate at a CSS of 0.9”, producing material with a P80 of ⅜”.

 

Hycroft Mine Project

Page 180

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Overall, the crushing plant product will have a P80 of ⅜”.

 

14.4.1.3 Crushed Ore Stockpile

 

The crushed product stockpile has a live capacity of 31,000 tons and a total capacity of 124,000 tons.

 

The crushed product will be reclaimed via two reclaim tunnels located beneath the crushed product stockpile. Each reclaim line consists of two reclaim feeders (one operating and one standby) and a primary ball mill feed conveyor.

 

14.4.2 Grinding Circuit

 

The grinding circuit consists of two parallel primary ball mills followed by two parallel secondary ball mills, arranged in a two-stage ball milling configuration. Each primary ball mill operates in closed circuit with a cluster of hydrocyclones.

 

Crushed mineralized material will be delivered by two primary ball mill feed conveyors to the two primary ball mills (26 ft diameter × 39.5 ft effective grinding length). Each primary ball mill is powered by a 21,500 hp drive. Primary ball mill discharge will report to a primary cyclone feed pump box, where dilution water will be added to control pulp density. The slurry will then be pumped to a cluster of 30” hydrocyclones. Primary cyclone underflow will return to the primary ball mills, while primary cyclone overflow will report to the secondary cyclone feed pump box, where it will combine with secondary ball mill discharge and dilution water.

 

The combined slurry will be pumped into a secondary hydrocyclone cluster (30” cyclones). Secondary cyclone underflow will report to the secondary ball mills (26 ft diameter × 39.5 ft EGL), each powered by a 21,500 hp drive. Secondary cyclone overflow will constitute the final grinding product and will be directed to the flotation circuit after passing through trash screens. The target grind size is a P80 of 85 µm.

 

14.4.3 Rougher Flotation

 

The rougher flotation circuit will be designed to produce a concentrate at 22% mass pull, containing a significant portion of the gold and silver from the sulfide mineralized material. The flotation concentrate will be oxidized in a POX circuit prior to feeding in a concentrate leach circuit to dissolve gold and silver from the flotation concentrate. The resulting pregnant solution will be further processed in a Merrill-Crowe circuit.

 

Cyclone overflow will gravitate over the vibrating trash screens to remove foreign material prior to flotation. Screen oversize will report to a trash bunker for periodic removal, while trash screen undersize will be pumped to two rougher flotation conditioning tanks.

 

Bench-scale flotation testing determined an average laboratory flotation time of 19 minutes. Applying a 2.5 scale-up factor, the required plant residence time is approximately 47.5 minutes.

 

Hycroft Mine Project

Page 181

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Flotation concentrates will be pumped to a concentrate thickener. Rougher flotation tailings will be pumped to a rougher tailings thickener (223 ft diameter) and thickened to 60% solids prior to pumping to the tailing storage facility.

 

Flotation reagents will include PAX as collector and MIBC or equivalent as frother. Flotation will be conducted at the pH of 4.7 and will therefore require sulfuric acid (H2SO4) for pH control in the flotation conditioning tanks. Blowers will supply air to the flotation cells.

 

Average recoveries to the flotation concentrate of 89.5% gold and 92.9% silver were estimated based on laboratory test results.

 

14.4.4 Concentrate Thickening

 

Flotation concentrate will be thickened in a high-rate thickener to produce a slurry of sufficient density for feed to the POX plant. Concentrate from the rougher flotation circuit will be dewatered in a 157 ft diameter concentrate thickener to a slurry density of 49% solids. The thickener underflow will be pumped to the pressure oxidation plant, while thickener overflow will be recycled to the thickener feed for dilution and directed to the process water tank.

 

14.4.5 POX and Neutralization

 

14.4.5.1 POX Feed System

 

The flotation concentrate will be transferred via a screen covered POX feed tank to four POX feed storage tanks, which will provide 12 hours of buffering capacity between the Concentrator and POX sections. The POX feed tank will be equipped with a vibrating screen to reject any +10-mesh deleterious material and protect the autoclave feed pumps. Screen oversize will be collected and periodically analyzed to determine the appropriate disposal location. The four POX feed storage tanks will operate in parallel and will be capable of feeding either autoclave train.

 

14.4.5.2 Pressure Oxidation

 

The POX facility will comprise two autoclave circuits. Each circuit will include a high-pressure slurry feed system, slurry preheater, an autoclave vessel with agitators, flash vessels, and a gas handling system. Autoclave operation will be supported by agitator seal systems, a steam boiler for start-up, and a high-pressure cooling water system for autoclave temperature control.

 

Slurry will be pumped into the first compartment of each autoclave using positive displacement pumps. The autoclaves will be mechanically agitated horizontal pressure vessels with approximate internal dimensions of 16.2 ft inside diameter and an overall length of 142.8 ft. Each autoclave will operate at 428 °F and 454 psi, and will consist of five compartments equipped with eight agitators, providing a nominal retention time of 60 minutes. The agitators in the first autoclave compartment will be driven by variable speed drives to optimize oxygen mass transfer. The first compartment is larger than the downstream compartments and contains four agitators to ensure that the introduction of cold slurry does not adversely affect the front-end reactor temperature or reduce the initial oxidation reaction rate.

 

Hycroft Mine Project

Page 182

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Oxidation of sulfides is an exothermic reaction, and to prevent overheating of the autoclaves, significant quantities of cooling water will be added to each compartment.

 

Steam will be required to heat the autoclaves during cold start-up conditions. Steam will be injected into the vapor space of the autoclaves with the agitators operating, and the autoclave will be preheated at a controlled, predetermined rate.

 

14.4.5.3 Flash System and Gas Cleaning

 

Due to the high autoclave discharge volume, each autoclave train will include two parallel single stage flash tanks, followed by two parallel high pressure cyclonic separators. The flash tanks will be equipped with level control valves and blast tubes to reduce pressure to near atmospheric conditions, generating large quantities of flash steam. The majority of slurry particles entrained in the steam will be removed in the cyclonic separators operating in parallel. Slurry discharged from the flash tanks and cyclonic separators will report to a closed seal leg tank, from which pumps will transfer the slurry to the subsequent process step.

 

The relatively cleaned flash steam from the two cyclonic separators will then combine into a single direct contact “splash” heater, which will be used to heat CCD underflow ahead of the lime boil circuit. Each autoclave train will be equipped with a splash heater, resulting in excess heating capacity. The heaters will be designed to operate without slurry, if required, and to pass the full stream load directly to the steam condensation and cleaning system.

 

Residual steam from the heaters will be partially condensed in a quench vessel, after which inert gases will be cleaned using a venturi scrubber to remove acidic droplets and solid particles. Vent streams from the autoclaves and the seal leg tank vents will be routed to the same venturi scrubber, which will condense most of the remaining steam when the heat exchangers and quench vessels are in operation. The scrubber system will also be capable of operating in a steam cleaning only mode when the heat exchangers and quench vessels are not in service.

 

All vent streams will be combined in a common blast spool prior to entering the venturi scrubber. Cold raw water will be continuously added to the clean (cold) side of the scrubber tank to maintain the minimum operating level. Underflow from the scrubber and quench tanks will be directed to the dirty (hot) side of the scrubber tank. Pumps will transfer the hot, dirty, and slightly acidic spent scrubber water to the solution neutralization circuit.

 

14.4.5.4 Oxygen Plant

 

The oxygen plant will supply gaseous oxygen to support the pressure oxidation process. Oxygen will be produced on site using cryogenic air separation units and injected directly into the autoclaves through spargers located beneath each agitator to promote sulfide oxidation. Approximately 70% of the total oxygen demand will be injected into the first compartment, distributed evenly among the four spargers/agitators. About 20% of the oxygen demand will be split between compartment 2 and 3, with the remaining oxygen injected into the final two compartments.

 

Hycroft Mine Project

Page 183

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

14.4.5.5 Hot Curing

 

The oxidized slurry will be processed through five cascading tanks operating in series, providing a total residence time of 10 hours to ensure dissolution of ferric sulfate. Slurry entering the hot cure circuit will be at approximately 221 °F and will exit at approximately 212 °F. Following curing, the slurry will flow by gravity to the first POX CCD thickener.

 

14.4.5.6 POX CCD Washing

 

A three-stage POX CCD circuit will be used to wash slurry from the hot cure circuit and remove acid and dissolved metal salts from the pressure oxidation residue. Each thickener will be 197 ft in diameter.

 

Slurry will advance through the POX CCD thickeners in series, while wash solution flows in the opposite (countercurrent) direction, with fresh washing water added to the final stage. Overflow solution from the first POX CCD thickener will be routed to the autoclave flash steam quench and solution neutralization circuit. Washed slurry from the final POX CCD thickener will be heated and forwarded to the lime boil circuit.

 

The POX CCD circuit will be designed to achieve a wash efficiency of approximately 98%.

 

14.4.5.7 Neutralization Circuit

 

Neutralization of acidity and precipitation of metals and sulfate from the POX CCD overflow solution and the quench and scrubbing solutions will be carried out in the neutralization circuit. The neutralization circuit will comprise four stages of limestone addition followed by two stages of milk of lime treatment.

 

The limestone and lime reactor tanks will be arranged in a staggered, cascading configuration, allowing slurry to flow by gravity from one stage to the next. Limestone slurry will be metered into a limestone sludge mix tank, where it will be blended with recycled neutralization thickener underflow to condition the recycled solids and promote precipitation seeding. Overflow from the mix tank will feed to the first neutralization tank. Neutralized slurry will flow by gravity from the final lime neutralization tank to the neutralization thickener. Neutralization thickener underflow will be pumped to the tailings storage facility (TMF) via the final tailings pump box, where neutralization thickener overflow will be directed to the neutralization thickener overflow tank and pumped to the solution cooling towers.

 

14.4.5.8 Solution Cooling

 

Neutralization thickener overflow solution will be pumped to a bank of four cooling towers to reduce temperature. The cooled solution will then be pumped to the POX water tank and process water tank.

 

14.4.5.9 Lime Boil Process

 

Underflow from the POX CCD circuit thickener will be pumped to the lime boil heat exchangers, where the slurry will be reheated to a temperature of 206 °F using steam from the autoclave flash system. The reheated slurry will be treated with lime to effectively decompose silver jarosites formed during the POX and hot cure stages, thereby enabling improved silver extraction in the downstream leach circuit.

 

Hycroft Mine Project

Page 184

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The lime boil circuit will consist of four agitated tanks. Lime boil discharge slurry will be cooled to approximately 108 °F in three slurry cooling towers and then pumped to the cyanide leach circuit for gold and silver extraction.

 

14.4.5.10 Limestone Plant

 

Ground limestone and lime will be required for neutralization of acidic liquors and pH control in the leach circuit. The limestone plant will include crushing and grinding facilities, producing limestone ground to a product size with a P80 of 53 µm.

 

14.4.6 Gold and Silver Recovery from Flotation Concentrate

 

The oxidized flotation concentrate (approximately 35% wt/wt solids) will be leached in the concentrate leaching circuit, which will consist of six mechanically agitated leach tanks operating in series.

 

Sodium cyanide (NaCN) will be added to the leach circuit to dissolve gold and silver. The primary cyanide addition point will be the leach feed distribution box, with additional dosing points located at leach tank No.3 and No.5. Lime addition in the upstream lime boil circuit will provide sufficient protective alkalinity for the leach circuit and no additional lime addition will be required during leaching. Estimated extraction in the concentrate leach circuit is 93.5% for gold and 86.0% for silver.

 

Air will be introduced into the leach circuit through the leach tank agitator shafts to maintain an air to leach rate of approximately 7.75 Nm3 oxygen per ton of solids in the circuit. The concentrate leach circuit will be designed for a total retention time of 24 hours, evenly distributed across the six leach tanks. Slurry exiting the leach circuit will flow by gravity to the CCD circuit for recovery of pregnant solution from the leached slurry.

 

To facilitate maintenance of individual leach tanks, the circuit will include provisions to bypass any single leach tank, allowing slurry to report directly to the downstream leach tank. This configuration will allow one tank to be taken out of service without requiring a shutdown of the entire circuit.

 

The leach circuit will be serviced by a vertical cantilevered centrifugal sump pump, which will return collected spillage to a nearby leach tank.

 

14.4.7 CCD Circuit

 

A four-stage CCD washing circuit will be used to recover pregnant solution from the cyanide-leached slurry.

 

Leached slurry will flow by gravity through a four-stage CCD circuit, with solids advancing sequentially to the final thickener (CCD No. 4). Washed tailings from CCD No. 4 underflow will be pumped to the cyanide destruction circuit. Barren solution from the Merrill-Crowe circuit will be added to CCD No. 4 as wash water, while overflow solution will advance counter currently through the CCD stages. Overflow from the first CCD thickener will be collected in a CCD overflow tank and fed to the Merrill-Crowe circuit.

 

Hycroft Mine Project

Page 185

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The washing ratio, defined as the flow rate of washing barren solution from the Merrill-Crowe plant to the solids flow rate in the CCD circuit feed, will be 4.5:1, providing an overall CCD washing efficiency of greater than 98%.

 

Solids settling will be enhanced by the addition of diluted flocculant at each CCD stage. Antiscalant can be added to the pregnant solution tank, as required, to inhibit scale formation in the Merrill-Crowe circuit.

 

A vertically cantilevered centrifugal sump pump will be provided in the CCD area to return spillage to the circuit.

 

14.4.8 Merrill-Crowe Precipitation and Refinery (Existing)

 

Due to the high silver content in the pregnant leach solution (PLS), gold and silver will be recovered using zinc cementation. Hycroft currently has two Merrill-Crowe plants. The Brimstone plant has a capacity of 5,000 gal/min, while the North plant is considerably larger, with a capacity of 21,000 gal/min. The combined capacity of the two Merrill-Crowe facilities is approximately 26,000 gal/min.

 

Upon mill start up, the Merrill-Crowe plants will process pregnant solutions from both the mill and the heap leach operations.

 

14.4.8.1 Merrill-Crowe

 

PLS from the CCD circuit will be pumped to the PLS tank at the Merrill-Crowe facilities, where it will be combined with solution from the heap leach operation. The combined solution will then be pumped to clarifying filters to remove suspended solids. Filtered PLS will flow through a deaeration column, where dissolved oxygen will be removed. Zinc will then be added to the filtered, deaerated solution, which will be pumped to precipitate filters. The resulting precipitate, containing gold and silver, will be recovered in the filter. Barren solution will flow to a storage tank for reuse in the mill or heap leach.

 

Precious metal recovery from solution to zinc precipitate is expected to be approximately 99.5%.

 

14.4.8.2 Gold and Silver Refinery

 

Wet filter cake from the Merrill-Crowe circuit will be transferred to retort pans and proceeded in a retort furnace to remove moisture and mercury. Water and mercury will be sequentially volatilized from the precipitate by heating under partial vacuum. Exhaust gases will pass through multiple stages of condensers, where mercury and water will be collected and drained into a collection vessel. Residual mercury in the retort off-gas will be removed using a sulfur-impregnated carbon packed bed prior to discharge to the atmosphere. Retorts will be operated in batch mode, with an approximate cycle time of 18 hours.

 

Hycroft Mine Project

Page 186

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The dried filter cake will then be mixed with flux and transferred to an electric arc furnace, where it will be smelted to produce gold-silver doré.

 

14.4.9 Cyanide Destruction

 

Washed leach residue slurry from the CCD circuit will be treated using a sulfur dioxide (SO2)-oxygen (O2) process to reduce the CNWAD cyanide concentration to less than 5 mg/L.

 

Thickened, washed tailings slurry from the final CCD thickener, at a solids concentration of approximately 35%, will be pumped to the cyanide destruction tanks. In the SO2-O2 process, sodium metabisulphite (SMBS), oxygen, copper sulfate (as catalyst), and milk of lime will be added to oxidize residual free cyanide and CNWAD species to cyanate, thereby reducing CNWAD concentrations to the target level prior to final tailings disposal. The cyanide destruction circuit will consist of two mechanically agitated tanks, providing a total residence time of two hours.

 

Oxygen will be supplied from the oxygen plant as required and introduced into the tanks via the agitator shafts. CNWAD concentration in the cyanide destruction discharge will be monitored through regular sampling and analysis.

 

The cyanide destruction circuit will be serviced by a dedicated sump pump, with any spillage in the area returned to the cyanide destruction feed box

 

14.4.10 Final Tailings and Reclaim Water Transport

 

Combined thickened tailings generated from the flotation process, POX neutralization, and cyanide destruction circuits will be conveyed from the tailings thickener to the TMF, following completion of TMF construction. A return water pipeline will convey reclaim water from the TMF seepage ponds back to the process plant along the same corridor.

 

14.5 Energy, Water, and Process Materials Requirements

 

14.5.1 Reagent Handling and Storage

 

The mixing and storage area for each reagent will be located proximate to their respective addition points throughout the plant. Reagents delivered in bulk bags will be transferred from storage to the mixing areas by forklift. Electric hoists serving the reagent areas will lift the bulk bags to the respective reagent bag brakers, which will be located above the reagent mixing tanks.

 

The reagent handling system will include unloading and storage facilities, mixing tanks, stock tanks, transfer pumps, and feeding equipment.

 

Quick lime will be delivered to the plant in regular bulk shipments and received in three 400 t storage silos, which at design operating rates will provide approximately three days of storage capacity. Lime will be slaked in a package slaking system. The resulting milk of lime slurry, at approximately 16% CaO solids %w/v, will be stored in an agitated tank and distributed to the various addition points via a ring-main system.

 

Hycroft Mine Project

Page 187

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Sodium cyanide will be supplied in liquid form by using DOT-412 tankers, each carrying approximately 6,400 gal of 30% cyanide solution, and will be received in a 25,000-gal storage tank. Diluted cyanide solution at approximately 23% cyanide will be stored in an agitated day tank, providing approximately four hours of cyanide supply at nominal production rates. From the day tank, sodium cyanide solution will be distributed to the leach circuits and Merrill-Crowe circuit as required. The cyanide storage and day tank will be fully contained in a bunded area and physically separated from the main plant site.

 

Limestone will be delivered to the site by rail and offloaded to a stockpile. A front-end loader will transfer limestone to a hopper feeding the limestone crushing and grinding circuits. Ground limestone slurry, at 38% solids, will be stored in a limestone slurry tank providing 12 hours of retention time.

 

Table 14-3 summarizes the reagents proposed for the process plant.

 

Table 14-3: Summary of Reagent Used in the Process Plant

 

Reagent Preparation Method Use
Lime Received as quicklime from 20 t pneumatic tanker trucks and transferred to silos; slaked and mixed to 16% strength; pumped to a storage tank and distributed to lime boil, POX neutralization, and cyanide destruction circuits as required pH control added as required
Sodium Cyanide Received as 30% cyanide solution in 6,400 gal of DOT 412 tanker trucks and transferred to a 25,000-gal storage tank; diluted to 23% NaCN in a day tank; dosed via metering pumps to the concentrate cyanide leaching circuit and Merrill-Crowe circuit as required. Gold and silver leaching agent
Flocculant Received as powder in 1,000 kg bags; mixed to 0.25% storing strength; transferred to a storage tank. Dosed directly to concentrate thickener, POX CCD washing thickeners, neutralization thickener, CCD washing thickeners, and tailings thickener with dilution as required Flocculation in thickeners
Oxygen Produced on site by the oxygen plant, gasified, and distributed to POX and cyanide destruction circuits Oxidation reagent, cyanide destruction reagent
PAX Received as pellets in 1,000 kg super sacks; mixed to 15% solution strength and transferred to a storage tank; dosed via multiple metering pumps to the required locations within the grinding and flotation circuit Flotation collector
Frother Delivered in liquid form by tanker truck and transferred to a 25,000-gal storage tank; dosed via multiple metering pumps to the required locations within the flotation circuit Flotation frother
Diatomaceous Earth Received as powder in 25 kg bags; mixed to about 5% solution strength; dosed to the clarifier and precipitate filters in Merrill-Crowe circuit Precoat and body feed in Merrill-Crowe circuit
Zinc Powder Received as powder in 50 lb bags; dosed via feeder to Zn mixing cone through at controlled rate in Merrill-Crowe circuit Precipitation regent in Merrill Crowe circuit
Copper Sulfate Received as powder in 500 kg bags; mixed to 10% solution strength and transferred to a storage tank; dosed to the cyanide destruction circuit Catalyst for cyanide destruction process
Sodium Metabisulfite Received as powder in 1,250 kg super sacks; mixed to 15% solution strength and transferred to a storage tank; dosed to the cyanide destruction circuit. Reactant for cyanide destruction process
Antiscalant Delivered in liquid form in IBC totes; dosed neat (undiluted) to barren solution and process water tanks Scale inhibition
Flux Received as bulk powder; blended with calcined charges prior to smelting Smelting flux
Limestone Delivered to the site by rail and offloaded to a stockpile Neutralization reagent for acid generated in POX circuit

 

Hycroft Mine Project

Page 188

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The estimated annual consumption based on nominal usage for major plant reagents is summarized in Table 14-4.

 

Table 14-4: Annual Consumption for Major Reagents

 

Reagent Annual Consumption (ton/a)
Quicklime 102,943
Sodium cyanide 9,567
Flocculant 2,757
Collector (PAX) 8,508
Frother (MIBC) 756
Sulfuric acid 69
Limestone 813,085
Copper Sulfate 304
Sodium Metabisulphite (SMBS) 3,452
Antiscalant 321
Diatomaceous Earth 1,267
Zinc dust 574

 

14.5.2 Fresh Water, Fire Water and Potable Water

 

Provisions will be made for fresh water supply from the water wells with fresh water transferred to a fresh/fire water storage tank.

 

Fresh water will be used for reagent mixing and preparation, general process uses in the crushing area, and gland water.

 

Wherever practicable, process water or barren solution will be used throughout the plant to minimize freshwater consumption. The total freshwater requirement for the plant is estimated at approximately 6,680 gal/min.

 

Hycroft plans to install a larger onsite potable water system sized to meet the requirements of the POX option, for the current IA-EA study, a potable water treatment system is not required.

 

14.5.3 Process Water, and Barren Solution

 

Process water will consist of reclaimed water from the concentrate thickener overflow, rougher tailings thickener overflow, TMF return water, and excess process water from the solution cooling towers. Process water will be used in the grinding and flotation circuits and in the limestone slurry preparation circuit.

 

POX Process water will consist of a solution from the solution cooling towers with freshwater make-up as required. POX process water will be used for POX flash vessel cooling and POX CCD washing.

 

Hycroft Mine Project

Page 189

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Barren solution from the Merrill-Crowe circuit will be stored in the existing barren solution tank and recycled to the CCD washing circuit as wash water. Barren solution will also be used as gland seal water for CCD thickener underflow pumps to minimize freshwater consumption. Excess barren solution will be routed to the heap leach operation.

 

14.5.4 Oxygen Plant

 

The oxygen plant will consist of an air separation unit (ASU) supplying gaseous oxygen and trickle liquid oxygen to support the pressure oxidation process. The ASU design is based on equipment and processes that are widely used in the cryogenic gas industry, employing a conventional air separation process. Oxygen production will be achieved through the cryogenic distillation of air.

 

The oxygen plant will have a nominal oxygen production capacity of approximately 2,204 ton/d, with an installed power requirement of approximately 32 MW. Oxygen will be produced at a purity of 99.5% and delivered at a pressure of approximately 116 psig (8 bar).

 

Oxygen will be used for POX circuit and cyanide destruction circuit.

 

14.5.5 Electrical Power

 

The total peak operating load for the project is estimated to be 124.3 MW.

 

14.5.6 High-Pressure and Low-Pressure Air

 

14.5.6.1 High Pressure Air

 

High-pressure air at 110 psi(g) will be supplied by high-pressure air compressors operating in a lead-lag configuration to serve the neutralization tanks and leach tanks. All high-pressure air produced will be dried and filtered and will be used to meet both plant air and instrument air requirements. Dried air will be distributed via the process plant air receiver.

 

14.5.6.2 Low Pressure Air for Flotation Circuit

 

Low pressure air for the flotation cells will be supplied by four dedicated blowers.

 

Hycroft Mine Project

Page 190

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15 Infrastructure

 

15.1 Introduction

 

This section discusses existing and proposed infrastructure for the Hycroft PEA. The proposed facilities include the Northeast TMF, the Waste Rock Storage Facility (WRSF), the Process Plant Site and associated infrastructure, the Limestone Plant, and new rail spur. This section also details the proposed ancillary facilities planned over the LOM, and the proposed upgrades of existing facilities. An overview of existing site infrastructure, site access, accommodations, and utilities is provided in this section. The layout of proposed and existing infrastructure is shown below in Figure 15-1.

 

Figure 15-1: Site Layout

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 191

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15.2 Site Access

 

15.2.1 Offsite Access and Security

 

Jungo Road (Nevada State Route 49) which connects the town of Winnemucca to Gerlach, is the main offsite access road to Hycroft Mine. This roadway is an all-weather dirt/gravel surfaced road that is well maintained by Humboldt County, Pershing County, and Hycroft. Jungo Road runs parallel to the site at the north and west extents and is accessible off the I-80E. The main gate to the Site is located within a few hundred feet from the Jungo Roadway. Figure 15-2, below, detail major nearby towns and Jungo Road in relation to the Hycroft Mine Site.

 

Figure 15-2: Site Access and Major Towns Near Hycroft Mine

 

 

Source: Google Earth, 2026

 

Hycroft Mine Project

Page 192

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

A major east-west bound railway runs adjacent to the mine site. Imports and exports via this railway shall be facilitated by the proposed rail spur discussed in Section 15.2.3 Rail Spur.

 

The main access guard house will be relocated as part of the layout improvement of the ancillary facilities. Primary access to the site will be regulated by swipe cards. The guard house will continue to house the security personnel offices, safety training rooms and medical facilities.

 

15.2.2 Onsite Access

 

Most of the existing onsite access and haul roads will remain. The project considers the development of plant access roads, a TMF access road, and a TMF construction haul road. The geometric design of the roads considers factors such as traffic, topography, and speed to provide a safe design that is cost effective compatible with project commitments.

 

Road drainage has been designed to eliminate or minimize road wear, road damage, downstream flooding, and erosion. Roads will be graded to convey stormwater away from the roads and plant facilities. Road drainage structures include parallel ditches and culverts for crossings.

 

15.2.2.1 Plant Access Roads

 

Approximately 0.6 miles of new plant access roads will be built branching out of existing roads and connecting different areas of the plant. Plant access roads are designed to be dirt roads with a maximum grade of 10% and a speed limit of 25 miles per hour (mph). Road will have a minimum of two 12-foot lanes and allow delivery access.

 

15.2.2.2 TMF Access Road

 

A new access road approximately 5.6 miles long will connect the process plant with the TMF running parallel to the tailings delivery and reclaim water pipeline corridor. This dirt road runs through one section of mountainous terrain and will have a maximum grade of 10% and a speed limit of 25 mph. The access road will have two 12-foot lanes.

 

15.2.2.3 TMF Construction Haul Road

 

A new TMF construction haul road approximately 3.4 miles long will connect the WRSF with the TMF. This road will allow haulage of waste rock for the TMF embankment construction. This haul road will cross the TMF access road instead of running parallel to it. The road runs through one section of mountainous terrain. This dirt haul road will have a maximum grade of 10% and a speed limit of 25 mph. The haul road will have two 60-foot lanes.

 

15.2.3 Rail Spur

 

The Hycroft Project will require a rail spur to extend access of the Union Pacific rail line located northwest of the plant to the Project site. The additional rail siding is designed to receive reagents and consumables such as limestone, grinding media, fuel and other supplies required by the proposed process plant. The rail siding is vital for the export of salable precious metals.

 

Hycroft Mine Project

Page 193

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Hycroft hired Mountain States Contracting Inc. to provide the design and cost estimate for this rail spur. Included in the design and cost estimate is the rail siding, required turnouts, derails, signals, tracks, ballast, bridges, and civil work to install and operate a rail loadout facility. The facility will have tracks to store rail cars as well as a loadout out port for rail hopper cars. The rail spur design layout proposed by Mountain States Contracting Inc is shown below in Figure 15-3.

 

Figure 15-3: Rail Spur Design

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 194

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15.3 New Infrastructure

 

This section details all required on, and off-site support infrastructure required for the operation of the sulfide ore processing plant. New onsite infrastructure includes new process plant facilities and its supporting tie-ins for its inclusion to the existing crushing facility, heap leach, and North Merrill-Crowe facility; most of the existing onsite access and haul roads will remain. Hycroft has identified the following offsite infrastructure for inclusion in this study: a main transmission line feeding the site and substation, mine power distribution, the rail spur for deliveries and shipping and the development of a freshwater production well field.

Onsite infrastructure to support the proposed process plant includes:

tie-ins to existing site utilities
water
compressed air
sewer and potable water
new power distribution lines and grids, substations and electrical rooms
new process control system and control room
new reagent buildings including an oxygen plant and limestone offloading, storage and slaking facilities
expanding, repurposing or modifying existing offices, maintenance areas, laboratories, and ancillary facilities throughout the mine.

 

15.3.1 New and Existing Facilities Layout

 

Ausenco designed the processing plant facility to tie into the existing crushing facility, which includes the primary crusher, secondary crushers and tertiary crushers. The overall site layout is shown in Figure 15-4. Figure 15-5 illustrates the existing crushing facility and ancillary buildings at the mine site while Figure 15-6 shows the proposed process plant layout developed for this Project. The proposed limestone offloading and rail spur planned for the Project is shown in Figure 15-7. Figure 15-8 shows the North Merrill-Crowe Facility and associated ponds. The TMF is detailed in Figure 15.10 and the WRSF locations are depicted in Figure 15-14.

 

Existing facilities on site consist of two administration buildings, a mobile maintenance shop, a light vehicle maintenance shop, a warehouse, an assay laboratory, three heap leach pads (Crofoot, North, Brimstone), primary, secondary, and tertiary crushers, two Merrill-Crowe Process Plants, a refinery, and other service-related structures. Table 15-1, below, details the existing Hycroft buildings based on owner-provided information. Many of the existing ancillary buildings are shown in Figure 15-5 through Figure 15-9.

 

Hycroft Mine Project

Page 195

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 15-1: Existing Hycroft Buildings

 

Hycroft Equipment Reference Ausenco WSP Area Description
BG 001 7000 Jungo Road
BG 900 6600 Administration Building
BG 902 6600 Old Core Building
BG 903 6700 Light Vehicle Fuel Island
BG 904 6600 Laboratory Building
BG 905 4100 Lime Silo
BG 906 6600 Safety Building
BG 907 4100 Mill Building
BG 908 6600 Welding Shop
BG 910 6600 Shifter Building
BG 911 4100 Operations Lineout Building
BG 912 6600 Warehouse Building
BG 913 6600 Wash Pad
BG 914 6600 New Maintenance Shop
BG 915 7200 Fire Water Pump House #1 – Old Shop
BG 916 7200 Fire Water Pump House #2 – New Shop
BG 917 6600 Light Vehicle / Tire Shop
BG 919 6500 Flocka Communications Building
BG 920 6500 Pump Room Communications Building
BG 921 6600 Direct Charge Building
BG 922 6700 Upper Fuel Island
BG 923 6600 Fabrication Shop
BG 924 6600 Process Maintenance Trailer
BG 926 6600 Human Resource Building
BG 928 6600 Technical Services Building
BG 929 6600 Geology Trailer
BG 930 6600 Front Gate Guard Shack
BG 932 4400 North Merrill-Crowe Building / Rest Rooms
BG 933 6500 Lower Server Room
BG 934 4400 Press Room North Merrill-Crowe
BG 935 6400 Electrical Dry Storage
BG 936 6600 Mechanical Dry Storage
BG 937 6700 Lower Fuel Island

 

Hycroft Mine Project

Page 196

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-4: Overall Site Layout

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 197

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The five boxes shown in Figure 15-4 are expanded in the figures below.

 

Figure 15-5: Existing Crushing Facility and Surrounding Infrastructure

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 198

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-6: The Proposed Process Plant Generic Site Plan

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 199

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-7: Proposed Limestone Plant and Rail Spur

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 200

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-8: North Merrill-Crowe Plant

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 201

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-9: Existing Mine Ancillary Buildings

 

 

Source: Ausenco, 2022

 

Hycroft Mine Project

Page 202

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Newly proposed ancillary facilities that have been designed and budgeted to support the Project are shown below in Table 15-2.

 

Table 15-2: New Ancillary Facilities Planned over the LOM

 

Facility Name Purpose
Crushed Ore Stockpile Cover Round dome to 313 ft Diameter X 104 ft Height
Laboratory New Assay Lab
Haul Truck Fuel Station New Fuel Station to service the mine equipment
Technical Services Building An additional building to support the new process plant
Maintenance Shop New maintenance shop for capital and consumable spare parts
Crusher Maintenance Building New crusher maintenance building in mine Year 5.

 

15.3.2 Upgrades to Existing Facilities

 

Table 15-3 list the proposed upgrades to the existing facilities at the mine required to support the Project.

 

Table 15-3: Proposed Upgrades for Existing Facilities

 

Existing Building Name Proposed Upgrades
Lime Silo The existing lime silo will be relocated closer to primary crusher
Warehouse The existing warehouse will be expanded and will include a larger storage yard in mine Year 3
Gate And Security Building The existing front gate/guard shack will be relocated to improve traffic flow
Truck Shop Add an additional wash bay to the existing Truck Shop
Primary Crusher Building Upgrade the existing primary crusher building
Crusher Control Room Upgrade the existing crusher control room
Mine Operation Building Repurpose the existing Mine Ops building to meet mine staffing needs and space.
Operation Lineout Building The existing Operation Lineout building will be converted to a 4-plex in mine Year 5
Process Maintenance Expand existing process maintenance for new equipment assembly in mine Year 1
North Merrill-Crowe Expand North Merrill-Crowe building for increased process operations and administration by mine Year 2
Technical Services Building Rehabilitate the existing technical services building

 

15.3.3 Accommodation

 

Hycroft Mine is located within a well-known mining jurisdiction near three communities: Winnemucca (Humboldt Country), Lovelock (Pershing County), and Gerlach (Washoe County). The majority of the mine’s employees reside in Winnemucca and Lovelock, with a small number from Gerlach. These towns are shown above in map-form in Figure 15-2.

 

Hycroft Mine Project

Page 203

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Most of Hycroft’s site employees are likely to reside in the town of Winnemucca (Humboldt Country), located 54 miles east of the mine. This town is accessible via a transcontinental railroad and a small public airport. A high clearance truck or SUV is recommended for the 90-minute commute from Winnemucca to site.

 

Winnemucca has the required infrastructure (short- and long-term rooming and boarding facilities, dining establishments, shopping, emergency services, schools, etc.) to support the maximum workforce and dependents required for the Project. As such, the construction labor force will be housed in Winnemucca and transported 54 miles via a contracted bus service to the job site.

 

15.4 Stockpiles

 

15.4.1 Mineralized Stockpiles

 

The mine plan and processing schedule includes long term stockpiling of mineralized material. These stockpiles consist of the coarse ore stockpile and the crushed ore stockpile based at the proposed process plant. The coarse ore stockpile has a live capacity of 56,000 tons and a total capacity of 175,400 tons while the crushed ore stockpile has a live capacity of 34,000 tons and a total capacity of 113,000 tons, with a round dome cover for the elements.

 

These stockpiles will support the existing crushing circuit availability of 31.3% for primary crushing and 65.1% combined for secondary and tertiary crushing. These stockpiles will allow buffer material flow between the crushers and mill.

 

15.4.2 Growth Media Stockpile

 

During construction of the TMF, growth medium will be stripped and stockpiled for future placement on the TMF surface and exposed embankment surfaces during reclamation.

 

15.4.3 Limestone Stockpile

 

Limestone will be delivered to the site by rail and offloaded to a stockpile.

 

15.5 Tailings Management Facilities

 

The primary design objectives of the Hycroft Northeast TMF are the secure containment of tailings and the protection of regional groundwater and surface water during mine operations and post-closure. The design of the TMF and accompanying water management facilities has considered the following:

 

Staged development of the facility over the LOM.
   
Impoundment geomembrane liner and overliner collection system to minimize potential seepage into the subgrade and groundwater
   
Control, collection, and removal of water from the facility for reuse as process water to the maximum extent practical.
   
Closure that takes into account long-term geochemical and physical stability to protect the environment and waterways using best available technology based on the physical and geochemical characteristics of the tailings

 

Hycroft Mine Project

Page 204

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The TMF has been designed to accommodate over 1.05 Btons of tailings produced over the LOM. The combined tailings embankment and impoundment occupy an ultimate footprint of approximately 4,915 acres. WSP has provided civil, geotechnical, and mechanical engineering services for the Hycroft mine since 2010. The 2026 PEA TMF design and drawings utilizing information from previous TMF studies completed for the Hycroft Mine.

 

The Northeast TMF PEA design incorporates data from several previous technical studies to meet the industry standards for design of TMF in accordance with GISTM 2020 Standards. The TMF embankment will be expanded during operations using centerline method of construction for the main embankment and downstream construction for the north embankment. The design criteria for the tailings facility are based on the information available during the development of the previous studies and this PEA along with applicable design standards.

 

15.5.1 Facility Design Basis

 

The TMF design basis was developed considering the mine Schedule, processing technology, and most importantly designing a safety and stable TMF that protect the environment. Below is the design basis utilized in the development of the TMF.

 

The general operational TMF parameters are:

 

average production rate of 57,000 tpd
   
LOM of 51 years
   
required storage capacity of 1.05 Btons
   
tailings discharge percent solids content of 48%
   
subaerial deposition
   
average tailings in-situ dry density ranging from 74 pounds per cubic foot (pcf) (starter facility) to 92 pcf (ultimate facility).

 

The design of the Hycroft Northeast TMF was developed based on the following major guidelines, regulations, client and site requirements, and industry best practices.

 

Nevada Administrative Code (NAC) Division 445A – Water Controls
   
NAC 525 – Dam Safety
   
Mining Association of Canada (MAC), A Guide to the Management of Tailings Facilities (MAC 2019)
   
International Council of Metals and Mining (ICMM), Global Industry Standard on Tailings Management (GISTM 2020)

 

Hycroft Mine Project

Page 205

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The facility design drawings meet the following objectives:

 

Solution containment compatible with “zero-discharge” design concepts using a geomembrane liner, and meeting or exceeding Nevada Administrative Code (NAC) regulations.
   
Safe, statically and seismically stable, and operationally feasible facilities.
   
Containment using waste rock material as a embankment fill.
   
“Design for Closure” philosophy to manage closure considerations during the construction and operation of the facilities.

 

Based on a conceptual qualitative dam breach analysis, the Northeast TMF is considered a Very High consequence dam. Based on this classification, design criteria for geotechnical stability and for minimum return periods for design earthquake and flood events are presented in Table 15-4 and Table 15-5. A figure of the ultimate TMF facility relative to the Hycroft Site is shown Figure 15-10.

 

Table 15-4: Minimum Pre-feasibility Seismic Design Criteria for Stability for Very High Dam Classification

 

Lifecycle Loading Condition Minimum Factor of Safety Design Event
Operation/Long Term Static 1.5 Steady state seepage, normal reservoir level
Seismic loading (pseudo-static) 1.1 1 in 5,000–year, normal reservoir level
Closure – Passive Care Static 1.5 Steady state seepage, normal reservoir level
Long-term Post Closure Static 1.5 Steady state seepage, normal reservoir level
Seismic loading (pseudo-static) 1.1 1 in 10,000-year, lowered reservoir level

 

Table 15-5: Minimum Pre-feasibility Hydrologic Design Criteria for Very High Dam Classification

 

Lifecycle Flood Event
Operation/Long Term 1 in 5,000-year contained within TMF
Closure – Passive Care 1 in 10,000-year conveyed by closure down chute

 

Hycroft Mine Project

Page 206

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-10: TMF Facility Layout

 

 

Source: WSP, 2026

 

Hycroft Mine Project

Page 207

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15.5.2 TMF Design

 

15.5.2.1 Embankment Construction

 

The Northeast TMF will be constructed using ROM waste rock generated from open pit mining operations. waste rock will be transported by mine haul trucks to a designated staging area northwest of the main embankment. During construction, waste rock will be transported by the contractor from the staging area to the embankment location(s) and placed as engineered fill in thin controlled and compacted lifts. The ultimate embankment will have a maximum height of 335 ft from crest to downstream toe and a crest width of 75 ft. Downstream slope angles for all stages of construction will be a minimum of 2.5H:1V. Two general types of embankment construction methods will be utilized including:

 

Main Embankment Dam: Centerline Raise Construction
   
North Embankment Dams: Downstream Raise Construction.

 

The initial starter embankment constructed for Stage 1 will have a maximum height of 92 ft from crest to the downstream toe. Based on the milling schedule presented in Table 13-1, Stage 1 is designed to store approximately 15.25 Mt over an eight-month period at a tailings production rate of 57,000 tons per day and a dry density of 74 pcf. After completion of the starter embankment, the embankment crest will be raised in stages utilizing a combination of downstream and centerline construction methods as presented on Figure 15-11 and Figure 15-12.

 

Figure 15-11: TMF Main Dam Section

 

 

Source: WSP, 2026

 

Hycroft Mine Project

Page 208

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15- 12: TMF North Dam Section

 

 

Source: WSP, 2026

 

Centerline Raise Construction method will be used for subsequent raises of the main embankment. The second stage of development will store three years of tailings, while subsequent stages will each accommodate between five and eight years of additional tailings storage.

 

A chimney drain will be installed along the dam centerline to control seepage through the dam and maintain a drained downstream zone for stability. Geomembrane liner will be installed in the impoundment and along the dam foundation beneath the embankment terminating at the containment berm downstream of the chimney drain.

 

Downstream Raise Construction method will be used for the ridge and saddle dams of the north embankment. downstream construction and will be accomplished by extending a new embankment against the existing downstream slope of the previous stage and then raising the embankment to the new crest elevation for each stage. The upstream face of the North Embankment will be lined with geomembrane for all raises of the embankment. A chimney drain will not be installed, since the upstream face of the embankment is lined with geomembrane.

 

15.5.2.2 Containment and Underdrain System

 

In general, the TMF impoundment area is gently sloping to the northwest and well-suited for a geomembrane liner system. Basin grading will consist of clearing and grubbing native vegetation, removing and stockpiling growth medium material for use during reclamation, and smoothing surface irregularities to promote gravity drainage to the reclaim pond.

 

An 80-mil HDPE geomembrane liner will be installed to cover the entire basin on top of a prepared bedding layer and will extend beneath the main embankment to the containment berm below the chimney drain.

 

Hycroft Mine Project

Page 209

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

An underdrain piping system will be placed above the basin geomembrane liner and will collect tailings seepage within the basin and convey the tailings water by gravity through the embankment to the Underdrain Collection Pond located at the downstream toe of the main embankment. The underdrain system will consist of a network of regularly spaced perforated dual-wall pipes bedded in drainage gravel. Below the containment berm the underdrain pipe will transition into a solid wall non-perforated pipe to Underdrain Collection Pond. Alluvial material will then be placed to cover the liner and underdrain system prior to tailings deposition to act as a filter to prevent migration of tailings into the drainage gravel.

 

15.5.2.3 Foundation Settlement

 

The embankments that form the TMF will be constructed primarily on dense to very dense alluvium overlying weathered bedrock which is expected to be relatively incompressible. The alluvium that blankets the TMF site extends to a depth of up to 43 ft bgs. Based on these foundation materials, settlements from the ultimate dam configuration are not expected to pose a risk to the TMF embankment’s structural integrity. Piping systems can readily be updated during future design stages to accommodate any anticipated differential settlements.

 

15.5.2.4 Geotechnical Stability

 

To comply with GISTM (2020) and NAC (2014) standards, the PEA design of TMF shown in Figure 15-10 meets or exceeds the following minimum design requirements:

 

Minimum design static (steady-state seepage) factor of safety (FOS) of 1.50.
   
Minimum design pseudo-static factor of safety of 1.10
   
Seismic design criteria based on the GISTM 2020 failure consequence classification of Very High are:

 

  the design earthquake during operations is the 1 in 5,000-year return event. The peak ground acceleration for this event is estimated to be 0.273 g.
     
  the design earthquake post closure is the 1 in 10,000-year return event. The PGA for this event is estimated to be 0.398 g.

 

A two-dimensional (2-D) limit-equilibrium (LEM) stability modeling was used to evaluate the stability of the dam in operational and closure conditions under both static and earthquake loads. While liquefaction potential of the tailings and foundation materials is a possibility, the post-earth earthquake liquefied condition was not evaluated for PEA design. Effects of liquefaction on TMF performance and stability are credible risks and must be addressed in future phases of design.

 

A pseudo-static analysis is a type of LEM analysis was used as a screening tool to assess the stability of a slope under loading from the design earthquake. In this analysis, stability models were used to determine the Factor of Safety (FOS) of the slope when subjected to seismic loading from the design earthquake event. To comply with GISTM (2020) for a Very High consequence classification dam, the seismic design events were selected according to Table 15-6.

 

Hycroft Mine Project

Page 210

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 15- 6: Selected Ground Motions and Associated Seismic Coefficients

 

Pseudo-static Model Probabilistic SHA Results

Probability of Exceedance

(Return period)

Mean Peak Ground Acceleration (PGA), g Seismic Coefficient, k (G)
Operations (Active Care) 1% in 50 years (4,975 year) 0.273 0.182
Closure (Passive Care) 0.5% in 50 years (9,975 year) 0.398 0.265

 

All the calculated FOS were found to be above the minimum criterion which the prefeasibility dam, as designed, is deemed to be stable with respect to geotechnical, geometric, and seismic loading conditions evaluated. These analyses are preliminary, and the level of both field and laboratory geotechnical characterization used to support these analyses were completed at a prefeasibility level.

 

15.5.2.5 TMF Surface Water Management

 

TMF Surface Water management is addressed in Section 15.10.2.2.

 

15.5.2.6 Monitoring

 

To support construction-level design and permitting, a detailed geotechnical monitoring plan will be prepared that defines the roles and responsibilities of key stakeholders (Owner, operator, engineer) for safe and stable TMF construction and operation. Monitoring will be accomplished through both measurements of monitoring points (e.g., survey monuments, piezometers readings), and visual observations of surface conditions.

 

15.5.2.7 Closure

 

The TMF conceptual closure and reclamation plan is shown on Figure 15-13. The general closure design strategy includes construction of a durable cover system that can generally remain in passive care for the main cover system with active care required for maintenance of surface water channels and as needed for monitoring. Growth medium stripped during TMF construction should be stockpiled for future placement on the TMF surface and exposed embankment surfaces during reclamation.

 

The downstream embankments that form the TMF have been designed with 2.5H to 1V downstream slopes that are sufficiently flat for effective revegetation. The tailings surface will be covered with a layer of rockfill overlain by stockpiled growth medium and revegetated. Capping of the tailings will start at the end of deposition of Stage 8 on areas where the tailings have reached final elevation. Capping material is expected to be sourced from onsite locations. Cover infiltration modeling has not been performed for this PEA to support estimation of closure cover thickness required on the tailings surface. For this Prefeasibility Study, Golder selected a three-foot-thick composite soil cover system above the final tailings surface (2 ft of waste rock and one foot of growth medium) and a one-foot-thick growth medium layer above the downstream embankment slopes. The closure cover will be graded with drainage swales to convey surface runoff to the closure spillway to the south of the main embankment. Surface water will be conveyed and discharged into the natural drainage north of the Underdrain and Event Ponds.

 

Hycroft Mine Project

Page 211

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The closure systems will be designed to have the same characteristics as the pre-development natural drainage systems. The closure spillway will be designed to convey the inflow resulting from the 10,000-year, 24-hour storm, assuming the permanent diversion channel overtops onto the TMF closure surface. Maintenance may be required to provide repair for any damage created by larger or more intense storms.

 

Figure 15-13: TMF Closure Plan

 

 

Source: WSP, 2026

 

15.6 Waste Rock Storage Facility

 

The Hycroft project will feature a WRSF, to store all non-mineralized materials from the pits. Initially, there will be two facilities, one to the west and one to the south. By the end of Mine Year 10, the two facilities will begin to merge into one single facility that is on the southwest perimeter of the developing pit.

 

Hycroft Mine Project

Page 212

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-14 Waste Rock Storage Facilities

 

 

Source: IMC, 2026

 

Slope stability analyses, material properties, and stacking geometry were the basis for foundation and dump formation design conditions. The dump will generally have inter-bench slope angle of 1.5H:1V with 50 ft high and 60 ft wide benches with some localized exceptions. The configuration of each bench has been developed assuming that the waste rock will be stacked with an overall slope of 3H: 1V. The dump will be built over a previously disturbed area.

 

Water management for the WRSF consists of two systems: upstream diversion channels for non-contact water (water flow from natural slopes) and a seepage collection system within the stockpile for contact water. These systems are further described in Section 15.10.3.

 

The physical stability of the WRSF will be monitored using geotechnical instrumentation installed in the facilities. The proposed instrumentation includes survey markers, vibrating wire piezometers, hydraulic piezometers and inclinometers.

 

Once areas of the mine are complete, in-pit backfill may also be utilized for waste storage, if required. During closure, areas close to the Waste Rock facility will be selected for harvesting topsoil and growth media suitable for vegetative growth.

 

15.7 Power and Electrical

 

Power is currently supplied to the site via nearby power lines fed directly from the main power grid, using the grid-side substation. It is assumed that 2 x 120 kV powerlines will be required. The estimated installed load for plant is 160 MW and estimated operating load is 124 MW. Power will have to supply the site via the Nevada Power Imlay Substation and across the existing power line corridor up to Jungo Road and then west along Jungo Road to Site. The proposed power supply configurations can be seen below in Figure 15-15 and Figure 15-16.

 

Hycroft Mine Project

Page 213

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-15: Proposed Power Line from Imlay Relay Station (Nevada Historical Marker 49) to Jungo Road (49 Road) - NTS

 

 

Source: Google Maps, 2026

 

Hycroft Mine Project

Page 214

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-16: Proposed Power Line along Jungo Road (Road 49) to Hycroft Mine Site (in total approximately 57 miles) - NTS

 

 

Source: Google Maps, 2026

 

15.8 Communication

 

The site currently operates with data and telephone communications provided by microwave facilities serviced from two different locations, alongside a 140-foot tower near the administration building, providing cellular communications throughout the site. Voice and data are already distributed throughout the mine via fiber optic cable, and cellular communication is available throughout the Mine site. If necessary, upgrades will be provided based on assessment by the current service provider during the execution phase of the project.

 

15.9 Fuel

 

Diesel fuel prices were provided by Hycroft at $3.76/gal for use in the economic assessment. Contracts for the purchase and delivery of the major consumables, including fuel, are in place and are renewed on an annual or bi-annual basis. Once complete, fuel will be delivered to site via the proposed rail spur, set to extend the existing Union Pacific rail line located north of the plant.

 

Fuel on site is stored within a fuel island. Hycroft plans to replace the existing fuel island with a high efficiency fuel island in Mine Years 3 and 4.

 

15.10 Water Supply and Management

 

The climate data utilized in this study were sourced from Rye Patch Dam climate station (ID 2670192-1) located approximately 32 miles southeast of the mine site. (Golder, 2022). Monthly precipitation and pan evaporation data were obtained from this weather station. Table 15-7 provides a summary of the average monthly climate data.

 

Hycroft Mine Project

Page 215

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 15-7: Weather Station Summary

 

Parameter Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average Annual
Max Average Temperature (°F) 42.8 49.7 57.5 65.6 75 84.2 94.2 92.3 83.3 70.6 54.3 44.5 67.8
Min Average Temperature (°F) 17.7 22.5 26.2 31.2 39.2 46.2 52.3 49.4 41.5 31.8 23.8 18.3 33.3
Mean Precipitation (in) 0.78 0.68 0.72 0.85 0.99 0.75 0.28 0.29 0.38 0.64 0.69 0.72 7.77
Mean Pan Evaporation (in) 0 0 3.71 5.83 7.38 9.23 11.15 10.06 6.95 4.3 0.77 0 59.38

 

 

Table 15-8 presents the precipitation data for 24-hour storm events used in design process. Rainfall depths corresponding to a 100-year frequency were used in the design of both the channels and ponds.

 

Table 15-8: Summary of Storm Event with Associated Rainfall Intensity

 

Return Period 24-hour (inches)
10-Year 1.31
100-Year 2.03
500-Year 2.58
1,000-Year 2.93
5,000-Year 3.27
10,000-Year 3.48

 

Existing water management controls will remain in place for the proposed project. Additional water controls for proposed structures and the overall site water balance are described in the following sections.

 

15.10.1 Fresh Water, Fire Water and Potable Water

 

Hycroft controls 16 distinct water-right permits granted from the Nevada Division of Water Resources (NDWR) in the form of either direct ownership or through leases from other private parties. Water rights on site are controlled by 14 permits in or around the Black Rock Desert Basin. These permits can be referenced in Table 4-1, Section 4. Hycroft currently owns a land position and water rights sufficient to support all planned facilities and process water demands. Freshwater at site is supplied via four water wells; one of which supplies potable water to site.

 

Fresh water is needed on site for reagent mixing and preparation, processing in the crushing area, and as gland water. These water consumption needs will be minimized where possible via the use of process water or barren solution in lieu of fresh water. An estimated 7,260 gal/min is required for the plant.

 

Hycroft Mine Project

Page 216

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The potable water well is located one mile south of the Crofoot Heap. Once taken from these wells, fresh water is to be transferred to a fresh/fire water storage tank. Provisions will be made for the fresh water to be supplied from the water wells. Fresh water will be transferred to a fresh/fire water storage tank.

 

In addition to the existing active and inactive freshwater production wells located at the well field southwest of the mine, an additional four wells shall be installed to deliver freshwater to site. A budget has been included to upgrade the existing freshwater pumps and include off-plot piping for a freshwater pipeline to a new freshwater tank at the process plant. The power supply to the new production wells is planned for the existing power line servicing the existing well field assuming it is sufficient.

 

15.10.2 Tailings Water Management

 

15.10.2.1 Tailing Deposition Management and Return Water

 

Slurry pumps at the tailings thickener will send concentrated tailings to the TMF through a tailings transport (delivery) pipeline at a solids concentration of 48% wt/wt. The tailings transport pipeline will consist of a pipe laid in an HDPE-lined containment channel. A tailings distribution system placed around the perimeter of each stage of TMF expansion will allow deposition in the basin using thin-layer subaerial deposition methods.

 

The distribution system has been designed by Ausenco and will include a 36” diameter distribution manifold and distribution branch pipelines, and valves and spigots. Tailings will be spigoted from the south, west, and east sides of the TMF to create a supernatant pool to the south near the Main Embankment. Focused spigoting from the Main Embankment will control the pool away from the embankment.

 

The return water pipeline from the TMF to the plant has been designed by Ausenco and will consist of a carrier pipeline within an HDPE-lined containment channel. In the first stage(s) of operation, underflow and decant water from the TMF will drain to the Underdrain Collection Pond, where all of the return water will then be pumped to the plant for reuse. In later years, barge mounted pumps will be installed in the TMF and a majority of the return water would be pumped directly to the plant from the supernatant pool. The Underdrain Collection Pond pumps would thereafter be used only for underflow water draining from the underdrain pipe system and embankment chimney drain.

 

15.10.2.2 TMF Surface Water Management

 

During operation, temporary storm water diversion channels will be constructed around the TMF impoundment to convey runoff around the proposed TMF ultimate footprint. Temporary stormwater diversion channels will be constructed at 0.5% grade for each stage of TMF construction. Temporary channels are sized to convey peak flows from the 25-yr, 24-hour storm, while maintaining 6” of freeboard, and convey flows from the 100-year, 24-hour storm with no freeboard. Any precipitation that runs off downslope of the temporary stormwater diversion channels will report to the impoundment area and will subsequently flow into the Underdrain Pond or Event Pond. During closure, all temporary diversion channels will be reclaimed and water will be managed by channels on the surface of the TMF.

 

Hycroft Mine Project

Page 217

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The permanent diversion system will be constructed during Stage 1 and will remain in place during the life of the TMF and into long-term closure. The permanent diversion channel is sized to convey peak flows from the 100-yr, 24-hour storm, while maintaining 6” of freeboard. The permanent diversion channel was design to handle flows from up to the 500-year, 24-hour storm, with no freeboard, to prevent surface runoff from contacting the TMF.

 

The TMF supernatant pool and dam crest were designed to consider 2ft of freeboard above the tailings surface during each stage in operations. However, the main embankment crest elevations consider inflow from storm events assuming the permanent diversion channel fails during extreme storms. During normal operation, the TMF is designed to contain all process fluids, annual precipitation, and storm flows resulting from the 1 in 100-year, 24-hour storm event falling on the impoundment catchment area below the temporary stormwater diversion channels.

 

During operation, the TMF is design to contain runoff from the 5,000-year, 24-hour storm event. During closure, the conceptual reclamation plan consists of a cover system that includes channels on the closed tailings cover surface to manage runoff to the TMF surface and a spillway that will convey runoff from the 10,000-year, 24-hour storm event. During long-term closure, the closure diversion channels will route storm water over the closed TMF tailings surface to the historic supernatant pool location at the southern edge of the impoundment. A closure spillway will be constructed through native ground to discharge surface water to the natural drainage north of the Underdrain and Event Ponds.

 

15.10.3 WRSF Water Management

 

15.10.3.1 WRSF Seepage

 

The proposed seepage collection system for the five dumps is made up of corrugated and perforated double-walled HDPE pipes with a diameter of 300 mm for the main pipes, and 100 mm for the secondary pipes. The seepage collection system was sized for the 100-year, 24-hour duration flood event. The installation of the seepage collection system will be executed during subgrade preparation and before placement of waste rock. The seepage collection system will discharge impacted water to the downstream collection ponds.

 

Collection ponds have storage depths of 15 ft and rectangular polygonal base, with 2H: 1V side slopes, based on stability analysis. These ponds have a freeboard of 5 ft above the maximum storage level, in addition to a 1.60 ft high berm around the upper perimeter. The ponds will be double lined with geosynthetic clay (GCL) and smooth 1.5 mm HDPE geomembrane. Water collected in seepage collected ponds will be trucked back to the process plant for reuse.

 

15.10.3.2 WRSF Surface Water Management

 

Diversion channels have been designed to capture, divert, and minimize the surface runoff infiltration through the base of the waste rock dumps. Diversion channels will discharge into natural drainage points or existing/projected structures. The dimensioning of the hydraulic structures has been carried out based on the maximum flow values estimated for the project’s 100-year, 24-hour flood event. Diversion channels will have a minimum slope of 2% in addition to riprap lining for erosion control. Only the Vortex, West, and Bay dumps will require the construction of diversion channels.

 

Hycroft Mine Project

Page 218

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15.10.4 Plant Site Stormwater Runoff and Drainage

 

The proposed plant site is divided into sub-catchments. Runoff from the sub-catchments will be conveyed away from the work area with perimeter drainage ditches and culverts. Slopes between pads of the process plant will be erosion protected with hydromulch. Ditches and culverts will convey stormwater to a sedimentation pond located to the south of the process plant adjacent to the oxygen plant. Mine affected runoff within the project area will be captured and recycled for us as process water.

 

Plant site ditches, culverts and the stormwater pond were sized based for one in 100-year, 24-hour duration flood event. The pond will have a storage capacity of 9,850 yd3 with 1 vertical to 2.5 horizontal internal side slopes and will be lined with HDPE liner and will serve the secondary purpose of emergency containment for spills from the process plant tanks. The design of the pond includes a spillway for excess stormwater to be released to the environment in the southwest direction away from the plant after sedimentation of particles.

 

15.10.5 Site Water Balance

 

A LOM water balance model was developed using GoldSim© software and considers the full life cycle of the Project. Key mine facilities and water management processes are represented in the model, in addition to modeling surface water runoff. The key objectives of the site water balance were to estimate water effluents of mine facilities and estimate make-up water requirements considering contact water reuse.

 

The site wide water balance schematic is shown in Figure 15-17.

 

Hycroft Mine Project

Page 219

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 15-17: Hycroft Water Balance Schematic

 

 

Source: Ausenco, 2022

 

The water balance model was developed using GoldSim© software. For stochastic analyses, GoldSim© uses the Monte Carlo method to generate monthly precipitation and evaporation time series, which are used as input climatic variable for the water balance model. A stochastics simulation was developed using different possible precipitation sequences that may contain groups of consecutive dry or wet years. For this purpose, synthetic series of monthly rainfall and evaporation of 15 years length were created.

 

The modeling process run over 250 simulations to obtain acceptable probabilistic estimates of the effluent flows for mean percentile 1% (dry years), and percentile 99% (wet years). Results of the water balance model in GoldSim are expressed in mean values, and those corresponding to situations of extreme abundance and scarcity denoted by percentiles of 100 years of return period (percentile of non-exceedance of 1% and 99% or risk of exceedance of 99% and 1%, respectively).

 

Hycroft Mine Project

Page 220

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The probabilistic terms used in the description of the results include:

 

Monthly average: The average monthly flow of all the simulation was estimated.
   
Maximum monthly with 1% of risk (p99%): Considering all the simulations, the 99% percentile of non-exceedance or 1% of monthly risk was estimated. This means that there is a 1% probability that the reported value will be exceeded due to excess rainfall in one month of the period of simulation.
   
Minimum monthly with 1% of risk (p1%): Considering all the simulations, the 99% percentile of exceedance or 1% of monthly risk was estimated. This means that there is a 1% probability that the reported value will be succeeded due to lack of rainfall in one month of the period of simulation.

 

Table 15-9 shows the LOM monthly average, the maximum (p99% or wet conditions), the minimum (p1% or dry conditions) make-up water demand. Figure 15-18 shows the make-up water demand variation through the operation stage. On average, make-up water requirements start at approximately 6,500 gal/min on the first year of operations. This requirement decreases to approximately 5,000 gal/min for Years 2 through 9. Average make-up water requirements further decrease to 4,400 gal/min for Years 10 through 13. Lastly, Years 14 and 15 have an average make-up water demand of 3,200 gal/min.

 

Table 15-9: Monthly Maximum Flows Demand

 

Facility Operation Stage (gal/min)
Monthly average Wet Conditions (p99%) Dry Conditions (p1%)
Well System 4,694 6,967 1,861

 

Note: 99% percentile of non-exceedance.

 

Figure 15-18: Total Fresh Water Demand

 

 

Source: Ausenco, 2022

 

Hycroft Mine Project

Page 221

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

15.10.6 Pit Dewatering

 

SRK Consulting (U.S.), Inc. (SRK), working with Hycroft prepared a Technical Memorandum that describes the hydrogeologic conditions, preliminary dewatering estimates, and associated costs for POX PFS Project. The hydrogeology of the mine and surroundings is complex. It includes a fault associated fluid barriers/conduits, high temperature groundwater, and the presence of hydrogen sulfide (H2S) gas. SRK conducted a three-year hydrogeologic data collection program incorporated pumping and monitoring wells, vibrating wire piezometers (VWP’s), core hole hydraulic testing, and short and long-term aquifer testing to characterize the local and regional (to the extent possible) groundwater system. The depth to groundwater is 700 ft below ground surface (bgs). Four depressurization wells are planned for dewatering the pit. SRK supplied a preliminary design for the location of the dewatering pumps, and pipeline required to convey water to the process plant from the pit. Power to these pumps will tie off existing powerlines in the area or the pumps maybe diesel-fueled if circumstances warrant.

 

15.11 Hazard Considerations

 

The climate at the Hycroft Site is arid with an average precipitation of 7.7 in/a falling mostly in the spring and winter months. Winds tend to be light in this area; however, occasional sandstorms or dust storms have been observed in spring months.

 

Temperatures in winter range from an average of 20 °F at night to 40 °F during the day. Fluctuations between freezing and non-freezing temperatures is sufficient to induce freeze–thaw cycling in near-surface soils, particularly in fine-grained or moisture-bearing materials. Winter snowpack is light, and snow does not normally present logistical problems.

 

Slope stability on site is governed by prevailing geotechnical conditions. According to the January 2012 Call & Nicholas, Inc. summary report of the 2011 reserve pit slope stability assessment, the principal factors governing slope stability are (1) the argillically altered Camel Conglomerate (Tc) and associated lakebed sediments (Tsg), (2) the thinly bedded siltstones of the Auld Lang Syne Formation, which are interpreted to dip toward the pit along the east walls of the Vortex and Brimstone pits, and (3) the East Fault.

 

Michael W. West and Associates Inc. (MWWAI) concluded after conducting a review of the Hycroft deterministic seismic hazard assessment in 2012, that seismicity in the area was low to moderate with no relation to mapped faults. Additionally, he noted that no faults in the area were classified as “active” or “capable”. According to MWWAI, these findings are consistent with the United States Geological Survey National Probabilistic Seismic Hazard Model.

 

15.12 Comments on Project Infrastructure

 

The Project is located within the established Hycroft Mine site and represents a brownfield development. A new sulfide ore processing plant is proposed. This plant will be integrated into the existing mining complex via tie-ins to current crushing infrastructure, utilities, and site services. Existing access roads across the site, in addition to many existing structures and facilities will remain in service.

 

Hycroft Mine Project

Page 222

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The Hycroft site currently includes primary, secondary, and tertiary crushing facilities, heap leach pads, the Merrill-Crowe processing plant complex, a refinery, administration buildings, maintenance shops, warehouse and laboratory facilities, fuel storage, and various ancillary service structures. Communications infrastructure is in place across the site and includes microwave-serviced data and telephone systems, fiber optic distribution, and site-wide cellular coverage.

 

The mine and its staffing requirements are supported by the nearby town of Winnemucca approximately 54 miles from site. Additional workforce may be drawn from the other nearby towns of Lovelock and Gerlach. Surveys indicate that the town of Winnemucca is large enough to provide adequate housing, personal services, and transportation infrastructure to support both operational and construction workforce requirements. A contracted bus service will provide transportation from Winnemucca to site.

 

Existing community infrastructure is considered sufficient to support both current and future staffing levels, with construction personnel transported to site via contracted bus services.

 

The proposed processing facility is designed to connect to the existing crushing circuit and North Merrill-Crowe facility. The proposed scope of work includes electrical distribution upgrades, new substations, process control systems, reagent handling facilities (including oxygen and limestone systems), and selective expansion or repurposing of existing maintenance and administrative buildings.

 

The site currently has access to grid power. Additional transmission capacity is required to support the new plant. The total estimated load factoring for load growth, including power for the oxygen plant, is 170 MW. Tie-ins to existing utilities shall include water, compressed air, and potable and sewer systems. The development of a freshwater production well field is also planned to support freshwater needs throughout the LOM.

 

A rail spur extension from the Union Pacific line is planned to support delivery of reagents, consumables, and fuel, and to facilitate shipment of salable metals. Additionally, the existing fuel island is to be replaced with a higher-efficiency system during the LOM.

 

Ancillary structures including a covered crushed ore stockpile, new laboratory and maintenance facilities, fuel station upgrades, and technical services expansion are proposed to support operations over the LOM. In addition to this, select existing buildings will be relocated, expanded, rehabilitated, or repurposed.

 

Hycroft Mine Project

Page 223

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

16 Market Studies and Contracts

 

16.1 Market Studies

 

Hycroft Mining has not completed any formal marketing studies with regards to gold production that will result from the mining and processing of ore from the Project into gold and silver doré bars. Gold and silver production is expected to be sold on the spot market, with the terms and conditions of sales contracts expected to be typical of similar contracts for the sale of doré throughout the world. Gold and silver are principal precious metals traded at spot prices for immediate delivery. The market for gold and silver is very liquid with many buyers and sellers - trading typically spans 24 hours/day across multiple locations around the world, making it straightforward to obtain a reliable market price at any time. The depth and stability of these markets support the expectation that gold and silver doré produced from the Project can be sold throughout the LOM.

 

16.2 Commodity Price Projections

 

The economic analysis for the Project was performed assuming a base case gold and silver price of US$3,600/oz and US$48.00/oz respectively. These prices are based on the average of long-term consensus price forecasts from numerous financial institutions as of April 2026.

 

16.3 Contracts

 

Hycroft has not at this stage entered into agreements related to refining Hycroft products, transporting products to market or smelting facilities, or insuring doré and/or concentrate products. As of this time, Hycroft does not have open hedging contracts or forwards agreements for their products. Marketing of doré is expected to be arranged through contractual relationships with major refineries for secure transportation of metal and refining. The cost of transporting and refining doré included in the economic analysis are US$5.00/oz for gold and US$0.50/oz for silver, based on terms recently published for comparable projects. Transportation and treatment contracts are not currently in place, though easily obtainable.

 

Hycroft Mine Project

Page 224

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17 Environmental Studies, Permitting, and Plan, Negotiations, or Agreements with Local Individuals or Groups

 

17.1 Overview

 

This section provides an environmental overview of the Project. It outlines existing biological and physical baseline conditions, proposed new baseline studies to support future permitting, existing permits, and permitting requirements to support the proposed revisions to the Project. This section also discusses socio-economic baseline conditions, community engagement, and conceptual mine closure and reclamation planning for the Project.

 

The Mine is located on public land administered by the Bureau of Land Management (BLM) and private land controlled by Hycroft Resources and Development, LLC, a wholly owned subsidiary of Hycroft Mining Holding Company. The Mine lies within the Sulfur Mining District, approximately 54 miles west of Winnemucca, Nevada. Access to the site is via Jungo Road (a Humboldt County maintained road).

 

Hycroft is authorized for ore extraction and processing, water management, engineering, environmental studies, and exploration. Existing facilities on site include two administration buildings, a laboratory, a mobile maintenance shop, a light vehicle maintenance shop, a warehouse, leach pads, primary, secondary, and tertiary crushing systems, two Merrill-Crowe process plants, and a refinery. The Mine is permitted for both heap leach and milling operations.

 

Hycroft is proposing the development of new infrastructure to support the requirements of the modified Project. Updates include construction of the North TMF, Waste Rock Storage Facilities (WRSF), rail spurs, and a new process plant area.

 

17.2 Environmental Considerations

 

17.2.1 Baseline and Supporting Studies

 

The Mine has conducted numerous environmental baseline studies as part of their previous permitting efforts and continues to collect certain environmental baseline data. The Mine area has been surveyed for surface water resources, including Waters of the United States (WOTUS), biological resources, cultural resources, and groundwater resources. These studies include:

 

Summary of Field Investigations and Conceptual Hydrogeology Report (2013)
   
Hydrogeologic Characterization Report (2014)
   
Baseline Spring Inventory and Surface Water Monitoring, Hycroft Mine (2014)
   
Rock and Water Baseline Characterization for the Phase II Expansion Project – Hycroft Mine (2014)
   
Air Quality Impact Analysis (2017).

 

Hycroft Mine Project

Page 225

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17.2.1.1 Hydrology and Climate

 

The Mine lies on the eastern edge of the Black Rock Desert, and there are no streams, rivers, or lakes in the immediate vicinity of the Project. Spring baseline surveys have been conducted biannually since 2011 within a 10-mile radius around the Mine. A total of 31 sites were identified in the baseline study. These included natural springs, man-made springs, and seasonal wetted areas. Nine of the sites were identified for monitoring to evaluate surface water resources near the Mine. Additionally, JBR Environmental Consultants, Inc. conducted spring surveys in 2012 and 2013 encompassing 560 square miles west of the Mine to assess whether groundwater pumping at the mine would impact other springs in the Black Rock Desert. Survey data and groundwater modeling predictions did not indicate drawdown would extend near any of the inventoried springs.

 

The Mine is in a semi-arid high desert environment, and climate is controlled primarily by the Sierra Nevada Range with minimal rainfall. Climate data including precipitation, temperature, and pan evaporation have been obtained from the Western Regional Climate Center’s database for the National Weather Service Cooperative Station at the Rye Patch Dam. The station is located approximately 32 miles from the Mine at a similar elevation and provides data from 1935-2012. The recorded precipitation at the Rye Patch Dam weather station averaged 8.93” annually. Additional precipitation data were collected at the Mine weather station from 2010-2012 and from the Rye Patch Dam weather station. Annual pan evaporation at the Rye Patch Dam is 59.38 in/a and the recorded average temperature is 51 °F.

 

17.2.1.2 Hydrogeology

 

A total of 16 wells and 23 piezometers are installed to evaluate the hydrogeologic baseline conditions at the Mine, with the majority of data being collected between 2010 and 2013. Instrumentation is located throughout the Mine site and completed in a variety of geologic formations representing the site. Static groundwater varies from 20 to 800 ft bgs and varies from 150 to 800 ft bgs directly beneath the mining operations. Groundwater generally flows southeast to northwest from recharge in the volcanic highlands to discharge in the alluvial basin beneath the Black Rock Desert. Results are summarized in detail in the Hydrogeologic Characterization Report and the Summary of Field Investigations and Conceptual Hydrogeology Report which were both developed in 2013 in support of the Phase II Expansion Project.

 

17.2.1.3 Soils, Vegetation and Wildlife Monitoring

 

The Mine released a Biological Baseline Report in 2019 that incorporated the results of 2014, 2015, and 2016 surveys conducted since the original release of the report in 2012. The report also included clarifications, edits, and missing information requested by BLM, as well as revised information based on updated Project details. The report focuses on soil, vegetation, and wildlife surveys and provides background consultation with regulatory agencies, as well as field methodologies and survey results. The combined surveys areas make up the “Biological Survey Area,” which encompasses the proposed area of disturbance of the Project. BLM has stated that any new areas that would be disturbed would require baseline surveys.

 

Hycroft Mine Project

Page 226

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Eight soil units have been mapped by Natural Resources Conservation Service within the 2012-2014 Biological Survey Area. The soil units are described both in the Soil Survey of Humboldt County, Nevada, West Part (NRCS, 2003) and Soil Survey of Pershing Country, Nevada, West Part (NRCS, 1998). There are no serious limitations related to soil quality that would limit the proposed development or future reclamation efforts.

 

Stantec completed vegetation surveys of the Biological Survey Area in 2012 and 2014, which included vegetation community mapping, floristic inventory, and noxious, invasive, and non-native species surveys. Twenty-eight vegetation communities were mapped, with the dominant communities being Desert Scrub-Wyoming Sagebrush (28%), Shadscale-Annual Grassland (23%), and Desert Scrub (10%). One noxious weed species, the five-stamen tamarisk, was identified during the surveys.

 

Eleven occurrences of one BLM sensitive plant species, sand cholla, were noted within the Biological Survey Area. As with all cacti in Nevada, the sand cholla is a protected cactus species, which requires a permit prior to commercial harvest. Botanists also identified 700 buckwheat occurrences, which is a known host plant to insects on the BLM Winnemucca District’s special status species list.

 

Overall, there is no presence of BLM sensitive plant species present on or near the Project which would present limitations to the proposed Project updates.

 

Stantec completed wildlife surveys of the Biological Survey Area from 2012-2016. Surveys ranged from General Wildlife surveys to more targeted surveys studying migratory birds, bats, western burrowing owls, greater sage-grouse, and various butterfly species.

 

BLM sensitive species identified during the surveys were:

 

Brewer’s sparrow
   
Sage thrasher
   
Loggerhead shrikes
   
Western burrowing owl.

 

Baseline surveys also identified the BLM sensitive species golden eagle (Aquila chrysaetos) in and around the Project site. The Biological Baseline Report details the results of golden eagle nest surveys conducted from 2012-2016, including information on nest condition, nest status, and the number of young. Eagles observed to be off the nest were checked for any evidence of nesting behavior, such as mated pairs, territorial defense, carrying nest material, or transporting food. Annual raptor and golden eagle surveys are completed annually, and results are submitted to the BLM as stand-alone reports.

 

The proposed modifications to the recovery process will not impact on the footprint of planned disturbance for the Project, and therefore additional wildlife baseline studies may not be required to support the Plan of Operations amendment.

 

Hycroft Mine Project

Page 227

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17.2.1.4 Geochemistry

 

The Mine has a waste rock characterization program which is performed in phases related to approved or proposed mining areas. Most recently, Phase 4 of the program was completed to collect additional data for the Phase II Expansion Project to ensure it is spatially representative of the material proposed to be mined as part of the Project. Static testing was completed to address total acid generating or neutralizing potential of the samples and concentration of constituents in leachates derived from the material. Kinetic testing for this Project is the standard humidity cell test (HCT) procedure.

 

The Phase 3 and 4 programs also included analysis of ore grade material, with 56 samples being collected and analyzed. From ABA testing, all but one ore grade sample showed uncertain potential for acid generation or potential for acid generation. ABA and NAG for ore grade samples fall within the same range as waste rock samples.

 

Pit wall and floor samples have been collected to evaluate geochemical interactions between groundwater, pit walls, and the water quality of the pit lake over time. The pit wall and floor sample are composed of the same material identified and characterized during the Phase 1-4 waste rock programs. Kinetic testing has shown that the submerged pit walls in a post mining environment have the potential to generate acid and leach metals into the anticipated lake.

 

Three types of tailings materials were analyzed as part of the Rail Spur Project EA: 26 variability composites, 6 master domain composites, and 8 bulk samples representing tailings. The samples underwent whole rock analysis, ABA, NAG testing, meteoric water mobility procedure testing, and mineralogy testing, and were deemed to be representative of site materials.

 

17.2.1.5 Air Quality

 

The Mine is located within the Humboldt and Pershing Counties, which lies within Air Quality Hydrographic Basin 28, which is unclassified for PM10, CO, SO2, and NOx. In 2017, Stantec completed an Air Quality Impact Analysis (AQIA) for the Phase II Expansion Project, which was later updated in 2018. The study includes near-field dispersion modeling to determine impacts of the Phase II Expansion Project against the Nevada Ambient Air Quality Standards and the National Ambient Air Quality Standards. The study included ancillary sources of emissions such as lime silos, storage tanks, and lighting plants, as well as fugitive, process, and traffic emissions. Monitoring data from the Lehman Caves in Great Basin National Park was utilized to simulate background concentrations of pollutants of concern in the Mine area. Modeling suggests that emissions from the approved Project will fall well below the lowest applicable air quality standards for all constituents.

 

17.2.2 Environmental Monitoring

 

The Mine has developed a series of environmental management and monitoring plans which are required to guide the development and operation of the Project to limit environmental impacts. These plans are developed to address legal requirements and committed Environmental Protection Measures (EPMs) made by the Mine during Project permitting and recent Plan of Operations amendments.

 

Hycroft Mine Project

Page 228

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The following is a list of Hycroft Environmental Management and Monitoring Plans:

 

Waste Rock Management Plan
   
Quality Assurance Plan
   
Eagle Conservation Plan
   
Stormwater Pollution Prevention Plan
   
Solid and Hazardous Waste Management Plan
   
Noxious Weed Monitoring and Control Plan
   
Interim Closure Plan
   
Monitoring Plan
   
Surface Area Disturbance Dust Control Plan
   
Lighting Management Plan
   
Historic Properties Treatment Plan.

 

17.2.3 Water Management

 

Details of the water management protocols have been included in each of the permits. These include, but not limited to, specific designated measuring and monitoring locations, sample schedules, sample sizes, testing parameters, reporting protocols, internal and third-party reviews and summaries, and notification protocols for any non-conformances or irregularities. Specifically, water management requirements are outlined in the Plan of Operation Permit, Permit to Operate a Public Water System, Water Pollution Control Permits, and each of the Pond Permits.

 

17.3 Permitting Considerations

 

The Mine operates under a series of permits which are issued by both federal and state regulators. Table 17-1 highlights the permits necessary to operate the Mine. The permits listed in bold are likely to require updates based on the proposed revisions to the Project.

 

Hycroft Mine Project

Page 229

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 17-1: Current Major Environmental Permits and Permits Necessary to Operate the Mine

 

Operating Permits Issuing Agency Number Status
Plan of Operations BLM N64641 Current
Mercury Operating Permit to Construct NDEP Bureau of Air Pollution Control AP1041-2255 Current
Class I Air Quality Operating Permit to Construct NDEP Bureau of Air Pollution Control AP1041-2964 Current
Class II Air Quality Permit NDEP Bureau of Air Pollution Control AP1041-0334.05 Current
Permit to Operate a Public Water System NDEP Bureau of Safe Drinking Water HU-0864-12NTNC Current
Water Pollution Control Permit-Crofoot Project NDEP Bureau of Mining Regulation & Reclamation NEV60013 Current
Water Pollution Control Permit-Hycroft Mine NDEP Bureau of Mining Regulation & Reclamation NEV94114 Current (Application Shield)
Reclamation Permit NDEP Bureau of Mining Regulation & Reclamation 134 Current
Mining General Stormwater Pollution Prevention Permit NDEP Bureau of Water Pollution Control NVR 300000 Current
Class III Landfill Waiver NDEP Bureau of Waste Management F-346 Current
Artificial Pond Permit (Brimstone Process Ponds) NV Department of Wildlife S34481 Current
Artificial Pond Permit (Crofoot Process Ponds) NV Department of Wildlife S36665 Current
Artificial Pond Permit (North Process Ponds) NV Department of Wildlife S36661 Current
Septic Onsite Disposal NDEP Bureau of Water Pollution Control GNEVOSD09L-0048 Current
Dam Safety Permits NV Division of Water Resources J-273 Current
Hazardous Materials Storage Permit NV State Fire Marshal 8250 Current
Special Use Permit Pershing County SUP 12-04 Current
Special Use Permit Humboldt County UH-12-04 Current
Golden Eagle Take Permit US Fish & Wildlife Service MB90099B-0 Current

 

17.3.1 Federal Permits

 

17.3.1.1 Bureau of Land Management Plan of Operations

 

The Mine is currently authorized to operate under a Plan of Operations (Plan) (NVN-064641) under 43 Code of Federal Regulations [CFR] 3809 which has gone through several amendments. In 2012, the BLM issued a Record of Decision (ROD) for an EIS conducted for the Mine to expand their heap leach operations, open pits, and waste rock facilities. In 2014, the BLM issued a Decision Record with an EA authorizing Hycroft’s Plan of Operations for construction and operations of a rail spur, open pit expansion, and construction of a processing complex, including the TMF located northeast of the mine.

 

The Mine is preparing materials for a modification to the Plan of Operations to propose the following updates to the Project.

 

Hycroft Mine Project

Page 230

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

New process plant that will be separate from the existing crushing facility and North Merril Crowe facility. The process plant will feature:

 

modifications to existing crush circuit conveyor layout with additional feeders and a new rock breaker
   
new process plant, including:

 

  new grinding circuit with four ball mills
     
  new multistage flotation circuit
     
  new POX circuit including lime boil tanks
     
  new leach circuit.

 

new process control room, power distribution lines, grids, substations, and electrical rooms to support the processing plant
   
new TMF located northeast of the Mine
   
new access roads to the process plant and TMF, as well as a TMF construction haul road
   
an additional rail siding of the existing Union Pacific rail line located in the NW location of the plant
   
WRSF features additional waste rock dumps

 

The review and approval process for the revisions to the Plan Application by the BLM constitutes a federal action under the National Environmental Policy Act (NEPA) and BLM regulations. Thus, for the BLM to process the Plan Application, they are required to comply with NEPA and prepare either an EA, or an EIS.

 

17.3.1.2 Bureau of Land Management Pre-Application Planning

 

As part of the pre-plan application planning process with the BLM, an initial meeting is scheduled between the proponent and the BLM to discuss the anticipated scope of the amended mining operation and to review the likely environmental resource baseline data needed for the processing of the Plan Amendment by the BLM. This initial meeting generally occurs prior to the submittal of the Plan Application, depending on the anticipated complexity of the mining operations and baseline data needs, which varies for each Project.

 

The process for collecting baseline data generally includes the development of baseline data collection work plans, which are submitted to the BLM for review and approval prior to initiating the baseline data collection. Following approval, field surveys are conducted to collect relevant baseline data. Depending on the environmental resources to be evaluated, desktop studies may be utilized in lieu of field surveys. Findings of the field surveys are then summarized in a report that documents the data collected. These technical reports are then submitted to the BLM for review and approval. In some cases, the baseline data collection process will also involve the State of Nevada, depending on the resource being assessed, particularly for geochemical and hydrological surveys.

 

Hycroft Mine Project

Page 231

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The most recent baseline data for the Project was collected as part of the 2019 EIS process. Additions to baseline data, and additional studies may be required as part of the proposed revisions to the Project.

 

17.3.1.3 Plan of Operations Processing

 

The Plan Application is submitted to the BLM and the Nevada Division of Environmental Protection (NDEP) Bureau of Mining Regulation & Reclamation (BMRR) for any surface disturbance in excess of five acres. The Plan Application describes the operational procedures for the construction, operation, and closure of the Project. As required by the BLM and BMRR, the Plan Application includes a waste rock management plan, quality assurance plan, a stormwater plan, a spill prevention plan, a reclamation plan, a monitoring plan, and an interim management plan. In addition, a reclamation report with a Reclamation Cost Estimate (RCE) for the closure of the Project is required. The content of the Plan Application is based on the Mine plan design and the data gathered as part of the environmental baseline studies. The Plan Application includes all mine and processing design information and mining methods. The BLM determines the completeness of the Plan Application and, when the completeness letter is submitted to the proponent, the NEPA process begins. The RCE is reviewed by both agencies, and the bond is determined prior to the BLM issuing a decision record on the Plan Application and BMRR issuing the Nevada Reclamation Permit (NRP).

 

The Plan Application will be submitted for the Project when operational and baseline surveys are complete, and operations and designs for the Project are at a level where a Plan Application can be developed to the necessary level of detail. Key baseline reports for the Project will be included in the Plan Application submittal to the BLM and BMRR.

 

The BLM will need to complete their administrative review of the Plan Application and issue a determination prior to moving on to the NEPA process.

 

17.3.1.4 Golden Eagle Take Permit

 

Golden eagles were observed in and around the Project site during environmental baseline studies. The Mine is working directly with the BLM and the USFWS on the management of this species and submits annual survey reports to the BLM. As part of the permitting process, the Mine will submit a golden eagle take permit application to USFWS requesting authorization to remove inactive golden eagle nests and incidental take under the Bald and Golden Eagle Protection Act (BGEPA).

 

17.3.1.5 National Environmental Policy Act

 

The NEPA process is triggered by the issuance of a Completeness letter for the Plan Application. The NEPA review process is completed with either an EA or an EIS.

 

The EA process is conducted in accordance with NEPA regulations (40 CFR 1500 et. seq.), BLM, as lead federal agency, guidelines for implementing the NEPA in BLM Handbook H-1790-1 (updated January 2008), and BLM Washington Office Bulletin 94-310. The intent of the EA or the EIS is to assess the direct, indirect, residual, and cumulative effects of the Project and to determine the significance of those effects. Scoping is conducted by the BLM and includes a determination of the environmental resources to be analyzed in the EA or the EIS, as well as a degree of analysis for each environmental resource. The scope of the cumulative analysis is also addressed during the scoping process. Following scoping and baseline information review, the EA or the EIS is prepared. When the BLM determines the EA or the EIS is complete, it will be submitted to the public for review. Comments received from the public would be incorporated into either a revised EA or the decision record, and for the EIS either a final EIS or a Record of Decision. Under an EA, there can be no significant impact. The preparation of an EIS is a lengthier and more expensive process than an EA. The Project proponent pays the third-party contractor to prepare the EIS and pays recovery costs to the BLM for any work on the Project by BLM specialists.

 

Hycroft Mine Project

Page 232

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17.3.2State of Nevada Permits

 

There are several environmental permits issued by the NDEP. NDEP will issue permits that address water and air pollution, as well as land reclamation. The Nevada Division of Water Resources (NDWR) issues water rights for the use and management of water.

 

17.3.2.1Nevada Reclamation Permit

 

Hycroft currently operates under a NRP under the Nevada Administrative Code [NAC] 519A) (Plan Application) issued by the NDEP. Hycroft will need to modify the NRP from the BMRR to include construction, operation, and reclamation details as applicable to the modified Project design. The contents of the modification are prescribed in the NAC Section 519A.140. Based on the Memorandum of Understanding between the BLM and NDEP, a joint application is submitted to the BLM and BMRR that addresses the requirements of the modified Plan and NRP.

 

17.3.2.2Water Pollution Control Permit

 

The water pollution control permits (WPCPs) from the BMRR will be revised to include the updated designs to construct, operate, and close a mining facility in the State of Nevada. The contents of the application are prescribed in the NAC Section 445A.394 through 445A.399. The revised WPCP applications for the Project will be updated based on the following:

 

Open pit mining, with an anticipated post-mining pit lake formation.

 

Storage of non-acid and acid generating waste rock.

 

Exploration.

 

Dewatering and water management.

 

Mill, NTF, and process plant management.

 

Ancillary facilities that include stormwater diversions, and sediment control basin.

 

WPCP applications include an engineering design for waste rock storage areas and mill/tailings facilities, waste rock characterization reports, hydrogeological summary reports, engineering design for process components including methods for the control of stormwater runoff, and containment reports detailing specifications for containment of process fluids. Applications will also contain the appropriate WPCP plans, including a process fluid management plan, a monitoring plan, an emergency response plan, a temporary closure plan, and a tentative plan for permanent closure of the Mine.

 

Hycroft Mine Project

Page 233

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17.3.2.3Air Quality Operating Permits

 

The Mine currently operates under a Class II Air Quality Operating Permit, a Mercury Operating Permit, and a Class I Operating Permit to Construct which include the Gyro Crushing Circuit, lime silos, and the Mill Project. A new Operating Permit to Construct could be required by the NDEP Bureau of Air Pollution Control (BAPC) for a roasting plant, and the existing permits may need to be revised to reflect the proposed changes to the Project. The permit modification applications would include specifics on each process component that could emit air pollutants and a detailed emissions inventory, as well as air quality modeling. The application preparation and processing time frame ranges from three to nine months, depending on the type of permit.

 

17.3.2.4Water Rights

 

The Mine currently holds 16 separate water rights permits administered by the NDWR. These rights are leased to Hycroft. The water resources to support the Mine are held under 14 of the water rights permits in the Black Rock Desert Basin and a total of 21,457.95 acre-ft/a (6.99 billion gal of water per year). The remaining two water rights permits are held outside of the Black Rock Desert Hydrographic Basin and are used to support maintenance of Jungo Road.

 

The proposed changes to the Project are not expected to materially change the water requirements of the operation, and thus the existing water rights permits will provide sufficient water to support those changes.

 

17.3.3Additional Permits and Authorizations

 

In addition to the principal environmental permits outlined above, Table 17-2 lists other notifications or ministerial permits that may likely be necessary to operate the Project.

 

Table 17-2: Ministerial Permits, Plans and Notifications

 

Notification/Permit Agency Timeframes
Above Ground Storage Tank Permit Nevada Bureau of Corrective Actions Up to six months to register. Cost is $100/tank per year and a requirement to perform monthly visual inspections.
Agreement for Road Maintenance Humboldt and Pershing Counties Up to six months to negotiate the agreement with the county roads department and the county commission.
Explosives Permit Bureau of Alcohol, Tobacco, Firearms, and Explosives n/a
Explosives User’s License (User’s Clearance) Bureau of Alcohol, Tobacco, Firearms, and Explosives n/a
Fire and Life Safety Nevada State Fire Marshal Approximately one month for review and approval. Applicant to submit a notification letter prior to construction and operation.

 

Hycroft Mine Project

Page 234

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Notification/Permit Agency Timeframes
Hazardous Materials Permit Nevada State Fire Marshal Approximately two months for review and approval. Applicant must submit a notification letter 30 days prior to the start of operations and then annually by March 1st of each year.
Industrial Artificial Pond Permit Nevada Department of Wildlife Four weeks
Leach Pad Commencement Nevada Bureau of Mining Regulation and Reclamation One week
Leach Pad As-Built Report Nevada Bureau of Mining Regulation and Reclamation Four weeks
Process Plant As-Built Report Nevada Bureau of Mining Regulation and Reclamation Four weeks
Dam Safety Permit Nevada Division of Water Resources Two months
Mine ID Number Mine Safety & Health Administration One week
Mine Opening Notification Nevada Division of Minerals One week
Mine Registry Nevada Division of Minerals One week
Notification of Commencement of Operations Mine Safety & Health Administration One week
Production/Dewatering Wells - Proof of Completion Nevada Division of Water Resources One week
Radio License Federal Communications Commission One week
RCRA Waste Mgt. ID - Mine Nevada Bureau of Sustainable Materials Management/U.S. Environmental Protection Agency Two weeks
Well Drilling Permit (Notice of Intent to Drill) Nevada Division of Water Resources One week
Potable Water System Nevada Bureau of Safe Drinking Water Eight months
Septic System Nevada Bureau of Water Pollution Control Six months to prepare application (including the mercury control system) and process to obtain the permit.

 

17.4Social Considerations

 

Social and community impacts are considered and evaluated for the revision to the Plan Application and would be used in the NEPA process. Potentially affected Native American tribes, tribal organizations, and/or individuals are consulted during the preparation of all plan amendments to advise on the proposed projects that may affect cultural sites, resources, and traditional activities. During the most recent permitting for the Phase II Expansion Project in 2019, the BLM engaged:

 

Fort McDermitt Paiute and Shoshone Tribe

 

Fallon Paiute-Shoshone Tribe

 

Battle Mountain Band of the Te-Moak Tribe of Western Shoshone

 

Lovelock Paiute Tribe

 

Hycroft Mine Project

Page 235

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Pyramid Lake Paiute Tribe

 

Summit Lake Paiute Tribe

 

Winnemucca Indian Colony.

 

Common concerns raised by the tribes during consultation meetings and site visits included:

 

environmental concerns with quarries

 

management of archaeological finds, and disturbance of cultural resources such as rock stacks

 

eagle nest removal

 

wildlife issues around the North TMF.

 

Potential community impacts to existing population and demographics, income, employment, economy, public finance, housing, community facilities, and community services are evaluated for potential impacts as part of the NEPA process. There are no known social or community issues that would have a material impact on the Project’s ability to extract mineral resources. Identified socioeconomic issues (employment, payroll, services and supply purchases, and state and local tax payments) are anticipated to be positive.

 

Should the proposed changes to the Project initiate an EIS, there would be a public scoping process involving public open house meetings. Members of the public are free to attend the sessions in person or provide questions in writing. In the past, public concerns have included, but not limited to:

 

air quality impacts and emissions from the Mine

 

impacts on cultural resources

 

mitigation measures to reduce environmental impacts

 

impacts on golden eagle nests and breeding territory

 

site reclamation.

 

Future Project updates will require continued engagement with Native American tribes and the public to understand concerns and identify key mitigations to environmental and social impacts. Engagement will be carried out by the proponent as well as regulators such as BLM and USFWS.

 

17.4.1National Register of Historic Places

 

The preservation of historic places and culturally significant resources is considered when a Project is being permitted. Updates to the Project may require additional assessment to determine whether any NRHP-eligible sites and culturally sensitive resources, such as rock stacks, would be affected by the new Project layout. There is a risk of community concerns if the new NTF will impact culturally sensitive areas or culturally sensitive species such as eagles.

 

Hycroft Mine Project

Page 236

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

17.5Closure and Reclamation Planning

 

17.5.1Closure and Reclamation Plans

 

A Tentative Plan for Permanent Closure (TPPC) for the Mine is in place and is currently being updated for future submission to the BMRR with the application to modify the WPCP (NEV0094114). In the TPPC, the proposed NTF closure approach would consist of fluid management through evaporation, covering the NTF with a geosynthetic cover and growth media, and then revegetation. The design of the process components is not sufficiently advanced to determine the closure costs. Any residual NTF drainage will be managed with evaporation cells. Surface management surety bonds currently total US$58.7 million with $58.3 million securing financial assurance requirements for the mine and $0.4 million securing financial assurance requirements for the water supply well field and exploration within the Project boundary. Future increases in reclamation bonding will either be through surety bonds supported by restricted cash balances or by letters of credit issued by banks.

 

Mine closure and reclamation will be performed in accordance with BLM and State of Nevada regulations and guidelines. Mining activities that occur near a National Conservation Area and associated pioneer trails will require careful planning and design, and particular attention will be paid to leaving a post-mining land configuration that minimizes visual impact. Facility expansions will continue to be designed and constructed to meet or exceed state and federal design criteria. The WRSFs will continue to be evaluated for their potential to release pollutants and monitored routinely in accordance with an approved waste rock management plan. After operations cease, effluent from the heap leach facilities will be allowed to drain until the rate of flow can be passively managed through evaporation or a combination of evaporation and infiltration. Current studies are gathering additional hydrology and geochemistry data for use in the development of final closure plans that meet the regulatory standards. All buildings and facilities not identified for a post-mining use will be razed during the salvage and site demolition phase.

 

17.5.2Closure Cost Estimates

 

A Tentative Plan for Permanent Closure (TPPC) for the Mine is in place and is currently being updated for future submission to the BMRR with the application to modify the WPCP (NEV0094114). In the TPPC, the proposed TMF closure approach would consist of fluid management through evaporation, covering the TMF with a geosynthetic cover and growth media, and then revegetation. The design of the process components is not sufficiently advanced to determine the closure costs. Any residual TMF drainage will be managed with evaporation cells. Surface management surety bonds currently total US$58.7 million with $58.3 million securing financial assurance requirements for the mine and $0.4 million securing financial assurance requirements for the water supply well field and exploration within the Project boundary. Future increases in reclamation bonding will either be through surety bonds supported by restricted cash balances or by letters of credit issued by banks.

 

17.6Comments on Environmental Studies, Permitting and Social or Community Impact

 

The scope of environmental studies undertaken by Hycroft are sufficient to address all permitting and environmental review requirements. The Mine currently holds all the necessary permits to operate. However, modifications to a number of those permits are necessary to construct and operate and complete the updates to the project as outlined in this document.

 

Hycroft has engaged in communications with all identified tribes that have expressed interest in the Project. There are no residences or towns in the immediate vicinity of the Project. The nearest community is Winnemucca, Nevada, approximately 60 miles northeast of the Project.

 

Hycroft Mine Project

Page 237

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18Capital and Operating Costs

 

18.1Introduction

 

The capital and operating costs described in this technical report are based on open-pit mining operations for the Hycroft project. The process plant is designed to treat 57,100 st/d of mineralized material over a mine life of 51 years.

 

18.2Capital Costs

 

18.2.1Overview

 

The capital cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The estimate includes mining, processing, on-site infrastructure, off-site infrastructure, project indirects, project delivery, owners’ costs, and provisions. The total initial capital costs for the Project are estimated at US$2,434 million, including capitalized operating costs, and contingency. The LOM sustaining costs are estimated at US$3,107 million, while the closure costs are estimated at US$243 million. The capital cost summary is presented in Table 18-1.

 

Table 18-1: Capital Cost Summary

 

WBS Description Capital Cost (US$M) Sustaining Cost (US$M) Total Cost1 (US$M)
1000 Mining 194 1,171 1,365
2000 Crushing 48 60 109
3000 Sulfide Process 915 776 1,692
4000 Oxide Process 16 46 63
5000 Waste Rock Storage & TMF 208 515 723
6000 Onsite Infrastructure 139 9 148
7000 Offsite Infrastructure 43 366 409
Total Direct Costs 1,563 2,944 4,507
8000 Indirects 382 27 409
9000 Provisions 448 136 584
10000 Owner’s Costs 41 - 41
Total Capital Cost 2,434 3,107 5,541

 

Note:

 

1.Totals may not match due to rounding

 

Hycroft Mine Project

Page 238

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18.2.2Basis of Estimate

 

The capital cost estimate was developed in Q1 2026 in U.S. dollars (US$). The estimate is based on budgetary quotations for equipment from recent advanced studies, supplemented with Ausenco’s in-house database, and informed by Ausenco’s experience from similar operations in North America.

 

The following data were used as the basis of estimate:

 

Mining schedules.

 

PEA-level engineering design by Ausenco, including but not limited to design criteria, equipment lists, and material take-offs (MTOs).

 

Budgetary equipment quotes from similar recently completed advanced studies.

 

Additional data such as lang factors and indirect costs from similar recently completed studies and projects.

 

The estimate also adhered to the following parameters:

 

No allowance was made for exchange rate fluctuations.

 

No escalation was added to the final estimate.

 

18.2.3Mine Capital Costs

 

Table 18-2 summarizes the annual mine capital costs for both initial and sustaining capital cost.

 

Preproduction mine development (preproduction stripping) is shown as a separate line item at nearly US$37.4 million. All other capital is for mine mobile equipment.

 

Sustaining capital includes both equipment replacements and fleet size increases for haul trucks.

 

Mine capital costs include:

 

all mine mobile equipment that are required to operate and maintain the mine

 

mine maintenance equipment, and shop tools

 

an allowance is included for the initial spare parts inventory

 

mine engineering equipment: computers, survey equipment, etc.

 

a dispatch system

 

a mine radio system.

 

Hycroft Mine Project

Page 239

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The mine capital costs do not include:

 

mine office buildings or shop buildings

 

mobile equipment that is not required by the mine

 

infrastructure or process plant related costs

 

equipment salvage credit

 

contingency.

 

Table 18-2: Baseline Mine Capital Cost (without Accuracy or Contingency adjustment)

 

Year Mine Equipment

Mine

Preproduction

Development

(US$M)

Total

Mine

Capital

(US$M)

Initial

Capital Cost

(US$M)

Sustaining

Capital

(US$M)

Preproduction 111.5 37.4 148.9
1 123.3 123.3
2 19.0 19.0
3
4 1.5 1.5
5 25.6 25.6
6 20.2 20.2
7 11.9 11.9
8 1.5 1.5
9 20.0 20.0
10 42.7 42.7
11-15 50.0 50.0
16-20 44.5 44.5
21-25 214.6 214.6
26-30 32.4 32.4
31-35 74.2 74.2
36-40 26.7 26.7
41-45 162.2 162.2
46-51 30.4 30.4
Total 111.5 900.7 37.4 1,049.6
Accuracy2 and Contingency3 27.5 270.3 17.6 315.4
Total 139 1,171 55 1,365

 

Note: 1. Totals may not match due to rounding; 2. 10% Accuracy adjustment applied to large fleet items; 3 Includes 25% Contingency

 

Hycroft Mine Project

Page 240

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18.2.4Process Capital Costs

 

The selection and sizing of process equipment requirements was based on process flowsheets and process design criteria as defined in Section 14. All major equipment was sized based on the process’ mass balance, as dictated by the process design criteria, to develop a mechanical equipment list (MEL). The MEL was then developed through recent budgetary quotations. The remaining value of the equipment list was developed through benchmarking against recent execution projects and advanced studies. Refurbishment costs for the existing equipment at primary crushing, heap leach, Merrill Crowe and refinery were included as part of initial capital cost.

 

The process plant and infrastructure engineering design was completed to an IA-EA study level of definition, allowing for the bulk material quantities (steel, concrete, piping, cables, instruments, etc.) to be derived for the major commodities using lang factors. Plant earthworks costs were derived from MTOs.

 

The total capital costs for the process plant are US$1,188 million. The capital cost breakdown for the process plant is summarized in Table 18-3.

 

Table 18-3: Process Plant Capital Cost Breakdown

 

WBS Description Initial Costs (US$M)
2100 Primary Crushing 10.6
2200 Coarse Ore Storage and Reclaim 8.4
2400 Crushed Ore Stockpile 29.3
3100 Process Plant Building 11.7
3200 Grinding and Screening 200.8
3300 Flotation 36.6
3400 Concentrate Thickening & Tailing Handling 12.1
3500 Pressure Oxidation 383.6
3600 CCD & Cyanide Destruction 22.4
3700 Reagents 53.3
3800 Process Services 194.1
3900 Tailings and Reclaim 0.7
4100 Heap Leach 2.7
4200 Brimstone Merrill-Crowe 0.4
4400 North Merrill-Crowe 9.2
4500 North Refinery 3.8
  Total 979.7

 

Note: Totals may not match due to rounding

 

Hycroft Mine Project

Page 241

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18.2.5Infrastructure Capital Costs

 

18.2.5.1On-site infrastructure

 

The on-site infrastructure costs consist of bulk earthworks, power switchyard and distribution, fuel storage, sewage, potable water, plant and infrastructure buildings, tailings facility and pipelines, temporary construction camp, and site services and mobile equipment. The total on-site infrastructure costs are estimated at US$139 million and are illustrated in Table 18-4.

 

Table 18-4: On-Site Infrastructure Capital Cost Breakdown

 

WBS Description Initial Costs (US$M)
5200 Tailing management Facility 207.8
6100 Site Civil Infrastructure 53.7
6200 Water Systems 6.1
6300 Sewage, Waste and Water Systems 0.3
6400 Electrical Services 78.2
6800 Plant Mobile Equipment 0.9
  Total 347.0

 

Note: Totals may not match due to rounding

 

18.2.5.2Off-Site infrastructure

 

The off-site infrastructure costs consist of water supply and power supply. The cost for the HV substation, step down substation and transmission lines are included as a lease back agreement. 10% downpayment is included as part of the initial capital. The remaining is included as lease payment as described in Section 18.2.8.3.

 

The total off-site infrastructure costs are estimated at US$43 million and are illustrated in Table 18-5.

 

Table 18-5: Off-Site Infrastructure Capital Cost Breakdown

 

WBS Description Initial Costs (US$M)
7300 Rail Spur 22.6
7400 Offsite Power Line 20.3
  Total 42.8

 

Note: Totals may not match due to rounding

 

18.2.6Indirect Capital Costs

 

Indirect costs include project preliminaries, field indirects (temporary construction facilities, camp, and associated services), commissioning and operational readiness, vendor representative support, spares, first fills, and project delivery (engineering services and construction management). Total indirect costs are estimated at US$382 million and are illustrated in Table 18-6.

 

Hycroft Mine Project

Page 242

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 18-6: Indirect Capital Cost Breakdown

 

WBS Description Initial Costs (US$M)
8100 Project Preliminaries 34.2
8200 Temporary Facilities 20.5
8300 Temporary Services 82.2
8500 Cranage 1.6
8600 EPCM Costs 205.5
8700 Commissioning Support 3.6
8800 First Fills/Spares 27.0
8900 Vendor support 7.2
Total Indirect Costs 381.8

 

Note: Totals may not match due to rounding

 

18.2.7Owner (Corporate) Capital Costs

 

Owner costs for pre-production have been estimated by factors. The estimated cost of US$41 million includes:

 

owner’s project team and expenses

 

administration, finance, insurance and legal fees

 

including pre-production general and administrative costs

 

environmental consultation and management

 

human resources, recruiting, and training

 

permitting and regulatory compliance activities

 

stakeholder relations

 

site security.

 

18.2.8Sustaining Capital

 

18.2.8.1Mining Sustaining Costs

 

Down payments, lease payments, and purchases for the mine equipment fleet scheduled throughout the LOM are capitalized through the sustaining periods of the project.

 

Hycroft Mine Project

Page 243

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 18-7 summarizes the mining sustaining cost estimates for the Project.

 

Table 18-7: Mining Sustaining Capital Costs

 

Year Sustaining Capital Cost (US$M)
1 123.3
2 19
3
4 1.5
5 25.6
6 20.2
7 11.9
8 1.5
9 20
10 42.7
15-Nov 50
16-20 44.5
21-25 214.6
26-30 32.4
31-35 74.2
36-40 26.7
41-45 162.2
46-51 30.4
Total 900.7

 

Note: Totals may not match due to rounding

 

18.2.8.2Process Sustaining Costs

 

The sustaining costs for the process plant are associated with the refurbishment and maintenance required for the process plant equipment incurred every five years from Year 20 to Year 45. The total sustaining capital cost is estimated at US$892 million.

 

18.2.8.3Infrastructure Sustaining Costs

 

The sustaining capital costs for the on-site infrastructure are associated with the staged expansion of the TMF in Years 3, 8, 13, 22, 31, and 43. These costs also include EPCM and contingency costs associated with the construction of the TMF. The total sustaining capital cost is estimated at US$678 million.

 

The sustaining capital costs for the off-site infrastructure are associated with the lease payments for the HV substation, step down substation and transmission lines. Total lease payments of US$18.3 million/year at 8% interest rate are included for 20 years as sustaining costs.

 

Hycroft Mine Project

Page 244

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18.2.9Contingency Costs

 

Contingency costs account for the difference in costs between the estimated and actual cost of materials and equipment. The contingency is developed based upon the level of study and considers the level of project definition, the source or methodology of the estimates, and the expected accuracy range. It allows the capital estimate to include a provision to cover the risk from uncertainties that may arise in between the time the capital cost was developed compared to the actual costs during construction and pre-production.

 

The contingency for the Project has been built up by considering each individual WBS area. The contingency included in the initial capital costs is estimated at US$448 million for the process plant and supporting infrastructure and US$45 million for mining. The total contingency for the initial capital costs for the project is estimated at US$493 million or 25.6% of total direct and indirect costs. The contingency of 25.6% reflects the current level of engineering definition and remaining uncertainty associated with process development, infrastructure assumptions, and estimate maturity at the Initial Assessment stage. No adjustment was made solely to meeting a reporting threshold.

 

18.2.10Closure and Reclamation Planning

 

Closure and reclamation costs for the Project include allocations for:

 

process plant and on-site infrastructure

 

TMF, WRSF and Water Management

 

mining and haul roads

 

long-term environmental monitoring.

 

The total closure and reclamation costs are estimated at US$243 million.

 

18.3Operating Costs

 

18.3.1Overview

 

The operating cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The total operating costs for the Project are estimated at US$21.96/ton processed (milled and heap leached) or US$27,592 million over the 51-year mine life. These operating costs do not include pre-production operating costs. A summary of operating costs is presented in Table 18-8.

 

Hycroft Mine Project

Page 245

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 18-8: Operating Cost Summary

 

Cost Area LOM Total (US$M)1 US$/ton processed % of Total
Mining 8,6832 6.91 31.5
Process 18,245 14.52 66.1
G&A 664 0.53 2.4
Total 27,592 21.96 100

 

Note:

 

1.Totals may not match due to rounding

 

2.Includes 10% contingency

 

18.3.2Basis of Estimate

 

The following was used to determine the project’s LOM process operating costs in agreement with the cost definition and estimate methodologies outlined below. This basis considers the development of a process plant designed to treat 57,100 t/d of mineralized material. Process unit operations were benchmarked against similar or comparable processing plants to ensure accuracy of cost estimates.

 

Assumptions made in developing the process operating cost estimate are listed below:

 

Mill production is designed to treat 57,100 t/d of mineralized material.

 

Process plant operating costs are calculated based on labor, power consumption, reagents, consumables, and process plant maintenance.

 

Off-site gold refining, insurance, and transportation costs are excluded, as they are included elsewhere in the financial model.

 

Labor rates were sourced from recent execution projects in the region.

 

Workforce will be comprised of local and regional workers.

 

Management and administrative staff will be on a 5/2 rotation (5 days in, 2 days out), whereas process plant labor was estimated based on continuous operation using a four-crew rotation.

 

G&A costs were baselined against previous project experience.

 

Grinding media consumption rates have been estimated based on the mill feed characteristics.

 

Reagent consumption rates have been estimated based on the metallurgical testwork results.

 

Reagents and consumable prices were obtained via email quotes from local vendors.

 

The unit rate power cost of US$0.075/kWh was adopted based on the NV Energy GS-3 tariff.

 

Hycroft Mine Project

Page 246

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The unit rate fuel cost for gasoline is US$4.28/gal based on the regional monthly three-year trailing average for Nevada.

 

The Basis of Estimate Costs for mining are described in section 18.3.3.

 

18.3.3Mine Operating Costs

 

Table 18-9 illustrates the mine operating costs on an annual basis for the first 10 years of the mine life. After Year 10, the costs have been calculated over five-year periods. Operating costs were developed using a cost of diesel fuel of US$3.76/gal. Consumables for lubricants, spare parts, and wear items have all been incorporated into the estimated operating costs. Labor costs were illustrated in the manpower tables in Section 13.

 

Mine operating costs include:

 

drilling, blasting, loading, hauling, and support equipment costs for the mine operation

 

delivery of material to the crusher, waste storage, or leach pad and placement of that material on the dump, stockpile, or leach pad

 

construction and maintenance of all mine roads where mine haul trucks operate

 

mine supervision, engineering, and geology personnel

 

operating labor and maintenance labor including burden

 

maintenance of all mine equipment

 

an allowance is included to cover pit dewatering, software licenses, and assaying

 

blasting costs are based on owner loading of blast holes and blasting.

 

Mine operating costs do not include:

 

crushing, conveying, processing, recontouring, or reclamation costs

 

remining of the low-grade stockpile after mine closure in Year 51

 

closure or reclamation costs.

 

Remining of the low-grade stockpile and haulage to the crusher after completion of the mine life would cost $1.04/ton of stockpile moved.

 

Table 18-9 provides more detail regarding the breakdown of mine operating costs on a cost per ton of material moved basis for the individual unit operations excluding contingency.

 

Hycroft Mine Project

Page 247

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 18-9: Mine Operating Cost per Ton of Total Material Moved, US$/ton (Mine Costs)

 

Mining

Year

Total

Material

(Mtons)

Drilling

(US$/ton)

Blasting

(US$/ton)

Loading

(US$/ton)

Hauling

(US$/ton)

Auxiliary

(US$/ton)

General

Mine

(US$/ton)

General

Maint.

(US$/ton)

G&A

(US$/ton)

TOTAL

(US$/ton)

Total

Cost

(US$M)

Preproduction 11.3 0.152 0.251 0.264 0.742 1.000 0.187 0.126 0.577 3.300 37.4
1 71.2 0.148 0.177 0.257 0.684 0.332 0.051 0.061 0.117 1.826 130.0
2 71.2 0.148 0.177 0.257 0.802 0.332 0.051 0.062 0.119 1.947 138.6
3 71.2 0.147 0.177 0.252 0.711 0.331 0.051 0.061 0.117 1.846 131.4
4 74.3 0.149 0.176 0.257 0.803 0.318 0.050 0.061 0.111 1.924 143.0
5 81.5 0.148 0.175 0.255 0.848 0.290 0.047 0.058 0.104 1.925 156.9
6 81.5 0.148 0.175 0.255 0.806 0.289 0.047 0.058 0.103 1.882 153.4
7 81.5 0.149 0.175 0.257 0.783 0.289 0.047 0.058 0.103 1.861 151.6
8 81.5 0.149 0.175 0.257 0.856 0.289 0.047 0.058 0.104 1.936 157.8
9 82.0 0.149 0.175 0.260 0.907 0.288 0.047 0.059 0.105 1.990 163.1
10 82.0 0.149 0.175 0.259 0.772 0.288 0.047 0.058 0.102 1.851 151.7
11-15 410.0 0.149 0.175 0.258 0.915 0.282 0.047 0.059 0.105 1.990 815.8
16-20 410.0 0.149 0.175 0.258 0.944 0.283 0.047 0.060 0.106 2.020 828.3
21-25 410.0 0.149 0.175 0.258 1.108 0.282 0.047 0.061 0.109 2.188 897.2
26-30 386.0 0.149 0.175 0.260 0.974 0.300 0.048 0.061 0.111 2.079 802.5
31-35 378.0 0.150 0.176 0.262 0.815 0.308 0.049 0.061 0.110 1.929 729.2
36-40 361.0 0.149 0.176 0.260 0.939 0.321 0.050 0.063 0.116 2.074 749.8
41-45 352.0 0.149 0.177 0.259 1.015 0.329 0.050 0.065 0.120 2.165 763.4
46-51 319.5 0.149 0.180 0.260 1.379 0.353 0.056 0.075 0.146 2.597 8298
Total or Avg 3,816.9 0.149 0.176 0.259 0.961 0.307 0.049 0.062 0.115 2.078 7,931.1

 

Note: Totals may not match due to rounding

 

18.3.4Process Operating Costs

 

The LOM average process operating cost was estimated at US$16.65/ton for process plant and US$2.49/ton for heap leach operation (oxide and transition material). Table 18-10 summarizes the LOM operating costs expected for the process area.

 

Table 18-10: Process Plant Operating Cost Summary

 

Cost Center M US$/a US$/ton (LOM Average)
Reagents 177 8.61
Consumables 51 2.47
Plant Maintenance 21 1.03
Mobile Equipment 2 0.09

 

Hycroft Mine Project

Page 248

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Cost Center M US$/a US$/ton (LOM Average)
Power 76 3.66
Labor 16 0.80
Total (LOM) - Plant Feed 342 16.65
Reagents and Consumables 17 2.05
Mobile Equipment 2 0.26
Labor 2 0.19
Total (LOM) - Heap Leach Feed 20 2.49
Total (LOM) – Combined Processed 362 14.52

 

18.3.4.1Labor

 

Process labor costs were derived from a staffing plan and applying prevailing hourly or annual labor rates in the area. The burden rates of 40% are included for salaried personnel and hourly personnel.

 

The staffing plan summary and labor costs are shown in Table 18-11 below.

 

Table 18-11: Process Plant Labor Cost Summary

 

Staff Number of personnel Annual Labor Cost (US$M/a) Labor Cost (US$/ton)
Process Plant Administration 6 0.7 0.03
Process Plant Operation 76 7.8 0.37
Process Plant Maintenance 47 5.3 0.26
Technical Services 26 2.7 0.13
Process Plant Sub-Total 155 16.4 0.80
Heap Leach Operation 16 1.5 0.19
Heap Leach Sub-Total 16 1.5 0.19
Total (Process Plant + Heap Leach) 171 17.5 0.56

 

Note: Totals may not match due to rounding

 

The estimated labor costs are US$0.80/ton for process plant and US$0.17/ton for heap leach operation. A total of 171 persons are required for the process plant, process maintenance shop, and heap leach operation.

 

18.3.4.2Electrical Power

 

The LOM average of electrical energy consumption in the process area is estimated to be 1,008 gigawatt-hours per year (GWh/a) or approximately 34.4 kilowatt-hours per ton (kWh/ton) of milled and heap leach material.

 

Electricity will be provided to site at a unit cost of US$0.075/kWh based on the recent operation (2021 to 2023).

 

The unit power cost is estimated at US$3.66/ton processed.

 

Hycroft Mine Project

Page 249

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

18.3.4.3Plant Maintenance

 

An allowance was made to cover the cost of maintenance of all items not specifically identified and the cost of maintenance of the facilities. The allowance was calculated for each project area as a percentage of the tangible equipment cost. The cost for maintenance supplies was estimated at US$1.03/ton processed.

 

18.3.4.4Reagents

 

Individual reagent consumption rates were estimated based on metallurgical testwork results and benchmarking against similar project operations. Budgetary quotations for reagents were obtained from local suppliers where available, with an allowance for freight to site.

 

A summary of process reagent consumption and costs are included in Table 18-12.

 

Table 18-12: Reagent Consumption Summary

 

Item Unit Consumption
Rate (t/Mton plant feed)
Unit Cost
(US$)
Cost
(US$/ton) LOM Average
Flotation
Collector (PAX) 0.43 3,310 1.49
Frother (MIBC) 0.04 3,310 0.14
Sulfuric acid (H2SO4) 0.00 150 0.00
Concentrate Thickening
Flocculant 0.01 3,780 0.05
POX, Neutralization, Concentrate Leach
Quick lime 5.44 280 1.58
Flocculant 0.03 3,780 0.10
Limestone 43.01 82 3.66
Flocculant 0.00 3,780 0.01
Sodium cyanide 0.51 2,644 1.39
CCD & Cyanide Destruction
Flocculant 0.06 3,780 0.22
Sodium Metabisulphite (SMBS) 0.18 1,124 0.21
Copper Sulfate (CuSO4) 0.02 4,100 0.07
Process Services (incl. Oxygen Plant)
Antiscalant 0.022 6,243 0.11
Tailings and Reclaim
Flocculant 0.05 3,780 0.18
Merrill Crowe
Zinc dust 0.03 7,500 0.24
Diatomaceous earth 0.07 650 0.05
Refinery
Borax 0.603 2,373 0.00
Silica 0.303 1,909 0.00
Sodium Nitrate 0.0503 1,920 0.00

 

Hycroft Mine Project

Page 250

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Item Unit Consumption
Rate (t/Mton plant feed)
Unit Cost
(US$)
Cost
(US$/ton) LOM Average
Sodium Carbonate 0.0503 683 0.00
Process Plant Sub-Total - - 8.61
Heap Leach
Quick lime 4.50 280 1.40
Cyanide 0.25 2,644 0.73
Zinc dust 0.01 7,500 0.04
Diatomaceous earth 0.05 650 0.03
Heap Leach Sub-Total - - 2.05
Total (Process Plant + Heap Leach) - - 6.02

 

Note:

 

1.Totals may not match due to rounding

 

2.The unit consumption rate is expressed as L/ton of plant feed.

 

3.The unit consumption rate is expressed as lb/lb precipitate.

 

The cost of reagents was estimated at US$8.61/ton for process plant and US$2.05/ton for heap leach operation.

 

18.3.4.5Consumables

 

Wear material (crusher and grinding mill liners and screen panels) and grinding media were based on industry practice for the crusher and grinding operations. A summary of process consumable consumption and costs are included in Table 18-13.

 

Table 18-13: Process Plant Consumable Consumption Summary

 

Item Consumption Rate Units Unit Cost
(US$’000)
Cost
(US$’000/a)
Cost
(US$/ton) LOM Average
Crushing
Primary gyratory crusher liners 3 units/a 527 1,580 0.08
Secondary crusher liners 6 units/a 253 1,515 0.08
Tertiary crusher liners 6 units/a 253 1,515 0.08
Secondary screen deck panels 16 units/a 57 917 0.05
Tertiary screen deck panels 8 units/a 40 321 0.02
Grinding and Screening
Ball mill media 28,469 ton/a 1.4 39,914 2.11
Ball mill liners 4.0 units/a 913 3,653 0.19
Trash screen deck panels 4.0 units/a 33 131 0.01
Limestone Preparation
Limestone cone crusher liner 2 units/a 21 41 0.00
Limestone ball mill media 570 ton/a 1.4 800 0.04
Limestone ball mill liner 1.0 units/a 105 105 0.01

 

Hycroft Mine Project

Page 251

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Item Consumption Rate Units Unit Cost
(US$’000)
Cost
(US$’000/a)
Cost
(US$/ton) LOM Average
Trash screen deck panels 2 units/a 7.2 14 0.00
Refinery
Crucibles 12 units/a 1.9 23 0.00
Miscellaneous consumables (filter cloths, bullion boxes, seals, labels) - allowance - - 40 40 0.00
Refinery
Miscellaneous consumables (filter cloths, bullion boxes, seals, labels) - allowance - - 1,000 1,000 0.05
Total - - - - 2.47

 

The cost of consumables was estimated at US$2.47/ton for process plant.

 

18.3.5General and Administrative Operating Costs

 

The annual general and administrative costs to support the mining operations of US$13 million were developed on a unit cost and quantity basis and utilized data from similar project operating records.

 

G&A costs include expenses associated with site management, administrative support, and general site services required to sustain plant operations but not directly related to mineral processing activities. These costs cover site maintenance (e.g., road maintenance materials), human resources functions such as recruiting and training, health and safety programs, environmental monitoring and compliance, information technology and communications services, and general mobile support equipment. Additional G&A components include contracted services, insurance, permitting and licensing fees, sanitation and waste management, snow removal, accommodation and travel costs, and general office administration such as utilities, office supplies, postage, and audit services. These expenditures represent the overhead required to maintain safe, compliant, and efficient site operations.

 

These costs include G&A labor, such as site management, administrative staff, human resources personnel, health and safety staff, environmental personnel, and other support functions.

 

Hycroft Mine Project

Page 252

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

19Economic Analysis

 

19.1Overview

 

The results of the economic analysis discussed in this section represent forward-looking information as defined under U.S. securities law. The results depend on inputs that are subject to a number of known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those presented here.

 

Information that is forward-looking include:

 

Mineral Resource Estimate
  
assumed commodity prices and exchange rates
  
the proposed mine production plan
  
projected mining and process recovery rates
  
assumptions as to mining dilution
  
capital and operating cost estimates and working capital requirements
  
assumptions as to closure costs and closure requirements
  
assumptions as to environmental, permitting and social consideration and risks.

 

Additional risks to the forward-looking information include:

 

changes to costs of production from what is assumed
  
unrecognized environmental risks
  
unanticipated reclamation expenses
  
unexpected variations in quantity of mineralized material, grade or recovery rates
  
geotechnical or hydrogeological considerations differing from what was assumed
  
failure of mining methods to operate as anticipated
  
failure of plant, equipment or processes to operate as anticipated
  
changes to assumptions as to the availability of electrical power, and the power rates used in the operating cost estimates and financial analysis
  
ability to maintain the social license to operate
  
accidents, labor disputes and other risks of the mining industry
  
changes to interest rates
  
changes to tax rates and availability of allowances for depreciation and amortization.

 

Hycroft Mine Project

Page 253

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

This economic assessment is preliminary in nature and there is no certainty that the economic assessment will be realized. However, the economic assessment does not include any inferred mineral resources.

 

19.2Methodologies Used

 

The project has been evaluated using a discounted cash flow (DCF) analysis based on a 5% discount rate. Cash inflows consist of annual revenue projections. Cash outflows consist of capital expenditures, including pre-production costs, operating costs, taxes, and royalties. These are subtracted from the inflows to arrive at the annual cash flow projections. Cash flows are taken to occur at the midpoint of each period.

 

It must be noted that tax calculations involve complex variables that can only be accurately determined during operations, and as such, the actual post-tax results may differ from those estimated. A sensitivity analysis was performed to assess the impact of variations in metals price, discount rate, head grade, recovery, total operating costs, and initial capital costs. The capital and operating cost estimates developed specifically for this project are presented in Section 18 of this report in Q1 2026 US dollars. The economic analysis has been run on a constant dollar basis with no inflation.

 

19.3Financial Model Parameters

 

19.3.1Assumptions

 

The economic analysis was performed assuming the base case silver price of US$48.00/oz and gold price of US$3,600/oz. The forecasts used are meant to reflect the average metals price expectation over the life of the project. No price inflation or escalation factors were considered. Commodity prices can be volatile, and there is the potential for deviation from the forecast.

 

The economic analysis also used the following assumptions:

 

The construction period will be 24 months.
  
The production life is 51 years, with the last year being a partial year.
  
Cost estimates are in constant Q1 2026 US dollars for capital and operating costs, with no inflation or escalation factors considered.
  
Results are based on 100% ownership with a 2.14% private royalty applying to NSR.
  
Capital costs are funded with 100% equity (no financing assumed).
  
All cash flows are discounted to the start of the construction period using a mid-period discounting convention.
  
All metal products will be sold in the same year they are produced.
  
Project revenue will be derived from the sale of gold-silver doré bars.
  
No contractual arrangement for refining currently exists.

 

19.3.2Taxes

 

Mining Tax Plan LLC has prepared the U.S federal and state income tax computation based on the Internal Revenue Code of 1986, as amended and the regulations thereunder including Nevada Revised Statutes as in effect as of May 1, 2026. Any subsequent changes or modifications to U.S. federal or state tax statutes, regulations or to the judicial and administrative interpretations thereof may impact the federal and state income tax computations. We have not audited or verified any of the economic or operating assumptions of the Preliminary Economic Assessment but have made inquiries to properly classified revenue, expenses and capital expenditures consistent with federal and state income tax statutes, regulations and case law.

 

The following is a summary of tax elections incorporated into this tax computation:

 

The overall effective federal and state income tax rate for Hycroft Mining Holding Corporation is 21% for federal tax purposes. Nevada does not impose income tax.
  
All tax elections have been made in order to maximize the net present value of the mine on an annual basis to the extent allowed.
  
The Hycroft mine will be treated as a single mineral property under Section 614.
  
Hycroft will elect to deduct exploration costs under Section 168(a) and deduct mine development under Section 616(a) subject to the corporate preference adjustment under Section 291(b)(2) to the extent incurred.
  
Hycroft will not elect out of federal Section 168(k) bonus depreciation except for tax year 2028.
  
Hycroft will elect Section 468 to deduct reclamation over the life of the mine.
  
Hycroft will sell its production outside of the U.S. and is therefore eligible for Section 250 FDII deduction available on exported goods.
  
Hycroft’s net operating losses and other tax attributes as of December 31, 2025 of Hycroft utilized in this model are subject to prior Section 382 limitations.
  
No Section 382 ownership changes are expected to occur after December 31, 2025 which could limit the availability of tax attributes during the construction and/or during the subsequent operation of the mine.
  
The Nevada gold and silver excise tax liability has been computed in accordance with the Nevada Revised Statue 363D and the administrative code thereunder. The tax applies on gross revenue in excess of $20,000,000 but not more than $150,000,000, at a rate of 0.75% with an annual exemption on the first $20 million in sales and thereafter sales are tax at a rate of 1.10%.

 

Hycroft Mine Project

Page 254

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

The Nevada Net Proceeds of Mines tax liability has been computed in accordance with the Nevada Revised Statue 362 and the administrative code thereunder. The tax rate applied is 5.0% based on the annual profitability of the Mine.

 

At the assumed metal prices, total payments are estimated to be US$3,618 million over the LOM.

 

19.3.3Royalties

 

Royalties payable for the Hycroft Project include a 2.14% private NSR royalty (1.5% NSR grossed up 30% for withholding taxes). Total royalty payments are US$1,155 million over the life of the mine and are part of the project economics.

 

19.4Economic Analysis

 

The economic analysis was performed assuming a 5% discount rate. The pre-tax NPV discounted at 5% is US$5,437 million; the IRR is 18.9%, and payback period is 4.3 years. On a post-tax basis, the NPV discounted at 5% is US$4,344 million, the IRR is 16.9%, and the payback period is 4.7 years. A summary of project economics is shown graphically in Figure 19-1 and listed in Table 19-1. The analysis was done on an annual cashflow basis; the cashflow output is shown Table 19-2.

 

Readers are cautioned that the assessment is preliminary in nature and there is no certainty that the economic assessment will be realized However, it does not include any inferred mineral resources.

 

Figure 19-1 : Project Post-Tax Unlevered Cashflow

 

 

Source: Ausenco, 2026

 

Hycroft Mine Project

Page 255

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 19-1: Economic Analysis Summary Table

 

  Unit Value
General Inputs
Gold Price USD$/oz 3,600
Silver Price USD$/oz 48.00
Discount Rate % 5.0
LOM Production
Total Mineralized Material Mined kst 1,496,134
Total Waste Mined kst 2,320,719
Average Strip Ratio w:o 1.55
Life of Mine years 50.5
Total Mill Feed Processed kst 1,046,284
Average Mill Feed Grade (Au) oz/st 0.012
Average Mill Feed Grade (Ag) oz/st 0.43
Total Leach Material Processed kst 210,010
Average Leach Feed Grade (Au) oz/st 0.005
Average Leach Feed Grade (Ag) oz/st 0.12
Total Recovered Gold koz 10,476
Total Recovered Silver koz 349,208
Average Mill Feed Gold Recovery % 82.8
Average Mill Feed Silver Recovery % 77.5
Average Leach Gold Recovery % 40.0
Average Leach Silver Recovery % 12.0
Life of Mine Payable Gold Production koz 10,424
Life of Mine Payable Silver Production koz 347,462
Life of Mine Payable Gold Equivalent Production koz 15,057
Refining, Royalties
Gold Payable % 99.5
Silver Payable % 99.5
NSR Royalty % NSR 2.14
Refining Costs – Au US$/oz 5.00
Refining Costs – Ag US$/oz 0.50
LOM Operating Costs
Mining Cost US$/st mined 2.28
Mining Cost US$/st processed 6.91
Processing Cost US$/st processed 14.52
G&A Cost US$/st processed 0.53
Total Operating Cost US$/st processed 21.96
Cash Costs1 US$/oz AuEq 1,924
All-In Sustaining Cost2 US$/oz AuEq 2,147
Capital Costs
Initial Capital US$M 2,434
Sustaining Capital US$M 3,107
Closure Costs US$M 243
Financials
Pre-Tax NPV (5%) US$M 5,437
Pre-Tax IRR % 18.9
Pre-Tax Payback years 4.3
Post-Tax NPV (5%) US$M 4,344
Post-Tax IRR % 16.9
Post-Tax Payback years 4.7

 

Notes:

 

1.Cash costs consist of mining costs, processing costs, mine-level G&A and refining charges and royalties.
2.AISC includes cash costs plus sustaining capital and closure costs.

 

Hycroft Mine Project

Page 256

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 19-2 : Life of Mine Economics

 

  Units Total/Avg -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Free Cash Flow
Revenue US$M 54,205 22 878 1,119 1,573 1,431 1,303 1,325 1,240 1,102 937 971 906 969 1,165 965 1,008 935 830 914 855 796 998 1,517 1,503 1,692 1,509 1,374
Operating Cost US$M (27,592) (18) (444) (563) (592) (591) (639) (601) (556) (555) (543) (541) (574) (566) (584) (562) (575) (568) (590) (598) (567) (533) (541) (540) (530) (541) (580) (547)
Refining Charges US$M (226) (0) (2) (4) (6) (6) (5) (5) (5) (3) (3) (4) (4) (4) (5) (4) (4) (4) (3) (4) (3) (3) (4) (6) (7) (10) (8) (6)
Royalties US$M (1,155) (0) (19) (24) (34) (30) (28) (28) (26) (24) (20) (21) (19) (21) (25) (21) (21) (20) (18) (19) (18) (17) (21) (32) (32) (36) (32) (29)
EBITDA US$M 25,232 3 413 528 942 803 631 691 652 520 370 405 309 378 551 378 408 343 219 292 266 243 431 939 934 1,106 889 791
Initial Capex US$M (2,434) (672) (1,762)
Sustaining Capex US$M (3,107) (179) (180) (18) (20) (52) (45) (131) (20) (44) (74) (31) (140) (31) (31) (31) (30) (30) (30) (30) (179) (155) (56) (56) (56) (204) (8)
Closure Capex US$M (243)
Changes in Working Capital US$M (1) (35) (10) (19) 6 5 (1) 3 6 7 (1) 3 (3) (8) 8 (2) 3 4 (3) 2 2 (8) (21) 1 (8) 8 6
Pre-Tax Unlevered Free Cash Flow US$M 19,447 (672) (1,760) 199 338 905 788 585 646 525 506 333 330 280 236 512 355 375 316 194 259 238 67 268 862 879 1,043 692 788
Pre-Tax Cumulative Unlevered Free Cash Flow US$M 19,447 (672) (2,432) (2,233) (1,895) (989) (201) 384 1,030 1,554 2,060 2,393 2,723 3,003 3,239 3,751 4,107 4,481 4,798 4,991 5,250 5,489 5,556 5,824 6,686 7,564 8,607 9,299 10,087
Tax Payable US$M (3,618) (0) (9) (27) (38) (69) (67) (70) (78) (76) (81) (53) (54) (45) (48) (85) (57) (61) (49) (31) (41) (36) (25) (64) (156) (157) (184) (124)
Post-Tax Unlevered Free Cash Flow US$M 15,829 (672) (1,760) 190 311 867 719 518 576 447 430 252 277 226 191 464 270 318 256 144 228 198 31 243 798 723 885 508 664
Post-Tax Cumulative Unlevered Free Cash Flow US$M 15,829 (672) (2,432) (2,242) (1,931) (1,063) (344) 174 750 1,197 1,627 1,878 2,156 2,382 2,573 3,037 3,307 3,625 3,880 4,025 4,253 4,451 4,482 4,725 5,523 6,245 7,131 7,639 8,302
Production
Total Resource Mined kton 1,496,134 2,462 25,898 28,882 53,915 46,012 50,111 47,788 40,873 38,365 23,852 26,046 35,948 36,182 37,057 30,048 32,398 28,549 27,237 39,479 37,432 32,344 33,003 33,513 29,128 31,589 35,565 27,504
Total Waste Mined kton 2,320,719 8,871 45,302 42,318 17,285 28,335 31,389 33,712 40,627 43,135 58,149 55,954 46,052 45,818 44,943 51,952 49,602 53,451 54,763 42,521 44,568 49,656 48,997 48,487 52,872 50,411 46,435 54,496
Strip Ratio w:o 1.55 3.60 1.75 1.47 0.32 0.62 0.63 0.71 0.99 1.12 2.44 2.15 1.28 1.27 1.21 1.73 1.53 1.87 2.01 1.08 1.19 1.54 1.48 1.45 1.82 1.60 1.31 1.98
Mill Feed kton 1,046,284 14,068 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841
Mill Head Grade (Au) oz/ton 0.012 0.016 0.013 0.016 0.015 0.014 0.014 0.013 0.014 0.012 0.011 0.009 0.010 0.011 0.011 0.011 0.010 0.009 0.010 0.010 0.010 0.012 0.018 0.015 0.014 0.012 0.014
Mill Head Grade (Ag) oz/ton 0.43 0.21 0.35 0.52 0.53 0.43 0.43 0.52 0.25 0.23 0.34 0.37 0.37 0.52 0.35 0.31 0.36 0.31 0.32 0.26 0.25 0.34 0.51 0.72 1.04 0.83 0.58
Mill Recovery (Au) % 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8
Mill Recovery (Ag) % 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5
Heap Leach Feed kton 210,010 2,462 10,825 5,740 17,228 14,623 16,614 14,813 6,350 3,376 107 2,840 8,654 6,052 8,301 511 11,056 5,116 4,817 4,907 2,201 126 388 2,900 4,704 9,451 12,335 4,375
Heap Leach Head Grade (Au) oz/ton 0.005 0.006 0.006 0.005 0.007 0.005 0.005 0.006 0.005 0.006 0.004 0.003 0.004 0.004 0.005 0.005 0.005 0.004 0.005 0.005 0.004 0.005 0.004 0.004 0.003 0.004 0.005 0.005
Heap Leach Head Grade (Ag) oz/ton 0.12 0.13 0.13 0.09 0.09 0.16 0.08 0.17 0.18 0.14 0.06 0.08 0.13 0.10 0.11 0.18 0.08 0.11 0.14 0.14 0.11 0.12 0.11 0.15 0.10 0.12 0.15 0.16
Heap Leach Recovery (Au) % 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0
Heap Leach Recovery (Ag) % 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0
Payable Gold koz 10,424 6 211 236 324 280 268 272 230 252 211 197 170 188 211 193 212 182 162 184 181 169 204 312 264 246 238 256
Payable Silver koz 347,462 39 2,455 5,639 8,474 8,801 7,041 7,209 8,556 4,040 3,725 5,450 6,154 6,071 8,425 5,601 5,092 5,843 5,129 5,209 4,221 3,947 5,503 8,235 11,546 16,806 13,600 9,426
Payable Gold Equivalent koz 15,057 6 244 311 437 397 362 368 345 306 260 270 252 269 324 268 280 260 231 254 237 221 277 422 417 470 419 382
Revenue US$M 54,205 22 878 1,119 1,573 1,431 1,303 1,325 1,240 1,102 937 971 906 969 1,165 965 1,008 935 830 914 855 796 998 1,517 1,503 1,692 1,509 1,374
Operating Costs
Total Operating Costs US$M 27,592 18 444 563 592 591 639 601 556 555 543 541 574 566 584 562 575 568 590 598 567 533 541 540 530 541 580 547
Mine Operating Costs US$M 8,683 143 152 145 157 173 169 167 174 179 167 179 179 179 179 179 182 182 182 182 182 197 197 197 197 197 177
Processing Costs US$M 18,245 11 288 397 434 421 453 418 376 369 351 361 382 374 391 370 382 373 394 403 372 338 331 330 320 330 370 358
G&A Costs US$M 664 7 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13

 

Hycroft Mine Project

Page 257

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

  Units Total/Avg -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Refining Costs & Royalties
Refining Charge US$M 226 0 2 4 6 6 5 5 5 3 3 4 4 4 5 4 4 4 3 4 3 3 4 6 7 10 8 6
Total Revenue US$M 54,205 22 878 1,119 1,573 1,431 1,303 1,325 1,240 1,102 937 971 906 969 1,165 965 1,008 935 830 914 855 796 998 1,517 1,503 1,692 1,509 1,374
Less: Refining Costs US$M (226) (0) (2) (4) (6) (6) (5) (5) (5) (3) (3) (4) (4) (4) (5) (4) (4) (4) (3) (4) (3) (3) (4) (6) (7) (10) (8) (6)
Total Net Revenue US$M 53,979 22 876 1,115 1,567 1,425 1,298 1,320 1,235 1,099 934 967 902 965 1,160 961 1,004 931 826 910 852 793 994 1,512 1,496 1,683 1,501 1,368
NSR Royalty % 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14
Royalties US$M 1,155 0 19 24 34 30 28 28 26 24 20 21 19 21 25 21 21 20 18 19 18 17 21 32 32 36 32 29
Cash Costs
Cash Cost1 US$/oz AuEq 1,924 3,066 1,907 1,901 1,444 1,580 1,855 1,722 1,706 1,901 2,176 2,097 2,373 2,195 1,897 2,188 2,144 2,279 2,649 2,448 2,480 2,499 2,043 1,372 1,363 1,247 1,480 1,527
All-in Sustaining Cost (AISC 2) US$/oz AuEq 2,147 3,066 2,639 2,480 1,486 1,631 1,998 1,843 2,088 1,967 2,346 2,371 2,497 2,714 1,993 2,305 2,255 2,394 2,779 2,566 2,606 3,307 2,603 1,505 1,497 1,366 1,968 1,549
Capital Expenditures
Initial Capital US$M 2,434 672 1,762
Total Sustaining Capital US$M 3,107 179 180 18 20 52 45 131 20 44 74 31 140 31 31 31 30 30 30 30 179 155 56 56 56 204 8
Closure Cost US$M 243
Total Capital Expenditures US$M 5,785 672 1,762 179 180 18 20 52 45 131 20 44 74 31 140 31 31 31 30 30 30 30 179 155 56 56 56 204 8

 

  Units 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
Free Cash Flow
Revenue US$M 1,361 1,443 885 804 858 797 781 832 839 868 1,117 1,088 1,085 1,148 1,353 860 790 781 744 734 909 1,052 1,034 1,365 839
Operating Cost US$M (535) (531) (549) (539) (527) (524) (521) (522) (528) (543) (554) (557) (524) (508) (514) (527) (526) (531) (549) (516) (511) (508) (500) (482) (323)
Refining Charges US$M (8) (10) (3) (3) (2) (2) (2) (2) (2) (3) (5) (5) (5) (6) (8) (3) (2) (2) (2) (2) (3) (4) (4) (8) (5)
Royalties US$M (29) (31) (19) (17) (18) (17) (17) (18) (18) (19) (24) (23) (23) (24) (29) (18) (17) (17) (16) (16) (19) (22) (22) (29) (18)
EBITDA US$M 788 871 313 245 310 255 241 290 290 303 535 503 532 610 803 312 244 231 177 200 376 517 508 846 493
Initial Capex US$M
Sustaining Capex US$M (8) (8) (8) (257) (19) (19) (19) (19) (168) (7) (7) (7) (7) (156) (42) (178) (42) (42) (191) (7) (7) (7) (7) (7) (7)
Closure Capex US$M (243)
Changes in Working Capital US$M 1 (3) 23 3 (2) 2 1 (2) (0) (1) (10) 1 0 (3) (8) 20 3 0 2 0 (7) (6) 1 (14) 56
Pre-Tax Unlevered Free Cash Flow US$M 780 859 327 (8) 288 238 222 268 122 295 518 498 526 452 752 154 205 189 (12) 194 362 505 502 825 542 (243)
Pre-Tax Cumulative Unlevered Free Cash Flow US$M 10,867 11,727 12,054 12,046 12,334 12,572 12,794 13,063 13,185 13,480 13,998 14,495 15,021 15,472 16,225 16,378 16,583 16,772 16,760 16,954 17,316 17,821 18,323 19,148 19,691 19,691 19,447
Tax Payable US$M (136) (137) (145) (50) (20) (42) (40) (39) (46) (30) (53) (91) (86) (92) (86) (129) (37) (37) (34) (16) (28) (64) (88) (90) (142) (76)
Post-Tax Unlevered Free Cash Flow US$M 644 723 183 (58) 268 195 182 230 76 265 465 406 439 360 666 24 168 152 (46) 179 333 441 414 736 401 (76) (243)
Post-Tax Cumulative Unlevered Free Cash Flow US$M 8,947 9,669 9,852 9,794 10,062 10,258 10,440 10,670 10,746 11,010 11,475 11,882 12,321 12,681 13,347 13,371 13,539 13,691 13,645 13,824 14,157 14,598 15,012 15,747 16,148 16,072 15,829
Production                                                        
Total Resource Mined kton 31,947 25,705 25,866 23,273 23,941 22,778 22,376 22,505 22,056 29,225 22,808 23,934 23,329 24,785 23,939 24,033 22,658 22,494 23,562 23,102 23,004 22,195 21,703 21,680 12,058
Total Waste Mined kton 50,053 48,295 48,134 50,727 50,059 53,222 53,624 53,495 53,944 46,775 51,192 46,566 47,171 45,715 46,561 46,467 47,842 48,006 47,038 47,498 49,370 33,556 33,706 19,302 12,300
Strip Ratio w:o 1.57 1.88 1.86 2.18 2.09 2.34 2.40 2.38 2.45 1.60 2.24 1.95 2.02 1.84 1.95 1.93 2.11 2.13 2.00 2.06 2.15 1.51 1.55 0.89 1.02
Mill Feed kton 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 20,841 11,008
Mill Head Grade (Au) oz/ton 0.010 0.009 0.010 0.010 0.011 0.011 0.011 0.011 0.011 0.009 0.012 0.011 0.012 0.010 0.011 0.010 0.011 0.011 0.010 0.010 0.011 0.012 0.011 0.011 0.011
Mill Head Grade (Ag) oz/ton 0.90 1.13 0.32 0.20 0.18 0.16 0.16 0.19 0.19 0.30 0.47 0.53 0.47 0.69 0.85 0.28 0.16 0.16 0.14 0.14 0.29 0.41 0.42 0.89 1.16

 

Hycroft Mine Project

Page 258

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

  Units 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
Mill Recovery (Au) % 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8 82.8
Mill Recovery (Ag) % 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5 77.5
Heap Leach Feed kton 3,916 1,026 1,303 209 1,610 877 734 987 622 7,636 406 1,583 985 1,940 1,612 1,548 66 251 580 351 270 324 114 102 86
Heap Leach Head Grade (Au) oz/ton 0.004 0.005 0.005 0.004 0.004 0.002 0.002 0.004 0.004 0.005 0.004 0.006 0.004 0.004 0.003 0.003 0.004 0.002 0.003 0.004 0.003 0.006 0.005 0.005 0.004
Heap Leach Head Grade (Ag) oz/ton 0.16 0.13 0.10 0.09 0.06 0.11 0.16 0.17 0.16 0.12 0.14 0.12 0.14 0.13 0.13 0.13 0.08 0.07 0.06 0.11 0.10 0.10 0.15 0.17 0.22
Heap Leach Recovery (Au) % 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0
Heap Leach Recovery (Ag) % 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0
Payable Gold koz 184 159 177 180 199 187 183 191 193 176 209 189 199 171 193 179 184 182 176 174 190 204 197 188 102
Payable Silver koz 14,557 18,152 5,132 3,251 2,974 2,576 2,508 3,042 3,015 4,861 7,568 8,511 7,636 11,133 13,706 4,522 2,646 2,617 2,327 2,242 4,711 6,600 6,790 14,329 9,819
Payable Gold Equivalent koz 378 401 246 223 238 222 217 231 233 241 310 302 301 319 376 239 219 217 207 204 253 292 287 379 233
Revenue US$M 1,361 1,443 885 804 858 797 781 832 839 868 1,117 1,088 1,085 1,148 1,353 860 790 781 744 734 909 1,052 1,034 1,365 839
Operating Costs                                                        
Total Operating Costs US$M 535 531 549 539 527 524 521 522 528 543 554 557 524 508 514 527 526 531 549 516 511 508 500 482 323
Mine Operating Costs US$M 177 177 177 177 160 160 160 160 160 165 165 165 165 165 168 168 168 168 168 152 152 152 152 152 152
Processing Costs US$M 346 342 360 349 354 350 347 349 355 366 376 379 346 330 333 346 346 350 368 351 346 343 335 317 164
G&A Costs US$M 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 7
Refining Costs & Royalties                                                        
Refining Charge US$M 8 10 3 3 2 2 2 2 2 3 5 5 5 6 8 3 2 2 2 2 3 4 4 8 5
Total Revenue US$M 1,361 1,443 885 804 858 797 781 832 839 868 1,117 1,088 1,085 1,148 1,353 860 790 781 744 734 909 1,052 1,034 1,365 839
Less: Refining Costs US$M (8) (10) (3) (3) (2) (2) (2) (2) (2) (3) (5) (5) (5) (6) (8) (3) (2) (2) (2) (2) (3) (4) (4) (8) (5)
Total Net Revenue US$M 1,352 1,433 881 801 855 795 778 830 837 865 1,112 1,083 1,080 1,142 1,346 857 787 779 742 732 906 1,048 1,030 1,357 834
NSR Royalty % 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14
Royalties US$M 29 31 19 17 18 17 17 18 18 19 24 23 23 24 29 18 17 17 16 16 19 22 22 29 18
Cash Costs                                                        
Cash Cost1 US$/oz AuEq 1,515 1,427 2,327 2,501 2,300 2,450 2,489 2,346 2,355 2,343 1,876 1,935 1,833 1,688 1,465 2,296 2,487 2,536 2,742 2,616 2,113 1,830 1,833 1,370 1,485
All-in Sustaining Cost (AISC 2) US$/oz AuEq 1,537 1,448 2,361 3,651 2,381 2,537 2,578 2,430 3,075 2,372 1,898 1,958 1,856 2,176 1,577 3,042 2,679 2,730 3,666 2,649 2,139 1,853 1,856 1,387 1,513
Capital Expenditures                                                        
Initial Capital US$M
Total Sustaining Capital US$M 8 8 8 257 19 19 19 19 168 7 7 7 7 156 42 178 42 42 191 7 7 7 7 7 7
Closure Cost US$M 243
Total Capital Expenditures US$M 8 8 8 257 19 19 19 19 168 7 7 7 7 156 42 178 42 42 191 7 7 7 7 7 7 243

 

Notes:

 

1.Cash costs consist of mining costs, processing costs, mine-level G&A and refining charges and royalties.
2.AISC includes cash costs plus sustaining capital and closure costs.
3.Dollar figures in Real 2026 US$M unless otherwise noted.
4.Total/Avg Column is for the entire LOM, Year -2 to Year 53.

 

Hycroft Mine Project

Page 259

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

19.5Sensitivity Analysis

 

A sensitivity analysis was conducted on the base case NPV and IRR of the project using the following variables: discount rate, head grade, recovery, total operating cost, initial capital cost, as well as silver and gold prices, which were encompassed in a single variable, metal price. Table 19-3 and Table 19-4 summarize the pre-tax and post-tax sensitivities of the project.

 

Table 19-3: Pre-Tax NPV (US$M) and IRR (%) Sensitivity Analysis

 

  Pre-Tax NPV5% Sensitivity to Discount Rate Pre-Tax IRR Sensitivity to Discount Rate
  Metal Price   Metal Price
Discount Rate   (20%) (10%) 0% 10% 20% Discount Rate   (20%) (10%) 0% 10% 20%
1.0% 6,399 10,514 14,629 18,744 22,859 1.0% 9.8 14.5 18.9 23.2 27.3
3.0% 3,391 6,041 8,690 11,340 13,989 3.0% 9.8 14.5 18.9 23.2 27.3
5.0% 1,746 3,591 5,437 7,282 9,127 5.0% 9.8 14.5 18.9 23.2 27.3
8.0% 449 1,650 2,852 4,054 5,256 8.0% 9.8 14.5 18.9 23.2 27.3
10.0% (36) 919 1,874 2,829 3,784 10.0% 9.8 14.5 18.9 23.2 27.3
  Pre-Tax NPV5% Sensitivity to Operating Costs Pre-Tax IRR Sensitivity to Operating Costs
  Metal Price   Metal Price
Operating Costs   (20%) (10%) 0% 10% 20% Operating Costs   (20%) (10%) 0% 10% 20%
(20.0%) 3,639 5,484 7,329 9,175 11,020 (20.0%) 14.5 18.9 23.1 27.2 31.1
(10.0%) 2,693 4,538 6,383 8,228 10,073 (10.0%) 12.2 16.7 21.0 25.2 29.2
1,746 3,591 5,437 7,282 9,127 9.8 14.5 18.9 23.2 27.3
10.0% 800 2,645 4,490 6,336 8,181 10.0% 7.3 12.2 16.7 21.1 25.3
20.0% (146) 1,699 3,544 5,389 7,234 20.0% 4.5 9.8 14.5 19.0 23.3
  Pre-Tax NPV5% Sensitivity to Initial Capital Pre-Tax IRR Sensitivity to Initial Capital
  Metal Price   Metal Price
Initial Capital   (20%) (10%) 0% 10% 20% Initial Capital   (20%) (10%) 0% 10% 20%
(20.0%) 2,208 4,054 5,899 7,744 9,589 (20.0%) 12.5 18.1 23.5 28.6 33.4
(10.0%) 1,977 3,822 5,668 7,513 9,358 (10.0%) 11.0 16.1 21.0 25.6 30.1
1,746 3,591 5,437 7,282 9,127 9.8 14.5 18.9 23.2 27.3
10.0% 1,515 3,360 5,206 7,051 8,896 10.0% 8.8 13.1 17.2 21.2 25.0
20.0% 1,284 3,129 4,975 6,820 8,665 20.0% 8.0 12.0 15.8 19.5 23.0
  Pre-Tax NPV5% Sensitivity to Head Grade Pre-Tax IRR Sensitivity to Head Grade
  Metal Price   Metal Price
Head Grade   (20%) (10%) 0% 10% 20% Head Grade   (20%) (10%) 0% 10% 20%
(20.0%) (1,191) 285 1,761 3,237 4,713 (20.0%) 0.7 5.8 9.9 13.6 17.2
(10.0%) 277 1,938 3,599 5,259 6,920 (10.0%) 5.8 10.3 14.5 18.5 22.4
1,746 3,591 5,437 7,282 9,127 9.8 14.5 18.9 23.2 27.3
10.0% 3,215 5,245 7,275 9,304 11,334 10.0% 13.5 18.5 23.2 27.7 32.0
20.0% 4,684 6,898 9,112 11,327 13,541 20.0% 17.1 22.3 27.3 32.0 36.5
  Pre-Tax NPV5% Sensitivity to Recovery Pre-Tax IRR Sensitivity to Recovery
  Metal Price   Metal Price
Recovery   (20%) (10%) 0% 10% 20% Recovery   (20%) (10%) 0% 10% 20%
(20.0%) (1,191) 285 1,761 3,237 4,713 (20.0%) 0.7 5.8 9.9 13.6 17.2
(10.0%) 277 1,938 3,599 5,259 6,920 (10.0%) 5.8 10.3 14.5 18.5 22.4
1,746 3,591 5,437 7,282 9,127 9.8 14.5 18.9 23.2 27.3
10.0% 3,215 5,245 7,275 9,304 11,334 10.0% 13.5 18.5 23.2 27.7 32.0
20.0% 4,684 6,898 9,112 11,327 13,541 20.0% 17.1 22.3 27.3 32.0 36.5

 

Hycroft Mine Project

Page 260

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 19-4: Post-Tax NPV (US$M) and IRR (%) Sensitivity Analysis

 

  Post-Tax NPV5% Sensitivity to Discount Rate Post-Tax IRR Sensitivity to Discount Rate
  Metal Price   Metal Price
Discount Rate   (20%) (10%) 0% 10% 20% Discount Rate   (20%) (10%) 0% 10% 20%
1.0% 5,042 8,472 11,896 15,306 18,708 1.0% 8.6 12.9 16.9 20.8 24.6
3.0% 2,584 4,809 7,027 9,233 11,433 3.0% 8.6 12.9 16.9 20.8 24.6
5.0% 1,226 2,790 4,344 5,887 7,426 5.0% 8.6 12.9 16.9 20.8 24.6
8.0% 144 1,176 2,197 3,209 4,217 8.0% 8.6 12.9 16.9 20.8 24.6
10.0% (264) 563 1,379 2,187 2,991 10.0% 8.6 12.9 16.9 20.8 24.6
  Post-Tax NPV5% Sensitivity to Operating Costs Post-Tax IRR Sensitivity to Operating Costs
  Metal Price   Metal Price
Operating Costs   (20%) (10%) 0% 10% 20% Operating Costs   (20%) (10%) 0% 10% 20%
(20.0%)  2,850 4,399 5,941 7,477 9,009 (20.0%) 12.9 17.0 20.8 24.5 28.2
(10.0%) 2,042 3,598 5,143 6,684 8,219 (10.0%) 10.8 15.0 18.9 22.7 26.4
1,226  2,790  4,344  5,887  7,426 8.6 12.9 16.9 20.8 24.6
10.0% 394 1,978 3,537  5,088  6,630 10.0% 6.2 10.7 14.9 18.9 22.7
20.0% (456) 1,160 2,725  4,283 5,831 20.0% 3.5 8.5 12.8 16.9 20.9
  Post-Tax NPV5% Sensitivity to Initial Capital Post-Tax IRR Sensitivity to Initial Capital
  Metal Price   Metal Price
Initial Capital   (20%) (10%) 0% 10% 20% Initial Capital   (20%) (10%) 0% 10% 20%
(20.0%)  1,644  3,204  4,754  6,294  7,830 (20.0%) 10.9 16.1 21.0 25.7 30.1
(10.0%)  1,436  2,997  4,549  6,091  7,628 (10.0%) 9.7 14.3 18.8 23.0 27.1
 1,226  2,790  4,344  5,887  7,426 8.6 12.9 16.9 20.8 24.6
10.0%  1,015  2,582  4,137  5,682  7,223 10.0% 7.7 11.7 15.4 19.0 22.5
20.0%  802  2,375  3,929  5,477  7,019 20.0% 7.0 10.7 14.1 17.5 20.7
  Post-Tax NPV5% Sensitivity to Head Grade Post-Tax IRR Sensitivity to Head Grade
  Metal Price   Metal Price
Head Grade   (20%) (10%) 0% 10% 20% Head Grade   (20%) (10%) 0% 10% 20%
(20.0%) (1,405) (43) 1,239 2,490 3,736 (20.0%) 0.0 4.9 8.7 12.1 15.4
(10.0%) (50) 1,390 2,796 4,195 5,585 (10.0%) 4.8 9.1 12.9 16.6 20.1
1,226 2,790 4,344 5,887 7,426 8.6 12.9 16.9 20.8 24.6
10.0% 2,472 4,183 5,881 7,573 9,260 10.0% 12.0 16.5 20.8 24.9 28.9
20.0% 3,711 5,567 7,414 9,254 11,087 20.0% 15.3 20.0 24.6 28.9 33.1
  Post-Tax NPV5% Sensitivity to Recovery Post-Tax IRR Sensitivity to Recovery
  Metal Price   Metal Price
Recovery   (20%) (10%) 0% 10% 20% Recovery   (20%) (10%) 0% 10% 20%
(20.0%) (1,405) (43) 1,239 2,490 3,736 (20.0%) 0.0 4.9 8.7 12.1 15.4
(10.0%) (50) 1,390 2,796 4,195 5,585 (10.0%) 4.8 9.1 12.9 16.6 20.1
1,226 2,790 4,344 5,887 7,426 8.6 12.9 16.9 20.8 24.6
10.0% 2,472 4,183 5,881 7,573 9,260 10.0% 12.0 16.5 20.8 24.9 28.9
20.0% 3,711 5,567 7,414 9,254 11,087 20.0% 15.3 20.0 24.6 28.9 33.1
                                     

 

Hycroft Mine Project

Page 261

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

As shown in Figure 19-2 and Figure 19-3, the sensitivity analysis revealed that the project is most sensitive to changes in metal price, head grade, and recovery.

 

Figure 19-2: Pre-Tax Sensitivity Analysis Results

 

 

 

Note: Metal price, head grade, and recovery series overlap on the above figures

 

Hycroft Mine Project

Page 262

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Figure 19-3: Post-Tax Sensitivity Analysis Results

 

 

 

Note: Metal price, head grade, and recovery series overlap on the above figures. Source: Ausenco, 2026

 

Hycroft Mine Project

Page 263

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

20Adjacent Properties

 

The Rosebud mine is located about 4.7 miles south-east of the Mine (Figure 20-1). Rosebud was operated as an underground stope mine between 1997 and 2000 by a joint venture between Hecla and Newmont. Additional details are available online at mindat.org. Information disclosed at this site has not been verified by a Qualified Person and may not necessarily indicative of the mineralization at Hycroft, which is the subject of this Technical Report.

 

Figure 20-1 : Location of Rosebud Property

 

 

Source: Hycroft, 2023

 

The deposit is part of a large, low-sulfidation hydrothermal system extending throughout most of the Kamma Mountains. Specifically, the deposit is a low-temperature epithermal, quartz-sericite, gold and silver deposit within Miocene andesitic and rhyolitic volcanics and volcaniclastics. The volcanics unconformably overlie a Jurassic/Triassic metasediment basement, which also hosts precious metal mineralization.

 

Main structural elements include the east-west trending South Ridge Fault and the northeast trending Rosebud Shear, which displays up to 2,000 ft of left-lateral displacement and about 400 ft of normal displacement. The South Ridge Fault is a mineralized listric normal fault which acted as a conduit for mineralizing fluids.

 

The mining method was overhand cut and fill with access via a decline. Equipment was rubber-tired, including drill jumbos, rock bolters, 3.5-yard loaders, and 20-ton haul trucks. Typical ore panels were 14 ft high, 18 ft wide and about 80 ft long. These were backfilled with cemented materials batched at the surface and hauled underground.

 

Ore was direct shipped to the Carlin district for processing.

 

The QP has been unable to verify the information in this section, and the information is not necessarily indicative of the mineralization on the property that is the subject of the technical report summary.

 

21Other Relevant Data and Information

 

There is no information in this section of the TRS.

  

Hycroft Mine Project

Page 264

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

22Interpretation and Conclusions

 

22.1Introduction

 

The QPs note the following interpretations and conclusions in their respective areas of expertise, based on the review of data available for this Report.

 

22.2Mineral Tenure, Surface Rights, Water Rights, Royalties and Agreements

 

Hycroft controls all surface and mineral rights within the Hycroft MRE area. No further land acquisition is required for the operation of the mine and contemplated processing facilities.

 

22.3Geology and Mineralization

 

The Hycroft deposit is a low-sulfidation, epithermal, hot springs system that contains gold and silver mineralization. Radiometric dating of adularia (potassium feldspar) indicates that the main phase of gold and silver mineralization formed approximately four million years ago (Ebert and Rye, 1997) when hydrothermal fluids were fed upward along high angle, normal faults. Low-grade gold and silver mineralization were co-deposited with silica and potassium feldspar throughout porous rock types.

 

22.4Exploration

 

The exploration drilling, sample preparation, analysis and security are typical for the US mining industry and is acceptable for application to mineral resource determination.

 

Within the block model, there are 5,813 drillholes with 516,901 drill intervals amounting to 2,668,616 ft of drilling. The work outlined is a summary of over a year’s worth of data verification and checking by Hycroft and IMC personnel. As a result, the Hycroft and IMC teams have gained significant confidence in this data set. IMC holds the opinion that the database as utilized in this statement of mineral resources inclusive the edits and corrections outlined is appropriate for the estimation of mineral resources.

 

The QP considers that exploration drilling, sampling, sample preparation, analytical methods and security are acceptable, are in line with industry-standard practices, and are adequate for mineral resource determination.

 

Hycroft Mine Project

Page 265

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

22.5Metallurgical Testwork

 

Metallurgical testwork has been conducted at multiple accredited laboratories with the following results:

 

The mineralized material at Hycroft is considered very abrasive.
  
The mineralized material at Hycroft is considered hard with respect to grinding.
  
Silver recovery decreases at low pH ranges (<5.0) during oxidation, indicating the need for a lime boil step following POX.
  
Oxygen consumption in POX circuit is primarily a function of the sulfide sulfur content of the concentrate. To achieve approximately 95% sulfide oxidation, about 0.19 ton of oxygen per ton of concentrate is required.
  
Metallurgical testwork completed between 2021 and 2025 confirms that Hycroft sulfide mineralization is amenable to a flotation and POX processing route. Optimized flotation conditions significantly improved gold recoveries, and subsequent POX testing demonstrated that POX followed by hot cure, lime boil, and cyanide leaching is a technically viable and repeatable flowsheet for treating pyrite concentrate.

 

22.6Mineral Resource Estimate

 

Mineral resources were developed based on a conventional computer-based block model of the deposit and the application of open pit optimization software to determine the mineralization with reasonable expectation of economic extraction.

Each block was evaluated to determine which process provides the best net return after operating cost. The following two processes were identified:

 

ROM cyanide heap leaching of oxide and some transition materials.
  
Milling, Flotation, POX, Hot Cure, and Lime Boil followed by Cyanide Leach and Merrill-Crowe of sulfide and some transition materials.

 

The MRE is based on metal prices of $3,100/oz Au and $36.00/oz Ag. Mineral resources were contained within a computer-generated pit.

 

Hycroft Mine Project

Page 266

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Table 22-1: Hycroft Mineral Resources as of 21 January 2026, US customary Units

 

Classification $ Net of
Process/ton
Approximate
Cutoff, AuEq oz/ton
Ktons Gold
oz/ton
Silver
oz/ton
Sulfide
%
Contained Ounces
Gold
Oz x 1000
Silver
Oz x 1000
Heap Leach Resource
Measured $1.88 - $3.63 0.001 - 0.002 92,994 0.005 0.11 1.83 446 10,322
Indicated $1.88 - $3.63 0.001 - 0.002 110,374 0.004 0.09 1.54 475 9,492
Meas + Ind $1.88 - $3.63 0.001 - 0.002 203,368 0.005 0.10 1.67 921 19,814
Inferred $1.88 - $3.63 0.001 - 0.002 110,018 0.005 0.09 1.41 528 10,122
Flotation Mill + Concentrate Treatment by Pressure Oxidation and Cyanide Leach
Measured $16.73 0.007 734,571 0.011 0.43 2.03 8,154 316,600
Indicated $16.73 0.007 748,876 0.010 0.30 1.84 7,339 226,161
Meas + Ind $16.73 0.007 1,483,447 0.010 0.37 1.93 15,493 542,761
Inferred $16.73 0.007 459,646 0.010 0.27 1.76 4,505 122,725
Combined Mineral Resources Leach Plus Mill
Measured $1.88 - $16.73 0.001 - 0.007 827,565 0.010 0.40 2.01 8,600 326,922
Indicated $1.88 - $16.73 0.001 - 0.007 859,250 0.009 0.27 1.80 7,814 235,653
Meas + Ind $1.88 - $16.73 0.001 - 0.007 1,686,815 0.010 0.33 1.90 16,414 562,575
Inferred $1.88 - $16.73 0.001 - 0.007 569,664 0.009 0.23 1.69 5,033 132,847

 

Notes:

 

1.Mineral resources based on metal prices of $3,100/oz Au and $36.00/oz Ag.
2.Cutoffs are income – process cost = NPR = NSR – Process + G&A Opex.
3.Gold Equivalent (AuEq) for Heap Leach = Cyanide Gold + 0.0019 x Total Silver Assay, or at average gold leach recovery AuEq = Fire Gold + 0.0035 Total Silver Assay.
4.Gold Equivalent for Mill + Pressure Oxidation = Fire Gold + 0.0107 x Total Silver Assay.
5.Numbers may not match exactly due to rounding.
6.Mineral resources are contained within a computer-generated optimized pit.
7.Total material in the pit is 5.42 billion tons.
8.Mineral resources are not mineral reserves, and detailed economic considerations have not been applied.
9.Modifying factors for mine and process design have not been applied.
10.All units are US customary. Ktons means 1,000 short tons of 2,000 lbs. Au and Ag grades are in troy ounces per short ton (oz/ton).

 

Contained within the MRE at Hycroft are a series of high-grade silver veins at Brimstone and zones of higher silver concentrations in Vortex that are associated with a low angle breccia body. Table 22-2 is the tabulation of gold and silver within the domain volumes that are contained within the MRE at 2 oz/ton cutoff grade in US customary units.

 

Table 22-2:High-grade Silver Bearing Domains, Contained within the Mineral Resource at 2 oz/ton Cutoff Grade, US customary Units

 

Classification Cutoff Grade Silver oz/ton Ktons

Gold

oz/ton

Silver
oz/ton
Sulfide Sulfur% Gold Contained
oz x 1000
Silver Contained
oz x 1000
Brimstone
Measured 2.00 3,195 0.011 8.35 1.33 35 26,686
Indicated 2.00 330 0.010 3.11 1.87 3 1,025
Meas + Ind 2.00 3,525 0.011 7.86 1.38 38 27,711
Inferred 2.00 15 0.008 3.52 1.13 0 52
Vortex
Measured 2.00 9,126 0.018 3.81 1.49 160 34,781
Indicated 2.00 7,342 0.014 3.78 1.24 100 27,726
Meas + Ind 2.00 16,468 0.016 3.80 1.38 261 62,507
Inferred 2.00 3,644 0.014 3.65 1.27 50 13,307
Brimstone + Vortex
Measured 2.00 12,322 0.016 4.99 1.45 195 61,467
Indicated 2.00 7,671 0.013 3.75 1.26 104 28,750
Meas + Ind 2.00 19,993 0.015 4.51 1.38 299 90,218
Inferred 2.00 3,659 0.014 3.65 1.27 51 13,359

 

22.7Recovery Plan

 

The proposed recovery methods for the Project are conventional and appropriate for the mineralization types identified at Hycroft. The process design incorporates two established treatment pathways: (i) cyanide heap leaching of ROM oxide and select transition materials, and (ii) milling, flotation, and POX of sulfide and higher-sulfur transition materials, followed by cyanide leaching and Merrill-Crowe recovery.

 

The sulfide processing flowsheet, comprising three-stage crushing, grinding, flotation concentration, concentrate thickening, POX, neutralization, CCD washing, cyanide leaching, and zinc precipitation, is based on well-established industry practices for treatment of refractory gold-silver mineralized material. The selected POX conditions, downstream neutralization and conditioning steps (including hot curing and lime boil), and subsequent cyanide leaching are consistent with standard approaches for oxidation of sulfide concentrates and recovery of precious metals.

 

The use of Merrill-Crowe zinc precipitation for gold and silver recovery is appropriate given the anticipated solution chemistry and elevated silver content. Integration of heap leach and milling/POX circuits, including handling of combined pregnant solutions and shared recovery infrastructure, is considered practical and consistent with current operations at the site.

 

Hycroft Mine Project

Page 267

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Testwork results support the application of the selected flowsheet, including flotation performance and POX oxidation behavior, although further metallurgical testwork is recommended at the PFS level to confirm design criteria, optimize operating parameters, and reduce technical uncertainty. Key areas for further work include flotation optimization, POX operating conditions, reagent consumptions, and solid-liquid separation performance.

 

In the opinion of the Qualified Person, the proposed recovery methods are suitable for the current level of study and provide a reasonable basis for the process design and economic evaluation presented in this report. The recovery methods are considered to be consistent with industry standards and applicable to the mineralization types identified, subject to the recommended further testwork and design refinement.

 

22.8Infrastructure

 

The Hycroft Site is accessible via Jungo Road (Nevada State Route 49), an all-weather gravel roadway connecting the mine to the town of Winnemucca and Interstate 80. Most current and future Hycroft employees reside in Winnemucca; transportation to site will be provided as required. A Union Pacific rail line runs adjacent to the mine, and a proposed rail spur and siding will allow for the delivery of bulk consumables including limestone, grinding media, and fuels. Rail infrastructure will also facilitate the shipment of finished products. New access roads shall be constructed to provide access to the new process plant and other proposed infrastructure. The new roads will complement the existing site haul roads which are to remain largely in use.

The proposed process plant will tie into the existing crushing circuit and portions of the current processing infrastructure. Upgrades to existing infrastructure are also planned to support the expanded operation. These upgrades include the relocation of existing site assets, expanding storage capacity, or expanding the operational or control of select facilities. Existing administrative and operational facilities will be repurposed where possible, while new ancillary facilities such as a laboratory, fueling station, maintenance shop, or other supporting infrastructure will be constructed to support Hycroft operations.

 

The site currently has power from the grid. Upgrades to site power distribution systems are proposed to support the increased power demand of the new process facility.

 

Existing telecommunication infrastructure currently supports data connectivity throughout the site.

 

Consumables including fuels and reagents are to be supplied to site via the proposed rail spur connecting the site to the nearby Union Pacific line. This transport system will also support the movement of Hycroft products off-site.

 

Water will be captured and stored from groundwater wells within the Black Rock Desert Basin. Drainage infrastructure on site will capture runoff water and recycle it to reduce freshwater demand at the process plant. A life-of-mine water balance model was developed to evaluate operational water requirements and variability under different climatic conditions.

 

The infrastructure design approach adopted prioritizes integrating new facilities within the network of existing facilities and upgrading existing facilities such that they may continue to support the project. Regional transportation and power networks will continue to serve the Hycroft Site.

 

Hycroft Mine Project

Page 268

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

22.8.1

Tailings Management Facility

 

The TMF uses conventional designs and assumes construction in a total of eight stages and zero discharge of process solutions. The TMF will fill the broad valley immediately northeast of the mill site and requires the main and north embankments to impound the tailings. The main embankment will cross the natural drainage on the west side of the TMF, and the north embankment will be constructed along the northern ridge. The facility will provide continuous containment of process solutions through the installation of a vertical chimney drain and engineered lining systems, extending across the impoundment basin and below a portion of the main embankment and along the upstream side of the north the embankment. The design can store runoff from the basin and direct precipitation on the facility resulting from the 5,000-year, 24-hour storm event during operation and the 10,000-year, 24-hour storm event post-closure.

 

The relevant results and interpretations related to the TMF design are based on the data and other information summarized in this Report.
  
Section 23 describes the recommended work and site investigations to be completed for detailed design and permitting of the TMF.

 

22.9Markets and Contracts

 

Gold and silver doré will be sold on the spot market under terms typical of comparable doré sales contracts. No refining, transportation, or hedging contracts are currently in place, though these are considered readily obtainable. Doré refining and marketing will occur through agreements with established refineries with terms aligning with industry standards.

 

22.10Capital Cost Estimate

 

The capital cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, and contingency is less than 25% which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The estimate includes mining, processing, on-site infrastructure, off-site infrastructure, project indirects, project delivery, owners’ costs, and provisions. The total initial capital costs for the Project are estimated at US$2,434 million, including capitalized operating costs, and contingency. The LOM sustaining costs are estimated at US$3,107 million, while the closure costs are estimated at US$243 million.

 

22.11Operating Cost Estimate

 

The operating cost estimate was developed in Q1 2026 to target a level of accuracy of -30% to +50%, and contingency is less than 25% which aligns with an Association for the Advancement of Cost Engineering International (AACE International) Class 5 level estimate. The total operating costs for the Project are estimated at US$21.96/t processed or US$27,592 million over the 51-year mine life. These operating costs do not include pre-production operating costs.

 

Hycroft Mine Project

Page 269

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

22.12Economic Analysis

 

The economic analysis was performed assuming a 5% discount rate. The pre-tax NPV discounted at 5% is US$5,437 million; the IRR is 18.9%, and payback period is 4.3 years. On a post-tax basis, the NPV discounted at 5% is US$4,344 million, the IRR is 16.9%, and the payback period is 4.7 years.

 

A sensitivity analysis was conducted on the base case NPV and IRR of the project using the following variables: discount rate, head grade, recovery, total operating cost, initial capital cost, as well as silver and gold prices, which were encompassed in a single variable, metal price. The sensitivity analysis revealed that the project is most sensitive to changes in metal price, head grade, and recovery.

 

22.13Risks and Opportunities

 

22.13.1Risks

 

22.13.1.1Exploration

 

There are structural complexities with yet underdetermined kinematics controlling the high-grade silver veins requiring additional drilling for further definition.

 

22.13.1.2Sample Preparation, Analysis and Security

 

In the future, IMC recommends that complete QA/QC procedures be applied to silver and sulfide sulfur assaying and sampling. Regular sampling for QA/QC should be applied to those values in the same way as they have been recently applied to gold.

 

22.13.1.3Metallurgical Testing

 

While the available metallurgical testwork supports the proposed flotation followed by POX flowsheet, several risks remain at the current level of study. Previous test programs did not fully evaluate mercury deportment during POX, and additional work is required to confirm mercury behavior in autoclave off-gas and determine whether mercury capture systems will be required to meet environmental compliance requirements. The potential need for such systems may result in additional capital and operating costs.

 

Uncertainty also remains with respect to POX performance, including oxidation efficiency, reagent consumption, and downstream process behavior, as well as variability in metallurgical response across different ore types. The assumed gold and silver recoveries are based on available testwork and are subject to refinement as additional data become available. In addition, operating cost estimates are sensitive to reagent consumption and market-driven pricing, including energy and consumables, which may fluctuate over time and impact overall project economics.

 

No metallurgical testwork has been completed on transition material for heap leach processing. Heap leach recovery, leach kinetics, reagent consumption, and permeability characteristics therefore remain uncertain, and the current assumptions may not fully represent actual operating performance. Additional transition material heap leach testwork is recommended in future study phases to reduce technical uncertainty.

 

Hycroft Mine Project

Page 270

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

22.13.1.4Mineral Resource Estimate

 

The risks to the MRE are project costs and project recoveries as well as metal prices that can have a substantial impact both positive and negative.

 

Cutoff grades for both heap leach and concentrator processing are low due to the current high level of metal prices.

 

Any reduction of process recovery near the heap leach or concentrator cutoff grades could result in a loss of mineral resource.

 

22.13.1.5Processing and Recovery Methods

 

The proposed recovery methods, consisting of flotation followed by POX and cyanide leaching, are supported by available metallurgical testwork; however, uncertainties remain at the current level of study. Key risks include incomplete definition of POX performance and downstream process behavior, and potential impacts from mercury deportment and reagent consumption. These factors may affect gold and silver recoveries and increase operating costs, and recovery assumptions remain subject to refinement as additional testwork is completed. The brownfield nature of some of the process plant introduces risk for cost and reliability.

 

22.13.1.6Infrastructure

 

The crushing facility, process plant, and associated office have a proposed location within 500 m of the pit blasting zone. This introduces the risk of blast-induced vibration, flyrock, or dust impacting facilities or personnel. The long mine life for plant and infrastructure, as well as the connection to grid which is critical to get the project into operation.

 

22.13.1.7TMF

 

The TMF has been sized to provide containment and storage of up to 1.05 Btons of tailings at an overall settled dry density of 92 pcf. Throughout operation of the TMF, testing in-situ tailings for density and strength properties may indicate a lower density is achieved due to various factors including increased water for slurry distribution. This would result in an additional stage beyond Stage 8 presented in this Report. In this event, local, State, and Federal permitting may be required and an increase construction sustaining capital and operating costs would be required for the additional stage.

 

At this stage of the Project, there is reasonable certainty that the location and design of the TMF as presented for this PEA study will be used as planned. No significant design changes are likely to be required provided that no material changes in location, geotechnical parameters, or design are needed as a result of the ongoing and future local, State, and Federal permitting process and future investigations and studies.

 

Hycroft Mine Project

Page 271

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

If actual activities related to the construction, management, operation, and closure of the TMF do differ materially from the results summarized in this Report, then the reasonably foreseeable impacts of these risks and uncertainties are most likely to be project delays and additional costs. However, any such delays or additional costs may reasonably be expected to be managed in the ordinary course and should not impact overall project viability.

 

Construction work in Nevada is seasonal. Poor weather during the construction season may result in delays to the Project schedule.

 

If additional, or alternative, borrow areas are required for construction and/or reclamation of the TMF that are more distant than contemplated in this prefeasibility study, then construction and/or reclamation construction costs of the TMF will increase as compared to the costs estimated in this Report.

 

22.13.2Opportunities

 

22.13.2.1Exploration

 

Hycroft holds a large land package with good growth potential.

 

Multiple episodes of mineralization within a well-developed structural framework may result in discovery of additional mineral trends that are open along strike and at depth.

 

Expanding the use of IP geophysics in the mineralization zone may identify multiple untested targets in the existing data set. This emerging technology has a proven record of success in similar applications.

 

22.13.2.2Metallurgical Testing

 

Additional metallurgical testwork provides opportunities to further optimize the POX circuit design and potentially reduce capital and operating costs. Key testwork opportunities include evaluating POX kinetics to confirm minimum autoclave retention time, assessing the impact of flotation grind size and mass pull on concentrate quality and POX performance, and optimizing oxygen partial pressure and utilization. Additional work is also recommended to confirm autothermal operation, characterize solids–liquid separation performance for flotation concentrate and POX discharge, and better define POX discharge chemistry to optimize neutralization and downstream processing. Targeted off-gas and condensate characterization may also be required to support environmental compliance requirements.

 

Alternatives for processing flotation concentrates are under process development, including but not limited to, roasting and sulfide sulfur recovery for sulfuric acid production. This has the potential to reduce operating costs, raise gold and silver recoveries and create an additional revenue stream.

 

22.13.2.3Mineral Resource Estimate

 

Alternatives are under evaluation for treatment of flotation concentrates. Improvements and confirmation of those alternatives could provide significant financial benefit and increase the volume and value of the MRE.

 

Minimal geotechnical information has been gathered resulting in very conservative slope parameters applied. Adding geotechnical data from the drilling and logging program may improve the alteration model which could lead to more beneficial slope parameters, thus reducing stripping ratios.

 

22.13.2.4Processing and Recovery Methods

 

The metallurgical testwork completed to date indicates that the proposed recovery methods are technically viable and provide opportunities for further optimization. Additional metallurgical testing and process refinement are expected to improve recovery performance, optimize operating conditions, and enhance overall process efficiency. Continued advancement of the flowsheet is anticipated to reduce technical uncertainty and support increased confidence in recovery assumptions as the Project progresses to a PFS study.

 

22.13.2.5Infrastructure

 

22.13.2.5.1TMF

 

There may be an opportunity to reduce capital construction costs for the TMF by using the mine haulage fleet for embankment and compact embankment fill, rather than a contractor. Additional cost savings may be achieved by increasing or decreasing intermediate TMF staged embankment construction to align with mine planning opportunities for more or less suitable waste materials.

 

The TMF has been sized to provide containment and storage of up to 1.05 Btons of tailings at an overall settled dry density of 92 pcf. Throughout the operation of the TMF, in-situ testing of tailings for density and strength properties may indicate that a higher density is achieved. This would result in either additional storage capacity beyond the Stage 8 design volume, or the ability to reduce the final Stage 8 dam crest elevation to match the in-situ tailings density.

 

Additional closer to the pit areas or pit backfill opportunities should be explored in the next phase of the project. Changing the location of the WRSF can have an impact on overall waste rock haulage costs.

 

Hycroft Mine Project

Page 272

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

23Recommendations

 

23.1Estimated Program Costs

 

Table 23-1 provides estimated program costs.

 

Table 23-1: Estimated Program Costs

 

Program Cost Estimated Cost (US$)
Updated Technical Report with Economics 200,000
Exploration Drilling East and South 1,600,000
Exploration Drilling Deep in Brimstone/Vortex 14,500,000
Regional Exploration Targets 500,000
Exploration for Leachable Opportunities (Bay and Camel) 1,800,000
Exploration - Leach Pads and Stockpiles 800,000
Sample Preparation - Procedural Upgrade 50,000
Metallurgical and Process Testwork Programs 1,500,000
Mineral Resource - Alternative Processing Method Development 800,000
Mineral Resource and Mine Planning – Additional Geotechnical Testing 300,000
Total: 22,050,000

 

Note:

 

1.All costs are subject to change based on project results

 

23.2Exploration

 

Increase the drill hole density in the Bay area.

 

Continue to develop drill plans in the exploration target areas to the east (Manganese and Wildrose) and south (Oscar), to further expand the resource.

 

Continue deep exploration on Brimstone and Vortex high-grade mineralization.

 

Drill the Bay and Camel targets to fully define leachable opportunities.

 

Continue developing regional exploration targets.

 

Continue exploring the total land package that Hycroft holds, including more geological mapping, soil and chip samples, geophysical information and drilling.

 

Drill out the current leach pads and stockpiles to better define potential economic benefit to future processing activities.

 

Hycroft Mine Project

Page 273

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

23.3Sample Preparation, Analysis and Security

 

Always complete QA/QC analysis on all potentially economic minerals including gold, silver, and sulfide sulfur. Avoid selective application of quality controls during the drilling, sampling, and assay process.

 

23.4Metallurgical Testing

 

It is recommended that Hycroft continue to evaluate known oxide/transition zones for further heap leach feed material. Also, Hycroft should investigate the potential to re-leach material from historic heap leach pads for an additional revenue source.

 

Undertake additional metallurgical testwork specifically on transition material to validate recovery assumptions, and operating parameters, as transition material performance to the heap has been identified as a project risk.

 

It is also recommended that Hycroft undertake additional metallurgical testwork covering flotation, POX, leaching, solids–liquid separation, cyanide destruction, and Merrill-Crowe processes. The results of this testwork should allow Hycroft to:

 

optimize the flotation reagent suite to reduce operating costs

 

optimize the autoclave retention time required for variations in flotation concentrate product size

 

evaluate the potential to reduce autoclave oxygen partial pressure to the range of 15–30 psi

 

generate additional recovery data as a function of retention time and extent of sulfide oxidation

 

investigate each of the POX, Hot Cure, and Lime Boil stages in sufficient detail to reduce capital costs by reducing lime and limestone consumption, eliminating unnecessary process steps or shortening retention times, thereby reducing equipment sizing and cost

 

investigate POX discharge solution chemistry and limestone/lime consumptions to reduce operating costs

 

determine whether flotation mass pull can be reduced. The sulfide grade of the concentrate may be marginal with respect to providing sufficient exothermic energy to sustain autoclave reactions. This information is required to determine whether preheating is necessary ahead of POX

 

obtain solids–liquid separation performance data and flocculant requirements for all thickeners, including tailings, concentrate, POX CCDs, and leach residue CCDs. Higher underflow density from the concentrate thickener would be beneficial to the autoclave heat balance

 

optimize cyanide addition and quantify cyanide consumption in the leach circuit, including levels of free and WAD cyanide post-leach

 

optimize reagent consumption in the cyanide destruction circuit by developing an accurate and reliable SO₂/CN ratio

 

determine whether post-leach solution chemistry impacts Merrill-Crowe recovery efficiency.

 

Hycroft Mine Project

Page 274

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

23.5Mineral Resource Estimate

 

Continue evaluation and testing of alternative processing methods of flotation concentrates.

 

Always complete QA/QC analysis on all potentially economic minerals including gold, silver, and sulfide sulfur.

 

Gather more geotechnical information from previous core samples and with the addition of new geotechnical core holes to improve slope stability parameters.

 

23.6Infrastructure

 

A power study is currently underway to determine the power line voltage and the number of powerlines required to feed the process plant. Currently, power is supplied to the site via nearby power lines which are energized via the main power grid. This technical report assumes that 2 x 120 kV powerlines will be required. Considering load growth and demand from the oxygen plant, the total estimated operating load is 160 MW (including the existing crushing plant and North Merrill-Crowe loads which are to be transferred to the new power distribution system once operational). The power will be delivered through one 120 kV overhead power line stretching 52 miles onto the site.

 

23.6.1TMF

 

To advance the TMF design beyond this PEA study level, WSP recommends the following evaluations, studies, and documents to support future feasibility-level and detailed design suitable for permitting:

 

Dam breach analysis and inundation mapping to assess downstream impacts and validate the Dam consequence classification of “Very High”.

 

Completion of a Failure Modes and Effects Analysis (FMEA) workshop for selection and/or or confirmation of the GISTM 2020 Failure Consequence Classification of Very High.

 

Supplemental geotechnical evaluations based on revised TMF geometry to include, but not limited to:

 

optimization of TMF layout taking advantage of topography

 

geotechnical investigation and laboratory program, that may include geotechnical boreholes, test pits, geophysics, instrumentation installation, and laboratory program to determine physical and mechanical properties of foundation soils and bedrock, construction materials, and tailings

 

characterization of geologic and foundations conditions, embankment construction materials, drainage and geomembrane bedding materials

 

update the site-specific seismic and geologic hazard assessment

 

update stability and deformation analyses

 

perform tailings, embankment materials, and foundation liquefaction assessment

 

perform foundation and embankment settlement analyses

 

Hycroft Mine Project

Page 275

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

completion of a hydrogeologic evaluation within the TMF area for groundwater and artesian springs

 

update TMF design based on mine schedule, process technology, geotechnical, hydrogeology, hydrology, and engineering analyses

 

update surface water management design based on updated TMF layout

 

development of a monthly time-step water balance that include extreme wet and dry annual climate conditions with consideration for climate change

 

completion of a seepage and consolidation model for the long-term closure condition of the tailings

 

preparation of a preliminary TMF closure plan, including design of closure cover channels and closure spillway and outlet structure

 

update capital, sustaining capital, and operating costs based on future investigations and design of the TMF.

 

As additional information is obtained, assumptions made in this study can be verified or updated to advance the project to the next level of design. The cost of implementing the above recommendations is estimated at US$1,360,000.

 

Hycroft Mine Project

Page 276

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

24References

 

Ausenco Engineering USA South Inc. (2023). Initial Assessment Technical Report Summary; Humboldt and Pershing Counties, Nevada Prepared by Ausenco for Hycroft Mining Holding Corp. Effective Date: March 27, 2023.

 

Ausenco Engineering USA South Inc, (2022). Technical Report Summary of Initial Assessment on the Hycroft Mine, Nevada, United States of America. Prepared by Ausenco for Hycroft Mining Holding Corp. Effective Date: February 18, 2022.

 

Bailey, E.H, & Phoenix, D.A. (1944). Quicksilver deposits in Nevada (University of Nevada Bulletin, Vol.38, No.5; Geology and Mining Series No 41). Nevada State Bureau of Mines.

 

Bates, W.R. (2001). A proposed exploration program for the hycroft mine. Unpublished Vista Gold report.

 

Bureau of Land Management (BLM). (2019). Hycroft mine phase II expansion project draft environmental impact statement (DOI-BLM-NV-W030-2015-007). U.S. Bureau of Land Management Winnemucca District Office, Black Rock Field Office, in coordination with U.S. Fish and Wildlife Service Pacific Southwest Region Division of Migratory Bird Management. May 2019.

 

California’s Office of Statewide Health Planning and Development (OSHPD), OSHPD Seismic design maps website for Hycroft Mine, Reference: ASCE 7-16, Site Class: D, Risk Category. Visited 20 Aug 2021. I Available at: https://seismicmaps.org/.

 

Clark, I.C. (1918). recently recognized alunite deposits at sulphur, Humboldt County, Nevada. Engineering and Mining Journal, 106(4), 159-162..

 

Couch, B.F. & Carpenter, J. A. (1943). Nevada’s metal and mineral production (1859-1940 inclusive). (University of Nevada Bulletin, Vol. 37, No.4; Geology and Mining Series No. 38). Nevada State Bureau of Mines.

 

Ebert, S.W., & Rye, R.O. (1997). Secondary precious metal enrichment by steam-heated fluids in the Crofoot-Lewis hot spring gold -silver deposit. Economic Geology, v.92(5), 578-600. https://doi.org/10.2113/gsecongeo.92.5.578

 

Friberg, R.S. (1980). Detailed evaluation report of the sulphur Au Ag prospect, Humboldt and Pershing Counties, Nevada. Unpublished Homestake Mining Company Report, 32 p.

 

Fulton, J.A., & Smith, A.M. (1932). Sulphur mining district file manuscript: Nevada Bureau of Mines and Geology Mining District Files (includes alunite production notes from 1931). Nevada Bureau of Mines and Geology, University of Nevada.

 

Hycroft Mine Project

Page 277

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Golder. (2011a). Pre-feasibility design report. Prepared by Golder Associates Inc for Allied Nevada Gold Corporation,, revised September 2011.

 

Golder. (2011b). Earthquake Ground Motions for the North and South Heap Leach Facilities Seismic Analyses and Design, Hycroft Mine, Nevada. Technical Memorandum prepared by Alan Hull and Eric Cannon of Golder Associates Inc. for Chris MacMahon of Golder Associates Inc. October 26, 2011.

 

Golder. (2014a). Feasibility design report, Tailings Management Facility, Hycroft Mine, Nevada. Report prepared by Golder Associates Inc. for Allied Nevada Gold Corporation. November 20, 2014.

 

Golder. (2014b). Geotechnical Characterization of Pilot Plant Mill Tailings. Report prepared by Golder Associates Inc. for Allied Nevada Gold Corporation. 2014.

 

Golder. (2014c). Hycroft Tailings – Consolidation Modelling. Report prepared by Golder Associates Inc. for Allied Nevada Gold Corporation. 2014.

 

Golder. (2014d). Tailings Stage-Density Relationship for Feasibility Design. Report prepared by Golder Associates Inc. for Allied Nevada Gold Corporation. 2014.

 

Golder. (2014e). Geotechnical Characterization of Pilot Plant Mill Tailings, Rev. 1. Report prepared by Golder Associates Inc. for Allied Nevada Gold Corporation. September 8, 2014.

 

Golder., (2016). Feasibility Design Report, Tailings Management Facility (TMF). Report prepared for Hycroft Mining Corporation by Golder Associates. November 3, 2016.

 

Golder. (2022). Hycroft Tailings Management Facility – Prefeasibility Design Report. for Hycroft Mining Corporation as of January 28, 2022.

 

Hazen Research Inc. (2011). POX-CIL Evaluation of Hycroft Flotation Concentrates, Hazen Project 11232 Report and Appendices A-F.

 

Hazen Research Inc. (2011). Evaluation of Hycroft Blend Flotation Concentrate, Hazen Project 11243-01 Report and Appendix.

 

Hazen Research Inc. (2011). Evaluation of Kappes, Cassiday & Associates Flotation Concentrate, Hazen Project 11307 Report and Appendix.

 

Hazen Research Inc. (2014). Atmospheric Alkaline Oxidation Pre-treatment Pilot Plant of Hycroft Flotation Concentrates, Hazen Project 11859.

 

Hazen Research Inc. (2014). Phase 2 Atmospheric Alkaline Oxidation of Hycroft Flotation Concentrate, Hazen Project 11821.

 

Hycroft Mine Project

Page 278

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Humboldt County Building Department. (2018). 2018 code amendments. Retrieved August 20, 2021. Available at: https://www.humboldtcountynv.gov/DocumentCenter/View/3415/2018-Code-Admendments-Approved.

 

Hycroft Mining Holding Corporation. (2021). Hycroft building a world-class operation. [PowerPoint presentation]; April 20, 2021. http://www.hycroftmining.com/wp-content/uploads/2021-Presentation-4-19-21.pdf.

 

Hycroft Resources and Development, Inc. (HRDI). (2017). Fact Sheet Pursuant to Hycroft Mine Project, Permit Number: NEV0094114. Renewal 2017, Fact Sheet Revision 01. https://ndep.nv.gov/uploads/documents/NEV0094114dfsFY20.pdf.

 

Hycroft Resources and Development, Inc. (HRDI). (2018). Hycroft Mine amendment to plan of operations (NVN-064641) Phase II Expansion Project. Prepared for the United States Department of the Interior, Bureau of Land Management, Black Rock Field Office, Winnemucca, Nevada. April 2014. Revised June 2014, Revised January 2017, Revised March 2017, and Revised June 2018.

 

Hynes-Griffin, M.E., & Franklin, A. G. (1984). Rationalizing the seismic coefficient method. Miscellaneous Paper GL-84-13, Geotechnical Laboratory, U. S. Army Engineer Waterways Experiment Station, Vicksburg, Mississippi.

 

Ibrado, A.S., Roth, D.K., Snider, J.W., Brown, R.A., Harris, D.A., Pennstrom, W.J., Peterson, A.T. (2014). NI 43-101 Technical Report Mill Expansion Feasibility Study Technical Report, Winnemucca, Nevada, USA. Prepared by M3 Engineering & Technology Corp for Allied Nevada Gold Corp., Effective date: November 03, 2014.

 

ICMM, UNEP, & PRI (2020). Global Industry Standards on Tailings Management (GISTM).

 

Jones, J.C. (1921). Report on the Property of the Ag Camel Mining and Development Company, Sulphur, Nevada. Unpublished Ag Camel Mining and Development Company Report, 6p.

 

J.P. Morgan Private Bank. (n.d). Is It a Golden Era for Gold? https://privatebank.jpmorgan.com/nam/en/insights/markets-and-investing/is-it-a-golden-era-for-gold

 

Kappes, Cassidy & Associates. (2013). Hycroft Pressure Oxidation and Leach Test Work (Project No. 189 C/Report I.D. KCA0120225_HY18_02 / Mainfile No. 7665). Internal report prepared for Hycroft.

 

London Bullion Market Association (LBMA), 2025, Month Unknown. LBMA Annual Precious Metals Forecast Survey 2025 – Winners Announced. https://www.lbma.org.uk/articles/lbma-annual-precious-metals-forecast-survey-2025-winners-announced

 

McLean, D.A. (1991). Geology of the Crofoot Mine. unpublished Report prepared for Hycroft Resources and Development Inc. 11p.

 

Michael W. West & Associates, Inc. (MMW). (2012). Review of Seismogenic Potential of the Kamma (East) Fault and Design Ground Motions, Proposed Heap Leach Facilities, Hycroft Mine, Humboldt County, Nevada. Report prepared by MMW for Knight Piésold & Company. December 18, 2012.

 

Hycroft Mine Project

Page 279

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Newman, S., DeLong, R.F., Clarkson, B. M., Carew, T., Hartmann, M. (2019). Hycroft Project Technical Report Summary: Heap Leaching Feasibility Study, Winnemucca, Nevada, USA. Prepared by M3 Engineering & Technology Corp for Hycroft, Effective date: July 31, 2019.

 

Pershing County Building Department. (n.d.). Commercial Guidelines: Minimum Standards for Building Plans (new commercial project permit application checklist for commercial structures, such as Groups: A, B, E, F, H, I, M, R, and S occupancies). Retrieved August 16, 2021. Available at: https://www.pershingcountynv.gov /document_center /Department/Building%20Department/CommercialGuidelines-002.pdf.

 

Prenn, N. (2006). Technical Report – Vista Gold Corp., Hycroft Mine, Winnemucca, Nevada, USA, NI 43-101 Technical Report. Prepared by Mine Development Associates (MDA) for Vista Gold Corp. 142 pages.

 

SGS Minerals Services. (2009). The Recovery of Au and Ag from Hycroft Project Sulphide Samples, Allied Nevada Gold Corporation – Hycroft Project – 12012-001 (Report 3).

 

SGS Minerals Services. (2013). An Investigation into Oxidative Pretreatment of Hycroft Flotation Concentrates,SGS Project 13224-001/003 – Final Report.

 

Shawn Gooch, P.E., (2020). Hycroft Resources and Development, Inc. (HDRI) Hycroft Mine Project NEV0094114 (Renewal 2017, Fact Sheet Revision 01).

 

SRK Consulting Inc (SRK). (2022). Preliminary Estimate of Dewatering Requirements to Support 2021 Pre-Feasibility Study Technical Memorandum.

 

Precious Metals Insights. (2025). Price Sensitivity of Above-ground Silver Stocks. The Silver Institute. https://silverinstitute.org/wp-content/uploads/2025/02Final_Price_Sensitivity_of_Above-Ground-Silver-Stocks.pdf

 

Metals Focus. (2025). World Silver Survey 2025. The Silver Institute. https://silverinstitute.org

 

The Silver Institute, (2026). Global Silver Investment to Remain Strong in 2026 Against the Backdrop of a Sixth Consecutive Annual Market Deficit. https://silverinstitute.org/global-silver-investment-to-remain-strong-in-2026-against-the-backdrop-of-a-sixth-consecutive-annual-market-deficit/

 

United States Geologic Survey, USGS. (2014). Unified Hazard Tool. U.S. Department of the Interior. https://earthquake.usgs.gov/hazards/interactive/index.php.

 

Vandenburg, W.O. (1938). Reconnaissance of Mining Districts in Humboldt County, Nevada; U.S. Bureau of Mines Circular 6995, 47p.

 

Wallace, A.B. (1980). Geology of the Sulphur District, Southwestern Humboldt County, Nevada. Unpublished report for the Society of Economic Geologists Field Trip Guidebook.

 

Hycroft Mine Project

Page 280

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Ware, G.H. (1989). Surface Mapping, Sampling and Selected Cross-Sections. Unpublished report for Hycroft Resources & Development.

 

Wilden R. (1964). Geology of Mineral Deposits of Humboldt County, Nevada. Nevada Bureau of Mines, Bulletin 59, 154p.

 

Wilson, S. E. (2008). Technical Report - Allied Nevada Gold Corp., Hycroft Mine, Winnemucca, Nevada, USA. NI 43-101 Technical Report (Effective Date: January 16, 2008). Prepared for Allied Nevada Gold Corp.

 

World Gold Council. (2026). Gold Demand Trends: Q4 and Full Year 2025. https://www.gold.org/goldhub/research/gold-demand-trends

 

World Gold Council, (n.d.). “Gold: The Most Effective Commodity Investment – Why it is Under-Represented in Commodity Indices and the Potential Impact on Your Portfolio. https://www.gold.org/goldhub/gold-focus/2019/09/gold-most-effective-commodity-investment

 

WSP (2024). Hycroft Mine Tailings Management Facility Preliminary Design. Hycroft Mine. Winnemucca, Nevada, USA.

 

WSP (2026). Hycroft Mine Tailings Management Facility Conceptual Design Update to Store 1.05B Tons Preliminary Economic Assessment Design Level. Hycroft Mine. Winnemucca, Nervada, USA.

 

25Reliance on Information Provided by the Registrant

 

Table 25-1 provides a detailed list of information provided by Hycroft (Registrant) for matters discussed in this Technical Report Summary.

 

Table 25-1: Information Provided by Hycroft

 

Category TRS Section Reliance
Legal Matters Section 3 - Property Description and Location Information and documentation regarding mineral titles, surface land agreements, current permitting status, royalties and other agreements provided by Hycroft.
Post Tax Evaluation Section 19 - Economic Analysis Macroeconomic trends, data and assumptions and interest rates - Post Tax Calculations

 

The QPs consider it reasonable to rely upon Hycroft for this information because Hycroft, along with its legal and other advisors, are best positioned to access and interpret existing information and documentation concerning these legal matters and interpretation of the same is outside of the expertise of the QPs.

 

Hycroft Mine Project

Page 281

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Appendix A – Patented Claims

 

Claim Name Patent No. Mineral Survey No.
Admission Placer 908431 4355
Black Rock (portion) 1064817 4688A
Black Rock (portion) 1064817 4688A
Brime Stone Placer - aka Brimstone Placer 1001727 4600
Cold Sulphur Placer 83151 3225
Green Rock Placer (portion) - aka Green Rock No. 1 1223182

4839

 

4857

Green Rock Placer (portion) - aka Green Rock No. 2 1223182

4839

 

4857

Green Rock Placer (portion) - aka Green Rock No. 3 1223182

4839

 

4857

Green Rock Placer (portion) - aka Green Rock No. 4 1223182

4839

 

4857

Hilltop Placer (portion) 1008652 4598
Hilltop Placer (portion) 1008652 4598
Hilltop Placer (portion) 1008652 4598
Occult Placer (portion) 1008652 4598
Occult Placer (portion) 1008652 4598
Occult Placer (portion) 1008652 4598
Scheol No. 9 Placer 1008652 4598
Sheol No. 4 Placer (portion) 908431 4355
Sheol No. 5 Placer (portion) 908431 4355
Sheol No. 6 Placer 908431 4355
Sheol No. 7 Placer 908431 4355
Sheol No. 8 Placer 908431 4355
Sheol Nos. 4 & 5 Placer (portions) 908431 4355
Sheol Sulphur Mine No. 1 Placer 908431 4355
Sheol Sulphur Mine No. 2 Placer 908431 4355
Sheol Sulphur Mine No. 3 Placer 908431 4355
Swager Placer 1213605 4839
West Virginia No. 1 1064817 4688A
West Virginia No. 2 1064817 4688A

 

Hycroft Mine Project

Page 282

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Appendix B – Unpatented Claims

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
Airstrip #1 4/09/1958 Crofoot Henry NMC88292 Humboldt
Airstrip #2 4/09/1958 Crofoot Henry NMC88293 Humboldt
Airstrip #3 4/09/1958 Crofoot Henry NMC88294 Humboldt
Airstrip #4 4/02/1958 Crofoot Henry NMC88295 Humboldt
Airstrip #5 4/02/1958 Crofoot Henry NMC88296 Humboldt
Airstrip Fraction 7/27/1967 Crofoot Henry NMC88297 Humboldt
Albert Lode 1 1/27/2026 Hycroft Resources & Development, LLC In Process - Application Submitted Humboldt
Albert Lode 2 1/27/2026 Hycroft Resources & Development, LLC In Process - Application Submitted Humboldt
Albert 3/11/1989 Kolb Theodore A NMC546000 Humboldt
Alunite 11/04/1980 Lewis Frank W NMC181012 Humboldt
Alunite #2 11/04/1980 Lewis Frank W NMC181013 Humboldt
Anita 3/11/1989 Kolb Theodore A NMC545998 Humboldt
Ashlode 3/11/1989 Kolb Theodore A NMC545999 Humboldt
Blackrock #2 3/11/1989 Kolb Theodore A NMC545996 Humboldt
CKC #1 3/03/1973 Crofoot Daniel M NMC88348 Humboldt
CKC #10 3/11/1989 Crofoot Daniel M NMC546001 Humboldt
CKC #11 3/11/1989 Crofoot Daniel M NMC546002 Humboldt
CKC #13 3/11/1989 Crofoot Daniel M NMC546003 Humboldt
CKC #14 3/11/1989 Crofoot Daniel M NMC546004 Humboldt
CKC #15 8/14/1987 Crofoot Daniel M NMC444112 Humboldt
CKC #2 3/03/1973 Crofoot Daniel M NMC88349 Humboldt
CKC #3 4/03/1973 Crofoot Daniel M NMC88350 Humboldt
CKC #4 4/03/1973 Crofoot Daniel M NMC88351 Humboldt
CKC #5 4/03/1973 Crofoot Daniel M NMC88352 Humboldt
CKC #6 4/03/1973 Crofoot Daniel M NMC88353 Humboldt
CKC #7 9/06/1973 Crofoot Daniel M NMC88354 Humboldt
DIA #1 8/25/1983 Lewis Frank W NMC284248 Humboldt
DIA #2 8/25/1983 Lewis Frank W NMC284249 Humboldt
DIA #3 8/25/1983 Lewis Frank W NMC284250 Humboldt
DIA #4 8/25/1983 Lewis Frank W NMC284251 Humboldt
DIA #5 8/25/1983 Lewis Frank W NMC284252 Humboldt
FG 223 9/05/2006 Hycroft Res & Dev Inc NMC939256 Humboldt
FG 224 9/05/2006 Hycroft Res & Dev Inc NMC939257 Humboldt
FG 225 9/05/2006 Hycroft Res & Dev Inc NMC939258 Humboldt
FG 270 9/01/2006 Hycroft Res & Dev Inc NMC939291 Humboldt
FG 271 9/01/2006 Hycroft Res & Dev Inc NMC939292 Humboldt
FG 272 9/01/2006 Hycroft Res & Dev Inc NMC939293 Humboldt
FG 273 9/01/2006 Hycroft Res & Dev Inc NMC939294 Humboldt
FG 274 9/01/2006 Hycroft Res & Dev Inc NMC939295 Humboldt
FG 319 9/01/2006 Hycroft Res & Dev Inc NMC939332 Humboldt
FG 320 9/01/2006 Hycroft Res & Dev Inc NMC939333 Humboldt
FG 321 9/01/2006 Hycroft Res & Dev Inc NMC939334 Humboldt

 

Hycroft Mine Project

Page 283

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 322 9/01/2006 Hycroft Res & Dev Inc NMC939335 Humboldt
FG 323 9/01/2006 Hycroft Res & Dev Inc NMC939336 Humboldt
FG 368 9/01/2006 Hycroft Res & Dev Inc NMC939373 Humboldt
FG 369 9/01/2006 Hycroft Res & Dev Inc NMC939374 Humboldt
FG 370 9/01/2006 Hycroft Res & Dev Inc NMC939375 Humboldt
FG 371 9/01/2006 Hycroft Res & Dev Inc NMC939376 Humboldt
FG 372 9/01/2006 Hycroft Res & Dev Inc NMC939377 Humboldt
FG 373 9/01/2006 Hycroft Res & Dev Inc NMC939378 Humboldt
FG 374 9/01/2006 Hycroft Res & Dev Inc NMC939379 Humboldt
FG 375 9/01/2006 Hycroft Res & Dev Inc NMC939380 Humboldt
FG 376 9/01/2006 Hycroft Res & Dev Inc NMC939381 Humboldt
FG 421 9/01/2006 Hycroft Res & Dev Inc NMC939426 Humboldt
FG 423 9/01/2006 Hycroft Res & Dev Inc NMC939428 Humboldt
FG 424 9/01/2006 Hycroft Res & Dev Inc NMC939429 Humboldt
FG 425 9/01/2006 Hycroft Res & Dev Inc NMC939430 Humboldt
FG 426 9/01/2006 Hycroft Res & Dev Inc NMC939431 Humboldt
FG 427 9/01/2006 Hycroft Res & Dev Inc NMC939432 Humboldt
FG 428 9/01/2006 Hycroft Res & Dev Inc NMC939433 Humboldt
FG 429 9/01/2006 Hycroft Res & Dev Inc NMC939434 Humboldt
FG 430 9/01/2006 Hycroft Res & Dev Inc NMC939435 Humboldt
FG 431 9/01/2006 Hycroft Res & Dev Inc NMC939436 Humboldt
FG 432 9/01/2006 Hycroft Res & Dev Inc NMC939437 Humboldt
FG422 9/01/2006 Hycroft Res & Dev Inc NMC939427 Humboldt
HRDI 224 4/15/2014 Hycroft Res & Dev Inc NMC1102182 Humboldt
HRDI 225 4/15/2014 Hycroft Res & Dev Inc NMC1102183 Humboldt
HRDI 226 4/15/2014 Hycroft Res & Dev Inc NMC1102184 Humboldt
HRDI 227 4/15/2014 Hycroft Res & Dev Inc NMC1102185 Humboldt
HRDI 228 4/15/2014 Hycroft Res & Dev Inc NMC1102186 Humboldt
HRDI 229 4/15/2014 Hycroft Res & Dev Inc NMC1102187 Humboldt
HRDI 230 4/15/2014 Hycroft Res & Dev Inc NMC1102188 Humboldt
Mayo 3/11/1989 Hycroft Res & Dev Inc NMC545997 Humboldt
NC 1 8/14/2010 Hycroft Res & Dev Inc NMC1027839 Humboldt
NC 10 8/14/2010 Hycroft Res & Dev Inc NMC1027848 Humboldt
NC 11 8/14/2010 Hycroft Res & Dev Inc NMC1027849 Humboldt
NC 110 8/14/2010 Hycroft Res & Dev Inc NMC1027948 Humboldt
NC 111 8/14/2010 Hycroft Res & Dev Inc NMC1027949 Humboldt
NC 112 8/14/2010 Hycroft Res & Dev Inc NMC1027950 Humboldt
NC 113 8/14/2010 Hycroft Res & Dev Inc NMC1027951 Humboldt
NC 114 8/14/2010 Hycroft Res & Dev Inc NMC1027952 Humboldt
NC 115 8/14/2010 Hycroft Res & Dev Inc NMC1027953 Humboldt
NC 116 8/14/2010 Hycroft Res & Dev Inc NMC1027954 Humboldt
NC 117 8/14/2010 Hycroft Res & Dev Inc NMC1027955 Humboldt
NC 118 8/14/2010 Hycroft Res & Dev Inc NMC1027956 Humboldt
NC 119 8/14/2010 Hycroft Res & Dev Inc NMC1027957 Humboldt
NC 12 8/14/2010 Hycroft Res & Dev Inc NMC1027850 Humboldt
NC 120 8/14/2010 Hycroft Res & Dev Inc NMC1027958 Humboldt
NC 121 8/14/2010 Hycroft Res & Dev Inc NMC1027959 Humboldt
NC 122 8/14/2010 Hycroft Res & Dev Inc NMC1027960 Humboldt

 

Hycroft Mine Project

Page 284

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 123 8/14/2010 Hycroft Res & Dev Inc NMC1027961 Humboldt
NC 124 8/14/2010 Hycroft Res & Dev Inc NMC1027962 Humboldt
NC 125 8/14/2010 Hycroft Res & Dev Inc NMC1027963 Humboldt
NC 126 8/14/2010 Hycroft Res & Dev Inc NMC1027964 Humboldt
NC 127 8/14/2010 Hycroft Res & Dev Inc NMC1027965 Humboldt
NC 128 8/14/2010 Hycroft Res & Dev Inc NMC1027966 Humboldt
NC 129 8/14/2010 Hycroft Res & Dev Inc NMC1027967 Humboldt
NC 13 8/14/2010 Hycroft Res & Dev Inc NMC1027851 Humboldt
NC 130 8/14/2010 Hycroft Res & Dev Inc NMC1027968 Humboldt
NC 131 8/14/2010 Hycroft Res & Dev Inc NMC1027969 Humboldt
NC 14 8/14/2010 Hycroft Res & Dev Inc NMC1027852 Humboldt
NC 15 8/14/2010 Hycroft Res & Dev Inc NMC1027853 Humboldt
NC 151 8/14/2010 Hycroft Res & Dev Inc NMC1027989 Humboldt
NC 152 8/14/2010 Hycroft Res & Dev Inc NMC1027990 Humboldt
NC 153 8/14/2010 Hycroft Res & Dev Inc NMC1027991 Humboldt
NC 154 8/14/2010 Hycroft Res & Dev Inc NMC1027992 Humboldt
NC 155 8/14/2010 Hycroft Res & Dev Inc NMC1027993 Humboldt
NC 156 8/14/2010 Hycroft Res & Dev Inc NMC1027994 Humboldt
NC 157 8/14/2010 Hycroft Res & Dev Inc NMC1027995 Humboldt
NC 158 8/14/2010 Hycroft Res & Dev Inc NMC1027996 Humboldt
NC 159 8/14/2010 Hycroft Res & Dev Inc NMC1027997 Humboldt
NC 16 8/14/2010 Hycroft Res & Dev Inc NMC1027854 Humboldt
NC 160 8/14/2010 Hycroft Res & Dev Inc NMC1027998 Humboldt
NC 161 8/14/2010 Hycroft Res & Dev Inc NMC1027999 Humboldt
NC 162 8/14/2010 Hycroft Res & Dev Inc NMC1028000 Humboldt
NC 163 8/14/2010 Hycroft Res & Dev Inc NMC1028001 Humboldt
NC 164 8/14/2010 Hycroft Res & Dev Inc NMC1028002 Humboldt
NC 165 8/14/2010 Hycroft Res & Dev Inc NMC1028003 Humboldt
NC 166 8/14/2010 Hycroft Res & Dev Inc NMC1028004 Humboldt
NC 167 8/14/2010 Hycroft Res & Dev Inc NMC1028005 Humboldt
NC 168 8/14/2010 Hycroft Res & Dev Inc NMC1028006 Humboldt
NC 169 8/14/2010 Hycroft Res & Dev Inc NMC1028007 Humboldt
NC 189 8/14/2010 Hycroft Res & Dev Inc NMC1028027 Humboldt
NC 190 8/14/2010 Hycroft Res & Dev Inc NMC1028028 Humboldt
NC 191 8/14/2010 Hycroft Res & Dev Inc NMC1028029 Humboldt
NC 192 8/14/2010 Hycroft Res & Dev Inc NMC1028030 Humboldt
NC 193 8/14/2010 Hycroft Res & Dev Inc NMC1028031 Humboldt
NC 194 8/14/2010 Hycroft Res & Dev Inc NMC1028032 Humboldt
NC 195 8/14/2010 Hycroft Res & Dev Inc NMC1028033 Humboldt
NC 196 8/14/2010 Hycroft Res & Dev Inc NMC1028034 Humboldt
NC 197 8/14/2010 Hycroft Res & Dev Inc NMC1028035 Humboldt
NC 198 8/14/2010 Hycroft Res & Dev Inc NMC1028036 Humboldt
NC 199 8/14/2010 Hycroft Res & Dev Inc NMC1028037 Humboldt
NC 2 8/14/2010 Hycroft Res & Dev Inc NMC1027840 Humboldt
NC 200 8/14/2010 Hycroft Res & Dev Inc NMC1028038 Humboldt
NC 201 8/14/2010 Hycroft Res & Dev Inc NMC1028039 Humboldt
NC 202 8/14/2010 Hycroft Res & Dev Inc NMC1028040 Humboldt
NC 203 8/14/2010 Hycroft Res & Dev Inc NMC1028041 Humboldt

 

Hycroft Mine Project

Page 285

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 204 8/14/2010 Hycroft Res & Dev Inc NMC1028042 Humboldt
NC 224 8/14/2010 Hycroft Res & Dev Inc NMC1028062 Humboldt
NC 225 8/14/2010 Hycroft Res & Dev Inc NMC1028063 Humboldt
NC 226 8/14/2010 Hycroft Res & Dev Inc NMC1028064 Humboldt
NC 227 8/14/2010 Hycroft Res & Dev Inc NMC1028065 Humboldt
NC 228 8/14/2010 Hycroft Res & Dev Inc NMC1028066 Humboldt
NC 229 8/14/2010 Hycroft Res & Dev Inc NMC1028067 Humboldt
NC 230 8/14/2010 Hycroft Res & Dev Inc NMC1028068 Humboldt
NC 231 8/14/2010 Hycroft Res & Dev Inc NMC1028069 Humboldt
NC 232 8/14/2010 Hycroft Res & Dev Inc NMC1028070 Humboldt
NC 233 8/14/2010 Hycroft Res & Dev Inc NMC1028071 Humboldt
NC 234 8/14/2010 Hycroft Res & Dev Inc NMC1028072 Humboldt
NC 235 8/14/2010 Hycroft Res & Dev Inc NMC1028073 Humboldt
NC 236 8/14/2010 Hycroft Res & Dev Inc NMC1028074 Humboldt
NC 237 8/14/2010 Hycroft Res & Dev Inc NMC1028075 Humboldt
NC 238 8/14/2010 Hycroft Res & Dev Inc NMC1028076 Humboldt
NC 239 8/14/2010 Hycroft Res & Dev Inc NMC1028077 Humboldt
NC 259 8/14/2010 Hycroft Res & Dev Inc NMC1028097 Humboldt
NC 260 8/14/2010 Hycroft Res & Dev Inc NMC1028098 Humboldt
NC 261 8/14/2010 Hycroft Res & Dev Inc NMC1028099 Humboldt
NC 262 8/14/2010 Hycroft Res & Dev Inc NMC1028100 Humboldt
NC 263 8/14/2010 Hycroft Res & Dev Inc NMC1028101 Humboldt
NC 264 8/14/2010 Hycroft Res & Dev Inc NMC1028102 Humboldt
NC 265 8/14/2010 Hycroft Res & Dev Inc NMC1028103 Humboldt
NC 266 8/14/2010 Hycroft Res & Dev Inc NMC1028104 Humboldt
NC 267 8/14/2010 Hycroft Res & Dev Inc NMC1028105 Humboldt
NC 268 8/14/2010 Hycroft Res & Dev Inc NMC1028106 Humboldt
NC 269 8/14/2010 Hycroft Res & Dev Inc NMC1028107 Humboldt
NC 270 8/14/2010 Hycroft Res & Dev Inc NMC1028108 Humboldt
NC 271 8/14/2010 Hycroft Res & Dev Inc NMC1028109 Humboldt
NC 272 8/14/2010 Hycroft Res & Dev Inc NMC1028110 Humboldt
NC 273 8/14/2010 Hycroft Res & Dev Inc NMC1028111 Humboldt
NC 293 8/14/2010 Hycroft Res & Dev Inc NMC1028131 Humboldt
NC 294 8/14/2010 Hycroft Res & Dev Inc NMC1028132 Humboldt
NC 295 8/14/2010 Hycroft Res & Dev Inc NMC1028133 Humboldt
NC 296 8/14/2010 Hycroft Res & Dev Inc NMC1028134 Humboldt
NC 297 8/14/2010 Hycroft Res & Dev Inc NMC1028135 Humboldt
NC 298 8/14/2010 Hycroft Res & Dev Inc NMC1028136 Humboldt
NC 299 8/14/2010 Hycroft Res & Dev Inc NMC1028137 Humboldt
NC 3 8/14/2010 Hycroft Res & Dev Inc NMC1027841 Humboldt
NC 300 8/14/2010 Hycroft Res & Dev Inc NMC1028138 Humboldt
NC 301 8/14/2010 Hycroft Res & Dev Inc NMC1028139 Humboldt
NC 302 8/14/2010 Hycroft Res & Dev Inc NMC1028140 Humboldt
NC 303 8/14/2010 Hycroft Res & Dev Inc NMC1028141 Humboldt
NC 304 8/14/2010 Hycroft Res & Dev Inc NMC1028142 Humboldt
NC 305 8/14/2010 Hycroft Res & Dev Inc NMC1028143 Humboldt
NC 31 8/14/2010 Hycroft Res & Dev Inc NMC1027869 Humboldt
NC 32 8/14/2010 Hycroft Res & Dev Inc NMC1027870 Humboldt

 

Hycroft Mine Project

Page 286

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 33 8/14/2010 Hycroft Res & Dev Inc NMC1027871 Humboldt
NC 34 8/14/2010 Hycroft Res & Dev Inc NMC1027872 Humboldt
NC 35 8/14/2010 Hycroft Res & Dev Inc NMC1027873 Humboldt
NC 36 8/14/2010 Hycroft Res & Dev Inc NMC1027874 Humboldt
NC 37 8/14/2010 Hycroft Res & Dev Inc NMC1027875 Humboldt
NC 38 8/14/2010 Hycroft Res & Dev Inc NMC1027876 Humboldt
NC 39 8/14/2010 Hycroft Res & Dev Inc NMC1027877 Humboldt
NC 4 8/14/2010 Hycroft Res & Dev Inc NMC1027842 Humboldt
NC 40 8/14/2010 Hycroft Res & Dev Inc NMC1027878 Humboldt
NC 41 8/14/2010 Hycroft Res & Dev Inc NMC1027879 Humboldt
NC 42 8/14/2010 Hycroft Res & Dev Inc NMC1027880 Humboldt
NC 43 8/14/2010 Hycroft Res & Dev Inc NMC1027881 Humboldt
NC 44 8/14/2010 Hycroft Res & Dev Inc NMC1027882 Humboldt
NC 45 8/14/2010 Hycroft Res & Dev Inc NMC1027883 Humboldt
NC 46 8/14/2010 Hycroft Res & Dev Inc NMC1027884 Humboldt
NC 47 8/14/2010 Hycroft Res & Dev Inc NMC1027885 Humboldt
NC 48 8/14/2010 Hycroft Res & Dev Inc NMC1027886 Humboldt
NC 49 8/14/2010 Hycroft Res & Dev Inc NMC1027887 Humboldt
NC 5 8/14/2010 Hycroft Res & Dev Inc NMC1027843 Humboldt
NC 6 8/14/2010 Hycroft Res & Dev Inc NMC1027844 Humboldt
NC 69 8/14/2010 Hycroft Res & Dev Inc NMC1027907 Humboldt
NC 7 8/14/2010 Hycroft Res & Dev Inc NMC1027845 Humboldt
NC 70 8/14/2010 Hycroft Res & Dev Inc NMC1027908 Humboldt
NC 71 8/14/2010 Hycroft Res & Dev Inc NMC1027909 Humboldt
NC 72 8/14/2010 Hycroft Res & Dev Inc NMC1027910 Humboldt
NC 73 8/14/2010 Hycroft Res & Dev Inc NMC1027911 Humboldt
NC 74 8/14/2010 Hycroft Res & Dev Inc NMC1027912 Humboldt
NC 75 8/14/2010 Hycroft Res & Dev Inc NMC1027913 Humboldt
NC 76 8/14/2010 Hycroft Res & Dev Inc NMC1027914 Humboldt
NC 77 8/14/2010 Hycroft Res & Dev Inc NMC1027915 Humboldt
NC 78 8/14/2010 Hycroft Res & Dev Inc NMC1027916 Humboldt
NC 79 8/14/2010 Hycroft Res & Dev Inc NMC1027917 Humboldt
NC 8 8/14/2010 Hycroft Res & Dev Inc NMC1027846 Humboldt
NC 80 8/14/2010 Hycroft Res & Dev Inc NMC1027918 Humboldt
NC 81 8/14/2010 Hycroft Res & Dev Inc NMC1027919 Humboldt
NC 82 8/14/2010 Hycroft Res & Dev Inc NMC1027920 Humboldt
NC 83 8/14/2010 Hycroft Res & Dev Inc NMC1027921 Humboldt
NC 84 8/14/2010 Hycroft Res & Dev Inc NMC1027922 Humboldt
NC 85 8/14/2010 Hycroft Res & Dev Inc NMC1027923 Humboldt
NC 86 8/14/2010 Hycroft Res & Dev Inc NMC1027924 Humboldt
NC 87 8/14/2010 Hycroft Res & Dev Inc NMC1027925 Humboldt
NC 88 8/14/2010 Hycroft Res & Dev Inc NMC1027926 Humboldt
NC 89 8/14/2010 Hycroft Res & Dev Inc NMC1027927 Humboldt
NC 9 8/14/2010 Hycroft Res & Dev Inc NMC1027847 Humboldt
NC 90 8/14/2010 Hycroft Res & Dev Inc NMC1027928 Humboldt
NFG 1 10/10/2006 Hycroft Res & Dev Inc NMC939506 Humboldt
NFG 10 10/10/2006 Hycroft Res & Dev Inc NMC939515 Humboldt
NFG 100 10/10/2006 Hycroft Res & Dev Inc NMC939604 Humboldt

 

Hycroft Mine Project

Page 287

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NFG 101 10/10/2006 Hycroft Res & Dev Inc NMC939605 Humboldt
NFG 102 10/10/2006 Hycroft Res & Dev Inc NMC939606 Humboldt
NFG 103 10/10/2006 Hycroft Res & Dev Inc NMC939607 Humboldt
NFG 104 10/10/2006 Hycroft Res & Dev Inc NMC939608 Humboldt
NFG 105 10/10/2006 Hycroft Res & Dev Inc NMC939609 Humboldt
NFG 106 10/10/2006 Hycroft Res & Dev Inc NMC939610 Humboldt
NFG 107 10/10/2006 Hycroft Res & Dev Inc NMC939611 Humboldt
NFG 108 10/10/2006 Hycroft Res & Dev Inc NMC939612 Humboldt
NFG 109 10/10/2006 Hycroft Res & Dev Inc NMC939613 Humboldt
NFG 11 10/10/2006 Hycroft Res & Dev Inc NMC939516 Humboldt
NFG 110 10/10/2006 Hycroft Res & Dev Inc NMC939614 Humboldt
NFG 111 10/10/2006 Hycroft Res & Dev Inc NMC939615 Humboldt
NFG 112 10/10/2006 Hycroft Res & Dev Inc NMC939616 Humboldt
NFG 113 10/10/2006 Hycroft Res & Dev Inc NMC939617 Humboldt
NFG 114 10/10/2006 Hycroft Res & Dev Inc NMC939618 Humboldt
NFG 115 10/10/2006 Hycroft Res & Dev Inc NMC939619 Humboldt
NFG 116 10/10/2006 Hycroft Res & Dev Inc NMC939620 Humboldt
NFG 117 10/10/2006 Hycroft Res & Dev Inc NMC939621 Humboldt
NFG 118 10/10/2006 Hycroft Res & Dev Inc NMC939622 Humboldt
NFG 119 10/10/2006 Hycroft Res & Dev Inc NMC939623 Humboldt
NFG 12 10/10/2006 Hycroft Res & Dev Inc NMC939517 Humboldt
NFG 120 10/10/2006 Hycroft Res & Dev Inc NMC939624 Humboldt
NFG 121 10/10/2006 Hycroft Res & Dev Inc NMC939625 Humboldt
NFG 122 10/10/2006 Hycroft Res & Dev Inc NMC939626 Humboldt
NFG 123 10/10/2006 Hycroft Res & Dev Inc NMC939627 Humboldt
NFG 124 10/10/2006 Hycroft Res & Dev Inc NMC939628 Humboldt
NFG 125 10/10/2006 Hycroft Res & Dev Inc NMC939629 Humboldt
NFG 126 10/10/2006 Hycroft Res & Dev Inc NMC939630 Humboldt
NFG 127 10/10/2006 Hycroft Res & Dev Inc NMC939631 Humboldt
NFG 128 10/10/2006 Hycroft Res & Dev Inc NMC939632 Humboldt
NFG 129 10/10/2006 Hycroft Res & Dev Inc NMC939633 Humboldt
NFG 13 10/10/2006 Hycroft Res & Dev Inc NMC939518 Humboldt
NFG 130 10/10/2006 Hycroft Res & Dev Inc NMC939634 Humboldt
NFG 131 10/10/2006 Hycroft Res & Dev Inc NMC939635 Humboldt
NFG 132 10/10/2006 Hycroft Res & Dev Inc NMC939636 Humboldt
NFG 133 10/10/2006 Hycroft Res & Dev Inc NMC939637 Humboldt
NFG 134 10/10/2006 Hycroft Res & Dev Inc NMC939638 Humboldt
NFG 135 10/10/2006 Hycroft Res & Dev Inc NMC939639 Humboldt
NFG 136 10/10/2006 Hycroft Res & Dev Inc NMC939640 Humboldt
NFG 137 10/10/2006 Hycroft Res & Dev Inc NMC939641 Humboldt
NFG 138 10/10/2006 Hycroft Res & Dev Inc NMC939642 Humboldt
NFG 139 10/10/2006 Hycroft Res & Dev Inc NMC939643 Humboldt
NFG 14 10/10/2006 Hycroft Res & Dev Inc NMC939519 Humboldt
NFG 140 10/10/2006 Hycroft Res & Dev Inc NMC939644 Humboldt
NFG 141 10/10/2006 Hycroft Res & Dev Inc NMC939645 Humboldt
NFG 142 10/10/2006 Hycroft Res & Dev Inc NMC939646 Humboldt
NFG 143 10/10/2006 Hycroft Res & Dev Inc NMC939647 Humboldt
NFG 144 10/10/2006 Hycroft Res & Dev Inc NMC939648 Humboldt

 

Hycroft Mine Project

Page 288

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NFG 145 10/10/2006 Hycroft Res & Dev Inc NMC939649 Humboldt
NFG 146 10/10/2006 Hycroft Res & Dev Inc NMC939650 Humboldt
NFG 147 10/10/2006 Hycroft Res & Dev Inc NMC939651 Humboldt
NFG 148 10/10/2006 Hycroft Res & Dev Inc NMC939652 Humboldt
NFG 149 10/10/2006 Hycroft Res & Dev Inc NMC939653 Humboldt
NFG 15 10/10/2006 Hycroft Res & Dev Inc NMC939520 Humboldt
NFG 150 10/10/2006 Hycroft Res & Dev Inc NMC939654 Humboldt
NFG 151 10/10/2006 Hycroft Res & Dev Inc NMC939655 Humboldt
NFG 152 10/10/2006 Hycroft Res & Dev Inc NMC939656 Humboldt
NFG 153 10/10/2006 Hycroft Res & Dev Inc NMC939657 Humboldt
NFG 154 10/10/2006 Hycroft Res & Dev Inc NMC939658 Humboldt
NFG 155 10/10/2006 Hycroft Res & Dev Inc NMC939659 Humboldt
NFG 156 10/10/2006 Hycroft Res & Dev Inc NMC939660 Humboldt
NFG 157 10/10/2006 Hycroft Res & Dev Inc NMC939661 Humboldt
NFG 158 10/10/2006 Hycroft Res & Dev Inc NMC939662 Humboldt
NFG 159 10/10/2006 Hycroft Res & Dev Inc NMC939663 Humboldt
NFG 16 10/10/2006 Hycroft Res & Dev Inc NMC939521 Humboldt
NFG 160 10/10/2006 Hycroft Res & Dev Inc NMC939664 Humboldt
NFG 161 10/10/2006 Hycroft Res & Dev Inc NMC939665 Humboldt
NFG 162 10/10/2006 Hycroft Res & Dev Inc NMC939666 Humboldt
NFG 163 10/10/2006 Hycroft Res & Dev Inc NMC939667 Humboldt
NFG 164 10/10/2006 Hycroft Res & Dev Inc NMC939668 Humboldt
NFG 165 10/10/2006 Hycroft Res & Dev Inc NMC939669 Humboldt
NFG 166 10/10/2006 Hycroft Res & Dev Inc NMC939670 Humboldt
NFG 167 10/10/2006 Hycroft Res & Dev Inc NMC939671 Humboldt
NFG 168 10/10/2006 Hycroft Res & Dev Inc NMC939672 Humboldt
NFG 169 10/10/2006 Hycroft Res & Dev Inc NMC939673 Humboldt
NFG 17 10/10/2006 Hycroft Res & Dev Inc NMC939522 Humboldt
NFG 170 10/10/2006 Hycroft Res & Dev Inc NMC939674 Humboldt
NFG 171 10/10/2006 Hycroft Res & Dev Inc NMC939675 Humboldt
NFG 172 10/10/2006 Hycroft Res & Dev Inc NMC939676 Humboldt
NFG 173 10/10/2006 Hycroft Res & Dev Inc NMC939677 Humboldt
NFG 174 10/10/2006 Hycroft Res & Dev Inc NMC939678 Humboldt
NFG 175 10/10/2006 Hycroft Res & Dev Inc NMC939679 Humboldt
NFG 176 10/10/2006 Hycroft Res & Dev Inc NMC939680 Humboldt
NFG 177 10/10/2006 Hycroft Res & Dev Inc NMC939681 Humboldt
NFG 178 10/10/2006 Hycroft Res & Dev Inc NMC939682 Humboldt
NFG 179 10/10/2006 Hycroft Res & Dev Inc NMC939683 Humboldt
NFG 18 10/10/2006 Hycroft Res & Dev Inc NMC939523 Humboldt
NFG 180 10/10/2006 Hycroft Res & Dev Inc NMC939684 Humboldt
NFG 181 10/10/2006 Hycroft Res & Dev Inc NMC939685 Humboldt
NFG 182 10/10/2006 Hycroft Res & Dev Inc NMC939686 Humboldt
NFG 183 10/10/2006 Hycroft Res & Dev Inc NMC939687 Humboldt
NFG 184 10/10/2006 Hycroft Res & Dev Inc NMC939688 Humboldt
NFG 185 10/10/2006 Hycroft Res & Dev Inc NMC939689 Humboldt
NFG 186 10/10/2006 Hycroft Res & Dev Inc NMC939690 Humboldt
NFG 187 10/10/2006 Hycroft Res & Dev Inc NMC939691 Humboldt
NFG 19 10/10/2006 Hycroft Res & Dev Inc NMC939524 Humboldt

 

Hycroft Mine Project

Page 289

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NFG 2 10/10/2006 Hycroft Res & Dev Inc NMC939507 Humboldt
NFG 20 10/10/2006 Hycroft Res & Dev Inc NMC939525 Humboldt
NFG 21 10/10/2006 Hycroft Res & Dev Inc NMC939526 Humboldt
NFG 22 10/10/2006 Hycroft Res & Dev Inc NMC939527 Humboldt
NFG 23 10/10/2006 Hycroft Res & Dev Inc NMC939528 Humboldt
NFG 24 10/10/2006 Hycroft Res & Dev Inc NMC939529 Humboldt
NFG 25 10/10/2006 Hycroft Res & Dev Inc NMC939530 Humboldt
NFG 26 10/10/2006 Hycroft Res & Dev Inc NMC939531 Humboldt
NFG 27 10/10/2006 Hycroft Res & Dev Inc NMC939532 Humboldt
NFG 28 10/10/2006 Hycroft Res & Dev Inc NMC939533 Humboldt
NFG 29 10/10/2006 Hycroft Res & Dev Inc NMC939534 Humboldt
NFG 3 10/10/2006 Hycroft Res & Dev Inc NMC939508 Humboldt
NFG 30 10/10/2006 Hycroft Res & Dev Inc NMC939535 Humboldt
NFG 31 10/10/2006 Hycroft Res & Dev Inc NMC939536 Humboldt
NFG 32 10/10/2006 Hycroft Res & Dev Inc NMC939537 Humboldt
NFG 33 10/10/2006 Hycroft Res & Dev Inc NMC939538 Humboldt
NFG 34 10/10/2006 Hycroft Res & Dev Inc NMC939539 Humboldt
NFG 35 10/10/2006 Hycroft Res & Dev Inc NMC939540 Humboldt
NFG 36 10/10/2006 Hycroft Res & Dev Inc NMC939541 Humboldt
NFG 37 10/10/2006 Hycroft Res & Dev Inc NMC939542 Humboldt
NFG 38 10/10/2006 Hycroft Res & Dev Inc NMC939543 Humboldt
NFG 39 10/10/2006 Hycroft Res & Dev Inc NMC939544 Humboldt
NFG 4 10/10/2006 Hycroft Res & Dev Inc NMC939509 Humboldt
NFG 40 10/10/2006 Hycroft Res & Dev Inc NMC939545 Humboldt
NFG 41 10/10/2006 Hycroft Res & Dev Inc NMC939546 Humboldt
NFG 42 10/10/2006 Hycroft Res & Dev Inc NMC939547 Humboldt
NFG 43 10/10/2006 Hycroft Res & Dev Inc NMC939548 Humboldt
NFG 44 10/10/2006 Hycroft Res & Dev Inc NMC939549 Humboldt
NFG 45 10/10/2006 Hycroft Res & Dev Inc NMC939550 Humboldt
NFG 46 10/10/2006 Hycroft Res & Dev Inc NMC939551 Humboldt
NFG 47 10/10/2006 Hycroft Res & Dev Inc NMC939552 Humboldt
NFG 48 10/10/2006 Hycroft Res & Dev Inc NMC939553 Humboldt
NFG 49 10/10/2006 Hycroft Res & Dev Inc NMC939554 Humboldt
NFG 5 10/10/2006 Hycroft Res & Dev Inc NMC939510 Humboldt
NFG 50 10/10/2006 Hycroft Res & Dev Inc NMC939555 Humboldt
NFG 51 10/10/2006 Hycroft Res & Dev Inc NMC939556 Humboldt
NFG 52 10/10/2006 Hycroft Res & Dev Inc NMC939557 Humboldt
NFG 53 10/10/2006 Hycroft Res & Dev Inc NMC939558 Humboldt
NFG 54 10/10/2006 Hycroft Res & Dev Inc NMC939559 Humboldt
NFG 55 10/10/2006 Hycroft Res & Dev Inc NMC939560 Humboldt
NFG 56 10/10/2006 Hycroft Res & Dev Inc NMC939561 Humboldt
NFG 57 10/10/2006 Hycroft Res & Dev Inc NMC939562 Humboldt
NFG 58 10/10/2006 Hycroft Res & Dev Inc NMC939563 Humboldt
NFG 59 10/10/2006 Hycroft Res & Dev Inc NMC939564 Humboldt
NFG 6 10/10/2006 Hycroft Res & Dev Inc NMC939511 Humboldt
NFG 60 10/10/2006 Hycroft Res & Dev Inc NMC939565 Humboldt
NFG 61 10/10/2006 Hycroft Res & Dev Inc NMC939566 Humboldt
NFG 62 10/10/2006 Hycroft Res & Dev Inc NMC939567 Humboldt

 

Hycroft Mine Project

Page 290

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NFG 63 10/10/2006 Hycroft Res & Dev Inc NMC939568 Humboldt
NFG 64 10/10/2006 Hycroft Res & Dev Inc NMC939569 Humboldt
NFG 65 10/10/2006 Hycroft Res & Dev Inc NMC939570 Humboldt
NFG 66 10/10/2006 Hycroft Res & Dev Inc NMC939571 Humboldt
NFG 67 10/10/2006 Hycroft Res & Dev Inc NMC939572 Humboldt
NFG 68 10/10/2006 Hycroft Res & Dev Inc NMC939573 Humboldt
NFG 69 10/10/2006 Hycroft Res & Dev Inc NMC939574 Humboldt
NFG 7 10/10/2006 Hycroft Res & Dev Inc NMC939512 Humboldt
NFG 70 10/10/2006 Hycroft Res & Dev Inc NMC939575 Humboldt
NFG 71 10/10/2006 Hycroft Res & Dev Inc NMC939576 Humboldt
NFG 72 10/10/2006 Hycroft Res & Dev Inc NMC939577 Humboldt
NFG 73 10/10/2006 Hycroft Res & Dev Inc NMC939578 Humboldt
NFG 74 10/10/2006 Hycroft Res & Dev Inc NMC939579 Humboldt
NFG 76 10/10/2006 Hycroft Res & Dev Inc NMC939580 Humboldt
NFG 78 10/10/2006 Hycroft Res & Dev Inc NMC939582 Humboldt
NFG 79 10/10/2006 Hycroft Res & Dev Inc NMC939583 Humboldt
NFG 8 10/10/2006 Hycroft Res & Dev Inc NMC939513 Humboldt
NFG 80 10/10/2006 Hycroft Res & Dev Inc NMC939584 Humboldt
NFG 81 10/10/2006 Hycroft Res & Dev Inc NMC939585 Humboldt
NFG 82 10/10/2006 Hycroft Res & Dev Inc NMC939586 Humboldt
NFG 83 10/10/2006 Hycroft Res & Dev Inc NMC939587 Humboldt
NFG 84 10/10/2006 Hycroft Res & Dev Inc NMC939588 Humboldt
NFG 85 10/10/2006 Hycroft Res & Dev Inc NMC939589 Humboldt
NFG 86 10/10/2006 Hycroft Res & Dev Inc NMC939590 Humboldt
NFG 87 10/10/2006 Hycroft Res & Dev Inc NMC939591 Humboldt
NFG 88 10/10/2006 Hycroft Res & Dev Inc NMC939592 Humboldt
NFG 89 10/10/2006 Hycroft Res & Dev Inc NMC939593 Humboldt
NFG 9 10/10/2006 Hycroft Res & Dev Inc NMC939514 Humboldt
NFG 90 10/10/2006 Hycroft Res & Dev Inc NMC939594 Humboldt
NFG 91 10/10/2006 Hycroft Res & Dev Inc NMC939595 Humboldt
NFG 92 10/10/2006 Hycroft Res & Dev Inc NMC939596 Humboldt
NFG 93 10/10/2006 Hycroft Res & Dev Inc NMC939597 Humboldt
NFG 94 10/10/2006 Hycroft Res & Dev Inc NMC939598 Humboldt
NFG 95 10/10/2006 Hycroft Res & Dev Inc NMC939599 Humboldt
NFG 96 10/10/2006 Hycroft Res & Dev Inc NMC939600 Humboldt
NFG 97 10/10/2006 Hycroft Res & Dev Inc NMC939601 Humboldt
NFG 98 10/10/2006 Hycroft Res & Dev Inc NMC939602 Humboldt
NFG 99 10/10/2006 Hycroft Res & Dev Inc NMC939603 Humboldt
NFG77 10/10/2006 Hycroft Res & Dev Inc NMC939581 Humboldt
NFRA 1 11/07/2007 Victory Exploration Inc. NMC977833 Humboldt
NFRA 2 11/07/2007 Victory Exploration Inc. NMC977834 Humboldt
NFRA 20 11/08/2007 Victory Exploration Inc. NMC977852 Humboldt
NFRA 3 11/07/2007 Victory Exploration Inc. NMC977835 Humboldt
NFRA16 11/07/2007 Victory Exploration Inc. NMC977848 Humboldt
NFRA17 11/07/2007 Victory Exploration Inc. NMC977849 Humboldt
NFRA18 11/07/2007 Victory Exploration Inc. NMC977850 Humboldt
NFRA19 11/07/2007 Victory Exploration Inc. NMC977851 Humboldt
NH 1 5/04/2008 Hycroft Res & Dev Inc NMC990154 Humboldt

 

Hycroft Mine Project

Page 291

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 10 5/04/2008 Hycroft Res & Dev Inc NMC990163 Humboldt
NH 100 5/03/2008 Hycroft Res & Dev Inc NMC990253 Humboldt
NH 101 5/03/2008 Hycroft Res & Dev Inc NMC990254 Humboldt
NH 102 5/03/2008 Hycroft Res & Dev Inc NMC990255 Humboldt
NH 103 5/03/2008 Hycroft Res & Dev Inc NMC990256 Humboldt
NH 104 5/03/2008 Hycroft Res & Dev Inc NMC990257 Humboldt
NH 105 5/03/2008 Hycroft Res & Dev Inc NMC990258 Humboldt
NH 106 5/03/2008 Hycroft Res & Dev Inc NMC990259 Humboldt
NH 107 5/03/2008 Hycroft Res & Dev Inc NMC990260 Humboldt
NH 108 5/03/2008 Hycroft Res & Dev Inc NMC990261 Humboldt
NH 109 5/03/2008 Hycroft Res & Dev Inc NMC990262 Humboldt
NH 11 5/04/2008 Hycroft Res & Dev Inc NMC990164 Humboldt
NH 110 5/03/2008 Hycroft Res & Dev Inc NMC990263 Humboldt
NH 111 5/03/2008 Hycroft Res & Dev Inc NMC990264 Humboldt
NH 112 5/03/2008 Hycroft Res & Dev Inc NMC990265 Humboldt
NH 113 5/03/2008 Hycroft Res & Dev Inc NMC990266 Humboldt
NH 114 5/03/2008 Hycroft Res & Dev Inc NMC990267 Humboldt
NH 115 5/03/2008 Hycroft Res & Dev Inc NMC990268 Humboldt
NH 116 5/03/2008 Hycroft Res & Dev Inc NMC990269 Humboldt
NH 117 5/03/2008 Hycroft Res & Dev Inc NMC990270 Humboldt
NH 118 5/03/2008 Hycroft Res & Dev Inc NMC990271 Humboldt
NH 119 5/03/2008 Hycroft Res & Dev Inc NMC990272 Humboldt
NH 12 5/04/2008 Hycroft Res & Dev Inc NMC990165 Humboldt
NH 120 5/03/2008 Hycroft Res & Dev Inc NMC990273 Humboldt
NH 121 5/03/2008 Hycroft Res & Dev Inc NMC990274 Humboldt
NH 122 5/03/2008 Hycroft Res & Dev Inc NMC990275 Humboldt
NH 123 5/03/2008 Hycroft Res & Dev Inc NMC990276 Humboldt
NH 124 5/03/2008 Hycroft Res & Dev Inc NMC990277 Humboldt
NH 125 5/03/2008 Hycroft Res & Dev Inc NMC990278 Humboldt
NH 126 5/03/2008 Hycroft Res & Dev Inc NMC990279 Humboldt
NH 127 5/03/2008 Hycroft Res & Dev Inc NMC990280 Humboldt
NH 128 5/03/2008 Hycroft Res & Dev Inc NMC990281 Humboldt
NH 129 5/03/2008 Hycroft Res & Dev Inc NMC990282 Humboldt
NH 13 5/04/2008 Hycroft Res & Dev Inc NMC990166 Humboldt
NH 130 5/03/2008 Hycroft Res & Dev Inc NMC990283 Humboldt
NH 131 5/03/2008 Hycroft Res & Dev Inc NMC990284 Humboldt
NH 132 5/03/2008 Hycroft Res & Dev Inc NMC990285 Humboldt
NH 133 5/03/2008 Hycroft Res & Dev Inc NMC990286 Humboldt
NH 134 5/03/2008 Hycroft Res & Dev Inc NMC990287 Humboldt
NH 135 5/03/2008 Hycroft Res & Dev Inc NMC990288 Humboldt
NH 136 5/03/2008 Hycroft Res & Dev Inc NMC990289 Humboldt
NH 137 5/03/2008 Hycroft Res & Dev Inc NMC990290 Humboldt
NH 138 5/03/2008 Hycroft Res & Dev Inc NMC990291 Humboldt
NH 139 5/03/2008 Hycroft Res & Dev Inc NMC990292 Humboldt
NH 14 5/04/2008 Hycroft Res & Dev Inc NMC990167 Humboldt
NH 140 5/03/2008 Hycroft Res & Dev Inc NMC990293 Humboldt
NH 141 5/03/2008 Hycroft Res & Dev Inc NMC990294 Humboldt
NH 142 5/03/2008 Hycroft Res & Dev Inc NMC990295 Humboldt

 

Hycroft Mine Project

Page 292

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 143 5/03/2008 Hycroft Res & Dev Inc NMC990296 Humboldt
NH 144 5/03/2008 Hycroft Res & Dev Inc NMC990297 Humboldt
NH 145 5/03/2008 Hycroft Res & Dev Inc NMC990298 Humboldt
NH 146 5/03/2008 Hycroft Res & Dev Inc NMC990299 Humboldt
NH 147 5/03/2008 Hycroft Res & Dev Inc NMC990300 Humboldt
NH 148 5/03/2008 Hycroft Res & Dev Inc NMC990301 Humboldt
NH 149 5/03/2008 Hycroft Res & Dev Inc NMC990302 Humboldt
NH 15 5/04/2008 Hycroft Res & Dev Inc NMC990168 Humboldt
NH 150 5/03/2008 Hycroft Res & Dev Inc NMC990303 Humboldt
NH 151 5/02/2008 Hycroft Res & Dev Inc NMC990304 Humboldt
NH 152 5/02/2008 Hycroft Res & Dev Inc NMC990305 Humboldt
NH 153 5/02/2008 Hycroft Res & Dev Inc NMC990306 Humboldt
NH 154 5/02/2008 Hycroft Res & Dev Inc NMC990307 Humboldt
NH 155 5/02/2008 Hycroft Res & Dev Inc NMC990308 Humboldt
NH 156 5/02/2008 Hycroft Res & Dev Inc NMC990309 Humboldt
NH 157 5/02/2008 Hycroft Res & Dev Inc NMC990310 Humboldt
NH 158 5/02/2008 Hycroft Res & Dev Inc NMC990311 Humboldt
NH 159 5/02/2008 Hycroft Res & Dev Inc NMC990312 Humboldt
NH 16 5/04/2008 Hycroft Res & Dev Inc NMC990169 Humboldt
NH 160 5/02/2008 Hycroft Res & Dev Inc NMC990313 Humboldt
NH 161 5/02/2008 Hycroft Res & Dev Inc NMC990314 Humboldt
NH 162 5/02/2008 Hycroft Res & Dev Inc NMC990315 Humboldt
NH 163 5/02/2008 Hycroft Res & Dev Inc NMC990316 Humboldt
NH 164 5/02/2008 Hycroft Res & Dev Inc NMC990317 Humboldt
NH 165 5/02/2008 Hycroft Res & Dev Inc NMC990318 Humboldt
NH 166 5/02/2008 Hycroft Res & Dev Inc NMC990319 Humboldt
NH 167 5/02/2008 Hycroft Res & Dev Inc NMC990320 Humboldt
NH 168 5/02/2008 Hycroft Res & Dev Inc NMC990321 Humboldt
NH 169 5/02/2008 Hycroft Res & Dev Inc NMC990322 Humboldt
NH 17 5/04/2008 Hycroft Res & Dev Inc NMC990170 Humboldt
NH 170 5/02/2008 Hycroft Res & Dev Inc NMC990323 Humboldt
NH 171 5/02/2008 Hycroft Res & Dev Inc NMC990324 Humboldt
NH 172 5/02/2008 Hycroft Res & Dev Inc NMC990325 Humboldt
NH 173 5/02/2008 Hycroft Res & Dev Inc NMC990326 Humboldt
NH 174 5/02/2008 Hycroft Res & Dev Inc NMC990327 Humboldt
NH 175 5/02/2008 Hycroft Res & Dev Inc NMC990328 Humboldt
NH 176 5/02/2008 Hycroft Res & Dev Inc NMC990329 Humboldt
NH 177 5/02/2008 Hycroft Res & Dev Inc NMC990330 Humboldt
NH 178 5/02/2008 Hycroft Res & Dev Inc NMC990331 Humboldt
NH 179 5/02/2008 Hycroft Res & Dev Inc NMC990332 Humboldt
NH 18 5/04/2008 Hycroft Res & Dev Inc NMC990171 Humboldt
NH 180 5/02/2008 Hycroft Res & Dev Inc NMC990333 Humboldt
NH 181 5/02/2008 Hycroft Res & Dev Inc NMC990334 Humboldt
NH 182 5/02/2008 Hycroft Res & Dev Inc NMC990335 Humboldt
NH 183 5/02/2008 Hycroft Res & Dev Inc NMC990336 Humboldt
NH 184 5/02/2008 Hycroft Res & Dev Inc NMC990337 Humboldt
NH 185 5/02/2008 Hycroft Res & Dev Inc NMC990338 Humboldt
NH 186 5/02/2008 Hycroft Res & Dev Inc NMC990339 Humboldt

 

Hycroft Mine Project

Page 293

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 187 5/02/2008 Hycroft Res & Dev Inc NMC990340 Humboldt
NH 188 5/02/2008 Hycroft Res & Dev Inc NMC990341 Humboldt
NH 189 5/02/2008 Hycroft Res & Dev Inc NMC990342 Humboldt
NH 19 5/04/2008 Hycroft Res & Dev Inc NMC990172 Humboldt
NH 190 5/02/2008 Hycroft Res & Dev Inc NMC990343 Humboldt
NH 191 5/02/2008 Hycroft Res & Dev Inc NMC990344 Humboldt
NH 192 5/02/2008 Hycroft Res & Dev Inc NMC990345 Humboldt
NH 193 5/02/2008 Hycroft Res & Dev Inc NMC990346 Humboldt
NH 194 5/02/2008 Hycroft Res & Dev Inc NMC990347 Humboldt
NH 195 5/02/2008 Hycroft Res & Dev Inc NMC990348 Humboldt
NH 196 5/02/2008 Hycroft Res & Dev Inc NMC990349 Humboldt
NH 197 5/02/2008 Hycroft Res & Dev Inc NMC990350 Humboldt
NH 198 5/02/2008 Hycroft Res & Dev Inc NMC990351 Humboldt
NH 199 5/02/2008 Hycroft Res & Dev Inc NMC990352 Humboldt
NH 2 5/04/2008 Hycroft Res & Dev Inc NMC990155 Humboldt
NH 20 5/04/2008 Hycroft Res & Dev Inc NMC990173 Humboldt
NH 200 5/02/2008 Hycroft Res & Dev Inc NMC990353 Humboldt
NH 201 5/02/2008 Hycroft Res & Dev Inc NMC990354 Humboldt
NH 202 5/02/2008 Hycroft Res & Dev Inc NMC990355 Humboldt
NH 203 5/02/2008 Hycroft Res & Dev Inc NMC990356 Humboldt
NH 204 5/02/2008 Hycroft Res & Dev Inc NMC990357 Humboldt
NH 205 5/02/2008 Hycroft Res & Dev Inc NMC990358 Humboldt
NH 206 5/02/2008 Hycroft Res & Dev Inc NMC990359 Humboldt
NH 207 5/02/2008 Hycroft Res & Dev Inc NMC990360 Humboldt
NH 208 5/02/2008 Hycroft Res & Dev Inc NMC990361 Humboldt
NH 209 5/02/2008 Hycroft Res & Dev Inc NMC990362 Humboldt
NH 21 5/04/2008 Hycroft Res & Dev Inc NMC990174 Humboldt
NH 210 5/02/2008 Hycroft Res & Dev Inc NMC990363 Humboldt
NH 211 5/02/2008 Hycroft Res & Dev Inc NMC990364 Humboldt
NH 212 5/02/2008 Hycroft Res & Dev Inc NMC990365 Humboldt
NH 213 5/02/2008 Hycroft Res & Dev Inc NMC990366 Humboldt
NH 214 5/02/2008 Hycroft Res & Dev Inc NMC990367 Humboldt
NH 215 5/02/2008 Hycroft Res & Dev Inc NMC990368 Humboldt
NH 216 5/02/2008 Hycroft Res & Dev Inc NMC990369 Humboldt
NH 217 5/02/2008 Hycroft Res & Dev Inc NMC990370 Humboldt
NH 218 5/02/2008 Hycroft Res & Dev Inc NMC990371 Humboldt
NH 219 5/02/2008 Hycroft Res & Dev Inc NMC990372 Humboldt
NH 22 5/04/2008 Hycroft Res & Dev Inc NMC990175 Humboldt
NH 220 5/02/2008 Hycroft Res & Dev Inc NMC990373 Humboldt
NH 221 5/02/2008 Hycroft Res & Dev Inc NMC990374 Humboldt
NH 222 5/02/2008 Hycroft Res & Dev Inc NMC990375 Humboldt
NH 223 5/02/2008 Hycroft Res & Dev Inc NMC990376 Humboldt
NH 224 5/02/2008 Hycroft Res & Dev Inc NMC990377 Humboldt
NH 225 5/02/2008 Hycroft Res & Dev Inc NMC990378 Humboldt
NH 226 5/02/2008 Hycroft Res & Dev Inc NMC990379 Humboldt
NH 227 5/02/2008 Hycroft Res & Dev Inc NMC990380 Humboldt
NH 228 5/02/2008 Hycroft Res & Dev Inc NMC990381 Humboldt
NH 229 5/02/2008 Hycroft Res & Dev Inc NMC990382 Humboldt

 

Hycroft Mine Project

Page 294

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 23 5/04/2008 Hycroft Res & Dev Inc NMC990176 Humboldt
NH 230 5/02/2008 Hycroft Res & Dev Inc NMC990383 Humboldt
NH 231 5/02/2008 Hycroft Res & Dev Inc NMC990384 Humboldt
NH 232 5/02/2008 Hycroft Res & Dev Inc NMC990385 Humboldt
NH 233 5/02/2008 Hycroft Res & Dev Inc NMC990386 Humboldt
NH 234 5/02/2008 Hycroft Res & Dev Inc NMC990387 Humboldt
NH 235 5/02/2008 Hycroft Res & Dev Inc NMC990388 Humboldt
NH 236 5/02/2008 Hycroft Res & Dev Inc NMC990389 Humboldt
NH 237 5/02/2008 Hycroft Res & Dev Inc NMC990390 Humboldt
NH 238 5/02/2008 Hycroft Res & Dev Inc NMC990391 Humboldt
NH 239 5/02/2008 Hycroft Res & Dev Inc NMC990392 Humboldt
NH 24 5/04/2008 Hycroft Res & Dev Inc NMC990177 Humboldt
NH 240 5/02/2008 Hycroft Res & Dev Inc NMC990393 Humboldt
NH 241 5/02/2008 Hycroft Res & Dev Inc NMC990394 Humboldt
NH 242 5/02/2008 Hycroft Res & Dev Inc NMC990395 Humboldt
NH 243 5/02/2008 Hycroft Res & Dev Inc NMC990396 Humboldt
NH 244 5/02/2008 Hycroft Res & Dev Inc NMC990397 Humboldt
NH 245 5/02/2008 Hycroft Res & Dev Inc NMC990398 Humboldt
NH 246 5/02/2008 Hycroft Res & Dev Inc NMC990399 Humboldt
NH 247 5/02/2008 Hycroft Res & Dev Inc NMC990400 Humboldt
NH 248 5/02/2008 Hycroft Res & Dev Inc NMC990401 Humboldt
NH 249 5/02/2008 Hycroft Res & Dev Inc NMC990402 Humboldt
NH 25 5/04/2008 Hycroft Res & Dev Inc NMC990178 Humboldt
NH 250 5/02/2008 Hycroft Res & Dev Inc NMC990403 Humboldt
NH 251 5/02/2008 Hycroft Res & Dev Inc NMC990404 Humboldt
NH 252 5/02/2008 Hycroft Res & Dev Inc NMC990405 Humboldt
NH 253 5/02/2008 Hycroft Res & Dev Inc NMC990406 Humboldt
NH 254 5/02/2008 Hycroft Res & Dev Inc NMC990407 Humboldt
NH 255 5/01/2008 Hycroft Res & Dev Inc NMC990408 Humboldt
NH 256 5/01/2008 Hycroft Res & Dev Inc NMC990409 Humboldt
NH 257 5/01/2008 Hycroft Res & Dev Inc NMC990410 Humboldt
NH 258 5/01/2008 Hycroft Res & Dev Inc NMC990411 Humboldt
NH 259 5/01/2008 Hycroft Res & Dev Inc NMC990412 Humboldt
NH 26 5/04/2008 Hycroft Res & Dev Inc NMC990179 Humboldt
NH 260 5/01/2008 Hycroft Res & Dev Inc NMC990413 Humboldt
NH 261 5/01/2008 Hycroft Res & Dev Inc NMC990414 Humboldt
NH 262 5/01/2008 Hycroft Res & Dev Inc NMC990415 Humboldt
NH 263 5/01/2008 Hycroft Res & Dev Inc NMC990416 Humboldt
NH 264 5/01/2008 Hycroft Res & Dev Inc NMC990417 Humboldt
NH 265 5/01/2008 Hycroft Res & Dev Inc NMC990418 Humboldt
NH 266 5/01/2008 Hycroft Res & Dev Inc NMC990419 Humboldt
NH 267 5/01/2008 Hycroft Res & Dev Inc NMC990420 Humboldt
NH 268 5/01/2008 Hycroft Res & Dev Inc NMC990421 Humboldt
NH 269 5/01/2008 Hycroft Res & Dev Inc NMC990422 Humboldt
NH 27 5/04/2008 Hycroft Res & Dev Inc NMC990180 Humboldt
NH 270 5/01/2008 Hycroft Res & Dev Inc NMC990423 Humboldt
NH 271 5/01/2008 Hycroft Res & Dev Inc NMC990424 Humboldt
NH 272 5/01/2008 Hycroft Res & Dev Inc NMC990425 Humboldt

 

Hycroft Mine Project

Page 295

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 273 5/01/2008 Hycroft Res & Dev Inc NMC990426 Humboldt
NH 274 5/01/2008 Hycroft Res & Dev Inc NMC990427 Humboldt
NH 275 5/01/2008 Hycroft Res & Dev Inc NMC990428 Humboldt
NH 276 5/01/2008 Hycroft Res & Dev Inc NMC990429 Humboldt
NH 277 5/01/2008 Hycroft Res & Dev Inc NMC990430 Humboldt
NH 278 5/01/2008 Hycroft Res & Dev Inc NMC990431 Humboldt
NH 279 5/01/2008 Hycroft Res & Dev Inc NMC990432 Humboldt
NH 28 5/04/2008 Hycroft Res & Dev Inc NMC990181 Humboldt
NH 280 5/01/2008 Hycroft Res & Dev Inc NMC990433 Humboldt
NH 281 5/01/2008 Hycroft Res & Dev Inc NMC990434 Humboldt
NH 282 5/01/2008 Hycroft Res & Dev Inc NMC990435 Humboldt
NH 283 5/01/2008 Hycroft Res & Dev Inc NMC990436 Humboldt
NH 284 5/01/2008 Hycroft Res & Dev Inc NMC990437 Humboldt
NH 285 5/01/2008 Hycroft Res & Dev Inc NMC990438 Humboldt
NH 286 5/01/2008 Hycroft Res & Dev Inc NMC990439 Humboldt
NH 287 5/01/2008 Hycroft Res & Dev Inc NMC990440 Humboldt
NH 288 5/01/2008 Hycroft Res & Dev Inc NMC990441 Humboldt
NH 289 5/01/2008 Hycroft Res & Dev Inc NMC990442 Humboldt
NH 29 5/04/2008 Hycroft Res & Dev Inc NMC990182 Humboldt
NH 290 5/01/2008 Hycroft Res & Dev Inc NMC990443 Humboldt
NH 291 5/01/2008 Hycroft Res & Dev Inc NMC990444 Humboldt
NH 292 5/01/2008 Hycroft Res & Dev Inc NMC990445 Humboldt
NH 293 5/01/2008 Hycroft Res & Dev Inc NMC990446 Humboldt
NH 294 5/01/2008 Hycroft Res & Dev Inc NMC990447 Humboldt
NH 295 5/01/2008 Hycroft Res & Dev Inc NMC990448 Humboldt
NH 296 5/01/2008 Hycroft Res & Dev Inc NMC990449 Humboldt
NH 297 5/01/2008 Hycroft Res & Dev Inc NMC990450 Humboldt
NH 298 5/01/2008 Hycroft Res & Dev Inc NMC990451 Humboldt
NH 299 5/01/2008 Hycroft Res & Dev Inc NMC990452 Humboldt
NH 3 5/04/2008 Hycroft Res & Dev Inc NMC990156 Humboldt
NH 30 5/04/2008 Hycroft Res & Dev Inc NMC990183 Humboldt
NH 300 5/01/2008 Hycroft Res & Dev Inc NMC990453 Humboldt
NH 301 5/01/2008 Hycroft Res & Dev Inc NMC990454 Humboldt
NH 302 5/01/2008 Hycroft Res & Dev Inc NMC990455 Humboldt
NH 303 5/01/2008 Hycroft Res & Dev Inc NMC990456 Humboldt
NH 304 5/01/2008 Hycroft Res & Dev Inc NMC990457 Humboldt
NH 305 5/01/2008 Hycroft Res & Dev Inc NMC990458 Humboldt
NH 306 5/01/2008 Hycroft Res & Dev Inc NMC990459 Humboldt
NH 307 5/01/2008 Hycroft Res & Dev Inc NMC990460 Humboldt
NH 308 5/01/2008 Hycroft Res & Dev Inc NMC990461 Humboldt
NH 309 5/01/2008 Hycroft Res & Dev Inc NMC990462 Humboldt
NH 31 5/04/2008 Hycroft Res & Dev Inc NMC990184 Humboldt
NH 310 5/01/2008 Hycroft Res & Dev Inc NMC990463 Humboldt
NH 311 5/01/2008 Hycroft Res & Dev Inc NMC990464 Humboldt
NH 312 5/01/2008 Hycroft Res & Dev Inc NMC990465 Humboldt
NH 313 5/01/2008 Hycroft Res & Dev Inc NMC990466 Humboldt
NH 314 5/01/2008 Hycroft Res & Dev Inc NMC990467 Humboldt
NH 315 5/01/2008 Hycroft Res & Dev Inc NMC990468 Humboldt

 

Hycroft Mine Project

Page 296

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 316 5/01/2008 Hycroft Res & Dev Inc NMC990469 Humboldt
NH 317 5/01/2008 Hycroft Res & Dev Inc NMC990470 Humboldt
NH 318 5/01/2008 Hycroft Res & Dev Inc NMC990471 Humboldt
NH 319 5/01/2008 Hycroft Res & Dev Inc NMC990472 Humboldt
NH 32 5/04/2008 Hycroft Res & Dev Inc NMC990185 Humboldt
NH 320 5/01/2008 Hycroft Res & Dev Inc NMC990473 Humboldt
NH 321 5/01/2008 Hycroft Res & Dev Inc NMC990474 Humboldt
NH 322 5/01/2008 Hycroft Res & Dev Inc NMC990475 Humboldt
NH 323 5/01/2008 Hycroft Res & Dev Inc NMC990476 Humboldt
NH 324 5/01/2008 Hycroft Res & Dev Inc NMC990477 Humboldt
NH 325 5/01/2008 Hycroft Res & Dev Inc NMC990478 Humboldt
NH 326 5/01/2008 Hycroft Res & Dev Inc NMC990479 Humboldt
NH 327 5/01/2008 Hycroft Res & Dev Inc NMC990480 Humboldt
NH 328 5/01/2008 Hycroft Res & Dev Inc NMC990481 Humboldt
NH 329 5/01/2008 Hycroft Res & Dev Inc NMC990482 Humboldt
NH 33 5/04/2008 Hycroft Res & Dev Inc NMC990186 Humboldt
NH 330 5/01/2008 Hycroft Res & Dev Inc NMC990483 Humboldt
NH 331 5/01/2008 Hycroft Res & Dev Inc NMC990484 Humboldt
NH 332 5/01/2008 Hycroft Res & Dev Inc NMC990485 Humboldt
NH 333 5/01/2008 Hycroft Res & Dev Inc NMC990486 Humboldt
NH 334 5/01/2008 Hycroft Res & Dev Inc NMC990487 Humboldt
NH 335 5/01/2008 Hycroft Res & Dev Inc NMC990488 Humboldt
NH 336 5/01/2008 Hycroft Res & Dev Inc NMC990489 Humboldt
NH 337 5/01/2008 Hycroft Res & Dev Inc NMC990490 Humboldt
NH 338 5/01/2008 Hycroft Res & Dev Inc NMC990491 Humboldt
NH 339 5/01/2008 Hycroft Res & Dev Inc NMC990492 Humboldt
NH 34 5/04/2008 Hycroft Res & Dev Inc NMC990187 Humboldt
NH 340 5/01/2008 Hycroft Res & Dev Inc NMC990493 Humboldt
NH 341 5/01/2008 Hycroft Res & Dev Inc NMC990494 Humboldt
NH 342 5/01/2008 Hycroft Res & Dev Inc NMC990495 Humboldt
NH 343 5/01/2008 Hycroft Res & Dev Inc NMC990496 Humboldt
NH 344 5/01/2008 Hycroft Res & Dev Inc NMC990497 Humboldt
NH 345 5/01/2008 Hycroft Res & Dev Inc NMC990498 Humboldt
NH 346 5/01/2008 Hycroft Res & Dev Inc NMC990499 Humboldt
NH 347 5/01/2008 Hycroft Res & Dev Inc NMC990500 Humboldt
NH 348 5/01/2008 Hycroft Res & Dev Inc NMC990501 Humboldt
NH 349 5/01/2008 Hycroft Res & Dev Inc NMC990502 Humboldt
NH 35 5/04/2008 Hycroft Res & Dev Inc NMC990188 Humboldt
NH 350 5/01/2008 Hycroft Res & Dev Inc NMC990503 Humboldt
NH 351 5/01/2008 Hycroft Res & Dev Inc NMC990504 Humboldt
NH 352 5/01/2008 Hycroft Res & Dev Inc NMC990505 Humboldt
NH 353 5/01/2008 Hycroft Res & Dev Inc NMC990506 Humboldt
NH 354 5/01/2008 Hycroft Res & Dev Inc NMC990507 Humboldt
NH 355 5/01/2008 Hycroft Res & Dev Inc NMC990508 Humboldt
NH 356 5/01/2008 Hycroft Res & Dev Inc NMC990509 Humboldt
NH 357 5/01/2008 Hycroft Res & Dev Inc NMC990510 Humboldt
NH 358 5/01/2008 Hycroft Res & Dev Inc NMC990511 Humboldt
NH 359 4/28/2008 Hycroft Res & Dev Inc NMC990512 Humboldt

 

Hycroft Mine Project

Page 297

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 36 5/04/2008 Hycroft Res & Dev Inc NMC990189 Humboldt
NH 360 4/28/2008 Hycroft Res & Dev Inc NMC990513 Humboldt
NH 361 4/28/2008 Hycroft Res & Dev Inc NMC990514 Humboldt
NH 362 4/28/2008 Hycroft Res & Dev Inc NMC990515 Humboldt
NH 363 4/28/2008 Hycroft Res & Dev Inc NMC990516 Humboldt
NH 364 4/28/2008 Hycroft Res & Dev Inc NMC990517 Humboldt
NH 365 4/28/2008 Hycroft Res & Dev Inc NMC990518 Humboldt
NH 366 4/28/2008 Hycroft Res & Dev Inc NMC990519 Humboldt
NH 367 4/28/2008 Hycroft Res & Dev Inc NMC990520 Humboldt
NH 368 4/28/2008 Hycroft Res & Dev Inc NMC990521 Humboldt
NH 369 4/28/2008 Hycroft Res & Dev Inc NMC990522 Humboldt
NH 37 5/04/2008 Hycroft Res & Dev Inc NMC990190 Humboldt
NH 370 4/28/2008 Hycroft Res & Dev Inc NMC990523 Humboldt
NH 371 4/28/2008 Hycroft Res & Dev Inc NMC990524 Humboldt
NH 372 4/28/2008 Hycroft Res & Dev Inc NMC990525 Humboldt
NH 373 4/28/2008 Hycroft Res & Dev Inc NMC990526 Humboldt
NH 374 4/28/2008 Hycroft Res & Dev Inc NMC990527 Humboldt
NH 375 4/28/2008 Hycroft Res & Dev Inc NMC990528 Humboldt
NH 376 4/28/2008 Hycroft Res & Dev Inc NMC990529 Humboldt
NH 377 4/28/2008 Hycroft Res & Dev Inc NMC990530 Humboldt
NH 378 4/28/2008 Hycroft Res & Dev Inc NMC990531 Humboldt
NH 379 4/28/2008 Hycroft Res & Dev Inc NMC990532 Humboldt
NH 38 5/04/2008 Hycroft Res & Dev Inc NMC990191 Humboldt
NH 380 4/28/2008 Hycroft Res & Dev Inc NMC990533 Humboldt
NH 381 4/28/2008 Hycroft Res & Dev Inc NMC990534 Humboldt
NH 382 4/28/2008 Hycroft Res & Dev Inc NMC990535 Humboldt
NH 383 4/28/2008 Hycroft Res & Dev Inc NMC990536 Humboldt
NH 384 4/28/2008 Hycroft Res & Dev Inc NMC990537 Humboldt
NH 385 4/28/2008 Hycroft Res & Dev Inc NMC990538 Humboldt
NH 386 4/28/2008 Hycroft Res & Dev Inc NMC990539 Humboldt
NH 387 4/28/2008 Hycroft Res & Dev Inc NMC990540 Humboldt
NH 388 4/28/2008 Hycroft Res & Dev Inc NMC990541 Humboldt
NH 389 4/28/2008 Hycroft Res & Dev Inc NMC990542 Humboldt
NH 39 5/04/2008 Hycroft Res & Dev Inc NMC990192 Humboldt
NH 390 4/28/2008 Hycroft Res & Dev Inc NMC990543 Humboldt
NH 391 4/28/2008 Hycroft Res & Dev Inc NMC990544 Humboldt
NH 392 4/28/2008 Hycroft Res & Dev Inc NMC990545 Humboldt
NH 393 4/28/2008 Hycroft Res & Dev Inc NMC990546 Humboldt
NH 394 4/28/2008 Hycroft Res & Dev Inc NMC990547 Humboldt
NH 395 4/28/2008 Hycroft Res & Dev Inc NMC990548 Humboldt
NH 396 4/28/2008 Hycroft Res & Dev Inc NMC990549 Humboldt
NH 397 4/28/2008 Hycroft Res & Dev Inc NMC990550 Humboldt
NH 398 4/28/2008 Hycroft Res & Dev Inc NMC990551 Humboldt
NH 399 4/28/2008 Hycroft Res & Dev Inc NMC990552 Humboldt
NH 4 5/04/2008 Hycroft Res & Dev Inc NMC990157 Humboldt
NH 40 5/04/2008 Hycroft Res & Dev Inc NMC990193 Humboldt
NH 400 4/28/2008 Hycroft Res & Dev Inc NMC990553 Humboldt
NH 401 4/28/2008 Hycroft Res & Dev Inc NMC990554 Humboldt

 

Hycroft Mine Project

Page 298

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 402 4/28/2008 Hycroft Res & Dev Inc NMC990555 Humboldt
NH 403 4/28/2008 Hycroft Res & Dev Inc NMC990556 Humboldt
NH 404 4/28/2008 Hycroft Res & Dev Inc NMC990557 Humboldt
NH 405 4/28/2008 Hycroft Res & Dev Inc NMC990558 Humboldt
NH 406 4/28/2008 Hycroft Res & Dev Inc NMC990559 Humboldt
NH 407 4/28/2008 Hycroft Res & Dev Inc NMC990560 Humboldt
NH 408 4/28/2008 Hycroft Res & Dev Inc NMC990561 Humboldt
NH 409 4/28/2008 Hycroft Res & Dev Inc NMC990562 Humboldt
NH 41 5/04/2008 Hycroft Res & Dev Inc NMC990194 Humboldt
NH 410 4/28/2008 Hycroft Res & Dev Inc NMC990563 Humboldt
NH 411 4/28/2008 Hycroft Res & Dev Inc NMC990564 Humboldt
NH 412 4/28/2008 Hycroft Res & Dev Inc NMC990565 Humboldt
NH 413 4/28/2008 Hycroft Res & Dev Inc NMC990566 Humboldt
NH 414 4/28/2008 Hycroft Res & Dev Inc NMC990567 Humboldt
NH 415 4/28/2008 Hycroft Res & Dev Inc NMC990568 Humboldt
NH 416 4/28/2008 Hycroft Res & Dev Inc NMC990569 Humboldt
NH 417 4/28/2008 Hycroft Res & Dev Inc NMC990570 Humboldt
NH 418 4/28/2008 Hycroft Res & Dev Inc NMC990571 Humboldt
NH 419 4/28/2008 Hycroft Res & Dev Inc NMC990572 Humboldt
NH 42 5/04/2008 Hycroft Res & Dev Inc NMC990195 Humboldt
NH 420 4/28/2008 Hycroft Res & Dev Inc NMC990573 Humboldt
NH 421 4/28/2008 Hycroft Res & Dev Inc NMC990574 Humboldt
NH 422 4/28/2008 Hycroft Res & Dev Inc NMC990575 Humboldt
NH 423 4/28/2008 Hycroft Res & Dev Inc NMC990576 Humboldt
NH 424 4/28/2008 Hycroft Res & Dev Inc NMC990577 Humboldt
NH 425 4/28/2008 Hycroft Res & Dev Inc NMC990578 Humboldt
NH 426 4/28/2008 Hycroft Res & Dev Inc NMC990579 Humboldt
NH 427 4/28/2008 Hycroft Res & Dev Inc NMC990580 Humboldt
NH 428 4/28/2008 Hycroft Res & Dev Inc NMC990581 Humboldt
NH 429 4/28/2008 Hycroft Res & Dev Inc NMC990582 Humboldt
NH 43 5/04/2008 Hycroft Res & Dev Inc NMC990196 Humboldt
NH 430 4/28/2008 Hycroft Res & Dev Inc NMC990583 Humboldt
NH 431 4/28/2008 Hycroft Res & Dev Inc NMC990584 Humboldt
NH 436 4/28/2008 Hycroft Res & Dev Inc NMC990589 Humboldt
NH 44 5/04/2008 Hycroft Res & Dev Inc NMC990197 Humboldt
NH 440 4/28/2008 Hycroft Res & Dev Inc NMC990593 Humboldt
NH 441 4/28/2008 Hycroft Res & Dev Inc NMC990594 Humboldt
NH 444 4/28/2008 Hycroft Res & Dev Inc NMC990597 Humboldt
NH 445 4/28/2008 Hycroft Res & Dev Inc NMC990598 Humboldt
NH 446 4/28/2008 Hycroft Res & Dev Inc NMC990599 Humboldt
NH 447 4/28/2008 Hycroft Res & Dev Inc NMC990600 Humboldt
NH 448 4/28/2008 Hycroft Res & Dev Inc NMC990601 Humboldt
NH 449 4/28/2008 Hycroft Res & Dev Inc NMC990602 Humboldt
NH 45 5/04/2008 Hycroft Res & Dev Inc NMC990198 Humboldt
NH 451 4/28/2008 Hycroft Res & Dev Inc NMC990604 Humboldt
NH 452 4/28/2008 Hycroft Res & Dev Inc NMC990605 Humboldt
NH 453 4/28/2008 Hycroft Res & Dev Inc NMC990606 Humboldt
NH 454 4/28/2008 Hycroft Res & Dev Inc NMC990607 Humboldt

 

Hycroft Mine Project

Page 299

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 455 4/28/2008 Hycroft Res & Dev Inc NMC990608 Humboldt
NH 456 4/28/2008 Hycroft Res & Dev Inc NMC990609 Humboldt
NH 457 4/28/2008 Hycroft Res & Dev Inc NMC990610 Humboldt
NH 458 4/28/2008 Hycroft Res & Dev Inc NMC990611 Humboldt
NH 459 4/28/2008 Hycroft Res & Dev Inc NMC990612 Humboldt
NH 46 5/04/2008 Hycroft Res & Dev Inc NMC990199 Humboldt
NH 460 4/28/2008 Hycroft Res & Dev Inc NMC990613 Humboldt
NH 461 4/28/2008 Hycroft Res & Dev Inc NMC990614 Humboldt
NH 462 4/28/2008 Hycroft Res & Dev Inc NMC990615 Humboldt
NH 463 4/28/2008 Hycroft Res & Dev Inc NMC990616 Humboldt
NH 464 4/28/2008 Hycroft Res & Dev Inc NMC990617 Humboldt
NH 465 4/28/2008 Hycroft Res & Dev Inc NMC990618 Humboldt
NH 466 4/28/2008 Hycroft Res & Dev Inc NMC990619 Humboldt
NH 467 4/28/2008 Hycroft Res & Dev Inc NMC990620 Humboldt
NH 468 4/28/2008 Hycroft Res & Dev Inc NMC990621 Humboldt
NH 469 4/28/2008 Hycroft Res & Dev Inc NMC990622 Humboldt
NH 47 5/03/2008 Hycroft Res & Dev Inc NMC990200 Humboldt
NH 470 4/28/2008 Hycroft Res & Dev Inc NMC990623 Humboldt
NH 471 4/28/2008 Hycroft Res & Dev Inc NMC990624 Humboldt
NH 472 4/28/2008 Hycroft Res & Dev Inc NMC990625 Humboldt
NH 473 4/28/2008 Hycroft Res & Dev Inc NMC990626 Humboldt
NH 474 4/28/2008 Hycroft Res & Dev Inc NMC990627 Humboldt
NH 475 4/28/2008 Hycroft Res & Dev Inc NMC990628 Humboldt
NH 476 4/28/2008 Hycroft Res & Dev Inc NMC990629 Humboldt
NH 477 4/28/2008 Hycroft Res & Dev Inc NMC990630 Humboldt
NH 478 4/28/2008 Hycroft Res & Dev Inc NMC990631 Humboldt
NH 479 4/28/2008 Hycroft Res & Dev Inc NMC990632 Humboldt
NH 48 5/03/2008 Hycroft Res & Dev Inc NMC990201 Humboldt
NH 480 4/28/2008 Hycroft Res & Dev Inc NMC990633 Humboldt
NH 481 4/28/2008 Hycroft Res & Dev Inc NMC990634 Humboldt
NH 482 4/28/2008 Hycroft Res & Dev Inc NMC990635 Humboldt
NH 483 4/28/2008 Hycroft Res & Dev Inc NMC990636 Humboldt
NH 484 4/28/2008 Hycroft Res & Dev Inc NMC990637 Humboldt
NH 485 4/29/2008 Hycroft Res & Dev Inc NMC990638 Humboldt
NH 486 4/29/2008 Hycroft Res & Dev Inc NMC990639 Humboldt
NH 487 4/29/2008 Hycroft Res & Dev Inc NMC990640 Humboldt
NH 488 4/29/2008 Hycroft Res & Dev Inc NMC990641 Humboldt
NH 489 4/29/2008 Hycroft Res & Dev Inc NMC990642 Humboldt
NH 49 5/03/2008 Hycroft Res & Dev Inc NMC990202 Humboldt
NH 490 4/29/2008 Hycroft Res & Dev Inc NMC990643 Humboldt
NH 491 4/29/2008 Hycroft Res & Dev Inc NMC990644 Humboldt
NH 492 4/29/2008 Hycroft Res & Dev Inc NMC990645 Humboldt
NH 493 4/29/2008 Hycroft Res & Dev Inc NMC990646 Humboldt
NH 494 4/29/2008 Hycroft Res & Dev Inc NMC990647 Humboldt
NH 495 4/29/2008 Hycroft Res & Dev Inc NMC990648 Humboldt
NH 496 4/29/2008 Hycroft Res & Dev Inc NMC990649 Humboldt
NH 497 4/29/2008 Hycroft Res & Dev Inc NMC990650 Humboldt
NH 498 4/29/2008 Hycroft Res & Dev Inc NMC990651 Humboldt

 

Hycroft Mine Project

Page 300

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 499 4/29/2008 Hycroft Res & Dev Inc NMC990652 Humboldt
NH 5 5/04/2008 Hycroft Res & Dev Inc NMC990158 Humboldt
NH 50 5/03/2008 Hycroft Res & Dev Inc NMC990203 Humboldt
NH 500 4/29/2008 Hycroft Res & Dev Inc NMC990653 Humboldt
NH 51 5/03/2008 Hycroft Res & Dev Inc NMC990204 Humboldt
NH 52 5/03/2008 Hycroft Res & Dev Inc NMC990205 Humboldt
NH 53 5/03/2008 Hycroft Res & Dev Inc NMC990206 Humboldt
NH 54 5/03/2008 Hycroft Res & Dev Inc NMC990207 Humboldt
NH 55 5/03/2008 Hycroft Res & Dev Inc NMC990208 Humboldt
NH 56 5/03/2008 Hycroft Res & Dev Inc NMC990209 Humboldt
NH 57 5/03/2008 Hycroft Res & Dev Inc NMC990210 Humboldt
NH 58 5/03/2008 Hycroft Res & Dev Inc NMC990211 Humboldt
NH 59 5/03/2008 Hycroft Res & Dev Inc NMC990212 Humboldt
NH 6 5/04/2008 Hycroft Res & Dev Inc NMC990159 Humboldt
NH 60 5/03/2008 Hycroft Res & Dev Inc NMC990213 Humboldt
NH 61 5/03/2008 Hycroft Res & Dev Inc NMC990214 Humboldt
NH 62 5/03/2008 Hycroft Res & Dev Inc NMC990215 Humboldt
NH 63 5/03/2008 Hycroft Res & Dev Inc NMC990216 Humboldt
NH 64 5/03/2008 Hycroft Res & Dev Inc NMC990217 Humboldt
NH 65 5/03/2008 Hycroft Res & Dev Inc NMC990218 Humboldt
NH 66 5/03/2008 Hycroft Res & Dev Inc NMC990219 Humboldt
NH 67 5/03/2008 Hycroft Res & Dev Inc NMC990220 Humboldt
NH 68 5/03/2008 Hycroft Res & Dev Inc NMC990221 Humboldt
NH 69 5/03/2008 Hycroft Res & Dev Inc NMC990222 Humboldt
NH 7 5/04/2008 Hycroft Res & Dev Inc NMC990160 Humboldt
NH 70 5/03/2008 Hycroft Res & Dev Inc NMC990223 Humboldt
NH 71 5/03/2008 Hycroft Res & Dev Inc NMC990224 Humboldt
NH 72 5/03/2008 Hycroft Res & Dev Inc NMC990225 Humboldt
NH 73 5/03/2008 Hycroft Res & Dev Inc NMC990226 Humboldt
NH 74 5/03/2008 Hycroft Res & Dev Inc NMC990227 Humboldt
NH 75 5/03/2008 Hycroft Res & Dev Inc NMC990228 Humboldt
NH 76 5/03/2008 Hycroft Res & Dev Inc NMC990229 Humboldt
NH 77 5/03/2008 Hycroft Res & Dev Inc NMC990230 Humboldt
NH 78 5/03/2008 Hycroft Res & Dev Inc NMC990231 Humboldt
NH 79 5/03/2008 Hycroft Res & Dev Inc NMC990232 Humboldt
NH 8 5/04/2008 Hycroft Res & Dev Inc NMC990161 Humboldt
NH 80 5/03/2008 Hycroft Res & Dev Inc NMC990233 Humboldt
NH 81 5/03/2008 Hycroft Res & Dev Inc NMC990234 Humboldt
NH 82 5/03/2008 Hycroft Res & Dev Inc NMC990235 Humboldt
NH 83 5/03/2008 Hycroft Res & Dev Inc NMC990236 Humboldt
NH 84 5/03/2008 Hycroft Res & Dev Inc NMC990237 Humboldt
NH 85 5/03/2008 Hycroft Res & Dev Inc NMC990238 Humboldt
NH 86 5/03/2008 Hycroft Res & Dev Inc NMC990239 Humboldt
NH 87 5/03/2008 Hycroft Res & Dev Inc NMC990240 Humboldt
NH 88 5/03/2008 Hycroft Res & Dev Inc NMC990241 Humboldt
NH 89 5/03/2008 Hycroft Res & Dev Inc NMC990242 Humboldt
NH 9 5/04/2008 Hycroft Res & Dev Inc NMC990162 Humboldt
NH 90 5/03/2008 Hycroft Res & Dev Inc NMC990243 Humboldt

 

Hycroft Mine Project

Page 301

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NH 91 5/03/2008 Hycroft Res & Dev Inc NMC990244 Humboldt
NH 92 5/03/2008 Hycroft Res & Dev Inc NMC990245 Humboldt
NH 93 5/03/2008 Hycroft Res & Dev Inc NMC990246 Humboldt
NH 94 5/03/2008 Hycroft Res & Dev Inc NMC990247 Humboldt
NH 95 5/03/2008 Hycroft Res & Dev Inc NMC990248 Humboldt
NH 96 5/03/2008 Hycroft Res & Dev Inc NMC990249 Humboldt
NH 97 5/03/2008 Hycroft Res & Dev Inc NMC990250 Humboldt
NH 98 5/03/2008 Hycroft Res & Dev Inc NMC990251 Humboldt
NH 99 5/03/2008 Hycroft Res & Dev Inc NMC990252 Humboldt
NH432 4/28/2008 Hycroft Res & Dev Inc NMC990585 Humboldt
NH433 4/28/2008 Hycroft Res & Dev Inc NMC990586 Humboldt
NH434 4/28/2008 Hycroft Res & Dev Inc NMC990587 Humboldt
NH435 4/28/2008 Hycroft Res & Dev Inc NMC990588 Humboldt
NH437 4/28/2008 Hycroft Res & Dev Inc NMC990590 Humboldt
NH438 4/28/2008 Hycroft Res & Dev Inc NMC990591 Humboldt
NH439 4/28/2008 Hycroft Res & Dev Inc NMC990592 Humboldt
NH442 4/28/2008 Hycroft Res & Dev Inc NMC990595 Humboldt
NH443 4/28/2008 Hycroft Res & Dev Inc NMC990596 Humboldt
NH450 4/28/2008 Hycroft Res & Dev Inc NMC990603 Humboldt
Pacific #2 11/04/1980 Lewis Frank W NMC181010 Humboldt
RFG # 39 6/28/1987 Lewis Frank W NMC436884 Humboldt
RFG # 72 6/28/1987 Lewis Frank W NMC436912 Humboldt
RFG #0BF 1/30/1980 Hrdi NMC143488 Humboldt
RFG #1 12/20/1979 Hrdi NMC143252 Humboldt
RFG #10 12/20/1979 Hrdi NMC143261 Humboldt
RFG #11 1/03/1980 Hrdi NMC143262 Humboldt
RFG #12 1/03/1980 Hrdi NMC143263 Humboldt
RFG #12A 2/20/1980 Hrdi NMC143490 Humboldt
RFG #13 12/27/1979 Hrdi NMC143264 Humboldt
RFG #13A 2/20/1980 Hrdi NMC143491 Humboldt
RFG #15 1/03/1980 Hrdi NMC143266 Humboldt
RFG #16 1/03/1980 Hrdi NMC143267 Humboldt
RFG #168 2/01/1980 Hrdi NMC143347 Humboldt
RFG #169 2/01/1980 Hrdi NMC143348 Humboldt
RFG #17 1/03/1980 Hrdi NMC143268 Humboldt
RFG #170 2/01/1980 Hrdi NMC143349 Humboldt
RFG #171 2/01/1980 Hrdi NMC143350 Humboldt
RFG #172 1/31/1980 Hrdi NMC143351 Humboldt
RFG #173 1/31/1980 Hrdi NMC143352 Humboldt
RFG #174 1/31/1980 Hrdi NMC143353 Humboldt
RFG #175 1/31/1980 Hrdi NMC143354 Humboldt
RFG #176 1/31/1980 Hrdi NMC143355 Humboldt
RFG #177 1/31/1980 Hrdi NMC143356 Humboldt
RFG #178 2/01/1980 Hrdi NMC143357 Humboldt
RFG #179 2/01/1980 Hrdi NMC143358 Humboldt
RFG #18 1/03/1980 Hrdi NMC143269 Humboldt
RFG #180 2/01/1980 Hrdi NMC143359 Humboldt
RFG #181 2/01/1980 Hrdi NMC143360 Humboldt

 

Hycroft Mine Project

Page 302

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #182 2/01/1980 Hrdi NMC143361 Humboldt
RFG #183 2/01/1980 Hrdi NMC143362 Humboldt
RFG #184 2/01/1980 Hrdi NMC143363 Humboldt
RFG #185 2/01/1980 Hrdi NMC143364 Humboldt
RFG #186 1/31/1980 Hrdi NMC143365 Humboldt
RFG #187 2/01/1980 Hrdi NMC143366 Humboldt
RFG #188 1/31/1980 Hrdi NMC143367 Humboldt
RFG #189 2/01/1980 Hrdi NMC143368 Humboldt
RFG #19 1/03/1980 Hrdi NMC143270 Humboldt
RFG #190 1/31/1980 Hrdi NMC143369 Humboldt
RFG #191 2/01/1980 Hrdi NMC143370 Humboldt
RFG #192 1/31/1980 Hrdi NMC143371 Humboldt
RFG #193 2/01/1980 Hrdi NMC143372 Humboldt
RFG #194 1/31/1980 Hrdi NMC143373 Humboldt
RFG #195 2/01/1980 Hrdi NMC143374 Humboldt
RFG #196 1/31/1980 Hrdi NMC143375 Humboldt
RFG #197 2/01/1980 Hrdi NMC143376 Humboldt
RFG #198 1/31/1980 Hrdi NMC143377 Humboldt
RFG #199 2/01/1980 Hrdi NMC143378 Humboldt
RFG #1FS 1/27/1980 Hrdi NMC143489 Humboldt
RFG #2 12/20/1979 Hrdi NMC143253 Humboldt
RFG #20 1/03/1980 Hrdi NMC143271 Humboldt
RFG #200 1/31/1980 Hrdi NMC143379 Humboldt
RFG #201 2/05/1980 Hrdi NMC143380 Humboldt
RFG #201A 2/05/1980 Hrdi NMC143504 Humboldt
RFG #202 1/03/1980 Hrdi NMC143381 Humboldt
RFG #203 1/30/1980 Hrdi NMC143382 Humboldt
RFG #204 1/30/1980 Hrdi NMC143383 Humboldt
RFG #205 1/30/1980 Hrdi NMC143384 Humboldt
RFG #206 1/30/1980 Hrdi NMC143385 Humboldt
RFG #207 1/30/1980 Hrdi NMC143386 Humboldt
RFG #208 1/30/1980 Hrdi NMC143387 Humboldt
RFG #209 1/30/1980 Hrdi NMC143388 Humboldt
RFG #21 1/03/1980 Hrdi NMC143272 Humboldt
RFG #210 1/30/1980 Hrdi NMC143389 Humboldt
RFG #211 1/30/1980 Hrdi NMC143390 Humboldt
RFG #212 1/30/1980 Hrdi NMC143391 Humboldt
RFG #213 1/30/1980 Hrdi NMC143392 Humboldt
RFG #214 1/30/1980 Hrdi NMC143393 Humboldt
RFG #215 1/30/1980 Hrdi NMC143394 Humboldt
RFG #2158 2/14/1980 Hrdi NMC143505 Humboldt
RFG #216 1/30/1980 Hrdi NMC143395 Humboldt
RFG #217 1/30/1980 Hrdi NMC143396 Humboldt
RFG #2178 2/14/1980 Hrdi NMC143506 Humboldt
RFG #218 2/13/1980 Hrdi NMC143397 Humboldt
RFG #2188 2/04/1980 Hrdi NMC143508 Humboldt
RFG #218A 2/04/1980 Hrdi NMC143507 Humboldt
RFG #219 2/13/1980 Hrdi NMC143398 Humboldt

 

Hycroft Mine Project

Page 303

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #2198 2/13/1980 Hrdi NMC143509 Humboldt
RFG #22 1/03/1980 Hrdi NMC143273 Humboldt
RFG #220 1/31/1980 Hrdi NMC143399 Humboldt
RFG #221 1/31/1980 Hrdi NMC143400 Humboldt
RFG #222 1/31/1980 Hrdi NMC143401 Humboldt
RFG #223 1/31/1980 Hrdi NMC143402 Humboldt
RFG #224 1/26/1980 Hrdi NMC143403 Humboldt
RFG #225 1/26/1980 Hrdi NMC143404 Humboldt
RFG #226 1/26/1980 Hrdi NMC143405 Humboldt
RFG #227 1/26/1980 Hrdi NMC143406 Humboldt
RFG #22A 2/20/1980 Hrdi NMC143492 Humboldt
RFG #23 1/03/1980 Hrdi NMC143274 Humboldt
RFG #238F 1/29/1980 Hrdi NMC143510 Humboldt
RFG #239 1/26/1980 Hrdi NMC143407 Humboldt
RFG #239 2/22/1980 Hrdi NMC143598 Humboldt
RFG #239A 2/22/1980 Hrdi NMC143511 Humboldt
RFG #24 12/22/1979 Hrdi NMC143275 Humboldt
RFG #240 2/22/1980 Hrdi NMC143408 Humboldt
RFG #240 2/22/1980 Hrdi NMC143597 Humboldt
RFG #241 3/11/1980 Hrdi NMC143409 Humboldt
RFG #241A 3/11/1980 Hrdi NMC143596 Humboldt
RFG #242 3/11/1980 Hrdi NMC143410 Humboldt
RFG #243 2/01/1980 Hrdi NMC143411 Humboldt
RFG #244 2/03/1980 Hrdi NMC143412 Humboldt
RFG #245 2/03/1980 Hrdi NMC143413 Humboldt
RFG #246 2/03/1980 Hrdi NMC143414 Humboldt
RFG #247 2/03/1980 Hrdi NMC143415 Humboldt
RFG #248 2/03/1980 Hrdi NMC143416 Humboldt
RFG #25 12/22/1979 Hrdi NMC143276 Humboldt
RFG #26 1/05/1980 Hrdi NMC143277 Humboldt
RFG #262 1/11/1980 Hrdi NMC143487 Humboldt
RFG #264 1/11/1980 Hrdi NMC143417 Humboldt
RFG #265 1/11/1980 Hrdi NMC143418 Humboldt
RFG #266 1/17/1980 Hrdi NMC143419 Humboldt
RFG #267 1/17/1980 Hrdi NMC143420 Humboldt
RFG #268 1/17/1980 Hrdi NMC143421 Humboldt
RFG #269 1/17/1980 Hrdi NMC143422 Humboldt
RFG #27 1/05/1980 Hrdi NMC143278 Humboldt
RFG #270 1/17/1980 Hrdi NMC143423 Humboldt
RFG #271 1/17/1980 Hrdi NMC143424 Humboldt
RFG #28 1/05/1980 Hrdi NMC143279 Humboldt
RFG #288 3/11/1989 Crofoot Daniel M NMC546067 Humboldt
RFG #29 1/05/1980 Hrdi NMC143280 Humboldt
RFG #290 3/11/1989 Crofoot Daniel M NMC546068 Humboldt
RFG #292 3/11/1989 Crofoot Daniel M NMC546069 Humboldt
RFG #294 3/11/1989 Crofoot Daniel M NMC546070 Humboldt
RFG #296 3/11/1989 Crofoot Daniel M NMC546071 Humboldt
RFG #298 2/06/1980 Hrdi NMC143494 Humboldt

 

Hycroft Mine Project

Page 304

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #298 3/11/1989 Crofoot Daniel M NMC546072 Humboldt
RFG #29A 2/06/1980 Hrdi NMC143493 Humboldt
RFG #3 12/20/1979 Hrdi NMC143254 Humboldt
RFG #30 12/22/1979 Hrdi NMC143281 Humboldt
RFG #300 3/11/1989 Crofoot Daniel M NMC546073 Humboldt
RFG #302 3/11/1989 Crofoot Daniel M NMC546074 Humboldt
RFG #304 3/11/1989 Crofoot Daniel M NMC546075 Humboldt
RFG #305 1/18/1980 Hrdi NMC143444 Humboldt
RFG #306 1/18/1980 Hrdi NMC143445 Humboldt
RFG #307 1/18/1980 Hrdi NMC143446 Humboldt
RFG #30A 1/05/1980 Hrdi NMC143495 Humboldt
RFG #31 12/22/1979 Hrdi NMC143282 Humboldt
RFG #32 12/22/1979 Hrdi NMC143283 Humboldt
RFG #322 3/11/1989 Crofoot Daniel M NMC546076 Humboldt
RFG #323 3/11/1989 Crofoot Daniel M NMC546077 Humboldt
RFG #324 3/11/1989 Crofoot Daniel M NMC546078 Humboldt
RFG #325 3/11/1989 Crofoot Daniel M NMC546079 Humboldt
RFG #326 3/11/1989 Crofoot Daniel M NMC546080 Humboldt
RFG #327 3/11/1989 Crofoot Daniel M NMC546081 Humboldt
RFG #328 1/11/1980 Hrdi NMC143453 Humboldt
RFG #329 3/11/1989 Crofoot Daniel M NMC546082 Humboldt
RFG #33 3/10/1989 Crofoot Daniel M NMC546005 Humboldt
RFG #330 1/11/1980 Hrdi NMC143455 Humboldt
RFG #331 3/11/1989 Crofoot Daniel M NMC546083 Humboldt
RFG #332 1/11/1980 Hrdi NMC143457 Humboldt
RFG #333 3/11/1989 Crofoot Daniel M NMC546084 Humboldt
RFG #334 1/11/1980 Hrdi NMC143459 Humboldt
RFG #335 3/11/1989 Crofoot Daniel M NMC546085 Humboldt
RFG #336 1/11/1980 Hrdi NMC143461 Humboldt
RFG #337 3/11/1989 Crofoot Daniel M NMC546086 Humboldt
RFG #338 1/22/1980 Hrdi NMC143463 Humboldt
RFG #339 3/11/1989 Crofoot Daniel M NMC546087 Humboldt
RFG #34 12/22/1979 Hrdi NMC143285 Humboldt
RFG #340 1/22/1980 Hrdi NMC143465 Humboldt
RFG #341 3/11/1989 Crofoot Daniel M NMC546088 Humboldt
RFG #342 1/22/1980 Hrdi NMC143467 Humboldt
RFG #343 3/11/1989 Crofoot Daniel M NMC546089 Humboldt
RFG #35 3/10/1989 Crofoot Daniel M NMC546006 Humboldt
RFG #358 1/31/1980 Hrdi NMC143469 Humboldt
RFG #359 1/31/1980 Hrdi NMC143470 Humboldt
RFG #36 12/22/1979 Hrdi NMC143287 Humboldt
RFG #360 1/31/1980 Hrdi NMC143471 Humboldt
RFG #361 1/31/1980 Hrdi NMC143472 Humboldt
RFG #362 1/31/1980 Homestake Mng Co Of Ca NMC143473 Humboldt
RFG #362A 2/05/1980 Hrdi NMC143512 Humboldt
RFG #363 1/31/1980 Hrdi NMC143474 Humboldt
RFG #364 1/31/1980 Homestake Mng Co Of Ca NMC143475 Humboldt
RFG #364A 2/05/1980 Hrdi NMC143513 Humboldt

 

Hycroft Mine Project

Page 305

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #365 1/31/1980 Hrdi NMC143476 Humboldt
RFG #366 1/31/1980 Homestake Mng Co Of Ca NMC143477 Humboldt
RFG #366A 2/06/1980 Hrdi NMC143514 Humboldt
RFG #367 1/31/1980 Hrdi NMC143478 Humboldt
RFG #368 2/01/1980 Homestake Mng Co Of Ca NMC143479 Humboldt
RFG #368 2/07/1980 Hrdi NMC143497 Humboldt
RFG #368A 2/06/1980 Hrdi NMC143515 Humboldt
RFG #36A 2/07/1980 Hrdi NMC143496 Humboldt
RFG #37 3/10/1989 Crofoot Daniel M NMC546007 Humboldt
RFG #38 3/10/1989 Crofoot Daniel M NMC546008 Humboldt
RFG #39A 3/10/1989 Crofoot Daniel M NMC546009 Humboldt
RFG #4 12/20/1979 Hrdi NMC143255 Humboldt
RFG #40 1/07/1980 Hrdi NMC143291 Humboldt
RFG #400 10/25/1980 Hrdi NMC175062 Humboldt
RFG #401 10/25/1980 Hrdi NMC175063 Humboldt
RFG #402 10/25/1980 Hrdi NMC175064 Humboldt
RFG #403 10/25/1980 Hrdi NMC175065 Humboldt
RFG #404 10/17/1980 Hrdi NMC175066 Humboldt
RFG #405 10/17/1980 Hrdi NMC175067 Humboldt
RFG #406 10/17/1980 Hrdi NMC175068 Humboldt
RFG #407 10/17/1980 Hrdi NMC175069 Humboldt
RFG #408 10/17/1980 Hrdi NMC175070 Humboldt
RFG #409 10/17/1980 Hrdi NMC175071 Humboldt
RFG #41 1/07/1980 Hrdi NMC143292 Humboldt
RFG #410 10/17/1980 Hrdi NMC175072 Humboldt
RFG #411 10/17/1980 Hrdi NMC175073 Humboldt
RFG #412 10/17/1980 Hrdi NMC175074 Humboldt
RFG #413 10/17/1980 Hrdi NMC175075 Humboldt
RFG #414 10/17/1980 Hrdi NMC175076 Humboldt
RFG #415 10/17/1980 Hrdi NMC175077 Humboldt
RFG #416 10/17/1980 Hrdi NMC175078 Humboldt
RFG #417 10/17/1980 Hrdi NMC175079 Humboldt
RFG #418 10/17/1980 Hrdi NMC175080 Humboldt
RFG #419 10/17/1980 Hrdi NMC175081 Humboldt
RFG #42 3/10/1989 Crofoot Daniel M NMC546010 Humboldt
RFG #420 10/17/1980 Hrdi NMC175082 Humboldt
RFG #421 10/17/1980 Hrdi NMC175083 Humboldt
RFG #422 10/17/1980 Hrdi NMC175084 Humboldt
RFG #423 10/17/1980 Hrdi NMC175085 Humboldt
RFG #424 10/17/1980 Hrdi NMC175086 Humboldt
RFG #425 10/17/1980 Hrdi NMC175087 Humboldt
RFG #426 10/17/1980 Hrdi NMC175088 Humboldt
RFG #43 3/10/1989 Crofoot Daniel M NMC546011 Humboldt
RFG #44 3/10/1989 Crofoot Daniel M NMC546012 Humboldt
RFG #45 3/10/1989 Crofoot Daniel M NMC546013 Humboldt
RFG #46 3/10/1989 Crofoot Daniel M NMC546014 Humboldt
RFG #47 3/10/1989 Crofoot Daniel M NMC546015 Humboldt
RFG #48 3/10/1989 Crofoot Daniel M NMC546016 Humboldt
RFG #49 3/10/1989 Crofoot Daniel M NMC546017 Humboldt

 

Hycroft Mine Project

Page 306

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #5 12/20/1979 Hrdi NMC143256 Humboldt
RFG #50 3/10/1989 Crofoot Daniel M NMC546018 Humboldt
RFG #51 3/10/1989 Crofoot Daniel M NMC546019 Humboldt
RFG #52 3/10/1989 Crofoot Daniel M NMC546020 Humboldt
RFG #52A 3/10/1989 Crofoot Daniel M NMC546021 Humboldt
RFG #53 3/10/1989 Crofoot Daniel M NMC546022 Humboldt
RFG #54 3/10/1989 Crofoot Daniel M NMC546023 Humboldt
RFG #55 1/09/1980 Hrdi NMC143306 Humboldt
RFG #56 1/09/1980 Hrdi NMC143307 Humboldt
RFG #57 3/10/1989 Crofoot Daniel M NMC546024 Humboldt
RFG #58 3/10/1989 Crofoot Daniel M NMC546025 Humboldt
RFG #59 3/10/1989 Crofoot Daniel M NMC546026 Humboldt
RFG #6 12/20/1979 Hrdi NMC143257 Humboldt
RFG #60 3/10/1989 Crofoot Daniel M NMC546027 Humboldt
RFG #61 3/10/1989 Crofoot Daniel M NMC546028 Humboldt
RFG #62 3/10/1989 Crofoot Daniel M NMC546029 Humboldt
RFG #63 3/10/1989 Crofoot Daniel M NMC546030 Humboldt
RFG #64 3/10/1989 Crofoot Daniel M NMC546031 Humboldt
RFG #65 3/10/1989 Crofoot Daniel M NMC546032 Humboldt
RFG #66 3/10/1989 Crofoot Daniel M NMC546033 Humboldt
RFG #67 3/10/1989 Crofoot Daniel M NMC546034 Humboldt
RFG #67A 3/10/1989 Crofoot Daniel M NMC546035 Humboldt
RFG #68 3/10/1989 Crofoot Daniel M NMC546036 Humboldt
RFG #68A 3/10/1989 Crofoot Daniel M NMC546037 Humboldt
RFG #69 1/10/1980 Hrdi NMC143320 Humboldt
RFG #7 12/20/1979 Hrdi NMC143258 Humboldt
RFG #70 1/10/1980 Hrdi NMC143321 Humboldt
RFG #71 3/11/1989 Crofoot Daniel M NMC546038 Humboldt
RFG #73 3/11/1989 Crofoot Daniel M NMC546039 Humboldt
RFG #74 3/11/1989 Crofoot Daniel M NMC546040 Humboldt
RFG #75 3/11/1989 Crofoot Daniel M NMC546041 Humboldt
RFG #76 3/11/1989 Crofoot Daniel M NMC546042 Humboldt
RFG #77 3/11/1989 Crofoot Daniel M NMC546043 Humboldt
RFG #78 3/11/1989 Crofoot Daniel M NMC546044 Humboldt
RFG #79 3/11/1989 Crofoot Daniel M NMC546045 Humboldt
RFG #8 12/20/1979 Hrdi NMC143259 Humboldt
RFG #80 3/11/1989 Crofoot Daniel M NMC546046 Humboldt
RFG #81 3/11/1989 Crofoot Daniel M NMC546047 Humboldt
RFG #81A 3/11/1989 Crofoot Daniel M NMC546048 Humboldt
RFG #82 3/11/1989 Crofoot Daniel M NMC546049 Humboldt
RFG #83 3/11/1989 Crofoot Daniel M NMC546050 Humboldt
RFG #85 3/11/1989 Crofoot Daniel M NMC546052 Humboldt
RFG #86 3/11/1989 Crofoot Daniel M NMC546053 Humboldt
RFG #87 3/11/1989 Crofoot Daniel M NMC546054 Humboldt
RFG #88 3/11/1989 Crofoot Daniel M NMC546055 Humboldt
RFG #89 3/11/1989 Crofoot Daniel M NMC546056 Humboldt

 

Hycroft Mine Project

Page 307

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #9 12/20/1979 Hrdi NMC143260 Humboldt
RFG #90 3/11/1989 Crofoot Daniel M NMC546057 Humboldt
RFG #91 3/11/1989 Crofoot Daniel M NMC546058 Humboldt
RFG #92 3/11/1989 Crofoot Daniel M NMC546059 Humboldt
RFG #93 3/11/1989 Crofoot Daniel M NMC546060 Humboldt
RFG #94 3/11/1989 Crofoot Daniel M NMC546061 Humboldt
RFG #95 3/11/1989 Crofoot Daniel M NMC546062 Humboldt
RFG #97 3/11/1989 Crofoot Daniel M NMC546063 Humboldt
RFG 102 5/20/2006 Hycroft Res & Dev Inc NMC932886 Humboldt
RFG 126 5/20/2006 Hycroft Res & Dev Inc NMC932903 Humboldt
RFG 128 5/20/2006 Hycroft Res & Dev Inc NMC932904 Humboldt
RFG 258 5/20/2006 Hycroft Res & Dev Inc NMC932912 Humboldt
RFG 260 5/20/2006 Hycroft Res & Dev Inc NMC932913 Humboldt
RFG 286 5/20/2006 Hycroft Res & Dev Inc NMC932914 Humboldt
RFG 287 5/20/2006 Hycroft Res & Dev Inc NMC932915 Humboldt
RFG 289 5/20/2006 Hycroft Res & Dev Inc NMC932916 Humboldt
RFG 291 5/20/2006 Hycroft Res & Dev Inc NMC932917 Humboldt
RFG 293 5/20/2006 Hycroft Res & Dev Inc NMC932918 Humboldt
RFG 295 5/20/2006 Hycroft Res & Dev Inc NMC932919 Humboldt
RFG 297 5/20/2006 Hycroft Res & Dev Inc NMC932920 Humboldt
RFG 299 5/20/2006 Hycroft Res & Dev Inc NMC932921 Humboldt
RFG 301 5/20/2006 Hycroft Res & Dev Inc NMC932922 Humboldt
RFG 303 5/20/2006 Hycroft Res & Dev Inc NMC932923 Humboldt
RFG 94A 5/20/2006 Hycroft Res & Dev Inc NMC932885 Humboldt
RFG Fraction #427 10/17/1980 Hrdi NMC175089 Humboldt
RFG#14 1/03/1980 Hrdi NMC143265 Humboldt
RFG#328X 5/15/1984 Lewis Frank W NMC307553 Humboldt
RFG#84 3/11/1989 Crofoot Daniel M NMC546051 Humboldt
RFG-130-A 1/08/2008 Victory Exploration Inc. NMC985654 Humboldt
RFGM 1 6/18/2009 Hycroft Res & Dev Inc NMC1008652 Humboldt
RFGM 10 6/18/2009 Hycroft Res & Dev Inc NMC1008661 Humboldt
RFGM 10A 6/18/2009 Hycroft Res & Dev Inc NMC1008716 Humboldt
RFGM 11 6/18/2009 Hycroft Res & Dev Inc NMC1008662 Humboldt
RFGM 11A 6/18/2009 Hycroft Res & Dev Inc NMC1008717 Humboldt
RFGM 12 6/18/2009 Hycroft Res & Dev Inc NMC1008663 Humboldt
RFGM 12A 6/18/2009 Hycroft Res & Dev Inc NMC1008718 Humboldt
RFGM 12B 6/18/2009 Hycroft Res & Dev Inc NMC1008728 Humboldt
RFGM 13 6/18/2009 Hycroft Res & Dev Inc NMC1008664 Humboldt
RFGM 13A 6/18/2009 Hycroft Res & Dev Inc NMC1008719 Humboldt
RFGM 13B 6/18/2009 Hycroft Res & Dev Inc NMC1008729 Humboldt
RFGM 14 6/18/2009 Hycroft Res & Dev Inc NMC1008665 Humboldt
RFGM 14A 6/18/2009 Hycroft Res & Dev Inc NMC1008720 Humboldt
RFGM 15 6/18/2009 Hycroft Res & Dev Inc NMC1008666 Humboldt
RFGM 16 6/18/2009 Hycroft Res & Dev Inc NMC1008667 Humboldt
RFGM 17 6/18/2009 Hycroft Res & Dev Inc NMC1008668 Humboldt
RFGM 171 6/18/2009 Hycroft Res & Dev Inc NMC1008691 Humboldt
RFGM 172 6/18/2009 Hycroft Res & Dev Inc NMC1008692 Humboldt
RFGM 176 6/18/2009 Hycroft Res & Dev Inc NMC1008693 Humboldt
RFGM 177 6/18/2009 Hycroft Res & Dev Inc NMC1008694 Humboldt

 

Hycroft Mine Project

Page 308

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFGM 177A 6/18/2009 Hycroft Res & Dev Inc NMC1008725 Humboldt
RFGM 178 6/18/2009 Hycroft Res & Dev Inc NMC1008695 Humboldt
RFGM 179 6/18/2009 Hycroft Res & Dev Inc NMC1008696 Humboldt
RFGM 18 6/18/2009 Hycroft Res & Dev Inc NMC1008669 Humboldt
RFGM 180 6/18/2009 Hycroft Res & Dev Inc NMC1008697 Humboldt
RFGM 181 6/18/2009 Hycroft Res & Dev Inc NMC1008698 Humboldt
RFGM 182 6/18/2009 Hycroft Res & Dev Inc NMC1008699 Humboldt
RFGM 183 6/18/2009 Hycroft Res & Dev Inc NMC1008700 Humboldt
RFGM 184 6/18/2009 Hycroft Res & Dev Inc NMC1008701 Humboldt
RFGM 186 6/18/2009 Hycroft Res & Dev Inc NMC1008702 Humboldt
RFGM 187 6/18/2009 Hycroft Res & Dev Inc NMC1008703 Humboldt
RFGM 18A 6/18/2009 Hycroft Res & Dev Inc NMC1008721 Humboldt
RFGM 19 6/18/2009 Hycroft Res & Dev Inc NMC1008670 Humboldt
RFGM 2 6/18/2009 Hycroft Res & Dev Inc NMC1008653 Humboldt
RFGM 20 6/18/2009 Hycroft Res & Dev Inc NMC1008671 Humboldt
RFGM 20A 6/18/2009 Hycroft Res & Dev Inc NMC1008722 Humboldt
RFGM 21 6/18/2009 Hycroft Res & Dev Inc NMC1008672 Humboldt
RFGM 22 6/18/2009 Hycroft Res & Dev Inc NMC1008673 Humboldt
RFGM 22A 6/18/2009 Hycroft Res & Dev Inc NMC1008723 Humboldt
RFGM 22B 6/18/2009 Hycroft Res & Dev Inc NMC1008730 Humboldt
RFGM 23 6/18/2009 Hycroft Res & Dev Inc NMC1008674 Humboldt
RFGM 24 6/18/2009 Hycroft Res & Dev Inc NMC1008675 Humboldt
RFGM 25 6/18/2009 Hycroft Res & Dev Inc NMC1008676 Humboldt
RFGM 26 6/18/2009 Hycroft Res & Dev Inc NMC1008677 Humboldt
RFGM 27 6/18/2009 Hycroft Res & Dev Inc NMC1008678 Humboldt
RFGM 27A 6/18/2009 Hycroft Res & Dev Inc NMC1008724 Humboldt
RFGM 28 6/18/2009 Hycroft Res & Dev Inc NMC1008679 Humboldt
RFGM 29 6/18/2009 Hycroft Res & Dev Inc NMC1008680 Humboldt
RFGM 3 6/18/2009 Hycroft Res & Dev Inc NMC1008654 Humboldt
RFGM 30 6/18/2009 Hycroft Res & Dev Inc NMC1008681 Humboldt
RFGM 31 6/18/2009 Hycroft Res & Dev Inc NMC1008682 Humboldt
RFGM 32 6/18/2009 Hycroft Res & Dev Inc NMC1008683 Humboldt
RFGM 33 6/18/2009 Hycroft Res & Dev Inc NMC1008684 Humboldt
RFGM 34 6/18/2009 Hycroft Res & Dev Inc NMC1008685 Humboldt
RFGM 357 6/18/2009 Hycroft Res & Dev Inc NMC1008704 Humboldt
RFGM 358 6/18/2009 Hycroft Res & Dev Inc NMC1008705 Humboldt
RFGM 358A 6/18/2009 Hycroft Res & Dev Inc NMC1008726 Humboldt
RFGM 359 6/18/2009 Hycroft Res & Dev Inc NMC1008706 Humboldt
RFGM 359A 6/18/2009 Hycroft Res & Dev Inc NMC1008727 Humboldt
RFGM 360 6/18/2009 Hycroft Res & Dev Inc NMC1008707 Humboldt
RFGM 361 6/18/2009 Hycroft Res & Dev Inc NMC1008708 Humboldt
RFGM 363 6/18/2009 Hycroft Res & Dev Inc NMC1008709 Humboldt
RFGM 365 6/18/2009 Hycroft Res & Dev Inc NMC1008710 Humboldt
RFGM 367 6/18/2009 Hycroft Res & Dev Inc NMC1008711 Humboldt
RFGM 4 6/18/2009 Hycroft Res & Dev Inc NMC1008655 Humboldt
RFGM 40 6/18/2009 Hycroft Res & Dev Inc NMC1008686 Humboldt
RFGM 41 6/18/2009 Hycroft Res & Dev Inc NMC1008687 Humboldt
RFGM 42 6/18/2009 Hycroft Res & Dev Inc NMC1008688 Humboldt

 

Hycroft Mine Project

Page 309

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFGM 43 6/18/2009 Hycroft Res & Dev Inc NMC1008689 Humboldt
RFGM 5 6/18/2009 Hycroft Res & Dev Inc NMC1008656 Humboldt
RFGM 57 6/18/2009 Hycroft Res & Dev Inc NMC1008690 Humboldt
RFGM 6 6/18/2009 Hycroft Res & Dev Inc NMC1008657 Humboldt
RFGM 6A 6/18/2009 Hycroft Res & Dev Inc NMC1008712 Humboldt
RFGM 7 6/18/2009 Hycroft Res & Dev Inc NMC1008658 Humboldt
RFGM 7A 6/18/2009 Hycroft Res & Dev Inc NMC1008713 Humboldt
RFGM 8 6/18/2009 Hycroft Res & Dev Inc NMC1008659 Humboldt
RFGM 8A 6/18/2009 Hycroft Res & Dev Inc NMC1008714 Humboldt
RFGM 9 6/18/2009 Hycroft Res & Dev Inc NMC1008660 Humboldt
RFGM 9A 6/18/2009 Hycroft Res & Dev Inc NMC1008715 Humboldt
SH 1 4/20/2008 Hycroft Res & Dev Inc NMC990654 Humboldt
SH 10 4/20/2008 Hycroft Res & Dev Inc NMC990663 Humboldt
SH 100 4/06/2008 Hycroft Res & Dev Inc NMC990753 Humboldt
SH 101 4/06/2008 Hycroft Res & Dev Inc NMC990754 Humboldt
SH 102 4/06/2008 Hycroft Res & Dev Inc NMC990755 Humboldt
SH 103 4/06/2008 Hycroft Res & Dev Inc NMC990756 Humboldt
SH 104 4/06/2008 Hycroft Res & Dev Inc NMC990757 Humboldt
SH 105 4/06/2008 Hycroft Res & Dev Inc NMC990758 Humboldt
SH 106 4/06/2008 Hycroft Res & Dev Inc NMC990759 Humboldt
SH 107 4/06/2008 Hycroft Res & Dev Inc NMC990760 Humboldt
SH 108 4/06/2008 Hycroft Res & Dev Inc NMC990761 Humboldt
SH 109 4/06/2008 Hycroft Res & Dev Inc NMC990762 Humboldt
SH 11 4/20/2008 Hycroft Res & Dev Inc NMC990664 Humboldt
SH 110 4/06/2008 Hycroft Res & Dev Inc NMC990763 Humboldt
SH 111 4/06/2008 Hycroft Res & Dev Inc NMC990764 Humboldt
SH 112 4/06/2008 Hycroft Res & Dev Inc NMC990765 Humboldt
SH 113 4/06/2008 Hycroft Res & Dev Inc NMC990766 Humboldt
SH 114 4/06/2008 Hycroft Res & Dev Inc NMC990767 Humboldt
SH 115 4/06/2008 Hycroft Res & Dev Inc NMC990768 Humboldt
SH 116 4/05/2008 Hycroft Res & Dev Inc NMC990769 Humboldt
SH 117 4/05/2008 Hycroft Res & Dev Inc NMC990770 Humboldt
SH 118 4/05/2008 Hycroft Res & Dev Inc NMC990771 Humboldt
SH 119 4/05/2008 Hycroft Res & Dev Inc NMC990772 Humboldt
SH 12 4/20/2008 Hycroft Res & Dev Inc NMC990665 Humboldt
SH 120 4/05/2008 Hycroft Res & Dev Inc NMC990773 Humboldt
SH 121 4/05/2008 Hycroft Res & Dev Inc NMC990774 Humboldt
SH 122 4/05/2008 Hycroft Res & Dev Inc NMC990775 Humboldt
SH 123 4/05/2008 Hycroft Res & Dev Inc NMC990776 Humboldt
SH 124 4/05/2008 Hycroft Res & Dev Inc NMC990777 Humboldt
SH 125 4/05/2008 Hycroft Res & Dev Inc NMC990778 Humboldt
SH 126 4/05/2008 Hycroft Res & Dev Inc NMC990779 Humboldt
SH 127 4/05/2008 Hycroft Res & Dev Inc NMC990780 Humboldt
SH 128 4/05/2008 Hycroft Res & Dev Inc NMC990781 Humboldt
SH 129 4/05/2008 Hycroft Res & Dev Inc NMC990782 Humboldt
SH 13 4/20/2008 Hycroft Res & Dev Inc NMC990666 Humboldt
SH 130 4/06/2008 Hycroft Res & Dev Inc NMC990783 Humboldt
SH 131 4/06/2008 Hycroft Res & Dev Inc NMC990784 Humboldt

 

Hycroft Mine Project

Page 310

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 132 4/06/2008 Hycroft Res & Dev Inc NMC990785 Humboldt
SH 133 4/06/2008 Hycroft Res & Dev Inc NMC990786 Humboldt
SH 134 4/06/2008 Hycroft Res & Dev Inc NMC990787 Humboldt
SH 135 4/06/2008 Hycroft Res & Dev Inc NMC990788 Humboldt
SH 136 4/06/2008 Hycroft Res & Dev Inc NMC990789 Humboldt
SH 137 4/06/2008 Hycroft Res & Dev Inc NMC990790 Humboldt
SH 138 4/06/2008 Hycroft Res & Dev Inc NMC990791 Humboldt
SH 139 4/06/2008 Hycroft Res & Dev Inc NMC990792 Humboldt
SH 14 4/20/2008 Hycroft Res & Dev Inc NMC990667 Humboldt
SH 140 4/06/2008 Hycroft Res & Dev Inc NMC990793 Humboldt
SH 141 4/06/2008 Hycroft Res & Dev Inc NMC990794 Humboldt
SH 142 4/06/2008 Hycroft Res & Dev Inc NMC990795 Humboldt
SH 143 4/06/2008 Hycroft Res & Dev Inc NMC990796 Humboldt
SH 144 4/06/2008 Hycroft Res & Dev Inc NMC990797 Humboldt
SH 145 4/06/2008 Hycroft Res & Dev Inc NMC990798 Humboldt
SH 146 4/06/2008 Hycroft Res & Dev Inc NMC990799 Humboldt
SH 147 4/06/2008 Hycroft Res & Dev Inc NMC990800 Humboldt
SH 148 4/06/2008 Hycroft Res & Dev Inc NMC990801 Humboldt
SH 149 4/06/2008 Hycroft Res & Dev Inc NMC990802 Humboldt
SH 15 4/20/2008 Hycroft Res & Dev Inc NMC990668 Humboldt
SH 150 4/06/2008 Hycroft Res & Dev Inc NMC990803 Humboldt
SH 151 4/06/2008 Hycroft Res & Dev Inc NMC990804 Humboldt
SH 152 4/06/2008 Hycroft Res & Dev Inc NMC990805 Humboldt
SH 153 4/06/2008 Hycroft Res & Dev Inc NMC990806 Humboldt
SH 154 4/06/2008 Hycroft Res & Dev Inc NMC990807 Humboldt
SH 155 4/05/2008 Hycroft Res & Dev Inc NMC990808 Humboldt
SH 156 4/05/2008 Hycroft Res & Dev Inc NMC990809 Humboldt
SH 157 4/05/2008 Hycroft Res & Dev Inc NMC990810 Humboldt
SH 158 4/05/2008 Hycroft Res & Dev Inc NMC990811 Humboldt
SH 159 4/05/2008 Hycroft Res & Dev Inc NMC990812 Humboldt
SH 16 4/20/2008 Hycroft Res & Dev Inc NMC990669 Humboldt
SH 160 4/05/2008 Hycroft Res & Dev Inc NMC990813 Humboldt
SH 161 4/05/2008 Hycroft Res & Dev Inc NMC990814 Humboldt
SH 162 4/05/2008 Hycroft Res & Dev Inc NMC990815 Humboldt
SH 163 4/05/2008 Hycroft Res & Dev Inc NMC990816 Humboldt
SH 164 4/05/2008 Hycroft Res & Dev Inc NMC990817 Humboldt
SH 165 4/05/2008 Hycroft Res & Dev Inc NMC990818 Humboldt
SH 166 4/05/2008 Hycroft Res & Dev Inc NMC990819 Humboldt
SH 167 4/05/2008 Hycroft Res & Dev Inc NMC990820 Humboldt
SH 168 4/05/2008 Hycroft Res & Dev Inc NMC990821 Humboldt
SH 17 4/20/2008 Hycroft Res & Dev Inc NMC990670 Humboldt
SH 18 4/20/2008 Hycroft Res & Dev Inc NMC990671 Humboldt
SH 19 4/20/2008 Hycroft Res & Dev Inc NMC990672 Humboldt
SH 2 4/20/2008 Hycroft Res & Dev Inc NMC990655 Humboldt
SH 20 4/20/2008 Hycroft Res & Dev Inc NMC990673 Humboldt
SH 21 4/20/2008 Hycroft Res & Dev Inc NMC990674 Humboldt
SH 22 4/20/2008 Hycroft Res & Dev Inc NMC990675 Humboldt
SH 23 4/20/2008 Hycroft Res & Dev Inc NMC990676 Humboldt

 

Hycroft Mine Project

Page 311

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 24 4/20/2008 Hycroft Res & Dev Inc NMC990677 Humboldt
SH 25 4/20/2008 Hycroft Res & Dev Inc NMC990678 Humboldt
SH 26 4/20/2008 Hycroft Res & Dev Inc NMC990679 Humboldt
SH 27 4/20/2008 Hycroft Res & Dev Inc NMC990680 Humboldt
SH 28 4/20/2008 Hycroft Res & Dev Inc NMC990681 Humboldt
SH 29 4/20/2008 Hycroft Res & Dev Inc NMC990682 Humboldt
SH 3 4/20/2008 Hycroft Res & Dev Inc NMC990656 Humboldt
SH 30 4/20/2008 Hycroft Res & Dev Inc NMC990683 Humboldt
SH 31 4/20/2008 Hycroft Res & Dev Inc NMC990684 Humboldt
SH 32 4/06/2008 Hycroft Res & Dev Inc NMC990685 Humboldt
SH 33 4/06/2008 Hycroft Res & Dev Inc NMC990686 Humboldt
SH 34 4/06/2008 Hycroft Res & Dev Inc NMC990687 Humboldt
SH 35 4/06/2008 Hycroft Res & Dev Inc NMC990688 Humboldt
SH 350 4/21/2008 Hycroft Res & Dev Inc NMC991002 Humboldt
SH 351 4/21/2008 Hycroft Res & Dev Inc NMC991003 Humboldt
SH 352 4/21/2008 Hycroft Res & Dev Inc NMC991004 Humboldt
SH 36 4/06/2008 Hycroft Res & Dev Inc NMC990689 Humboldt
SH 37 4/06/2008 Hycroft Res & Dev Inc NMC990690 Humboldt
SH 373 4/21/2008 Hycroft Res & Dev Inc NMC991025 Humboldt
SH 374 4/21/2008 Hycroft Res & Dev Inc NMC991026 Humboldt
SH 375 4/21/2008 Hycroft Res & Dev Inc NMC991027 Humboldt
SH 376 4/21/2008 Hycroft Res & Dev Inc NMC991028 Humboldt
SH 377 4/21/2008 Hycroft Res & Dev Inc NMC991029 Humboldt
SH 378 4/21/2008 Hycroft Res & Dev Inc NMC991030 Humboldt
SH 379 4/21/2008 Hycroft Res & Dev Inc NMC991031 Humboldt
SH 38 4/06/2008 Hycroft Res & Dev Inc NMC990691 Humboldt
SH 380 4/21/2008 Hycroft Res & Dev Inc NMC991032 Humboldt
SH 381 4/21/2008 Hycroft Res & Dev Inc NMC991033 Humboldt
SH 39 4/06/2008 Hycroft Res & Dev Inc NMC990692 Humboldt
SH 396 4/21/2008 Hycroft Res & Dev Inc NMC991048 Humboldt
SH 397 4/21/2008 Hycroft Res & Dev Inc NMC991049 Humboldt
SH 398 4/21/2008 Hycroft Res & Dev Inc NMC991050 Humboldt
SH 399 4/21/2008 Hycroft Res & Dev Inc NMC991051 Humboldt
SH 400 4/21/2008 Hycroft Res & Dev Inc NMC991052 Humboldt
SH 401 4/21/2008 Hycroft Res & Dev Inc NMC991053 Humboldt
SH 402 4/21/2008 Hycroft Res & Dev Inc NMC991054 Humboldt
SH 403 4/21/2008 Hycroft Res & Dev Inc NMC991055 Humboldt
SH 404 4/21/2008 Hycroft Res & Dev Inc NMC991056 Humboldt
SH 405 4/21/2008 Hycroft Res & Dev Inc NMC991057 Humboldt
SH 406 4/21/2008 Hycroft Res & Dev Inc NMC991058 Humboldt
SH 41 4/06/2008 Hycroft Res & Dev Inc NMC990694 Humboldt
SH 419 4/21/2008 Hycroft Res & Dev Inc NMC991071 Humboldt
SH 42 4/06/2008 Hycroft Res & Dev Inc NMC990695 Humboldt
SH 420 4/21/2008 Hycroft Res & Dev Inc NMC991072 Humboldt
SH 421 4/21/2008 Hycroft Res & Dev Inc NMC991073 Humboldt
SH 422 4/21/2008 Hycroft Res & Dev Inc NMC991074 Humboldt
SH 423 4/21/2008 Hycroft Res & Dev Inc NMC991075 Humboldt
SH 424 4/21/2008 Hycroft Res & Dev Inc NMC991076 Humboldt

 

Hycroft Mine Project

Page 312

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 425 4/21/2008 Hycroft Res & Dev Inc NMC991077 Humboldt
SH 426 4/21/2008 Hycroft Res & Dev Inc NMC991078 Humboldt
SH 427 4/21/2008 Hycroft Res & Dev Inc NMC991079 Humboldt
SH 428 4/21/2008 Hycroft Res & Dev Inc NMC991080 Humboldt
SH 429 4/21/2008 Hycroft Res & Dev Inc NMC991081 Humboldt
SH 43 4/06/2008 Hycroft Res & Dev Inc NMC990696 Humboldt
SH 430 4/21/2008 Hycroft Res & Dev Inc NMC991082 Humboldt
SH 439 4/21/2008 Hycroft Res & Dev Inc NMC991090 Humboldt
SH 44 4/06/2008 Hycroft Res & Dev Inc NMC990697 Humboldt
SH 440 4/21/2008 Hycroft Res & Dev Inc NMC991091 Humboldt
SH 441 4/21/2008 Hycroft Res & Dev Inc NMC991092 Humboldt
SH 442 4/21/2008 Hycroft Res & Dev Inc NMC991093 Humboldt
SH 443 4/21/2008 Hycroft Res & Dev Inc NMC991094 Humboldt
SH 444 4/21/2008 Hycroft Res & Dev Inc NMC991095 Humboldt
SH 445 4/21/2008 Hycroft Res & Dev Inc NMC991096 Humboldt
SH 446 4/21/2008 Hycroft Res & Dev Inc NMC991097 Humboldt
SH 447 4/21/2008 Hycroft Res & Dev Inc NMC991098 Humboldt
SH 448 4/21/2008 Hycroft Res & Dev Inc NMC991099 Humboldt
SH 449 4/21/2008 Hycroft Res & Dev Inc NMC991100 Humboldt
SH 45 4/06/2008 Hycroft Res & Dev Inc NMC990698 Humboldt
SH 450 4/21/2008 Hycroft Res & Dev Inc NMC991101 Humboldt
SH 451 4/21/2008 Hycroft Res & Dev Inc NMC991102 Humboldt
SH 452 4/21/2008 Hycroft Res & Dev Inc NMC991103 Humboldt
SH 453 4/21/2008 Hycroft Res & Dev Inc NMC991104 Humboldt
SH 454 4/21/2008 Hycroft Res & Dev Inc NMC991105 Humboldt
SH 455 4/21/2008 Hycroft Res & Dev Inc NMC991106 Humboldt
SH 456 4/21/2008 Hycroft Res & Dev Inc NMC991107 Humboldt
SH 46 4/06/2008 Hycroft Res & Dev Inc NMC990699 Humboldt
SH 47 4/06/2008 Hycroft Res & Dev Inc NMC990700 Humboldt
SH 48 4/06/2008 Hycroft Res & Dev Inc NMC990701 Humboldt
SH 49 4/06/2008 Hycroft Res & Dev Inc NMC990702 Humboldt
SH 5 4/20/2008 Hycroft Res & Dev Inc NMC990658 Humboldt
SH 50 4/06/2008 Hycroft Res & Dev Inc NMC990703 Humboldt
SH 51 4/06/2008 Hycroft Res & Dev Inc NMC990704 Humboldt
SH 52 4/06/2008 Hycroft Res & Dev Inc NMC990705 Humboldt
SH 53 4/06/2008 Hycroft Res & Dev Inc NMC990706 Humboldt
SH 54 4/06/2008 Hycroft Res & Dev Inc NMC990707 Humboldt
SH 55 4/06/2008 Hycroft Res & Dev Inc NMC990708 Humboldt
SH 56 4/06/2008 Hycroft Res & Dev Inc NMC990709 Humboldt
SH 57 4/06/2008 Hycroft Res & Dev Inc NMC990710 Humboldt
SH 58 4/06/2008 Hycroft Res & Dev Inc NMC990711 Humboldt
SH 59 4/06/2008 Hycroft Res & Dev Inc NMC990712 Humboldt
SH 6 4/20/2008 Hycroft Res & Dev Inc NMC990659 Humboldt
SH 60 4/06/2008 Hycroft Res & Dev Inc NMC990713 Humboldt
SH 61 4/06/2008 Hycroft Res & Dev Inc NMC990714 Humboldt
SH 62 4/06/2008 Hycroft Res & Dev Inc NMC990715 Humboldt
SH 63 4/06/2008 Hycroft Res & Dev Inc NMC990716 Humboldt
SH 64 4/06/2008 Hycroft Res & Dev Inc NMC990717 Humboldt

 

Hycroft Mine Project

Page 313

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 65 4/06/2008 Hycroft Res & Dev Inc NMC990718 Humboldt
SH 66 4/06/2008 Hycroft Res & Dev Inc NMC990719 Humboldt
SH 67 4/06/2008 Hycroft Res & Dev Inc NMC990720 Humboldt
SH 68 4/06/2008 Hycroft Res & Dev Inc NMC990721 Humboldt
SH 69 4/06/2008 Hycroft Res & Dev Inc NMC990722 Humboldt
SH 7 4/20/2008 Hycroft Res & Dev Inc NMC990660 Humboldt
SH 70 4/06/2008 Hycroft Res & Dev Inc NMC990723 Humboldt
SH 71 4/06/2008 Hycroft Res & Dev Inc NMC990724 Humboldt
SH 72 4/06/2008 Hycroft Res & Dev Inc NMC990725 Humboldt
SH 73 4/06/2008 Hycroft Res & Dev Inc NMC990726 Humboldt
SH 74 4/06/2008 Hycroft Res & Dev Inc NMC990727 Humboldt
SH 75 4/06/2008 Hycroft Res & Dev Inc NMC990728 Humboldt
SH 76 4/06/2008 Hycroft Res & Dev Inc NMC990729 Humboldt
SH 77 4/06/2008 Hycroft Res & Dev Inc NMC990730 Humboldt
SH 78 4/06/2008 Hycroft Res & Dev Inc NMC990731 Humboldt
SH 79 4/06/2008 Hycroft Res & Dev Inc NMC990732 Humboldt
SH 8 4/20/2008 Hycroft Res & Dev Inc NMC990661 Humboldt
SH 80 4/06/2008 Hycroft Res & Dev Inc NMC990733 Humboldt
SH 81 4/06/2008 Hycroft Res & Dev Inc NMC990734 Humboldt
SH 82 4/05/2008 Hycroft Res & Dev Inc NMC990735 Humboldt
SH 83 4/05/2008 Hycroft Res & Dev Inc NMC990736 Humboldt
SH 84 4/05/2008 Hycroft Res & Dev Inc NMC990737 Humboldt
SH 85 4/05/2008 Hycroft Res & Dev Inc NMC990738 Humboldt
SH 86 4/05/2008 Hycroft Res & Dev Inc NMC990739 Humboldt
SH 87 4/05/2008 Hycroft Res & Dev Inc NMC990740 Humboldt
SH 88 4/05/2008 Hycroft Res & Dev Inc NMC990741 Humboldt
SH 89 4/05/2008 Hycroft Res & Dev Inc NMC990742 Humboldt
SH 9 4/20/2008 Hycroft Res & Dev Inc NMC990662 Humboldt
SH 90 4/05/2008 Hycroft Res & Dev Inc NMC990743 Humboldt
SH 91 4/06/2008 Hycroft Res & Dev Inc NMC990744 Humboldt
SH 92 4/06/2008 Hycroft Res & Dev Inc NMC990745 Humboldt
SH 93 4/06/2008 Hycroft Res & Dev Inc NMC990746 Humboldt
SH 94 4/06/2008 Hycroft Res & Dev Inc NMC990747 Humboldt
SH 95 4/06/2008 Hycroft Res & Dev Inc NMC990748 Humboldt
SH 96 4/06/2008 Hycroft Res & Dev Inc NMC990749 Humboldt
SH 97 4/06/2008 Hycroft Res & Dev Inc NMC990750 Humboldt
SH 98 4/06/2008 Hycroft Res & Dev Inc NMC990751 Humboldt
SH 99 4/06/2008 Hycroft Res & Dev Inc NMC990752 Humboldt
SH4 4/20/2008 Hycroft Res & Dev Inc NMC990657 Humboldt
SH40 4/06/2008 Hycroft Res & Dev Inc NMC990693 Humboldt
SL 1 10/18/2012 Hycroft Res & Dev Inc NMC1080086 Humboldt
SL 2 10/18/2012 Hycroft Res & Dev Inc NMC1080087 Humboldt
SL 3 10/18/2012 Hycroft Res & Dev Inc NMC1080088 Humboldt
SL 4 10/18/2012 Hycroft Res & Dev Inc NMC1080089 Humboldt
SL 5 10/18/2012 Hycroft Res & Dev Inc NMC1080090 Humboldt
SL 6 10/18/2012 Hycroft Res & Dev Inc NMC1080091 Humboldt
Sulphate 11/04/1980 Lewis Frank W NMC181011 Humboldt
Triple L #1 10/13/1979 Lewis Frank W NMC127534 Humboldt

 

Hycroft Mine Project

Page 314

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
Triple L #2 10/13/1979 Lewis Frank W NMC127535 Humboldt
Triple L #3 10/13/1979 Lewis Frank W NMC127536 Humboldt
Triple L #4 10/13/1979 Lewis Frank W NMC127537 Humboldt
Triple L #5 10/13/1979 Lewis Frank W NMC127538 Humboldt
WKM-1 9/30/1997 F W Lewis Inc NMC780688 Humboldt
WKM-10 9/30/1997 F W Lewis Inc NMC780697 Humboldt
WKM-11 9/30/1997 F W Lewis Inc NMC780698 Humboldt
WKM-12 9/30/1997 F W Lewis Inc NMC780699 Humboldt
WKM-13 9/30/1997 F W Lewis Inc NMC780700 Humboldt
WKM-14 9/30/1997 F W Lewis Inc NMC780701 Humboldt
WKM-15 9/30/1997 F W Lewis Inc NMC780702 Humboldt
WKM-16 9/30/1997 F W Lewis Inc NMC780703 Humboldt
WKM-17 9/30/1997 F W Lewis Inc NMC780704 Humboldt
WKM-18 9/30/1997 F W Lewis Inc NMC780705 Humboldt
WKM-19 10/01/1997 F W Lewis Inc NMC780706 Humboldt
WKM-2 9/30/1997 F W Lewis Inc NMC780689 Humboldt
WKM-20 10/01/1997 F W Lewis Inc NMC780707 Humboldt
WKM-21 10/01/1997 F W Lewis Inc NMC780708 Humboldt
WKM-22 10/01/1997 F W Lewis Inc NMC780709 Humboldt
WKM-23 10/01/1997 F W Lewis Inc NMC780710 Humboldt
WKM-24 10/01/1997 F W Lewis Inc NMC780711 Humboldt
WKM-25 10/01/1997 F W Lewis Inc NMC780712 Humboldt
WKM-26 10/01/1997 F W Lewis Inc NMC780713 Humboldt
WKM-27 10/01/1997 F W Lewis Inc NMC780714 Humboldt
WKM-28 10/01/1997 F W Lewis Inc NMC780715 Humboldt
WKM-29 10/01/1997 F W Lewis Inc NMC780716 Humboldt
WKM-3 9/30/1997 F W Lewis Inc NMC780690 Humboldt
WKM-30 10/01/1997 F W Lewis Inc NMC780717 Humboldt
WKM-31 10/01/1997 F W Lewis Inc NMC780718 Humboldt
WKM-32 10/01/1997 F W Lewis Inc NMC780719 Humboldt
WKM-33 10/01/1997 F W Lewis Inc NMC780720 Humboldt
WKM-34 10/01/1997 F W Lewis Inc NMC780721 Humboldt
WKM-35 10/01/1997 F W Lewis Inc NMC780722 Humboldt
WKM-36 10/01/1997 F W Lewis Inc NMC780723 Humboldt
WKM-37 10/01/1997 F W Lewis Inc NMC780724 Humboldt
WKM-38 10/01/1997 F W Lewis Inc NMC780725 Humboldt
WKM-39 10/01/1997 F W Lewis Inc NMC780726 Humboldt
WKM-4 9/30/1997 F W Lewis Inc NMC780691 Humboldt
WKM-40 10/01/1997 F W Lewis Inc NMC780727 Humboldt
WKM-41 10/01/1997 F W Lewis Inc NMC780728 Humboldt
WKM-42 10/01/1997 F W Lewis Inc NMC780729 Humboldt
WKM-43 10/01/1997 F W Lewis Inc NMC780730 Humboldt
WKM-44 10/01/1997 F W Lewis Inc NMC780731 Humboldt
WKM-45 10/01/1997 F W Lewis Inc NMC780732 Humboldt
WKM-46 10/01/1997 F W Lewis Inc NMC780733 Humboldt
WKM-47 10/01/1997 F W Lewis Inc NMC780734 Humboldt
WKM-48 10/01/1997 F W Lewis Inc NMC780735 Humboldt

 

Hycroft Mine Project

Page 315

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
WKM-5 9/30/1997 F W Lewis Inc NMC780692 Humboldt
WKM-50 10/01/1997 F W Lewis Inc NMC780736 Humboldt
WKM-51 10/02/1997 F W Lewis Inc NMC780737 Humboldt
WKM-52 10/02/1997 F W Lewis Inc NMC780738 Humboldt
WKM-53 10/02/1997 F W Lewis Inc NMC780739 Humboldt
WKM-54 10/02/1997 F W Lewis Inc NMC780740 Humboldt
WKM-55 10/02/1997 F W Lewis Inc NMC780741 Humboldt
WKM-56 10/02/1997 F W Lewis Inc NMC780742 Humboldt
WKM-57 10/02/1997 F W Lewis Inc NMC780743 Humboldt
WKM-58 10/02/1997 F W Lewis Inc NMC780744 Humboldt
WKM-6 9/30/1997 F W Lewis Inc NMC780693 Humboldt
WKM-60 10/06/1997 F W Lewis Inc NMC780745 Humboldt
WKM-62 10/06/1997 F W Lewis Inc NMC780746 Humboldt
WKM-64 10/06/1997 F W Lewis Inc NMC780747 Humboldt
WKM-7 9/30/1997 F W Lewis Inc NMC780694 Humboldt
WKM-8 9/30/1997 F W Lewis Inc NMC780695 Humboldt
WKM-9 9/30/1997 F W Lewis Inc NMC780696 Humboldt
FG 49 12/18/2013 Hycroft Res & Dev Inc NMC1100166 Pershing
FG 71 12/18/2013 Hycroft Res & Dev Inc NMC1100167 Pershing
HRD1212 4/16/2014 Hycroft Res & Dev Inc NMC1102169 Pershing
HRDI 218 4/16/2014 Hycroft Res & Dev Inc NMC1102176 Pershing
HRDI 219 4/16/2014 Hycroft Res & Dev Inc NMC1102177 Pershing
HRDI 1 12/16/2013 Hycroft Res & Dev Inc NMC1100176 Pershing
HRDI 10 12/16/2013 Hycroft Res & Dev Inc NMC1100185 Pershing
HRDI 100 4/8/2014 Hycroft Res & Dev Inc NMC1102058 Pershing
HRDI 101 4/8/2014 Hycroft Res & Dev Inc NMC1102059 Pershing
HRDI 102 4/8/2014 Hycroft Res & Dev Inc NMC1102060 Pershing
HRDI 103 4/8/2014 Hycroft Res & Dev Inc NMC1102061 Pershing
HRDI 104 4/8/2014 Hycroft Res & Dev Inc NMC1102062 Pershing
HRDI 105 4/8/2014 Hycroft Res & Dev Inc NMC1102063 Pershing
HRDI 106 4/8/2014 Hycroft Res & Dev Inc NMC1102064 Pershing
HRDI 107 4/8/2014 Hycroft Res & Dev Inc NMC1102065 Pershing
HRDI 108 4/8/2014 Hycroft Res & Dev Inc NMC1102066 Pershing
HRDI 109 4/8/2014 Hycroft Res & Dev Inc NMC1102067 Pershing
HRDI 11 12/16/2013 Hycroft Res & Dev Inc NMC1100186 Pershing
HRDI 110 4/8/2014 Hycroft Res & Dev Inc NMC1102068 Pershing
HRDI 111 4/9/2014 Hycroft Res & Dev Inc NMC1102069 Pershing
HRDI 112 4/9/2014 Hycroft Res & Dev Inc NMC1102070 Pershing
HRDI 113 4/9/2014 Hycroft Res & Dev Inc NMC1102071 Pershing
HRDI 114 4/9/2014 Hycroft Res & Dev Inc NMC1102072 Pershing
HRDI 115 4/9/2014 Hycroft Res & Dev Inc NMC1102073 Pershing
HRDI 116 4/9/2014 Hycroft Res & Dev Inc NMC1102074 Pershing
HRDI 117 4/9/2014 Hycroft Res & Dev Inc NMC1102075 Pershing
HRDI 118 4/9/2014 Hycroft Res & Dev Inc NMC1102076 Pershing
HRDI 119 4/9/2014 Hycroft Res & Dev Inc NMC1102077 Pershing
HRDI 12 12/16/2013 Hycroft Res & Dev Inc NMC1100187 Pershing
HRDI 120 4/9/2014 Hycroft Res & Dev Inc NMC1102078 Pershing
HRDI 121 4/9/2014 Hycroft Res & Dev Inc NMC1102079 Pershing
HRDI 122 4/9/2014 Hycroft Res & Dev Inc NMC1102080 Pershing

 

Hycroft Mine Project

Page 316

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
HRDI 123 4/9/2014 Hycroft Res & Dev Inc NMC1102081 Pershing
HRDI 124 4/9/2014 Hycroft Res & Dev Inc NMC1102082 Pershing
HRDI 125 4/9/2014 Hycroft Res & Dev Inc NMC1102083 Pershing
HRDI 126 4/9/2014 Hycroft Res & Dev Inc NMC1102084 Pershing
HRDI 127 4/9/2014 Hycroft Res & Dev Inc NMC1102085 Pershing
HRDI 128 4/9/2014 Hycroft Res & Dev Inc NMC1102086 Pershing
HRDI 129 4/9/2014 Hycroft Res & Dev Inc NMC1102087 Pershing
HRDI 13 12/16/2013 Hycroft Res & Dev Inc NMC1100188 Pershing
HRDI 130 4/9/2014 Hycroft Res & Dev Inc NMC1102088 Pershing
HRDI 131 4/9/2014 Hycroft Res & Dev Inc NMC1102089 Pershing
HRDI 132 4/9/2014 Hycroft Res & Dev Inc NMC1102090 Pershing
HRDI 133 4/9/2014 Hycroft Res & Dev Inc NMC1102091 Pershing
HRDI 134 4/9/2014 Hycroft Res & Dev Inc NMC1102092 Pershing
HRDI 135 4/9/2014 Hycroft Res & Dev Inc NMC1102093 Pershing
HRDI 136 4/9/2014 Hycroft Res & Dev Inc NMC1102094 Pershing
HRDI 137 4/9/2014 Hycroft Res & Dev Inc NMC1102095 Pershing
HRDI 138 4/9/2014 Hycroft Res & Dev Inc NMC1102096 Pershing
HRDI 139 4/9/2014 Hycroft Res & Dev Inc NMC1102097 Pershing
HRDI 14 12/16/2013 Hycroft Res & Dev Inc NMC1100189 Pershing
HRDI 140 4/9/2014 Hycroft Res & Dev Inc NMC1102098 Pershing
HRDI 141 4/9/2014 Hycroft Res & Dev Inc NMC1102099 Pershing
HRDI 142 4/9/2014 Hycroft Res & Dev Inc NMC1102100 Pershing
HRDI 143 4/9/2014 Hycroft Res & Dev Inc NMC1102101 Pershing
HRDI 144 4/10/2014 Hycroft Res & Dev Inc NMC1102102 Pershing
HRDI 145 4/10/2014 Hycroft Res & Dev Inc NMC1102103 Pershing
HRDI 146 4/10/2014 Hycroft Res & Dev Inc NMC1102104 Pershing
HRDI 147 4/10/2014 Hycroft Res & Dev Inc NMC1102105 Pershing
HRDI 148 4/10/2014 Hycroft Res & Dev Inc NMC1102106 Pershing
HRDI 149 4/10/2014 Hycroft Res & Dev Inc NMC1102107 Pershing
HRDI 15 12/16/2013 Hycroft Res & Dev Inc NMC1100190 Pershing
HRDI 150 4/10/2014 Hycroft Res & Dev Inc NMC1102108 Pershing
HRDI 151 4/10/2014 Hycroft Res & Dev Inc NMC1102109 Pershing
HRDI 152 4/10/2014 Hycroft Res & Dev Inc NMC1102110 Pershing
HRDI 153 4/10/2014 Hycroft Res & Dev Inc NMC1102111 Pershing
HRDI 154 4/9/2014 Hycroft Res & Dev Inc NMC1102112 Pershing
HRDI 155 4/9/2014 Hycroft Res & Dev Inc NMC1102113 Pershing
HRDI 156 4/9/2014 Hycroft Res & Dev Inc NMC1102114 Pershing
HRDI 157 4/9/2014 Hycroft Res & Dev Inc NMC1102115 Pershing
HRDI 158 4/10/2014 Hycroft Res & Dev Inc NMC1102116 Pershing
HRDI 159 4/10/2014 Hycroft Res & Dev Inc NMC1102117 Pershing
HRDI 16 12/16/2013 Hycroft Res & Dev Inc NMC1100191 Pershing
HRDI 160 4/10/2014 Hycroft Res & Dev Inc NMC1102118 Pershing
HRDI 161 4/10/2014 Hycroft Res & Dev Inc NMC1102119 Pershing
HRDI 162 4/10/2014 Hycroft Res & Dev Inc NMC1102120 Pershing
HRDI 163 4/10/2014 Hycroft Res & Dev Inc NMC1102121 Pershing
HRDI 164 4/10/2014 Hycroft Res & Dev Inc NMC1102122 Pershing
HRDI 165 4/10/2014 Hycroft Res & Dev Inc NMC1102123 Pershing
HRDI 166 4/10/2014 Hycroft Res & Dev Inc NMC1102124 Pershing

 

Hycroft Mine Project

Page 317

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
HRDI 167 4/10/2014 Hycroft Res & Dev Inc NMC1102125 Pershing
HRDI 168 4/9/2014 Hycroft Res & Dev Inc NMC1102126 Pershing
HRDI 169 4/9/2014 Hycroft Res & Dev Inc NMC1102127 Pershing
HRDI 17 12/16/2013 Hycroft Res & Dev Inc NMC1100192 Pershing
HRDI 170 4/9/2014 Hycroft Res & Dev Inc NMC1102128 Pershing
HRDI 171 4/9/2014 Hycroft Res & Dev Inc NMC1102129 Pershing
HRDI 172 4/11/2014 Hycroft Res & Dev Inc NMC1102130 Pershing
HRDI 173 4/11/2014 Hycroft Res & Dev Inc NMC1102131 Pershing
HRDI 174 4/11/2014 Hycroft Res & Dev Inc NMC1102132 Pershing
HRDI 175 4/11/2014 Hycroft Res & Dev Inc NMC1102133 Pershing
HRDI 176 4/11/2014 Hycroft Res & Dev Inc NMC1102134 Pershing
HRDI 177 4/11/2014 Hycroft Res & Dev Inc NMC1102135 Pershing
HRDI 178 4/11/2014 Hycroft Res & Dev Inc NMC1102136 Pershing
HRDI 179 4/11/2014 Hycroft Res & Dev Inc NMC1102137 Pershing
HRDI 18 12/16/2013 Hycroft Res & Dev Inc NMC1100193 Pershing
HRDI 180 4/11/2014 Hycroft Res & Dev Inc NMC1102138 Pershing
HRDI 181 4/11/2014 Hycroft Res & Dev Inc NMC1102139 Pershing
HRDI 182 4/11/2014 Hycroft Res & Dev Inc NMC1102140 Pershing
HRDI 183 4/11/2014 Hycroft Res & Dev Inc NMC1102141 Pershing
HRDI 184 4/11/2014 Hycroft Res & Dev Inc NMC1102142 Pershing
HRDI 185 4/11/2014 Hycroft Res & Dev Inc NMC1102143 Pershing
HRDI 186 4/11/2014 Hycroft Res & Dev Inc NMC1102144 Pershing
HRDI 187 4/11/2014 Hycroft Res & Dev Inc NMC1102145 Pershing
HRDI 188 4/10/2014 Hycroft Res & Dev Inc NMC1102146 Pershing
HRDI 189 4/10/2014 Hycroft Res & Dev Inc NMC1102147 Pershing
HRDI 19 12/16/2013 Hycroft Res & Dev Inc NMC1100194 Pershing
HRDI 190 4/10/2014 Hycroft Res & Dev Inc NMC1102148 Pershing
HRDI 191 4/10/2014 Hycroft Res & Dev Inc NMC1102149 Pershing
HRDI 192 4/15/2014 Hycroft Res & Dev Inc NMC1102150 Pershing
HRDI 193 4/15/2014 Hycroft Res & Dev Inc NMC1102151 Pershing
HRDI 194 4/10/2014 Hycroft Res & Dev Inc NMC1102152 Pershing
HRDI 195 4/10/2014 Hycroft Res & Dev Inc NMC1102153 Pershing
HRDI 196 4/10/2014 Hycroft Res & Dev Inc NMC1102154 Pershing
HRDI 197 4/10/2014 Hycroft Res & Dev Inc NMC1102155 Pershing
HRDI 198 4/16/2014 Hycroft Res & Dev Inc NMC1102156 Pershing
HRDI 199 4/10/2014 Hycroft Res & Dev Inc NMC1102157 Pershing
HRDI 2 12/16/2013 Hycroft Res & Dev Inc NMC1100177 Pershing
HRDI 20 12/16/2013 Hycroft Res & Dev Inc NMC1100195 Pershing
HRDI 200 4/15/2014 Hycroft Res & Dev Inc NMC1102158 Pershing
HRDI 201 4/15/2014 Hycroft Res & Dev Inc NMC1102159 Pershing
HRDI 202 4/10/2014 Hycroft Res & Dev Inc NMC1102160 Pershing
HRDI 203 4/16/2014 Hycroft Res & Dev Inc NMC1102161 Pershing
HRDI 204 4/16/2014 Hycroft Res & Dev Inc NMC1102162 Pershing
HRDI 205 4/16/2014 Hycroft Res & Dev Inc NMC1102163 Pershing
HRDI 206 4/16/2014 Hycroft Res & Dev Inc NMC1102164 Pershing
HRDI 207 4/16/2014 Hycroft Res & Dev Inc NMC1102165 Pershing
HRDI 208 4/16/2014 Hycroft Res & Dev Inc NMC1102166 Pershing
HRDI 209 4/16/2014 Hycroft Res & Dev Inc NMC1102167 Pershing
HRDI 21 12/16/2013 Hycroft Res & Dev Inc NMC1100196 Pershing

 

Hycroft Mine Project

Page 318

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
HRDI 210 4/16/2014 Hycroft Res & Dev Inc NMC1102168 Pershing
HRDI 211 4/16/2014 Hycroft Res & Dev Inc NMC1102170 Pershing
HRDI 213 4/16/2014 Hycroft Res & Dev Inc NMC1102171 Pershing
HRDI 214 4/16/2014 Hycroft Res & Dev Inc NMC1102172 Pershing
HRDI 215 4/16/2014 Hycroft Res & Dev Inc NMC1102173 Pershing
HRDI 216 4/16/2014 Hycroft Res & Dev Inc NMC1102174 Pershing
HRDI 217 4/16/2014 Hycroft Res & Dev Inc NMC1102175 Pershing
HRDI 22 12/16/2013 Hycroft Res & Dev Inc NMC1100197 Pershing
HRDI 220 4/16/2014 Hycroft Res & Dev Inc NMC1102178 Pershing
HRDI 221 4/15/2014 Hycroft Res & Dev Inc NMC1102179 Pershing
HRDI 222 4/15/2014 Hycroft Res & Dev Inc NMC1102180 Pershing
HRDI 223 4/15/2014 Hycroft Res & Dev Inc NMC1102181 Pershing
HRDI 23 12/16/2013 Hycroft Res & Dev Inc NMC1100198 Pershing
HRDI 24 12/16/2013 Hycroft Res & Dev Inc NMC1100199 Pershing
HRDI 25 12/16/2013 Hycroft Res & Dev Inc NMC1100200 Pershing
HRDI 26 12/16/2013 Hycroft Res & Dev Inc NMC1100201 Pershing
HRDI 27 12/16/2013 Hycroft Res & Dev Inc NMC1100202 Pershing
HRDI 28 12/17/2013 Hycroft Res & Dev Inc NMC1100203 Pershing
HRDI 29 12/17/2013 Hycroft Res & Dev Inc NMC1100204 Pershing
HRDI 3 12/16/2013 Hycroft Res & Dev Inc NMC1100178 Pershing
HRDI 30 12/17/2013 Hycroft Res & Dev Inc NMC1100205 Pershing
HRDI 31 12/17/2013 Hycroft Res & Dev Inc NMC1100206 Pershing
HRDI 32 12/17/2013 Hycroft Res & Dev Inc NMC1100207 Pershing
HRDI 33 12/17/2013 Hycroft Res & Dev Inc NMC1100208 Pershing
HRDI 34 12/18/2013 Hycroft Res & Dev Inc NMC1100209 Pershing
HRDI 35 12/18/2013 Hycroft Res & Dev Inc NMC1100210 Pershing
HRDI 36 12/17/2013 Hycroft Res & Dev Inc NMC1100211 Pershing
HRDI 37 12/17/2013 Hycroft Res & Dev Inc NMC1100212 Pershing
HRDI 38 12/17/2013 Hycroft Res & Dev Inc NMC1100213 Pershing
HRDI 39 12/17/2013 Hycroft Res & Dev Inc NMC1100214 Pershing
HRDI 4 12/16/2013 Hycroft Res & Dev Inc NMC1100179 Pershing
HRDI 40 12/17/2013 Hycroft Res & Dev Inc NMC1100215 Pershing
HRDI 41 12/17/2013 Hycroft Res & Dev Inc NMC1100216 Pershing
HRDI 42 12/17/2013 Hycroft Res & Dev Inc NMC1100217 Pershing
HRDI 43 12/17/2013 Hycroft Res & Dev Inc NMC1100218 Pershing
HRDI 44 12/17/2013 Hycroft Res & Dev Inc NMC1100219 Pershing
HRDI 45 12/17/2013 Hycroft Res & Dev Inc NMC1100220 Pershing
HRDI 46 12/17/2013 Hycroft Res & Dev Inc NMC1100221 Pershing
HRDI 47 4/7/2014 Hycroft Res & Dev Inc NMC1102005 Pershing
HRDI 48 4/7/2014 Hycroft Res & Dev Inc NMC1102006 Pershing
HRDI 49 4/7/2014 Hycroft Res & Dev Inc NMC1102007 Pershing
HRDI 5 12/16/2013 Hycroft Res & Dev Inc NMC1100180 Pershing
HRDI 50 4/7/2014 Hycroft Res & Dev Inc NMC1102008 Pershing
HRDI 51 4/7/2014 Hycroft Res & Dev Inc NMC1102009 Pershing
HRDI 52 4/7/2014 Hycroft Res & Dev Inc NMC1102010 Pershing
HRDI 53 4/7/2014 Hycroft Res & Dev Inc NMC1102011 Pershing
HRDI 54 4/7/2014 Hycroft Res & Dev Inc NMC1102012 Pershing

 

Hycroft Mine Project

Page 319

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
HRDI 55 4/7/2014 Hycroft Res & Dev Inc NMC1102013 Pershing
HRDI 56 4/7/2014 Hycroft Res & Dev Inc NMC1102014 Pershing
HRDI 57 4/7/2014 Hycroft Res & Dev Inc NMC1102015 Pershing
HRDI 58 4/7/2014 Hycroft Res & Dev Inc NMC1102016 Pershing
HRDI 59 4/7/2014 Hycroft Res & Dev Inc NMC1102017 Pershing
HRDI 6 12/16/2013 Hycroft Res & Dev Inc NMC1100181 Pershing
HRDI 60 4/7/2014 Hycroft Res & Dev Inc NMC1102018 Pershing
HRDI 61 4/7/2014 Hycroft Res & Dev Inc NMC1102019 Pershing
HRDI 62 4/7/2014 Hycroft Res & Dev Inc NMC1102020 Pershing
HRDI 63 4/7/2014 Hycroft Res & Dev Inc NMC1102021 Pershing
HRDI 64 4/7/2014 Hycroft Res & Dev Inc NMC1102022 Pershing
HRDI 65 4/7/2014 Hycroft Res & Dev Inc NMC1102023 Pershing
HRDI 66 4/7/2014 Hycroft Res & Dev Inc NMC1102024 Pershing
HRDI 67 4/7/2014 Hycroft Res & Dev Inc NMC1102025 Pershing
HRDI 68 4/7/2014 Hycroft Res & Dev Inc NMC1102026 Pershing
HRDI 69 4/7/2014 Hycroft Res & Dev Inc NMC1102027 Pershing
HRDI 7 12/16/2013 Hycroft Res & Dev Inc NMC1100182 Pershing
HRDI 70 4/7/2014 Hycroft Res & Dev Inc NMC1102028 Pershing
HRDI 71 4/7/2014 Hycroft Res & Dev Inc NMC1102029 Pershing
HRDI 72 4/7/2014 Hycroft Res & Dev Inc NMC1102030 Pershing
HRDI 73 4/7/2014 Hycroft Res & Dev Inc NMC1102031 Pershing
HRDI 74 4/7/2014 Hycroft Res & Dev Inc NMC1102032 Pershing
HRDI 75 4/7/2014 Hycroft Res & Dev Inc NMC1102033 Pershing
HRDI 76 4/7/2014 Hycroft Res & Dev Inc NMC1102034 Pershing
HRDI 77 4/8/2014 Hycroft Res & Dev Inc NMC1102035 Pershing
HRDI 78 4/8/2014 Hycroft Res & Dev Inc NMC1102036 Pershing
HRDI 79 4/8/2014 Hycroft Res & Dev Inc NMC1102037 Pershing
HRDI 8 12/16/2013 Hycroft Res & Dev Inc NMC1100183 Pershing
HRDI 80 4/8/2014 Hycroft Res & Dev Inc NMC1102038 Pershing
HRDI 81 4/8/2014 Hycroft Res & Dev Inc NMC1102039 Pershing
HRDI 82 4/8/2014 Hycroft Res & Dev Inc NMC1102040 Pershing
HRDI 83 4/8/2014 Hycroft Res & Dev Inc NMC1102041 Pershing
HRDI 84 4/8/2014 Hycroft Res & Dev Inc NMC1102042 Pershing
HRDI 85 4/8/2014 Hycroft Res & Dev Inc NMC1102043 Pershing
HRDI 86 4/8/2014 Hycroft Res & Dev Inc NMC1102044 Pershing
HRDI 87 4/8/2014 Hycroft Res & Dev Inc NMC1102045 Pershing
HRDI 88 4/8/2014 Hycroft Res & Dev Inc NMC1102046 Pershing
HRDI 89 4/8/2014 Hycroft Res & Dev Inc NMC1102047 Pershing
HRDI 9 12/16/2013 Hycroft Res & Dev Inc NMC1100184 Pershing
HRDI 90 4/8/2014 Hycroft Res & Dev Inc NMC1102048 Pershing
HRDI 91 4/8/2014 Hycroft Res & Dev Inc NMC1102049 Pershing
HRDI 92 4/8/2014 Hycroft Res & Dev Inc NMC1102050 Pershing
HRDI 93 4/8/2014 Hycroft Res & Dev Inc NMC1102051 Pershing
HRDI 94 4/8/2014 Hycroft Res & Dev Inc NMC1102052 Pershing
HRDI 95 4/8/2014 Hycroft Res & Dev Inc NMC1102053 Pershing
HRDI 96 4/8/2014 Hycroft Res & Dev Inc NMC1102054 Pershing
HRDI 97 4/8/2014 Hycroft Res & Dev Inc NMC1102055 Pershing
HRDI 98 4/8/2014 Hycroft Res & Dev Inc NMC1102056 Pershing

 

Hycroft Mine Project

Page 320

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
HRDI 99 4/8/2014 Hycroft Res & Dev Inc NMC1102057 Pershing
NC 102 8/13/2010 Hycroft Res & Dev Inc NMC1027940 Pershing
NC 103 8/13/2010 Hycroft Res & Dev Inc NMC1027941 Pershing
NC 104 8/13/2010 Hycroft Res & Dev Inc NMC1027942 Pershing
NC 105 8/13/2010 Hycroft Res & Dev Inc NMC1027943 Pershing
NC 106 8/13/2010 Hycroft Res & Dev Inc NMC1027944 Pershing
NC 107 8/13/2010 Hycroft Res & Dev Inc NMC1027945 Pershing
NC 108 8/13/2010 Hycroft Res & Dev Inc NMC1027946 Pershing
NC 109 8/13/2010 Hycroft Res & Dev Inc NMC1027947 Pershing
NC 133 8/13/2010 Hycroft Res & Dev Inc NMC1027971 Pershing
NC 134 8/13/2010 Hycroft Res & Dev Inc NMC1027972 Pershing
NC 135 8/13/2010 Hycroft Res & Dev Inc NMC1027973 Pershing
NC 136 8/13/2010 Hycroft Res & Dev Inc NMC1027974 Pershing
NC 137 8/13/2010 Hycroft Res & Dev Inc NMC1027975 Pershing
NC 138 8/13/2010 Hycroft Res & Dev Inc NMC1027976 Pershing
NC 139 8/13/2010 Hycroft Res & Dev Inc NMC1027977 Pershing
NC 140 8/13/2010 Hycroft Res & Dev Inc NMC1027978 Pershing
NC 141 8/13/2010 Hycroft Res & Dev Inc NMC1027979 Pershing
NC 142 8/13/2010 Hycroft Res & Dev Inc NMC1027980 Pershing
NC 143 8/13/2010 Hycroft Res & Dev Inc NMC1027981 Pershing
NC 144 8/13/2010 Hycroft Res & Dev Inc NMC1027982 Pershing
NC 145 8/13/2010 Hycroft Res & Dev Inc NMC1027983 Pershing
NC 146 8/13/2010 Hycroft Res & Dev Inc NMC1027984 Pershing
NC 147 8/13/2010 Hycroft Res & Dev Inc NMC1027985 Pershing
NC 148 8/13/2010 Hycroft Res & Dev Inc NMC1027986 Pershing
NC 149 8/13/2010 Hycroft Res & Dev Inc NMC1027987 Pershing
NC 150 8/13/2010 Hycroft Res & Dev Inc NMC1027988 Pershing
NC 171 8/13/2010 Hycroft Res & Dev Inc NMC1028009 Pershing
NC 172 8/13/2010 Hycroft Res & Dev Inc NMC1028010 Pershing
NC 173 8/13/2010 Hycroft Res & Dev Inc NMC1028011 Pershing
NC 174 8/13/2010 Hycroft Res & Dev Inc NMC1028012 Pershing
NC 175 8/13/2010 Hycroft Res & Dev Inc NMC1028013 Pershing
NC 176 8/13/2010 Hycroft Res & Dev Inc NMC1028014 Pershing
NC 177 8/13/2010 Hycroft Res & Dev Inc NMC1028015 Pershing
NC 178 8/13/2010 Hycroft Res & Dev Inc NMC1028016 Pershing
NC 179 8/13/2010 Hycroft Res & Dev Inc NMC1028017 Pershing
NC 180 8/13/2010 Hycroft Res & Dev Inc NMC1028018 Pershing
NC 181 8/13/2010 Hycroft Res & Dev Inc NMC1028019 Pershing
NC 182 8/13/2010 Hycroft Res & Dev Inc NMC1028020 Pershing
NC 183 8/13/2010 Hycroft Res & Dev Inc NMC1028021 Pershing
NC 184 8/13/2010 Hycroft Res & Dev Inc NMC1028022 Pershing
NC 185 8/13/2010 Hycroft Res & Dev Inc NMC1028023 Pershing
NC 186 8/13/2010 Hycroft Res & Dev Inc NMC1028024 Pershing
NC 187 8/13/2010 Hycroft Res & Dev Inc NMC1028025 Pershing
NC 188 8/13/2010 Hycroft Res & Dev Inc NMC1028026 Pershing
NC 206 8/13/2010 Hycroft Res & Dev Inc NMC1028044 Pershing
NC 207 8/13/2010 Hycroft Res & Dev Inc NMC1028045 Pershing
NC 208 8/13/2010 Hycroft Res & Dev Inc NMC1028046 Pershing

 

Hycroft Mine Project

Page 321

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 209 8/13/2010 Hycroft Res & Dev Inc NMC1028047 Pershing
NC 210 8/13/2010 Hycroft Res & Dev Inc NMC1028048 Pershing
NC 211 8/13/2010 Hycroft Res & Dev Inc NMC1028049 Pershing
NC 212 8/13/2010 Hycroft Res & Dev Inc NMC1028050 Pershing
NC 213 8/13/2010 Hycroft Res & Dev Inc NMC1028051 Pershing
NC 214 8/13/2010 Hycroft Res & Dev Inc NMC1028052 Pershing
NC 215 8/13/2010 Hycroft Res & Dev Inc NMC1028053 Pershing
NC 216 8/13/2010 Hycroft Res & Dev Inc NMC1028054 Pershing
NC 217 8/13/2010 Hycroft Res & Dev Inc NMC1028055 Pershing
NC 218 8/13/2010 Hycroft Res & Dev Inc NMC1028056 Pershing
NC 219 8/13/2010 Hycroft Res & Dev Inc NMC1028057 Pershing
NC 220 8/13/2010 Hycroft Res & Dev Inc NMC1028058 Pershing
NC 221 8/13/2010 Hycroft Res & Dev Inc NMC1028059 Pershing
NC 222 8/13/2010 Hycroft Res & Dev Inc NMC1028060 Pershing
NC 223 8/13/2010 Hycroft Res & Dev Inc NMC1028061 Pershing
NC 241 8/13/2010 Hycroft Res & Dev Inc NMC1028079 Pershing
NC 242 8/13/2010 Hycroft Res & Dev Inc NMC1028080 Pershing
NC 243 8/13/2010 Hycroft Res & Dev Inc NMC1028081 Pershing
NC 244 8/13/2010 Hycroft Res & Dev Inc NMC1028082 Pershing
NC 245 8/13/2010 Hycroft Res & Dev Inc NMC1028083 Pershing
NC 246 8/13/2010 Hycroft Res & Dev Inc NMC1028084 Pershing
NC 247 8/13/2010 Hycroft Res & Dev Inc NMC1028085 Pershing
NC 248 8/13/2010 Hycroft Res & Dev Inc NMC1028086 Pershing
NC 249 8/13/2010 Hycroft Res & Dev Inc NMC1028087 Pershing
NC 250 8/13/2010 Hycroft Res & Dev Inc NMC1028088 Pershing
NC 251 8/13/2010 Hycroft Res & Dev Inc NMC1028089 Pershing
NC 252 8/13/2010 Hycroft Res & Dev Inc NMC1028090 Pershing
NC 253 8/13/2010 Hycroft Res & Dev Inc NMC1028091 Pershing
NC 254 8/13/2010 Hycroft Res & Dev Inc NMC1028092 Pershing
NC 255 8/13/2010 Hycroft Res & Dev Inc NMC1028093 Pershing
NC 256 8/13/2010 Hycroft Res & Dev Inc NMC1028094 Pershing
NC 257 8/13/2010 Hycroft Res & Dev Inc NMC1028095 Pershing
NC 258 8/13/2010 Hycroft Res & Dev Inc NMC1028096 Pershing
NC 275 8/13/2010 Hycroft Res & Dev Inc NMC1028113 Pershing
NC 276 8/13/2010 Hycroft Res & Dev Inc NMC1028114 Pershing
NC 277 8/13/2010 Hycroft Res & Dev Inc NMC1028115 Pershing
NC 278 8/13/2010 Hycroft Res & Dev Inc NMC1028116 Pershing
NC 279 8/13/2010 Hycroft Res & Dev Inc NMC1028117 Pershing
NC 280 8/13/2010 Hycroft Res & Dev Inc NMC1028118 Pershing
NC 281 8/13/2010 Hycroft Res & Dev Inc NMC1028119 Pershing
NC 282 8/13/2010 Hycroft Res & Dev Inc NMC1028120 Pershing
NC 283 8/13/2010 Hycroft Res & Dev Inc NMC1028121 Pershing
NC 284 8/13/2010 Hycroft Res & Dev Inc NMC1028122 Pershing
NC 285 8/13/2010 Hycroft Res & Dev Inc NMC1028123 Pershing
NC 286 8/13/2010 Hycroft Res & Dev Inc NMC1028124 Pershing
NC 287 8/13/2010 Hycroft Res & Dev Inc NMC1028125 Pershing
NC 288 8/13/2010 Hycroft Res & Dev Inc NMC1028126 Pershing
NC 289 8/13/2010 Hycroft Res & Dev Inc NMC1028127 Pershing

 

Hycroft Mine Project

Page 322

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 290 8/13/2010 Hycroft Res & Dev Inc NMC1028128 Pershing
NC 291 8/13/2010 Hycroft Res & Dev Inc NMC1028129 Pershing
NC 292 8/13/2010 Hycroft Res & Dev Inc NMC1028130 Pershing
NC 307 8/13/2010 Hycroft Res & Dev Inc NMC1028145 Pershing
NC 308 8/13/2010 Hycroft Res & Dev Inc NMC1028146 Pershing
NC 309 8/13/2010 Hycroft Res & Dev Inc NMC1028147 Pershing
NC 310 8/13/2010 Hycroft Res & Dev Inc NMC1028148 Pershing
NC 311 8/13/2010 Hycroft Res & Dev Inc NMC1028149 Pershing
NC 312 8/13/2010 Hycroft Res & Dev Inc NMC1028150 Pershing
NC 313 8/13/2010 Hycroft Res & Dev Inc NMC1028151 Pershing
NC 314 8/13/2010 Hycroft Res & Dev Inc NMC1028152 Pershing
NC 315 8/13/2010 Hycroft Res & Dev Inc NMC1028153 Pershing
NC 316 8/13/2010 Hycroft Res & Dev Inc NMC1028154 Pershing
NC 317 8/13/2010 Hycroft Res & Dev Inc NMC1028155 Pershing
NC 318 8/13/2010 Hycroft Res & Dev Inc NMC1028156 Pershing
NC 319 8/13/2010 Hycroft Res & Dev Inc NMC1028157 Pershing
NC 320 8/13/2010 Hycroft Res & Dev Inc NMC1028158 Pershing
NC 321 8/13/2010 Hycroft Res & Dev Inc NMC1028159 Pershing
NC 322 8/13/2010 Hycroft Res & Dev Inc NMC1028160 Pershing
NC 323 8/13/2010 Hycroft Res & Dev Inc NMC1028161 Pershing
NC 324 8/13/2010 Hycroft Res & Dev Inc NMC1028162 Pershing
OS 1 9/11/2012 Hycroft Res & Dev Inc NMC1078793 Pershing
OS 10 9/11/2012 Hycroft Res & Dev Inc NMC1078802 Pershing
OS 11 9/11/2012 Hycroft Res & Dev Inc NMC1078803 Pershing
OS 12 9/11/2012 Hycroft Res & Dev Inc NMC1078804 Pershing
OS 2 9/11/2012 Hycroft Res & Dev Inc NMC1078794 Pershing
OS 3 9/11/2012 Hycroft Res & Dev Inc NMC1078795 Pershing
OS 4 9/11/2012 Hycroft Res & Dev Inc NMC1078796 Pershing
OS 5 9/11/2012 Hycroft Res & Dev Inc NMC1078797 Pershing
OS 6 9/11/2012 Hycroft Res & Dev Inc NMC1078798 Pershing
OS 7 9/11/2012 Hycroft Res & Dev Inc NMC1078799 Pershing
OS 8 9/11/2012 Hycroft Res & Dev Inc NMC1078800 Pershing
OS 9 9/11/2012 Hycroft Res & Dev Inc NMC1078801 Pershing
OSC 1 10/28/2010 Hycroft Res & Dev Inc NMC1035889 Pershing
OSC 2 10/28/2010 Hycroft Res & Dev Inc NMC1035890 Pershing
OSC 3 10/28/2010 Hycroft Res & Dev Inc NMC1035891 Pershing
OSC 35 11/1/2010 Hycroft Res & Dev Inc NMC1035895 Pershing
OSC 36 10/29/2010 Hycroft Res & Dev Inc NMC1035896 Pershing
OSC 37 10/29/2010 Hycroft Res & Dev Inc NMC1035897 Pershing
OSC 38 11/1/2010 Hycroft Res & Dev Inc NMC1035898 Pershing
OSC 39 10/29/2010 Hycroft Res & Dev Inc NMC1035899 Pershing
OSC 4 10/28/2010 Hycroft Res & Dev Inc NMC1035892 Pershing
OSC 40 10/29/2010 Hycroft Res & Dev Inc NMC1035900 Pershing
OSC 41 11/1/2010 Hycroft Res & Dev Inc NMC1035901 Pershing
OSC 42 10/29/2010 Hycroft Res & Dev Inc NMC1035902 Pershing
OSC 43 10/29/2010 Hycroft Res & Dev Inc NMC1035903 Pershing
OSC 44 11/1/2010 Hycroft Res & Dev Inc NMC1035904 Pershing
OSC 45 10/29/2010 Hycroft Res & Dev Inc NMC1035905 Pershing

 

Hycroft Mine Project

Page 323

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
OSC 46 10/29/2010 Hycroft Res & Dev Inc NMC1035906 Pershing
OSC 47 10/31/2010 Hycroft Res & Dev Inc NMC1035907 Pershing
OSC 48 10/31/2010 Hycroft Res & Dev Inc NMC1035908 Pershing
OSC 49 10/31/2010 Hycroft Res & Dev Inc NMC1035909 Pershing
OSC 5 10/28/2010 Hycroft Res & Dev Inc NMC1035893 Pershing
OSC 50 10/31/2010 Hycroft Res & Dev Inc NMC1035910 Pershing
OSC 51 10/31/2010 Hycroft Res & Dev Inc NMC1035911 Pershing
OSC 52 10/31/2010 Hycroft Res & Dev Inc NMC1035912 Pershing
OSC 53 10/31/2010 Hycroft Res & Dev Inc NMC1035913 Pershing
OSC 54 10/31/2010 Hycroft Res & Dev Inc NMC1035914 Pershing
OSC 55 10/31/2010 Hycroft Res & Dev Inc NMC1035915 Pershing
OSC 56 10/31/2010 Hycroft Res & Dev Inc NMC1035916 Pershing
OSC 57 10/31/2010 Hycroft Res & Dev Inc NMC1035917 Pershing
OSC 58 10/31/2010 Hycroft Res & Dev Inc NMC1035918 Pershing
OSC 59 10/31/2010 Hycroft Res & Dev Inc NMC1035919 Pershing
OSC 6 10/28/2010 Hycroft Res & Dev Inc NMC1035894 Pershing
OSC 60 10/31/2010 Hycroft Res & Dev Inc NMC1035920 Pershing
OSC 61 10/31/2010 Hycroft Res & Dev Inc NMC1035921 Pershing
OSC 62 10/31/2010 Hycroft Res & Dev Inc NMC1035922 Pershing
OSC 63 10/31/2010 Hycroft Res & Dev Inc NMC1035923 Pershing
OSC 64 10/31/2010 Hycroft Res & Dev Inc NMC1035924 Pershing
OSC 65 10/31/2010 Hycroft Res & Dev Inc NMC1035925 Pershing
OSC 66 10/31/2010 Hycroft Res & Dev Inc NMC1035926 Pershing
OSC 67 11/1/2010 Hycroft Res & Dev Inc NMC1035927 Pershing
OSC 68 11/1/2010 Hycroft Res & Dev Inc NMC1035928 Pershing
OSC 69 11/1/2010 Hycroft Res & Dev Inc NMC1035929 Pershing
OSC 70 11/1/2010 Hycroft Res & Dev Inc NMC1035930 Pershing
OSC 71 11/1/2010 Hycroft Res & Dev Inc NMC1035931 Pershing
OSC 72 11/1/2010 Hycroft Res & Dev Inc NMC1035932 Pershing
OSC 73 11/1/2010 Hycroft Res & Dev Inc NMC1035933 Pershing
OSC 74 11/1/2010 Hycroft Res & Dev Inc NMC1035934 Pershing
OSC 75 11/1/2010 Hycroft Res & Dev Inc NMC1035935 Pershing
OSC 76 11/1/2010 Hycroft Res & Dev Inc NMC1035936 Pershing
RMK 1 9/27/2012 Hycroft Res & Dev Inc NMC1078774 Pershing
RMK 10 9/27/2012 Hycroft Res & Dev Inc NMC1078783 Pershing
RMK 11 9/27/2012 Hycroft Res & Dev Inc NMC1078784 Pershing
RMK 12 9/27/2012 Hycroft Res & Dev Inc NMC1078785 Pershing
RMK 13 9/27/2012 Hycroft Res & Dev Inc NMC1078786 Pershing
RMK 14 9/27/2012 Hycroft Res & Dev Inc NMC1078787 Pershing
RMK 15 9/27/2012 Hycroft Res & Dev Inc NMC1078788 Pershing
RMK 16 9/27/2012 Hycroft Res & Dev Inc NMC1078789 Pershing
RMK 17 9/27/2012 Hycroft Res & Dev Inc NMC1078790 Pershing
RMK 18 9/27/2012 Hycroft Res & Dev Inc NMC1078791 Pershing
RMK 19 9/27/2012 Hycroft Res & Dev Inc NMC1078792 Pershing
RMK 2 9/27/2012 Hycroft Res & Dev Inc NMC1078775 Pershing
RMK 3 9/27/2012 Hycroft Res & Dev Inc NMC1078776 Pershing
RMK 4 9/27/2012 Hycroft Res & Dev Inc NMC1078777 Pershing
RMK 5 9/27/2012 Hycroft Res & Dev Inc NMC1078778 Pershing

 

Hycroft Mine Project

Page 324

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RMK 6 9/27/2012 Hycroft Res & Dev Inc NMC1078779 Pershing
RMK 7 9/27/2012 Hycroft Res & Dev Inc NMC1078780 Pershing
RMK 8 9/27/2012 Hycroft Res & Dev Inc NMC1078781 Pershing
RMK 9 9/27/2012 Hycroft Res & Dev Inc NMC1078782 Pershing
WCR 100 7/25/2012 Hycroft Res & Dev Inc NMC1076520 Pershing
WCR 101 7/25/2012 Hycroft Res & Dev Inc NMC1076521 Pershing
WCR 102 7/25/2012 Hycroft Res & Dev Inc NMC1076522 Pershing
WCR 103 7/26/2012 Hycroft Res & Dev Inc NMC1076523 Pershing
WCR 104 7/26/2012 Hycroft Res & Dev Inc NMC1076524 Pershing
WCR 105 7/26/2012 Hycroft Res & Dev Inc NMC1076525 Pershing
WCR 106 7/26/2012 Hycroft Res & Dev Inc NMC1076526 Pershing
WCR 107 7/26/2012 Hycroft Res & Dev Inc NMC1076527 Pershing
WCR 108 7/26/2012 Hycroft Res & Dev Inc NMC1076528 Pershing
WCR 109 7/25/2012 Hycroft Res & Dev Inc NMC1076529 Pershing
WCR 11 7/26/2012 Hycroft Res & Dev Inc NMC1076453 Pershing
WCR 110 7/25/2012 Hycroft Res & Dev Inc NMC1076530 Pershing
WCR 111 7/25/2012 Hycroft Res & Dev Inc NMC1076531 Pershing
WCR 112 7/25/2012 Hycroft Res & Dev Inc NMC1076532 Pershing
WCR 113 7/25/2012 Hycroft Res & Dev Inc NMC1076533 Pershing
WCR 114 7/25/2012 Hycroft Res & Dev Inc NMC1076534 Pershing
WCR 115 7/25/2012 Hycroft Res & Dev Inc NMC1076535 Pershing
WCR 116 7/25/2012 Hycroft Res & Dev Inc NMC1076536 Pershing
WCR 117 7/25/2012 Hycroft Res & Dev Inc NMC1076537 Pershing
WCR 12 7/26/2012 Hycroft Res & Dev Inc NMC1076454 Pershing
WCR 13 7/26/2012 Hycroft Res & Dev Inc NMC1076455 Pershing
WCR 14 7/26/2012 Hycroft Res & Dev Inc NMC1076456 Pershing
WCR 15 7/26/2012 Hycroft Res & Dev Inc NMC1076457 Pershing
WCR 16 7/26/2012 Hycroft Res & Dev Inc NMC1076458 Pershing
WCR 17 7/26/2012 Hycroft Res & Dev Inc NMC1076459 Pershing
WCR 18 7/26/2012 Hycroft Res & Dev Inc NMC1076460 Pershing
WCR 19 7/26/2012 Hycroft Res & Dev Inc NMC1076461 Pershing
WCR 20 7/26/2012 Hycroft Res & Dev Inc NMC1076462 Pershing
WCR 21 7/26/2012 Hycroft Res & Dev Inc NMC1076463 Pershing
WCR 22 7/26/2012 Hycroft Res & Dev Inc NMC1076464 Pershing
WCR 23 7/26/2012 Hycroft Res & Dev Inc NMC1076465 Pershing
WCR 24 7/26/2012 Hycroft Res & Dev Inc NMC1076466 Pershing
WCR 25 7/26/2012 Hycroft Res & Dev Inc NMC1076467 Pershing
WCR 26 7/26/2012 Hycroft Res & Dev Inc NMC1076468 Pershing
WCR 27 7/26/2012 Hycroft Res & Dev Inc NMC1076469 Pershing
WCR 28 7/26/2012 Hycroft Res & Dev Inc NMC1076470 Pershing
WCR 29 7/26/2012 Hycroft Res & Dev Inc NMC1076471 Pershing
WCR 30 7/26/2012 Hycroft Res & Dev Inc NMC1076472 Pershing
WCR 31 7/26/2012 Hycroft Res & Dev Inc NMC1076473 Pershing
WCR 32 7/26/2012 Hycroft Res & Dev Inc NMC1076474 Pershing
WCR 33 7/26/2012 Hycroft Res & Dev Inc NMC1076475 Pershing
WCR 34 7/26/2012 Hycroft Res & Dev Inc NMC1076476 Pershing
WCR 35 7/26/2012 Hycroft Res & Dev Inc NMC1076477 Pershing
WCR 36 7/26/2012 Hycroft Res & Dev Inc NMC1076478 Pershing

 

Hycroft Mine Project

Page 325

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
WCR 47 7/25/2012 Hycroft Res & Dev Inc NMC1076479 Pershing
WCR 48 7/25/2012 Hycroft Res & Dev Inc NMC1076480 Pershing
WCR 49 7/25/2012 Hycroft Res & Dev Inc NMC1076481 Pershing
WCR 50 7/25/2012 Hycroft Res & Dev Inc NMC1076482 Pershing
WCR 51 7/25/2012 Hycroft Res & Dev Inc NMC1076483 Pershing
WCR 52 7/25/2012 Hycroft Res & Dev Inc NMC1076484 Pershing
WCR 53 7/25/2012 Hycroft Res & Dev Inc NMC1076485 Pershing
WCR 54 7/25/2012 Hycroft Res & Dev Inc NMC1076486 Pershing
WCR 55 7/25/2012 Hycroft Res & Dev Inc NMC1076487 Pershing
WCR 56 7/25/2012 Hycroft Res & Dev Inc NMC1076488 Pershing
WCR 57 7/25/2012 Hycroft Res & Dev Inc NMC1076489 Pershing
WCR 58 7/25/2012 Hycroft Res & Dev Inc NMC1076490 Pershing
WCR 59 7/25/2012 Hycroft Res & Dev Inc NMC1076491 Pershing
WCR 60 7/25/2012 Hycroft Res & Dev Inc NMC1076492 Pershing
WCR 61 7/25/2012 Hycroft Res & Dev Inc NMC1076493 Pershing
WCR 62 7/25/2012 Hycroft Res & Dev Inc NMC1076494 Pershing
WCR 63 7/25/2012 Hycroft Res & Dev Inc NMC1076495 Pershing
WCR 64 7/25/2012 Hycroft Res & Dev Inc NMC1076496 Pershing
WCR 65 7/25/2012 Hycroft Res & Dev Inc NMC1076497 Pershing
WCR 66 7/25/2012 Hycroft Res & Dev Inc NMC1076498 Pershing
WCR 67 7/25/2012 Hycroft Res & Dev Inc NMC1076499 Pershing
WCR 68 7/25/2012 Hycroft Res & Dev Inc NMC1076500 Pershing
WCR 69 7/25/2012 Hycroft Res & Dev Inc NMC1076501 Pershing
WCR 70 7/25/2012 Hycroft Res & Dev Inc NMC1076502 Pershing
WCR 71 7/25/2012 Hycroft Res & Dev Inc NMC1076503 Pershing
WCR 72 7/25/2012 Hycroft Res & Dev Inc NMC1076504 Pershing
WCR 73 7/25/2012 Hycroft Res & Dev Inc NMC1076505 Pershing
WCR 74 7/25/2012 Hycroft Res & Dev Inc NMC1076506 Pershing
WCR 75 7/25/2012 Hycroft Res & Dev Inc NMC1076507 Pershing
WCR 76 7/25/2012 Hycroft Res & Dev Inc NMC1076508 Pershing
WCR 77 7/25/2012 Hycroft Res & Dev Inc NMC1076509 Pershing
WCR 78 7/25/2012 Hycroft Res & Dev Inc NMC1076510 Pershing
WCR 79 7/25/2012 Hycroft Res & Dev Inc NMC1076511 Pershing
WCR 80 7/25/2012 Hycroft Res & Dev Inc NMC1076512 Pershing
WCR 81 7/25/2012 Hycroft Res & Dev Inc NMC1076513 Pershing
WCR 82 7/25/2012 Hycroft Res & Dev Inc NMC1076514 Pershing
WCR 83 7/25/2012 Hycroft Res & Dev Inc NMC1076515 Pershing
WCR 84 7/25/2012 Hycroft Res & Dev Inc NMC1076516 Pershing
WCR 97 7/25/2012 Hycroft Res & Dev Inc NMC1076517 Pershing
WCR 98 7/25/2012 Hycroft Res & Dev Inc NMC1076518 Pershing
WCR 99 7/25/2012 Hycroft Res & Dev Inc NMC1076519 Pershing
CKC#8 9/6/1973 Crofoot Daniel M NMC 88355 Pershing
CKC#9 9/6/1973 Crofoot Daniel M NMC 88356 Pershing
FG 1 9/1/2006 Hycroft Res & Dev Inc NMC 939059 Pershing
FG 10 9/11/2006 Hycroft Res & Dev Inc NMC 939068 Pershing
FG 100 9/2/2006 Hycroft Res & Dev Inc NMC 939157 Pershing
FG 101 9/2/2006 Hycroft Res & Dev Inc NMC 939158 Pershing
FG 102 9/2/2006 Hycroft Res & Dev Inc NMC 939159 Pershing

 

Hycroft Mine Project

Page 326

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 103 9/2/2006 Hycroft Res & Dev Inc NMC 939160 Pershing
FG 104 9/2/2006 Hycroft Res & Dev Inc NMC 939161 Pershing
FG 105 9/2/2006 Hycroft Res & Dev Inc NMC 939162 Pershing
FG 106 9/2/2006 Hycroft Res & Dev Inc NMC 939163 Pershing
FG 107 9/2/2006 Hycroft Res & Dev Inc NMC 939164 Pershing
FG 108 9/2/2006 Hycroft Res & Dev Inc NMC 939165 Pershing
FG 109 9/2/2006 Hycroft Res & Dev Inc NMC 939166 Pershing
FG 11 9/11/2006 Hycroft Res & Dev Inc NMC 939069 Pershing
FG 110 9/2/2006 Hycroft Res & Dev Inc NMC 939167 Pershing
FG 111 9/2/2006 Hycroft Res & Dev Inc NMC 939168 Pershing
FG 112 9/2/2006 Hycroft Res & Dev Inc NMC 939169 Pershing
FG 113 9/8/2006 Hycroft Res & Dev Inc NMC 939170 Pershing
FG 114 9/8/2006 Hycroft Res & Dev Inc NMC 939171 Pershing
FG 115 9/8/2006 Hycroft Res & Dev Inc NMC 939172 Pershing
FG 116 9/8/2006 Hycroft Res & Dev Inc NMC 939173 Pershing
FG 12 9/11/2006 Hycroft Res & Dev Inc NMC 939070 Pershing
FG 121 9/9/2006 Hycroft Res & Dev Inc NMC 939174 Pershing
FG 122 9/9/2006 Hycroft Res & Dev Inc NMC 939175 Pershing
FG 123 9/9/2006 Hycroft Res & Dev Inc NMC 939176 Pershing
FG 124 9/9/2006 Hycroft Res & Dev Inc NMC 939177 Pershing
FG 125 9/9/2006 Hycroft Res & Dev Inc NMC 939178 Pershing
FG 126 9/9/2006 Hycroft Res & Dev Inc NMC 939179 Pershing
FG 127 9/9/2006 Hycroft Res & Dev Inc NMC 939180 Pershing
FG 13 9/1/2006 Hycroft Res & Dev Inc NMC 939071 Pershing
FG 130 9/11/2006 Hycroft Res & Dev Inc NMC 939181 Pershing
FG 131 9/11/2006 Hycroft Res & Dev Inc NMC 939182 Pershing
FG 132 9/11/2006 Hycroft Res & Dev Inc NMC 939183 Pershing
FG 133 9/11/2006 Hycroft Res & Dev Inc NMC 939184 Pershing
FG 134 9/11/2006 Hycroft Res & Dev Inc NMC 939185 Pershing
FG 135 9/11/2006 Hycroft Res & Dev Inc NMC 939186 Pershing
FG 136 9/11/2006 Hycroft Res & Dev Inc NMC 939187 Pershing
FG 137 9/2/2006 Hycroft Res & Dev Inc NMC 939188 Pershing
FG 138 9/2/2006 Hycroft Res & Dev Inc NMC 939189 Pershing
FG 139 9/2/2006 Hycroft Res & Dev Inc NMC 939190 Pershing
FG 14 9/1/2006 Hycroft Res & Dev Inc NMC 939072 Pershing
FG 140 9/2/2006 Hycroft Res & Dev Inc NMC 939191 Pershing
FG 141 9/2/2006 Hycroft Res & Dev Inc NMC 939192 Pershing
FG 142 9/2/2006 Hycroft Res & Dev Inc NMC 939193 Pershing
FG 143 9/2/2006 Hycroft Res & Dev Inc NMC 939194 Pershing
FG 144 9/2/2006 Hycroft Res & Dev Inc NMC 939195 Pershing
FG 145 9/2/2006 Hycroft Res & Dev Inc NMC 939196 Pershing
FG 146 9/2/2006 Hycroft Res & Dev Inc NMC 939197 Pershing
FG 147 9/2/2006 Hycroft Res & Dev Inc NMC 939198 Pershing
FG 148 9/2/2006 Hycroft Res & Dev Inc NMC 939199 Pershing
FG 149 9/2/2006 Hycroft Res & Dev Inc NMC 939200 Pershing
FG 15 9/1/2006 Hycroft Res & Dev Inc NMC 939073 Pershing
FG 150 9/2/2006 Hycroft Res & Dev Inc NMC 939201 Pershing
FG 151 9/2/2006 Hycroft Res & Dev Inc NMC 939202 Pershing

 

Hycroft Mine Project

Page 327

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 152 9/2/2006 Hycroft Res & Dev Inc NMC 939203 Pershing
FG 153 9/2/2006 Hycroft Res & Dev Inc NMC 939204 Pershing
FG 154 9/2/2006 Hycroft Res & Dev Inc NMC 939205 Pershing
FG 155 9/2/2006 Hycroft Res & Dev Inc NMC 939206 Pershing
FG 156 9/8/2006 Hycroft Res & Dev Inc NMC 939207 Pershing
FG 157 9/8/2006 Hycroft Res & Dev Inc NMC 939208 Pershing
FG 158 9/8/2006 Hycroft Res & Dev Inc NMC 939209 Pershing
FG 159 9/8/2006 Hycroft Res & Dev Inc NMC 939210 Pershing
FG 16 9/1/2006 Hycroft Res & Dev Inc NMC 939074 Pershing
FG 160 9/8/2006 Hycroft Res & Dev Inc NMC 939211 Pershing
FG 161 9/8/2006 Hycroft Res & Dev Inc NMC 939212 Pershing
FG 162 9/8/2006 Hycroft Res & Dev Inc NMC 939213 Pershing
FG 164 9/8/2006 Hycroft Res & Dev Inc NMC 939214 Pershing
FG 165 9/8/2006 Hycroft Res & Dev Inc NMC 939215 Pershing
FG 166 9/8/2006 Hycroft Res & Dev Inc NMC 939216 Pershing
FG 167 9/8/2006 Hycroft Res & Dev Inc NMC 939217 Pershing
FG 17 9/1/2006 Hycroft Res & Dev Inc NMC 939075 Pershing
FG 173 9/11/2006 Hycroft Res & Dev Inc NMC 939218 Pershing
FG 174 9/11/2006 Hycroft Res & Dev Inc NMC 939219 Pershing
FG 175 9/11/2006 Hycroft Res & Dev Inc NMC 939220 Pershing
FG 176 9/11/2006 Hycroft Res & Dev Inc NMC 939221 Pershing
FG 177 9/11/2006 Hycroft Res & Dev Inc NMC 939222 Pershing
FG 178 9/11/2006 Hycroft Res & Dev Inc NMC 939223 Pershing
FG 179 9/11/2006 Hycroft Res & Dev Inc NMC 939224 Pershing
FG 18 9/1/2006 Hycroft Res & Dev Inc NMC 939076 Pershing
FG 180 9/2/2006 Hycroft Res & Dev Inc NMC 939225 Pershing
FG 181 9/2/2006 Hycroft Res & Dev Inc NMC 939226 Pershing
FG 182 9/2/2006 Hycroft Res & Dev Inc NMC 939227 Pershing
FG 183 9/2/2006 Hycroft Res & Dev Inc NMC 939228 Pershing
FG 184 9/2/2006 Hycroft Res & Dev Inc NMC 939229 Pershing
FG 185 9/2/2006 Hycroft Res & Dev Inc NMC 939230 Pershing
FG 186 9/2/2006 Hycroft Res & Dev Inc NMC 939231 Pershing
FG 187 9/2/2006 Hycroft Res & Dev Inc NMC 939232 Pershing
FG 188 9/2/2006 Hycroft Res & Dev Inc NMC 939233 Pershing
FG 189 9/2/2006 Hycroft Res & Dev Inc NMC 939234 Pershing
FG 19 9/1/2006 Hycroft Res & Dev Inc NMC 939077 Pershing
FG 190 9/2/2006 Hycroft Res & Dev Inc NMC 939235 Pershing
FG 191 9/2/2006 Hycroft Res & Dev Inc NMC 939236 Pershing
FG 192 9/2/2006 Hycroft Res & Dev Inc NMC 939237 Pershing
FG 193 9/2/2006 Hycroft Res & Dev Inc NMC 939238 Pershing
FG 194 9/2/2006 Hycroft Res & Dev Inc NMC 939239 Pershing
FG 195 9/2/2006 Hycroft Res & Dev Inc NMC 939240 Pershing
FG 196 9/2/2006 Hycroft Res & Dev Inc NMC 939241 Pershing
FG 197 9/2/2006 Hycroft Res & Dev Inc NMC 939242 Pershing
FG 198 9/8/2006 Hycroft Res & Dev Inc NMC 939243 Pershing
FG 199 9/8/2006 Hycroft Res & Dev Inc NMC 939244 Pershing
FG 2 9/1/2006 Hycroft Res & Dev Inc NMC 939060 Pershing
FG 20 9/1/2006 Hycroft Res & Dev Inc NMC 939078 Pershing

 

Hycroft Mine Project

Page 328

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 200 9/8/2006 Hycroft Res & Dev Inc NMC 939245 Pershing
FG 201 9/8/2006 Hycroft Res & Dev Inc NMC 939246 Pershing
FG 202 9/8/2006 Hycroft Res & Dev Inc NMC 939247 Pershing
FG 21 9/1/2006 Hycroft Res & Dev Inc NMC 939079 Pershing
FG 215 9/11/2006 Hycroft Res & Dev Inc NMC 939248 Pershing
FG 216 9/11/2006 Hycroft Res & Dev Inc NMC 939249 Pershing
FG 217 9/11/2006 Hycroft Res & Dev Inc NMC 939250 Pershing
FG 218 9/11/2006 Hycroft Res & Dev Inc NMC 939251 Pershing
FG 219 9/11/2006 Hycroft Res & Dev Inc NMC 939252 Pershing
FG 22 9/1/2006 Hycroft Res & Dev Inc NMC 939080 Pershing
FG 220 9/11/2006 Hycroft Res & Dev Inc NMC 939253 Pershing
FG 221 9/11/2006 Hycroft Res & Dev Inc NMC 939254 Pershing
FG 222 9/11/2006 Hycroft Res & Dev Inc NMC 939255 Pershing
FG 227 9/2/2006 Hycroft Res & Dev Inc NMC 939260 Pershing
FG 228 9/2/2006 Hycroft Res & Dev Inc NMC 939261 Pershing
FG 229 9/2/2006 Hycroft Res & Dev Inc NMC 939262 Pershing
FG 23 9/11/2006 Hycroft Res & Dev Inc NMC 939081 Pershing
FG 230 9/2/2006 Hycroft Res & Dev Inc NMC 939263 Pershing
FG 231 9/2/2006 Hycroft Res & Dev Inc NMC 939264 Pershing
FG 232 9/2/2006 Hycroft Res & Dev Inc NMC 939265 Pershing
FG 233 9/2/2006 Hycroft Res & Dev Inc NMC 939266 Pershing
FG 234 9/2/2006 Hycroft Res & Dev Inc NMC 939267 Pershing
FG 235 9/2/2006 Hycroft Res & Dev Inc NMC 939268 Pershing
FG 236 9/2/2006 Hycroft Res & Dev Inc NMC 939269 Pershing
FG 237 9/2/2006 Hycroft Res & Dev Inc NMC 939270 Pershing
FG 238 9/2/2006 Hycroft Res & Dev Inc NMC 939271 Pershing
FG 239 9/2/2006 Hycroft Res & Dev Inc NMC 939272 Pershing
FG 24 9/11/2006 Hycroft Res & Dev Inc NMC 939082 Pershing
FG 240 9/2/2006 Hycroft Res & Dev Inc NMC 939273 Pershing
FG 241 9/2/2006 Hycroft Res & Dev Inc NMC 939274 Pershing
FG 242 9/2/2006 Hycroft Res & Dev Inc NMC 939275 Pershing
FG 243 9/2/2006 Hycroft Res & Dev Inc NMC 939276 Pershing
FG 244 9/2/2006 Hycroft Res & Dev Inc NMC 939277 Pershing
FG 245 9/8/2006 Hycroft Res & Dev Inc NMC 939278 Pershing
FG 246 9/8/2006 Hycroft Res & Dev Inc NMC 939279 Pershing
FG 247 9/8/2006 Hycroft Res & Dev Inc NMC 939280 Pershing
FG 248 9/8/2006 Hycroft Res & Dev Inc NMC 939281 Pershing
FG 249 9/8/2006 Hycroft Res & Dev Inc NMC 939282 Pershing
FG 25 9/11/2006 Hycroft Res & Dev Inc NMC 939083 Pershing
FG 26 9/11/2006 Hycroft Res & Dev Inc NMC 939084 Pershing
FG 262 9/11/2006 Hycroft Res & Dev Inc NMC 939283 Pershing
FG 263 9/11/2006 Hycroft Res & Dev Inc NMC 939284 Pershing
FG 264 9/11/2006 Hycroft Res & Dev Inc NMC 939285 Pershing
FG 265 9/11/2006 Hycroft Res & Dev Inc NMC 939286 Pershing
FG 266 9/11/2006 Hycroft Res & Dev Inc NMC 939287 Pershing
FG 267 9/11/2006 Hycroft Res & Dev Inc NMC 939288 Pershing
FG 268 9/11/2006 Hycroft Res & Dev Inc NMC 939289 Pershing
FG 269 9/11/2006 Hycroft Res & Dev Inc NMC 939290 Pershing

 

Hycroft Mine Project

Page 329

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 27 9/5/2006 Hycroft Res & Dev Inc NMC 939085 Pershing
FG 276 9/1/2006 Hycroft Res & Dev Inc NMC 939297 Pershing
FG 277 9/1/2006 Hycroft Res & Dev Inc NMC 939298 Pershing
FG 278 9/1/2006 Hycroft Res & Dev Inc NMC 939299 Pershing
FG 279 9/1/2006 Hycroft Res & Dev Inc NMC 939300 Pershing
FG 28 9/5/2006 Hycroft Res & Dev Inc NMC 939086 Pershing
FG 280 9/1/2006 Hycroft Res & Dev Inc NMC 939301 Pershing
FG 281 9/1/2006 Hycroft Res & Dev Inc NMC 939302 Pershing
FG 282 9/1/2006 Hycroft Res & Dev Inc NMC 939303 Pershing
FG 283 9/1/2006 Hycroft Res & Dev Inc NMC 939304 Pershing
FG 284 9/1/2006 Hycroft Res & Dev Inc NMC 939305 Pershing
FG 285 9/1/2006 Hycroft Res & Dev Inc NMC 939306 Pershing
FG 286 9/1/2006 Hycroft Res & Dev Inc NMC 939307 Pershing
FG 287 9/1/2006 Hycroft Res & Dev Inc NMC 939308 Pershing
FG 288 9/1/2006 Hycroft Res & Dev Inc NMC 939309 Pershing
FG 289 9/1/2006 Hycroft Res & Dev Inc NMC 939310 Pershing
FG 29 9/5/2006 Hycroft Res & Dev Inc NMC 939087 Pershing
FG 290 9/1/2006 Hycroft Res & Dev Inc NMC 939311 Pershing
FG 291 9/1/2006 Hycroft Res & Dev Inc NMC 939312 Pershing
FG 292 9/1/2006 Hycroft Res & Dev Inc NMC 939313 Pershing
FG 293 9/1/2006 Hycroft Res & Dev Inc NMC 939314 Pershing
FG 294 9/10/2006 Hycroft Res & Dev Inc NMC 939315 Pershing
FG 295 9/10/2006 Hycroft Res & Dev Inc NMC 939316 Pershing
FG 296 9/10/2006 Hycroft Res & Dev Inc NMC 939317 Pershing
FG 297 9/10/2006 Hycroft Res & Dev Inc NMC 939318 Pershing
FG 298 9/10/2006 Hycroft Res & Dev Inc NMC 939319 Pershing
FG 299 9/10/2006 Hycroft Res & Dev Inc NMC 939320 Pershing
FG 3 9/1/2006 Hycroft Res & Dev Inc NMC 939061 Pershing
FG 30 9/1/2006 Hycroft Res & Dev Inc NMC 939088 Pershing
FG 300 9/10/2006 Hycroft Res & Dev Inc NMC 939321 Pershing
FG 301 9/10/2006 Hycroft Res & Dev Inc NMC 939322 Pershing
FG 302 9/10/2006 Hycroft Res & Dev Inc NMC 939323 Pershing
FG 31 9/1/2006 Hycroft Res & Dev Inc NMC 939089 Pershing
FG 311 9/10/2006 Hycroft Res & Dev Inc NMC 939324 Pershing
FG 312 9/10/2006 Hycroft Res & Dev Inc NMC 939325 Pershing
FG 313 9/10/2006 Hycroft Res & Dev Inc NMC 939326 Pershing
FG 314 9/10/2006 Hycroft Res & Dev Inc NMC 939327 Pershing
FG 315 9/10/2006 Hycroft Res & Dev Inc NMC 939328 Pershing
FG 316 9/10/2006 Hycroft Res & Dev Inc NMC 939329 Pershing
FG 317 9/10/2006 Hycroft Res & Dev Inc NMC 939330 Pershing
FG 318 9/10/2006 Hycroft Res & Dev Inc NMC 939331 Pershing
FG 32 9/1/2006 Hycroft Res & Dev Inc NMC 939090 Pershing
FG 325 9/1/2006 Hycroft Res & Dev Inc NMC 939338 Pershing
FG 326 9/1/2006 Hycroft Res & Dev Inc NMC 939339 Pershing
FG 327 9/1/2006 Hycroft Res & Dev Inc NMC 939340 Pershing
FG 328 9/1/2006 Hycroft Res & Dev Inc NMC 939341 Pershing
FG 329 9/1/2006 Hycroft Res & Dev Inc NMC 939342 Pershing

 

Hycroft Mine Project

Page 330

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 33 9/1/2006 Hycroft Res & Dev Inc NMC 939091 Pershing
FG 330 9/1/2006 Hycroft Res & Dev Inc NMC 939343 Pershing
FG 331 9/1/2006 Hycroft Res & Dev Inc NMC 939344 Pershing
FG 332 9/1/2006 Hycroft Res & Dev Inc NMC 939345 Pershing
FG 333 9/1/2006 Hycroft Res & Dev Inc NMC 939346 Pershing
FG 334 9/1/2006 Hycroft Res & Dev Inc NMC 939347 Pershing
FG 335 9/1/2006 Hycroft Res & Dev Inc NMC 939348 Pershing
FG 336 9/1/2006 Hycroft Res & Dev Inc NMC 939349 Pershing
FG 337 9/1/2006 Hycroft Res & Dev Inc NMC 939350 Pershing
FG 338 9/1/2006 Hycroft Res & Dev Inc NMC 939351 Pershing
FG 339 9/1/2006 Hycroft Res & Dev Inc NMC 939352 Pershing
FG 34 9/1/2006 Hycroft Res & Dev Inc NMC 939092 Pershing
FG 340 9/1/2006 Hycroft Res & Dev Inc NMC 939353 Pershing
FG 341 9/1/2006 Hycroft Res & Dev Inc NMC 939354 Pershing
FG 342 9/1/2006 Hycroft Res & Dev Inc NMC 939355 Pershing
FG 343 9/10/2006 Hycroft Res & Dev Inc NMC 939356 Pershing
FG 344 9/10/2006 Hycroft Res & Dev Inc NMC 939357 Pershing
FG 345 9/10/2006 Hycroft Res & Dev Inc NMC 939358 Pershing
FG 346 9/10/2006 Hycroft Res & Dev Inc NMC 939359 Pershing
FG 347 9/10/2006 Hycroft Res & Dev Inc NMC 939360 Pershing
FG 349 9/10/2006 Hycroft Res & Dev Inc NMC 939362 Pershing
FG 35 9/1/2006 Hycroft Res & Dev Inc NMC 939093 Pershing
FG 350 9/10/2006 Hycroft Res & Dev Inc NMC 939363 Pershing
FG 351 9/10/2006 Hycroft Res & Dev Inc NMC 939364 Pershing
FG 36 9/1/2006 Hycroft Res & Dev Inc NMC 939094 Pershing
FG 360 9/10/2006 Hycroft Res & Dev Inc NMC 939365 Pershing
FG 361 9/10/2006 Hycroft Res & Dev Inc NMC 939366 Pershing
FG 362 9/10/2006 Hycroft Res & Dev Inc NMC 939367 Pershing
FG 363 9/10/2006 Hycroft Res & Dev Inc NMC 939368 Pershing
FG 364 9/10/2006 Hycroft Res & Dev Inc NMC 939369 Pershing
FG 365 9/10/2006 Hycroft Res & Dev Inc NMC 939370 Pershing
FG 366 9/10/2006 Hycroft Res & Dev Inc NMC 939371 Pershing
FG 367 9/10/2006 Hycroft Res & Dev Inc NMC 939372 Pershing
FG 37 9/1/2006 Hycroft Res & Dev Inc NMC 939095 Pershing
FG 378 9/1/2006 Hycroft Res & Dev Inc NMC 939383 Pershing
FG 379 9/1/2006 Hycroft Res & Dev Inc NMC 939384 Pershing
FG 380 9/1/2006 Hycroft Res & Dev Inc NMC 939385 Pershing
FG 381 9/1/2006 Hycroft Res & Dev Inc NMC 939386 Pershing
FG 382 9/1/2006 Hycroft Res & Dev Inc NMC 939387 Pershing
FG 383 9/1/2006 Hycroft Res & Dev Inc NMC 939388 Pershing
FG 384 9/1/2006 Hycroft Res & Dev Inc NMC 939389 Pershing
FG 385 9/1/2006 Hycroft Res & Dev Inc NMC 939390 Pershing
FG 386 9/1/2006 Hycroft Res & Dev Inc NMC 939391 Pershing
FG 387 9/1/2006 Hycroft Res & Dev Inc NMC 939392 Pershing
FG 388 9/1/2006 Hycroft Res & Dev Inc NMC 939393 Pershing
FG 389 9/1/2006 Hycroft Res & Dev Inc NMC 939394 Pershing
FG 39 9/1/2006 Hycroft Res & Dev Inc NMC 939097 Pershing
FG 390 9/1/2006 Hycroft Res & Dev Inc NMC 939395 Pershing
FG 391 9/1/2006 Hycroft Res & Dev Inc NMC 939396 Pershing

 

Hycroft Mine Project

Page 331

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 392 9/1/2006 Hycroft Res & Dev Inc NMC 939397 Pershing
FG 393 9/1/2006 Hycroft Res & Dev Inc NMC 939398 Pershing
FG 394 9/1/2006 Hycroft Res & Dev Inc NMC 939399 Pershing
FG 395 9/1/2006 Hycroft Res & Dev Inc NMC 939400 Pershing
FG 396 9/10/2006 Hycroft Res & Dev Inc NMC 939401 Pershing
FG 397 9/10/2006 Hycroft Res & Dev Inc NMC 939402 Pershing
FG 398 9/10/2006 Hycroft Res & Dev Inc NMC 939403 Pershing
FG 399 9/10/2006 Hycroft Res & Dev Inc NMC 939404 Pershing
FG 4 9/1/2006 Hycroft Res & Dev Inc NMC 939062 Pershing
FG 40 9/11/2006 Hycroft Res & Dev Inc NMC 939098 Pershing
FG 400 9/10/2006 Hycroft Res & Dev Inc NMC 939405 Pershing
FG 401 9/10/2006 Hycroft Res & Dev Inc NMC 939406 Pershing
FG 402 9/10/2006 Hycroft Res & Dev Inc NMC 939407 Pershing
FG 403 9/10/2006 Hycroft Res & Dev Inc NMC 939408 Pershing
FG 404 9/10/2006 Hycroft Res & Dev Inc NMC 939409 Pershing
FG 405 9/10/2006 Hycroft Res & Dev Inc NMC 939410 Pershing
FG 406 9/10/2006 Hycroft Res & Dev Inc NMC 939411 Pershing
FG 407 9/10/2006 Hycroft Res & Dev Inc NMC 939412 Pershing
FG 408 9/10/2006 Hycroft Res & Dev Inc NMC 939413 Pershing
FG 409 9/10/2006 Hycroft Res & Dev Inc NMC 939414 Pershing
FG 41 9/11/2006 Hycroft Res & Dev Inc NMC 939099 Pershing
FG 410 9/10/2006 Hycroft Res & Dev Inc NMC 939415 Pershing
FG 411 9/10/2006 Hycroft Res & Dev Inc NMC 939416 Pershing
FG 412 9/10/2006 Hycroft Res & Dev Inc NMC 939417 Pershing
FG 413 9/10/2006 Hycroft Res & Dev Inc NMC 939418 Pershing
FG 414 9/10/2006 Hycroft Res & Dev Inc NMC 939419 Pershing
FG 415 9/10/2006 Hycroft Res & Dev Inc NMC 939420 Pershing
FG 416 9/10/2006 Hycroft Res & Dev Inc NMC 939421 Pershing
FG 417 9/10/2006 Hycroft Res & Dev Inc NMC 939422 Pershing
FG 418 9/10/2006 Hycroft Res & Dev Inc NMC 939423 Pershing
FG 419 9/10/2006 Hycroft Res & Dev Inc NMC 939424 Pershing
FG 42 9/11/2006 Hycroft Res & Dev Inc NMC 939100 Pershing
FG 420 9/10/2006 Hycroft Res & Dev Inc NMC 939425 Pershing
FG 43 9/11/2006 Hycroft Res & Dev Inc NMC 939101 Pershing
FG 434 9/1/2006 Hycroft Res & Dev Inc NMC 939439 Pershing
FG 435 9/1/2006 Hycroft Res & Dev Inc NMC 939440 Pershing
FG 436 9/1/2006 Hycroft Res & Dev Inc NMC 939441 Pershing
FG 437 9/1/2006 Hycroft Res & Dev Inc NMC 939442 Pershing
FG 438 9/1/2006 Hycroft Res & Dev Inc NMC 939443 Pershing
FG 439 9/1/2006 Hycroft Res & Dev Inc NMC 939444 Pershing
FG 44 9/2/2006 Hycroft Res & Dev Inc NMC 939102 Pershing
FG 440 9/1/2006 Hycroft Res & Dev Inc NMC 939445 Pershing
FG 441 9/1/2006 Hycroft Res & Dev Inc NMC 939446 Pershing
FG 442 9/1/2006 Hycroft Res & Dev Inc NMC 939447 Pershing
FG 443 9/1/2006 Hycroft Res & Dev Inc NMC 939448 Pershing
FG 444 9/1/2006 Hycroft Res & Dev Inc NMC 939449 Pershing
FG 445 9/1/2006 Hycroft Res & Dev Inc NMC 939450 Pershing
FG 446 9/1/2006 Hycroft Res & Dev Inc NMC 939451 Pershing

 

Hycroft Mine Project

Page 332

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 447 9/1/2006 Hycroft Res & Dev Inc NMC 939452 Pershing
FG 448 9/1/2006 Hycroft Res & Dev Inc NMC 939453 Pershing
FG 449 9/1/2006 Hycroft Res & Dev Inc NMC 939454 Pershing
FG 45 9/2/2006 Hycroft Res & Dev Inc NMC 939103 Pershing
FG 450 9/1/2006 Hycroft Res & Dev Inc NMC 939455 Pershing
FG 451 9/1/2006 Hycroft Res & Dev Inc NMC 939456 Pershing
FG 452 9/10/2006 Hycroft Res & Dev Inc NMC 939457 Pershing
FG 453 9/10/2006 Hycroft Res & Dev Inc NMC 939458 Pershing
FG 454 9/10/2006 Hycroft Res & Dev Inc NMC 939459 Pershing
FG 455 9/10/2006 Hycroft Res & Dev Inc NMC 939460 Pershing
FG 456 9/10/2006 Hycroft Res & Dev Inc NMC 939461 Pershing
FG 457 9/10/2006 Hycroft Res & Dev Inc NMC 939462 Pershing
FG 458 9/10/2006 Hycroft Res & Dev Inc NMC 939463 Pershing
FG 459 9/10/2006 Hycroft Res & Dev Inc NMC 939464 Pershing
FG 46 9/2/2006 Hycroft Res & Dev Inc NMC 939104 Pershing
FG 460 9/10/2006 Hycroft Res & Dev Inc NMC 939465 Pershing
FG 461 9/10/2006 Hycroft Res & Dev Inc NMC 939466 Pershing
FG 462 9/10/2006 Hycroft Res & Dev Inc NMC 939467 Pershing
FG 463 9/10/2006 Hycroft Res & Dev Inc NMC 939468 Pershing
FG 464 9/10/2006 Hycroft Res & Dev Inc NMC 939469 Pershing
FG 465 9/10/2006 Hycroft Res & Dev Inc NMC 939470 Pershing
FG 466 9/10/2006 Hycroft Res & Dev Inc NMC 939471 Pershing
FG 467 9/10/2006 Hycroft Res & Dev Inc NMC 939472 Pershing
FG 468 9/10/2006 Hycroft Res & Dev Inc NMC 939473 Pershing
FG 469 9/10/2006 Hycroft Res & Dev Inc NMC 939474 Pershing
FG 47 9/2/2006 Hycroft Res & Dev Inc NMC 939105 Pershing
FG 470 9/10/2006 Hycroft Res & Dev Inc NMC 939475 Pershing
FG 471 9/10/2006 Hycroft Res & Dev Inc NMC 939476 Pershing
FG 472 9/10/2006 Hycroft Res & Dev Inc NMC 939477 Pershing
FG 473 9/10/2006 Hycroft Res & Dev Inc NMC 939478 Pershing
FG 474 9/10/2006 Hycroft Res & Dev Inc NMC 939479 Pershing
FG 475 9/10/2006 Hycroft Res & Dev Inc NMC 939480 Pershing
FG 476 9/10/2006 Hycroft Res & Dev Inc NMC 939481 Pershing
FG 477 9/11/2006 Hycroft Res & Dev Inc NMC 939482 Pershing
FG 478 9/11/2006 Hycroft Res & Dev Inc NMC 939483 Pershing
FG 479 9/11/2006 Hycroft Res & Dev Inc NMC 939484 Pershing
FG 48 9/2/2006 Hycroft Res & Dev Inc NMC 939106 Pershing
FG 480 9/11/2006 Hycroft Res & Dev Inc NMC 939485 Pershing
FG 481 9/11/2006 Hycroft Res & Dev Inc NMC 939486 Pershing
FG 482 9/11/2006 Hycroft Res & Dev Inc NMC 939487 Pershing
FG 483 9/11/2006 Hycroft Res & Dev Inc NMC 939488 Pershing
FG 484 9/11/2006 Hycroft Res & Dev Inc NMC 939489 Pershing
FG 485 9/11/2006 Hycroft Res & Dev Inc NMC 939490 Pershing
FG 486 9/11/2006 Hycroft Res & Dev Inc NMC 939491 Pershing
FG 487 9/11/2006 Hycroft Res & Dev Inc NMC 939492 Pershing
FG 488 9/11/2006 Hycroft Res & Dev Inc NMC 939493 Pershing
FG 489 9/11/2006 Hycroft Res & Dev Inc NMC 939494 Pershing

 

Hycroft Mine Project

Page 333

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 49 9/2/2006 Hycroft Res & Dev Inc NMC 939107 Pershing
FG 490 9/11/2006 Hycroft Res & Dev Inc NMC 939495 Pershing
FG 491 9/9/2006 Hycroft Res & Dev Inc NMC 939496 Pershing
FG 492 9/11/2006 Hycroft Res & Dev Inc NMC 939497 Pershing
FG 493 9/11/2006 Hycroft Res & Dev Inc NMC 939498 Pershing
FG 494 9/11/2006 Hycroft Res & Dev Inc NMC 939499 Pershing
FG 495 9/11/2006 Hycroft Res & Dev Inc NMC 939500 Pershing
FG 496 9/9/2006 Hycroft Res & Dev Inc NMC 939501 Pershing
FG 497 9/11/2006 Hycroft Res & Dev Inc NMC 939502 Pershing
FG 498 9/11/2006 Hycroft Res & Dev Inc NMC 939503 Pershing
FG 499 9/11/2006 Hycroft Res & Dev Inc NMC 939504 Pershing
FG 5 9/1/2006 Hycroft Res & Dev Inc NMC 939063 Pershing
FG 50 9/2/2006 Hycroft Res & Dev Inc NMC 939108 Pershing
FG 500 9/11/2006 Hycroft Res & Dev Inc NMC 939505 Pershing
FG 51 9/2/2006 Hycroft Res & Dev Inc NMC 939109 Pershing
FG 52 9/2/2006 Hycroft Res & Dev Inc NMC 939110 Pershing
FG 53 9/8/2006 Hycroft Res & Dev Inc NMC 939111 Pershing
FG 54 9/8/2006 Hycroft Res & Dev Inc NMC 939112 Pershing
FG 55 9/8/2006 Hycroft Res & Dev Inc NMC 939113 Pershing
FG 56 9/9/2006 Hycroft Res & Dev Inc NMC 939114 Pershing
FG 57 9/9/2006 Hycroft Res & Dev Inc NMC 939115 Pershing
FG 58 9/9/2006 Hycroft Res & Dev Inc NMC 939116 Pershing
FG 59 9/9/2006 Hycroft Res & Dev Inc NMC 939117 Pershing
FG 6 9/1/2006 Hycroft Res & Dev Inc NMC 939064 Pershing
FG 60 9/9/2006 Hycroft Res & Dev Inc NMC 939118 Pershing
FG 61 9/9/2006 Hycroft Res & Dev Inc NMC 939119 Pershing
FG 62 9/9/2006 Hycroft Res & Dev Inc NMC 939120 Pershing
FG 63 9/9/2006 Hycroft Res & Dev Inc NMC 939121 Pershing
FG 64 9/9/2006 Hycroft Res & Dev Inc NMC 939122 Pershing
FG 65 9/9/2006 Hycroft Res & Dev Inc NMC 939123 Pershing
FG 66 9/9/2006 Hycroft Res & Dev Inc NMC 939124 Pershing
FG 67 9/9/2006 Hycroft Res & Dev Inc NMC 939125 Pershing
FG 68 9/9/2006 Hycroft Res & Dev Inc NMC 939126 Pershing
FG 69 9/9/2006 Hycroft Res & Dev Inc NMC 939127 Pershing
FG 7 9/1/2006 Hycroft Res & Dev Inc NMC 939065 Pershing
FG 70 9/2/2006 Hycroft Res & Dev Inc NMC 939128 Pershing
FG 71 9/2/2006 Hycroft Res & Dev Inc NMC 939129 Pershing
FG 73 9/2/2006 Hycroft Res & Dev Inc NMC 939131 Pershing
FG 74 9/2/2006 Hycroft Res & Dev Inc NMC 939132 Pershing
FG 75 9/2/2006 Hycroft Res & Dev Inc NMC 939133 Pershing
FG 76 9/2/2006 Hycroft Res & Dev Inc NMC 939134 Pershing
FG 77 9/2/2006 Hycroft Res & Dev Inc NMC 939135 Pershing
FG 78 9/2/2006 Hycroft Res & Dev Inc NMC 939136 Pershing
FG 79 9/2/2006 Hycroft Res & Dev Inc NMC 939137 Pershing
FG 8 9/1/2006 Hycroft Res & Dev Inc NMC 939066 Pershing
FG 80 9/2/2006 Hycroft Res & Dev Inc NMC 939138 Pershing
FG 81 9/2/2006 Hycroft Res & Dev Inc NMC 939139 Pershing
FG 82 9/8/2006 Hycroft Res & Dev Inc NMC 939140 Pershing
FG 84 9/8/2006 Hycroft Res & Dev Inc NMC 939141 Pershing

 

Hycroft Mine Project

Page 334

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
FG 85 9/9/2006 Hycroft Res & Dev Inc NMC 939142 Pershing
FG 86 9/9/2006 Hycroft Res & Dev Inc NMC 939143 Pershing
FG 87 9/9/2006 Hycroft Res & Dev Inc NMC 939144 Pershing
FG 88 9/9/2006 Hycroft Res & Dev Inc NMC 939145 Pershing
FG 89 9/9/2006 Hycroft Res & Dev Inc NMC 939146 Pershing
FG 9 9/11/2006 Hycroft Res & Dev Inc NMC 939067 Pershing
FG 90 9/9/2006 Hycroft Res & Dev Inc NMC 939147 Pershing
FG 91 9/9/2006 Hycroft Res & Dev Inc NMC 939148 Pershing
FG 92 9/9/2006 Hycroft Res & Dev Inc NMC 939149 Pershing
FG 93 9/9/2006 Hycroft Res & Dev Inc NMC 939150 Pershing
FG 94 9/9/2006 Hycroft Res & Dev Inc NMC 939151 Pershing
FG 95 9/9/2006 Hycroft Res & Dev Inc NMC 939152 Pershing
FG 96 9/9/2006 Hycroft Res & Dev Inc NMC 939153 Pershing
FG 97 9/9/2006 Hycroft Res & Dev Inc NMC 939154 Pershing
FG 98 9/9/2006 Hycroft Res & Dev Inc NMC 939155 Pershing
FG 99 9/2/2006 Hycroft Res & Dev Inc NMC 939156 Pershing
FG348 9/10/2006 Hycroft Res & Dev Inc NMC 939361 Pershing
FG38 9/1/2006 Hycroft Res & Dev Inc NMC 939096 Pershing
FG72 9/2/2006 Hycroft Res & Dev Inc NMC 939130 Pershing
Nadine #1 1/20/2007 Hrdi NMC 946619 Pershing
NC 100 8/13/2010 Hycroft Res & Dev Inc NMC1027938 Pershing
NC 101 8/13/2010 Hycroft Res & Dev Inc NMC1027939 Pershing
NC 18 8/13/2010 Hycroft Res & Dev Inc NMC1027856 Pershing
NC 19 8/13/2010 Hycroft Res & Dev Inc NMC1027857 Pershing
NC 20 8/13/2010 Hycroft Res & Dev Inc NMC1027858 Pershing
NC 21 8/13/2010 Hycroft Res & Dev Inc NMC1027859 Pershing
NC 22 8/13/2010 Hycroft Res & Dev Inc NMC1027860 Pershing
NC 23 8/13/2010 Hycroft Res & Dev Inc NMC1027861 Pershing
NC 24 8/13/2010 Hycroft Res & Dev Inc NMC1027862 Pershing
NC 25 8/13/2010 Hycroft Res & Dev Inc NMC1027863 Pershing
NC 26 8/13/2010 Hycroft Res & Dev Inc NMC1027864 Pershing
NC 27 8/13/2010 Hycroft Res & Dev Inc NMC1027865 Pershing
NC 28 8/13/2010 Hycroft Res & Dev Inc NMC1027866 Pershing
NC 29 8/13/2010 Hycroft Res & Dev Inc NMC1027867 Pershing
NC 30 8/13/2010 Hycroft Res & Dev Inc NMC1027868 Pershing
NC 51 8/13/2010 Hycroft Res & Dev Inc NMC1027889 Pershing
NC 52 8/13/2010 Hycroft Res & Dev Inc NMC1027890 Pershing
NC 53 8/13/2010 Hycroft Res & Dev Inc NMC1027891 Pershing
NC 54 8/13/2010 Hycroft Res & Dev Inc NMC1027892 Pershing
NC 55 8/13/2010 Hycroft Res & Dev Inc NMC1027893 Pershing
NC 56 8/13/2010 Hycroft Res & Dev Inc NMC1027894 Pershing
NC 57 8/13/2010 Hycroft Res & Dev Inc NMC1027895 Pershing
NC 58 8/13/2010 Hycroft Res & Dev Inc NMC1027896 Pershing
NC 59 8/13/2010 Hycroft Res & Dev Inc NMC1027897 Pershing
NC 60 8/13/2010 Hycroft Res & Dev Inc NMC1027898 Pershing
NC 61 8/13/2010 Hycroft Res & Dev Inc NMC1027899 Pershing
NC 62 8/13/2010 Hycroft Res & Dev Inc NMC1027900 Pershing
NC 63 8/13/2010 Hycroft Res & Dev Inc NMC1027901 Pershing

 

Hycroft Mine Project

Page 335

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
NC 64 8/13/2010 Hycroft Res & Dev Inc NMC1027902 Pershing
NC 65 8/13/2010 Hycroft Res & Dev Inc NMC1027903 Pershing
NC 66 8/13/2010 Hycroft Res & Dev Inc NMC1027904 Pershing
NC 67 8/13/2010 Hycroft Res & Dev Inc NMC1027905 Pershing
NC 68 8/13/2010 Hycroft Res & Dev Inc NMC1027906 Pershing
NC 92 8/13/2010 Hycroft Res & Dev Inc NMC1027930 Pershing
NC 93 8/13/2010 Hycroft Res & Dev Inc NMC1027931 Pershing
NC 94 8/13/2010 Hycroft Res & Dev Inc NMC1027932 Pershing
NC 95 8/13/2010 Hycroft Res & Dev Inc NMC1027933 Pershing
NC 96 8/13/2010 Hycroft Res & Dev Inc NMC1027934 Pershing
NC 97 8/13/2010 Hycroft Res & Dev Inc NMC1027935 Pershing
NC 98 8/13/2010 Hycroft Res & Dev Inc NMC1027936 Pershing
NC 99 8/13/2010 Hycroft Res & Dev Inc NMC1027937 Pershing
NFRA 10 11/8/2007 Victory Exploration Inc. NMC 977842 Pershing
NFRA 11 11/8/2007 Victory Exploration Inc. NMC 977843 Pershing
NFRA 21 11/8/2007 Victory Exploration Inc. NMC 977853 Pershing
NFRA 22 11/8/2007 Victory Exploration Inc. NMC 977854 Pershing
NFRA 25 11/8/2007 Victory Exploration Inc. NMC 977857 Pershing
NFRA 6 11/8/2007 Victory Exploration Inc. NMC 977838 Pershing
NFRA 7 11/8/2007 Victory Exploration Inc. NMC 977839 Pershing
NFRA 8 11/8/2007 Victory Exploration Inc. NMC 977840 Pershing
NFRA 9 11/8/2007 Victory Exploration Inc. NMC 977841 Pershing
RFG #120 1/24/1980 Lewis Frank W NMC 141680 Pershing
RFG #121 1/24/1980 Lewis Frank W NMC 141681 Pershing
RFG #122 1/24/1980 Lewis Frank W NMC 141682 Pershing
RFG #123 1/24/1980 Lewis Frank W NMC 141683 Pershing
RFG #124 1/24/1980 Lewis Frank W NMC 141684 Pershing
RFG #125 1/24/1980 Lewis Frank W NMC 141685 Pershing
RFG #135 1/9/1980 Lewis Frank W NMC 141692 Pershing
RFG #137 1/9/1980 Lewis Frank W NMC 141694 Pershing
RFG #139 1/9/1980 Lewis Frank W NMC 141696 Pershing
RFG #141 1/9/1980 Lewis Frank W NMC 141698 Pershing
RFG #143 1/22/1980 Lewis Frank W NMC 141700 Pershing
RFG #145 1/22/1980 Lewis Frank W NMC 141702 Pershing
RFG #147 1/22/1980 Lewis Frank W NMC 141704 Pershing
RFG #148 1/22/1980 Lewis Frank W NMC 141705 Pershing
RFG #149 1/22/1980 Lewis Frank W NMC 141706 Pershing
RFG #150 1/22/1980 Lewis Frank W NMC 141707 Pershing
RFG #151 1/22/1980 Lewis Frank W NMC 141708 Pershing
RFG #152 1/22/1980 Lewis Frank W NMC 141709 Pershing
RFG #153 1/22/1980 Lewis Frank W NMC 141710 Pershing
RFG #154 1/22/1980 Lewis Frank W NMC 141711 Pershing
RFG #155 1/22/1980 Lewis Frank W NMC 141712 Pershing
RFG #156 1/22/1980 Lewis Frank W NMC 141713 Pershing
RFG #157 1/22/1980 Lewis Frank W NMC 141714 Pershing
RFG #158 1/22/1980 Lewis Frank W NMC 141715 Pershing
RFG #159 1/22/1980 Lewis Frank W NMC 141716 Pershing
RFG #160 1/22/1980 Lewis Frank W NMC 141717 Pershing

 

Hycroft Mine Project

Page 336

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #161 1/22/1980 Lewis Frank W NMC 141718 Pershing
RFG #162 1/23/1980 Lewis Frank W NMC 141719 Pershing
RFG #163 1/23/1980 Lewis Frank W NMC 141720 Pershing
RFG #164 1/23/1980 Lewis Frank W NMC 141721 Pershing
RFG #165 1/23/1980 Lewis Frank W NMC 141722 Pershing
RFG #166 1/23/1980 Lewis Frank W NMC 141723 Pershing
RFG #167 1/23/1980 Lewis Frank W NMC 141724 Pershing
RFG #201A 12/28/1979 Lewis Frank W NMC 141726 Pershing
RFG #202A 12/28/1979 Lewis Frank W NMC 141727 Pershing
RFG #203A 12/28/1979 Lewis Frank W NMC 141728 Pershing
RFG #204A 12/28/1979 Lewis Frank W NMC 141729 Pershing
RFG #205A 12/28/1979 Lewis Frank W NMC 141730 Pershing
RFG #206A 12/28/1979 Lewis Frank W NMC 141731 Pershing
RFG #207A 12/28/1979 Lewis Frank W NMC 141732 Pershing
RFG #208A 12/28/1979 Lewis Frank W NMC 141733 Pershing
RFG #209A 12/28/1979 Lewis Frank W NMC 141734 Pershing
RFG #210A 12/28/1979 Lewis Frank W NMC 141735 Pershing
RFG #211A 12/28/1979 Lewis Frank W NMC 141736 Pershing
RFG #212A 12/28/1979 Lewis Frank W NMC 141737 Pershing
RFG #213A 12/28/1979 Lewis Frank W NMC 141738 Pershing
RFG #214A 12/28/1979 Lewis Frank W NMC 141739 Pershing
RFG #215A 12/28/1979 Lewis Frank W NMC 141740 Pershing
RFG #216A 12/28/1979 Lewis Frank W NMC 141741 Pershing
RFG #217A 12/28/1979 Lewis Frank W NMC 141742 Pershing
RFG #218A 12/28/1979 Lewis Frank W NMC 141743 Pershing
RFG #219A 12/28/1979 Lewis Frank W NMC 141744 Pershing
RFG #220A 12/28/1979 Lewis Frank W NMC 141745 Pershing
RFG #221A 12/28/1979 Lewis Frank W NMC 141746 Pershing
RFG #222A 12/28/1979 Lewis Frank W NMC 141747 Pershing
RFG #223A 12/28/1979 Lewis Frank W NMC 141748 Pershing
RFG #225A 1/7/1980 Lewis Frank W NMC 141750 Pershing
RFG #226A 1/7/1980 Lewis Frank W NMC 141751 Pershing
RFG #227A 1/7/1980 Lewis Frank W NMC 141752 Pershing
RFG #228A 1/7/1980 Lewis Frank W NMC 141754 Pershing
RFG #229 1/25/1980 Lewis Frank W NMC 141755 Pershing
RFG #229A 1/7/1980 Lewis Frank W NMC 141756 Pershing
RFG #230A 1/7/1980 Lewis Frank W NMC 141758 Pershing
RFG #231 1/25/1980 Lewis Frank W NMC 141759 Pershing
RFG #231A 1/7/1980 Lewis Frank W NMC 141760 Pershing
RFG #232A 1/7/1980 Lewis Frank W NMC 141761 Pershing
RFG #233 1/26/1980 Lewis Frank W NMC 141762 Pershing
RFG #233A 1/7/1980 Lewis Frank W NMC 141763 Pershing
RFG #234A 1/7/1980 Lewis Frank W NMC 141765 Pershing
RFG #235A 1/7/1980 Lewis Frank W NMC 141767 Pershing
RFG #236A 1/8/1980 Lewis Frank W NMC 141769 Pershing
RFG #237A 1/8/1980 Lewis Frank W NMC 141771 Pershing
RFG #238A 1/8/1980 Lewis Frank W NMC 141772 Pershing
RFG #239A 1/8/1980 Lewis Frank W NMC 141773 Pershing

 

Hycroft Mine Project

Page 337

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #240A 1/8/1980 Lewis Frank W NMC 141774 Pershing
RFG #241A 1/8/1980 Lewis Frank W NMC 141775 Pershing
RFG #251 1/11/1980 Lewis Frank W NMC 141777 Pershing
RFG #253 1/11/1980 Lewis Frank W NMC 141779 Pershing
RFG #255 1/11/1980 Hrdi NMC 141781 Pershing
RFG 107 5/20/2006 Hycroft Res & Dev Inc NMC 932890 Pershing
RFG 109 5/20/2006 Hycroft Res & Dev Inc NMC 932892 Pershing
RFG 111 5/20/2006 Hycroft Res & Dev Inc NMC 932894 Pershing
RFG 113 5/20/2006 Hycroft Res & Dev Inc NMC 932896 Pershing
RFG 114 5/20/2006 Hycroft Res & Dev Inc NMC 932897 Pershing
RFG 115 5/20/2006 Hycroft Res & Dev Inc NMC 932898 Pershing
RFG 116 5/20/2006 Hycroft Res & Dev Inc NMC 932899 Pershing
RFG 117 5/20/2006 Hycroft Res & Dev Inc NMC 932900 Pershing
RFG 118 5/20/2006 Hycroft Res & Dev Inc NMC 932901 Pershing
RFG 119 5/20/2006 Hycroft Res & Dev Inc NMC 932902 Pershing
RFG 142 5/20/2006 Hycroft Res & Dev Inc NMC 932908 Pershing
RFG 144 5/20/2006 Hycroft Res & Dev Inc NMC 932909 Pershing
RFG 146 5/20/2006 Hycroft Res & Dev Inc NMC 932910 Pershing
RFG#224A 1/7/1980 Lewis Frank W NMC 141749 Pershing
SH 169 4/24/2008 Hycroft Res & Dev Inc NMC 990822 Pershing
SH 170 4/24/2008 Hycroft Res & Dev Inc NMC 990823 Pershing
SH 171 4/24/2008 Hycroft Res & Dev Inc NMC 990824 Pershing
SH 172 4/24/2008 Hycroft Res & Dev Inc NMC 990825 Pershing
SH 173 4/24/2008 Hycroft Res & Dev Inc NMC 990826 Pershing
SH 174 4/24/2008 Hycroft Res & Dev Inc NMC 990827 Pershing
SH 175 4/24/2008 Hycroft Res & Dev Inc NMC 990828 Pershing
SH 176 4/24/2008 Hycroft Res & Dev Inc NMC990829 Pershing
SH 177 4/24/2008 Hycroft Res & Dev Inc NMC 990830 Pershing
SH 178 4/24/2008 Hycroft Res & Dev Inc NMC 990831 Pershing
SH 179 4/24/2008 Hycroft Res & Dev Inc NMC 990832 Pershing
SH 180 4/24/2008 Hycroft Res & Dev Inc NMC 990833 Pershing
SH 181 4/24/2008 Hycroft Res & Dev Inc NMC 990834 Pershing
SH 182 4/24/2008 Hycroft Res & Dev Inc NMC 990835 Pershing
SH 183 4/24/2008 Hycroft Res & Dev Inc NMC 990836 Pershing
SH 184 4/24/2008 Hycroft Res & Dev Inc NMC 990837 Pershing
SH 185 4/24/2008 Hycroft Res & Dev Inc NMC 990838 Pershing
SH 186 4/24/2008 Hycroft Res & Dev Inc NMC 990839 Pershing
SH 187 4/24/2008 Hycroft Res & Dev Inc NMC 990840 Pershing
SH 188 4/24/2008 Hycroft Res & Dev Inc NMC 990841 Pershing
SH 189 4/24/2008 Hycroft Res & Dev Inc NMC 990842 Pershing
SH 190 4/24/2008 Hycroft Res & Dev Inc NMC 990843 Pershing
SH 191 4/24/2008 Hycroft Res & Dev Inc NMC 990844 Pershing
SH 192 4/24/2008 Hycroft Res & Dev Inc NMC 990845 Pershing
SH 193 4/24/2008 Hycroft Res & Dev Inc NMC 990846 Pershing
SH 194 4/24/2008 Hycroft Res & Dev Inc NMC 990847 Pershing
SH 195 4/24/2008 Hycroft Res & Dev Inc NMC 990848 Pershing
SH 196 4/24/2008 Hycroft Res & Dev Inc NMC 990849 Pershing
SH 197 4/24/2008 Hycroft Res & Dev Inc NMC990850 Pershing

 

Hycroft Mine Project

Page 338

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 198 4/24/2008 Hycroft Res & Dev Inc NMC 990851 Pershing
SH 199 4/24/2008 Hycroft Res & Dev Inc NMC 990852 Pershing
SH 200 4/24/2008 Hycroft Res & Dev Inc NMC 990853 Pershing
SH 201 4/24/2008 Hycroft Res & Dev Inc NMC 990854 Pershing
SH 202 4/24/2008 Hycroft Res & Dev Inc NMC 990855 Pershing
SH 203 4/24/2008 Hycroft Res & Dev Inc NMC 990856 Pershing
SH 204 4/24/2008 Hycroft Res & Dev Inc NMC 990857 Pershing
SH 205 4/24/2008 Hycroft Res & Dev Inc NMC 990858 Pershing
SH 206 4/24/2008 Hycroft Res & Dev Inc NMC 990859 Pershing
SH 207 4/24/2008 Hycroft Res & Dev Inc NMC 990860 Pershing
SH 208 4/24/2008 Hycroft Res & Dev Inc NMC 990861 Pershing
SH 209 4/24/2008 Hycroft Res & Dev Inc NMC 990862 Pershing
SH 210 4/24/2008 Hycroft Res & Dev Inc NMC 990863 Pershing
SH 211 4/24/2008 Hycroft Res & Dev Inc NMC 990864 Pershing
SH 212 4/24/2008 Hycroft Res & Dev Inc NMC 990865 Pershing
SH 213 4/24/2008 Hycroft Res & Dev Inc NMC 990866 Pershing
SH 214 4/24/2008 Hycroft Res & Dev Inc NMC 990867 Pershing
SH 215 4/24/2008 Hycroft Res & Dev Inc NMC 990868 Pershing
SH 216 4/24/2008 Hycroft Res & Dev Inc NMC 990869 Pershing
SH 217 4/24/2008 Hycroft Res & Dev Inc NMC 990870 Pershing
SH 218 4/24/2008 Hycroft Res & Dev Inc NMC 990871 Pershing
SH 219 4/24/2008 Hycroft Res & Dev Inc NMC 990872 Pershing
SH 220 4/24/2008 Hycroft Res & Dev Inc NMC 990873 Pershing
SH 221 4/24/2008 Hycroft Res & Dev Inc NMC 990874 Pershing
SH 222 4/24/2008 Hycroft Res & Dev Inc NMC 990875 Pershing
SH 223 4/24/2008 Hycroft Res & Dev Inc NMC 990876 Pershing
SH 224 4/24/2008 Hycroft Res & Dev Inc NMC 990877 Pershing
SH 225 4/24/2008 Hycroft Res & Dev Inc NMC 990878 Pershing
SH 226 4/24/2008 Hycroft Res & Dev Inc NMC 990879 Pershing
SH 227 4/24/2008 Hycroft Res & Dev Inc NMC 990880 Pershing
SH 228 4/24/2008 Hycroft Res & Dev Inc NMC 990881 Pershing
SH 229 4/24/2008 Hycroft Res & Dev Inc NMC 990882 Pershing
SH 230 4/24/2008 Hycroft Res & Dev Inc NMC 990883 Pershing
SH 231 4/23/2008 Hycroft Res & Dev Inc NMC 990884 Pershing
SH 235 4/23/2008 Hycroft Res & Dev Inc NMC 990888 Pershing
SH 236 4/23/2008 Hycroft Res & Dev Inc NMC 990889 Pershing
SH 237 4/23/2008 Hycroft Res & Dev Inc NMC 990890 Pershing
SH 238 4/23/2008 Hycroft Res & Dev Inc NMC 990891 Pershing
SH 239 4/23/2008 Hycroft Res & Dev Inc NMC 990892 Pershing
SH 240 4/23/2008 Hycroft Res & Dev Inc NMC 990893 Pershing
SH 241 4/23/2008 Hycroft Res & Dev Inc NMC 990894 Pershing
SH 244 4/23/2008 Hycroft Res & Dev Inc NMC 990895 Pershing
SH 245 4/23/2008 Hycroft Res & Dev Inc NMC 990896 Pershing
SH 247 4/23/2008 Hycroft Res & Dev Inc NMC 990900 Pershing
SH 249 4/23/2008 Hycroft Res & Dev Inc NMC 990905 Pershing
SH 250 4/23/2008 Hycroft Res & Dev Inc NMC 990901 Pershing
SH 251 4/23/2008 Hycroft Res & Dev Inc NMC 990902 Pershing
SH 252 4/25/2008 Hycroft Res & Dev Inc NMC 990903 Pershing

 

Hycroft Mine Project

Page 339

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 253 4/25/2008 Hycroft Res & Dev Inc NMC 990904 Pershing
SH 254 4/25/2008 Hycroft Res & Dev Inc NMC 990906 Pershing
SH 255 4/25/2008 Hycroft Res & Dev Inc NMC 990907 Pershing
SH 256 4/25/2008 Hycroft Res & Dev Inc NMC 990908 Pershing
SH 257 4/25/2008 Hycroft Res & Dev Inc NMC 990909 Pershing
SH 258 4/25/2008 Hycroft Res & Dev Inc NMC 990910 Pershing
SH 259 4/25/2008 Hycroft Res & Dev Inc NMC 990911 Pershing
SH 260 4/25/2008 Hycroft Res & Dev Inc NMC 990912 Pershing
SH 261 4/25/2008 Hycroft Res & Dev Inc NMC 990913 Pershing
SH 262 4/25/2008 Hycroft Res & Dev Inc NMC 990914 Pershing
SH 263 4/25/2008 Hycroft Res & Dev Inc NMC 990915 Pershing
SH 265 4/25/2008 Hycroft Res & Dev Inc NMC 990917 Pershing
SH 266 4/25/2008 Hycroft Res & Dev Inc NMC 990918 Pershing
SH 269 4/23/2008 Hycroft Res & Dev Inc NMC 990921 Pershing
SH 270 4/23/2008 Hycroft Res & Dev Inc NMC 990922 Pershing
SH 271 4/23/2008 Hycroft Res & Dev Inc NMC 990923 Pershing
SH 272 4/23/2008 Hycroft Res & Dev Inc NMC 990924 Pershing
SH 273 4/23/2008 Hycroft Res & Dev Inc NMC 990925 Pershing
SH 274 4/23/2008 Hycroft Res & Dev Inc NMC 990926 Pershing
SH 276 4/23/2008 Hycroft Res & Dev Inc NMC 990928 Pershing
SH 277 4/23/2008 Hycroft Res & Dev Inc NMC 990929 Pershing
SH 278 4/22/2008 Hycroft Res & Dev Inc NMC 990930 Pershing
SH 279 4/22/2008 Hycroft Res & Dev Inc NMC 990931 Pershing
SH 280 4/22/2008 Hycroft Res & Dev Inc NMC 990932 Pershing
SH 281 4/22/2008 Hycroft Res & Dev Inc NMC 990933 Pershing
SH 282 4/22/2008 Hycroft Res & Dev Inc NMC 990934 Pershing
SH 284 4/22/2008 Hycroft Res & Dev Inc NMC 990936 Pershing
SH 285 4/22/2008 Hycroft Res & Dev Inc NMC 990937 Pershing
SH 286 4/22/2008 Hycroft Res & Dev Inc NMC 990938 Pershing
SH 288 4/22/2008 Hycroft Res & Dev Inc NMC 990940 Pershing
SH 290 4/22/2008 Hycroft Res & Dev Inc NMC990942 Pershing
SH 291 4/22/2008 Hycroft Res & Dev Inc NMC 990943 Pershing
SH 292 4/22/2008 Hycroft Res & Dev Inc NMC 990944 Pershing
SH 293 4/22/2008 Hycroft Res & Dev Inc NMC 990945 Pershing
SH 294 4/22/2008 Hycroft Res & Dev Inc NMC 990946 Pershing
SH 296 4/22/2008 Hycroft Res & Dev Inc NMC 990948 Pershing
SH 297 4/22/2008 Hycroft Res & Dev Inc NMC 990956 Pershing
SH 298 4/22/2008 Hycroft Res & Dev Inc NMC 990957 Pershing
SH 300 4/22/2008 Hycroft Res & Dev Inc NMC 990950 Pershing
SH 301 4/22/2008 Hycroft Res & Dev Inc NMC 990951 Pershing
SH 303 4/22/2008 Hycroft Res & Dev Inc NMC 990953 Pershing
SH 304 4/22/2008 Hycroft Res & Dev Inc NMC 990954 Pershing
SH 305 4/22/2008 Hycroft Res & Dev Inc NMC 990955 Pershing
SH 307 4/22/2008 Hycroft Res & Dev Inc NMC 990959 Pershing
SH 308 4/22/2008 Hycroft Res & Dev Inc NMC 990960 Pershing
SH 309 4/22/2008 Hycroft Res & Dev Inc NMC 990961 Pershing
SH 310 4/22/2008 Hycroft Res & Dev Inc NMC 990962 Pershing
SH 311 4/22/2008 Hycroft Res & Dev Inc NMC 990963 Pershing

 

Hycroft Mine Project

Page 340

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 312 4/22/2008 Hycroft Res & Dev Inc NMC 990964 Pershing
SH 313 4/22/2008 Hycroft Res & Dev Inc NMC 990965 Pershing
SH 314 4/22/2008 Hycroft Res & Dev Inc NMC 990966 Pershing
SH 315 4/22/2008 Hycroft Res & Dev Inc NMC 990967 Pershing
SH 316 4/22/2008 Hycroft Res & Dev Inc NMC 990968 Pershing
SH 317 4/22/2008 Hycroft Res & Dev Inc NMC 990969 Pershing
SH 318 4/22/2008 Hycroft Res & Dev Inc NMC 990970 Pershing
SH 319 4/22/2008 Hycroft Res & Dev Inc NMC 990971 Pershing
SH 320 4/22/2008 Hycroft Res & Dev Inc NMC 990972 Pershing
SH 321 4/22/2008 Hycroft Res & Dev Inc NMC 990973 Pershing
SH 323 4/22/2008 Hycroft Res & Dev Inc NMC 990975 Pershing
SH 324 4/22/2008 Hycroft Res & Dev Inc NMC 990976 Pershing
SH 325 4/22/2008 Hycroft Res & Dev Inc NMC 990977 Pershing
SH 326 4/22/2008 Hycroft Res & Dev Inc NMC 990978 Pershing
SH 327 4/22/2008 Hycroft Res & Dev Inc NMC 990979 Pershing
SH 328 4/22/2008 Hycroft Res & Dev Inc NMC 990980 Pershing
SH 334 4/22/2008 Hycroft Res & Dev Inc NMC 990986 Pershing
SH 335 4/22/2008 Hycroft Res & Dev Inc NMC 990987 Pershing
SH 336 4/22/2008 Hycroft Res & Dev Inc NMC 990988 Pershing
SH 337 4/22/2008 Hycroft Res & Dev Inc NMC 990989 Pershing
SH 338 4/22/2008 Hycroft Res & Dev Inc NMC 990990 Pershing
SH 339 4/22/2008 Hycroft Res & Dev Inc NMC 990991 Pershing
SH 340 4/22/2008 Hycroft Res & Dev Inc NMC 990992 Pershing
SH 341 4/22/2008 Hycroft Res & Dev Inc NMC 990993 Pershing
SH 342 4/22/2008 Hycroft Res & Dev Inc NMC 990994 Pershing
SH 343 4/22/2008 Hycroft Res & Dev Inc NMC 990995 Pershing
SH 345 4/22/2008 Hycroft Res & Dev Inc NMC 990997 Pershing
SH 346 4/21/2008 Hycroft Res & Dev Inc NMC 990998 Pershing
SH 347 4/21/2008 Hycroft Res & Dev Inc NMC 990999 Pershing
SH 358 4/21/2008 Hycroft Res & Dev Inc NMC 991010 Pershing
SH 359 4/21/2008 Hycroft Res & Dev Inc NMC 991011 Pershing
SH 360 4/21/2008 Hycroft Res & Dev Inc NMC 991012 Pershing
SH 361 4/21/2008 Hycroft Res & Dev Inc NMC 991013 Pershing
SH 362 4/21/2008 Hycroft Res & Dev Inc NMC 991014 Pershing
SH 363 4/21/2008 Hycroft Res & Dev Inc NMC 991015 Pershing
SH 364 4/21/2008 Hycroft Res & Dev Inc NMC 991016 Pershing
SH 365 4/21/2008 Hycroft Res & Dev Inc NMC 991017 Pershing
SH 366 4/21/2008 Hycroft Res & Dev Inc NMC 991018 Pershing
SH 367 4/21/2008 Hycroft Res & Dev Inc NMC 991019 Pershing
SH 368 4/21/2008 Hycroft Res & Dev Inc NMC 991020 Pershing
SH 370 4/21/2008 Hycroft Res & Dev Inc NMC 991022 Pershing
SH 387 4/21/2008 Hycroft Res & Dev Inc NMC 991039 Pershing
SH 388 4/21/2008 Hycroft Res & Dev Inc NMC 991040 Pershing
SH 389 4/21/2008 Hycroft Res & Dev Inc NMC 991041 Pershing
SH 390 4/21/2008 Hycroft Res & Dev Inc NMC 991042 Pershing
SH 391 4/21/2008 Hycroft Res & Dev Inc NMC 991043 Pershing
SH 392 4/21/2008 Hycroft Res & Dev Inc NMC 991044 Pershing
SH 393 4/21/2008 Hycroft Res & Dev Inc NMC 991045 Pershing

 

Hycroft Mine Project

Page 341

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 394 4/21/2008 Hycroft Res & Dev Inc NMC 991046 Pershing
SH 395 4/21/2008 Hycroft Res & Dev Inc NMC 991047 Pershing
SH 412 4/21/2008 Hycroft Res & Dev Inc NMC 991064 Pershing
SH 413 4/21/2008 Hycroft Res & Dev Inc NMC 991065 Pershing
SH 414 4/21/2008 Hycroft Res & Dev Inc NMC 991066 Pershing
SH 415 4/21/2008 Hycroft Res & Dev Inc NMC 991067 Pershing
SH 416 4/21/2008 Hycroft Res & Dev Inc NMC 991068 Pershing
SH 417 4/21/2008 Hycroft Res & Dev Inc NMC 991069 Pershing
SH 435 4/21/2008 Hycroft Res & Dev Inc NMC 991210 Pershing
SH 436 4/21/2008 Hycroft Res & Dev Inc NMC 991087 Pershing
SH 437 4/21/2008 Hycroft Res & Dev Inc NMC 991088 Pershing
SH 438 4/21/2008 Hycroft Res & Dev Inc NMC 991089 Pershing
SH 461 4/22/2008 Hycroft Res & Dev Inc NMC 991112 Pershing
SH 462 4/22/2008 Hycroft Res & Dev Inc NMC 991113 Pershing
SH 463 4/22/2008 Hycroft Res & Dev Inc NMC 991114 Pershing
SH 468 4/22/2008 Hycroft Res & Dev Inc NMC 991119 Pershing
SH 469 4/22/2008 Hycroft Res & Dev Inc NMC 991120 Pershing
SH 470 4/22/2008 Hycroft Res & Dev Inc NMC 991121 Pershing
SH 471 4/22/2008 Hycroft Res & Dev Inc NMC 991122 Pershing
SH 473 4/22/2008 Hycroft Res & Dev Inc NMC 991124 Pershing
SH 474 4/22/2008 Hycroft Res & Dev Inc NMC 991125 Pershing
SH 477 4/22/2008 Hycroft Res & Dev Inc NMC 991128 Pershing
SH 478 4/22/2008 Hycroft Res & Dev Inc NMC 991129 Pershing
SH 480 4/22/2008 Hycroft Res & Dev Inc NMC 991131 Pershing
SH 481 4/22/2008 Hycroft Res & Dev Inc NMC 991132 Pershing
SH 482 4/22/2008 Hycroft Res & Dev Inc NMC 991133 Pershing
SH 483 4/22/2008 Hycroft Res & Dev Inc NMC 991134 Pershing
SH 485 4/22/2008 Hycroft Res & Dev Inc NMC 991136 Pershing
SH 486 4/22/2008 Hycroft Res & Dev Inc NMC 991137 Pershing
SH 488 4/22/2008 Hycroft Res & Dev Inc NMC 991139 Pershing
SH 489 4/22/2008 Hycroft Res & Dev Inc NMC 991140 Pershing
SH 490 4/22/2008 Hycroft Res & Dev Inc NMC991141 Pershing
SH 491 4/22/2008 Hycroft Res & Dev Inc NMC 991142 Pershing
SH 492 4/22/2008 Hycroft Res & Dev Inc NMC 991143 Pershing
SH 493 4/22/2008 Hycroft Res & Dev Inc NMC 991144 Pershing
SH 497 4/22/2008 Hycroft Res & Dev Inc NMC 991148 Pershing
SH 498 4/22/2008 Hycroft Res & Dev Inc NMC 991149 Pershing
SH 499 4/22/2008 Hycroft Res & Dev Inc NMC 991150 Pershing
SH 500 4/22/2008 Hycroft Res & Dev Inc NMC 991151 Pershing
SH 501 4/22/2008 Hycroft Res & Dev Inc NMC 991152 Pershing
SH 502 4/22/2008 Hycroft Res & Dev Inc NMC 991153 Pershing
SH 503 4/22/2008 Hycroft Res & Dev Inc NMC 991154 Pershing
SH 504 4/22/2008 Hycroft Res & Dev Inc NMC 991155 Pershing
SH 505 4/22/2008 Hycroft Res & Dev Inc NMC 991156 Pershing
SH 507 4/22/2008 Hycroft Res & Dev Inc NMC 991158 Pershing
SH 508 4/22/2008 Hycroft Res & Dev Inc NMC 991159 Pershing
SH 509 4/22/2008 Hycroft Res & Dev Inc NMC 991160 Pershing
SH 510 4/22/2008 Hycroft Res & Dev Inc NMC 991161 Pershing

 

Hycroft Mine Project

Page 342

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 511 4/22/2008 Hycroft Res & Dev Inc NMC 991162 Pershing
SH 512 4/22/2008 Hycroft Res & Dev Inc NMC 991163 Pershing
SH 513 4/22/2008 Hycroft Res & Dev Inc NMC 991164 Pershing
SH 514 4/22/2008 Hycroft Res & Dev Inc NMC 991165 Pershing
SH 515 4/22/2008 Hycroft Res & Dev Inc NMC 991166 Pershing
SH 516 4/22/2008 Hycroft Res & Dev Inc NMC 991167 Pershing
SH 517 4/22/2008 Hycroft Res & Dev Inc NMC 991168 Pershing
SH 519 4/22/2008 Hycroft Res & Dev Inc NMC 991170 Pershing
SH 520 4/22/2008 Hycroft Res & Dev Inc NMC 991171 Pershing
SH 521 4/22/2008 Hycroft Res & Dev Inc NMC 991172 Pershing
SH 523 4/22/2008 Hycroft Res & Dev Inc NMC 991174 Pershing
SH 524 4/22/2008 Hycroft Res & Dev Inc NMC 991175 Pershing
SH 526 4/22/2008 Hycroft Res & Dev Inc NMC 991177 Pershing
SH 528 4/22/2008 Hycroft Res & Dev Inc NMC 991179 Pershing
SH 529 4/22/2008 Hycroft Res & Dev Inc NMC 991180 Pershing
SH 530 4/22/2008 Hycroft Res & Dev Inc NMC 991181 Pershing
SH 531 4/22/2008 Hycroft Res & Dev Inc NMC 991182 Pershing
SH 532 4/22/2008 Hycroft Res & Dev Inc NMC 991183 Pershing
SH 533 4/22/2008 Hycroft Res & Dev Inc NMC 991184 Pershing
SH 534 4/22/2008 Hycroft Res & Dev Inc NMC 991185 Pershing
SH 535 4/22/2008 Hycroft Res & Dev Inc NMC 991186 Pershing
SH 536 4/22/2008 Hycroft Res & Dev Inc NMC 991187 Pershing
SH 537 4/22/2008 Hycroft Res & Dev Inc NMC 991188 Pershing
SH 538 4/22/2008 Hycroft Res & Dev Inc NMC 991189 Pershing
SH 539 4/22/2008 Hycroft Res & Dev Inc NMC 991190 Pershing
SH 540 4/22/2008 Hycroft Res & Dev Inc NMC 991191 Pershing
SH 541 4/22/2008 Hycroft Res & Dev Inc NMC 991192 Pershing
SH 542 4/22/2008 Hycroft Res & Dev Inc NMC 991193 Pershing
SH 543 4/22/2008 Hycroft Res & Dev Inc NMC 991194 Pershing
SH 544 4/22/2008 Hycroft Res & Dev Inc NMC 991195 Pershing
SH 545 4/22/2008 Hycroft Res & Dev Inc NMC 991196 Pershing
SH 546 4/22/2008 Hycroft Res & Dev Inc NMC 991197 Pershing
SH 548 4/22/2008 Hycroft Res & Dev Inc NMC 991199 Pershing
SH 549 4/22/2008 Hycroft Res & Dev Inc NMC 991200 Pershing
SH 550 4/22/2008 Hycroft Res & Dev Inc NMC 991201 Pershing
SH 551 4/22/2008 Hycroft Res & Dev Inc NMC 991202 Pershing
SH 552 4/22/2008 Hycroft Res & Dev Inc NMC 991203 Pershing
SH 553 4/22/2008 Hycroft Res & Dev Inc NMC 991204 Pershing
SH 554 4/22/2008 Hycroft Res & Dev Inc NMC 991205 Pershing
SH 555 4/22/2008 Hycroft Res & Dev Inc NMC 991206 Pershing
SH 556 4/22/2008 Hycroft Res & Dev Inc NMC 991207 Pershing
SH 557 4/22/2008 Hycroft Res & Dev Inc NMC 991208 Pershing
SH 558 3/13/2010 Hycroft Res & Dev Inc NMC 1022749 Pershing
SH 559 3/13/2010 Hycroft Res & Dev Inc NMC 1022750 Pershing
SH 560 3/13/2010 Hycroft Res & Dev Inc NMC 1022751 Pershing
SH 561 3/13/2010 Hycroft Res & Dev Inc NMC 1022752 Pershing
SH 562 3/13/2010 Hycroft Res & Dev Inc NMC 1022753 Pershing
SH 563 3/13/2010 Hycroft Res & Dev Inc NMC 1022754 Pershing

 

Hycroft Mine Project

Page 343

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 564 3/13/2010 Hycroft Res & Dev Inc NMC 1022755 Pershing
SH 565 3/13/2010 Hycroft Res & Dev Inc NMC 1022756 Pershing
SH 566 3/13/2010 Hycroft Res & Dev Inc NMC 1022757 Pershing
SH 567 3/13/2010 Hycroft Res & Dev Inc NMC 1022758 Pershing
SH 568 3/13/2010 Hycroft Res & Dev Inc NMC 1022759 Pershing
SH 569 3/13/2010 Hycroft Res & Dev Inc NMC 1022760 Pershing
SH 570 3/13/2010 Hycroft Res & Dev Inc NMC 1022761 Pershing
SH 571 3/13/2010 Hycroft Res & Dev Inc NMC 1022762 Pershing
SH 572 3/13/2010 Hycroft Res & Dev Inc NMC 1022763 Pershing
SH 573 3/13/2010 Hycroft Res & Dev Inc NMC 1022764 Pershing
SH 574 3/13/2010 Hycroft Res & Dev Inc NMC 1022765 Pershing
SH 575 3/13/2010 Hycroft Res & Dev Inc NMC 1022766 Pershing
SH 576 3/13/2010 Hycroft Res & Dev Inc NMC 1022767 Pershing
SH 577 3/13/2010 Hycroft Res & Dev Inc NMC 1022768 Pershing
SH 578 3/13/2010 Hycroft Res & Dev Inc NMC 1022769 Pershing
SH 579 3/13/2010 Hycroft Res & Dev Inc NMC 1022770 Pershing
SH 580 3/13/2010 Hycroft Res & Dev Inc NMC 1022771 Pershing
SH 581 3/13/2010 Hycroft Res & Dev Inc NMC 1022772 Pershing
SH 582 3/13/2010 Hycroft Res & Dev Inc NMC 1022773 Pershing
SH 583 3/13/2010 Hycroft Res & Dev Inc NMC 1022774 Pershing
SH 584 3/13/2010 Hycroft Res & Dev Inc NMC 1022775 Pershing
SH 585 3/13/2010 Hycroft Res & Dev Inc NMC 1022776 Pershing
SH 586 3/13/2010 Hycroft Res & Dev Inc NMC 1022777 Pershing
SH 587 3/13/2010 Hycroft Res & Dev Inc NMC 1022778 Pershing
SH 588 3/13/2010 Hycroft Res & Dev Inc NMC 1022779 Pershing
SH 589 3/13/2010 Hycroft Res & Dev Inc NMC 1022780 Pershing
SH 590 3/13/2010 Hycroft Res & Dev Inc NMC 1022781 Pershing
SH 591 3/13/2010 Hycroft Res & Dev Inc NMC 1022782 Pershing
SH 592 3/13/2010 Hycroft Res & Dev Inc NMC 1022783 Pershing
SH 593 3/13/2010 Hycroft Res & Dev Inc NMC 1022784 Pershing
SH 594 3/13/2010 Hycroft Res & Dev Inc NMC 1022785 Pershing
SH 595 3/13/2010 Hycroft Res & Dev Inc NMC 1022786 Pershing
SH 596 3/13/2010 Hycroft Res & Dev Inc NMC 1022787 Pershing
SH 597 3/13/2010 Hycroft Res & Dev Inc NMC 1022788 Pershing
SH 598 3/13/2010 Hycroft Res & Dev Inc NMC 1022789 Pershing
SH 599 3/13/2010 Hycroft Res & Dev Inc NMC 1022790 Pershing
SH 600 3/13/2010 Hycroft Res & Dev Inc NMC 1022791 Pershing
SH 601 3/13/2010 Hycroft Res & Dev Inc NMC 1022792 Pershing
SH 602 3/13/2010 Hycroft Res & Dev Inc NMC 1022793 Pershing
SH 603 3/13/2010 Hycroft Res & Dev Inc NMC 1022794 Pershing
SH 604 3/13/2010 Hycroft Res & Dev Inc NMC 1022795 Pershing
SH 605 3/13/2010 Hycroft Res & Dev Inc NMC 1022796 Pershing
SH 606 3/13/2010 Hycroft Res & Dev Inc NMC 1022797 Pershing
SH 607 3/13/2010 Hycroft Res & Dev Inc NMC 1022798 Pershing
SH 608 3/13/2010 Hycroft Res & Dev Inc NMC 1022799 Pershing
SH 609 3/13/2010 Hycroft Res & Dev Inc NMC 1022800 Pershing
SH 610 3/13/2010 Hycroft Res & Dev Inc NMC 1022801 Pershing
SH 611 3/13/2010 Hycroft Res & Dev Inc NMC 1022802 Pershing

 

Hycroft Mine Project

Page 344

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 612 3/13/2010 Hycroft Res & Dev Inc NMC 1022803 Pershing
SH 613 3/13/2010 Hycroft Res & Dev Inc NMC 1022804 Pershing
SH 614 3/13/2010 Hycroft Res & Dev Inc NMC 1022805 Pershing
SH 615 3/13/2010 Hycroft Res & Dev Inc NMC 1022806 Pershing
SH 616 3/13/2010 Hycroft Res & Dev Inc NMC 1022807 Pershing
SH 617 3/13/2010 Hycroft Res & Dev Inc NMC 1022808 Pershing
SH 618 3/13/2010 Hycroft Res & Dev Inc NMC 1022809 Pershing
SH 619 3/13/2010 Hycroft Res & Dev Inc NMC 1022810 Pershing
SH 620 3/13/2010 Hycroft Res & Dev Inc NMC 1022811 Pershing
SH 621 3/13/2010 Hycroft Res & Dev Inc NMC 1022812 Pershing
SH 622 3/13/2010 Hycroft Res & Dev Inc NMC 1022813 Pershing
SH 623 3/13/2010 Hycroft Res & Dev Inc NMC 1022814 Pershing
SH 624 3/13/2010 Hycroft Res & Dev Inc NMC 1022815 Pershing
SH 625 3/13/2010 Hycroft Res & Dev Inc NMC 1022816 Pershing
SH 626 3/13/2010 Hycroft Res & Dev Inc NMC 1022817 Pershing
SH 627 3/13/2010 Hycroft Res & Dev Inc NMC 1022818 Pershing
SH 628 3/13/2010 Hycroft Res & Dev Inc NMC 1022819 Pershing
SH 629 3/13/2010 Hycroft Res & Dev Inc NMC 1022820 Pershing
SH 630 3/13/2010 Hycroft Res & Dev Inc NMC 1022821 Pershing
SH 631 3/13/2010 Hycroft Res & Dev Inc NMC 1022822 Pershing
SH 632 3/13/2010 Hycroft Res & Dev Inc NMC 1022823 Pershing
SH 633 3/13/2010 Hycroft Res & Dev Inc NMC 1022824 Pershing
SH 232 4/23/2008 Hycroft Res & Dev Inc NMC 990885 Pershing
SH 233 4/23/2008 Hycroft Res & Dev Inc NMC 990886 Pershing
SH 234 4/23/2008 Hycroft Res & Dev Inc NMC 990887 Pershing
SH 242 4/23/2008 Hycroft Res & Dev Inc NMC 990898 Pershing
SH 243 4/23/2008 Hycroft Res & Dev Inc NMC 990899 Pershing
SH 246 4/23/2008 Hycroft Res & Dev Inc NMC 990897 Pershing
SH 248 4/23/2008 Hycroft Res & Dev Inc NMC 991209 Pershing
SH 264 4/25/2008 Hycroft Res & Dev Inc NMC 990916 Pershing
SH 267 4/23/2008 Hycroft Res & Dev Inc NMC 990919 Pershing
SH 268 4/23/2008 Hycroft Res & Dev Inc NMC 990920 Pershing
SH 275 4/23/2008 Hycroft Res & Dev Inc NMC 990927 Pershing
SH 283 4/22/2008 Hycroft Res & Dev Inc NMC 990935 Pershing
SH 287 4/22/2008 Hycroft Res & Dev Inc NMC 990939 Pershing
SH 289 4/22/2008 Hycroft Res & Dev Inc NMC 990941 Pershing
SH 295 4/22/2008 Hycroft Res & Dev Inc NMC 990947 Pershing
SH 299 4/22/2008 Hycroft Res & Dev Inc NMC 990949 Pershing
SH 302 4/22/2008 Hycroft Res & Dev Inc NMC 990952 Pershing
SH 306 4/22/2008 Hycroft Res & Dev Inc NMC 990958 Pershing
SH 322 4/22/2008 Hycroft Res & Dev Inc NMC 990974 Pershing
SH 344 4/22/2008 Hycroft Res & Dev Inc NMC 990996 Pershing
SH 369 4/21/2008 Hycroft Res & Dev Inc NMC 991021 Pershing
SH 386 4/21/2008 Hycroft Res & Dev Inc NMC 991038 Pershing
SH 418 4/21/2008 Hycroft Res & Dev Inc NMC 991070 Pershing
SH 457 4/22/2008 Hycroft Res & Dev Inc NMC 991108 Pershing
SH 458 4/22/2008 Hycroft Res & Dev Inc NMC 991109 Pershing
SH 459 4/22/2008 Hycroft Res & Dev Inc NMC 991110 Pershing

 

Hycroft Mine Project

Page 345

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
SH 460 4/22/2008 Hycroft Res & Dev Inc NMC 991111 Pershing
SH 464 4/22/2008 Hycroft Res & Dev Inc NMC991115 Pershing
SH 465 4/22/2008 Hycroft Res & Dev Inc NMC 991116 Pershing
SH 466 4/22/2008 Hycroft Res & Dev Inc NMC991117 Pershing
SH 467 4/22/2008 Hycroft Res & Dev Inc NMC 991118 Pershing
SH 472 4/22/2008 Hycroft Res & Dev Inc NMC 991123 Pershing
SH 475 4/22/2008 Hycroft Res & Dev Inc NMC 991126 Pershing
SH 476 4/22/2008 Hycroft Res & Dev Inc NMC 991127 Pershing
SH 479 4/22/2008 Hycroft Res & Dev Inc NMC 991130 Pershing
SH 484 4/22/2008 Hycroft Res & Dev Inc NMC 991135 Pershing
SH 487 4/22/2008 Hycroft Res & Dev Inc NMC 991138 Pershing
SH 494 4/22/2008 Hycroft Res & Dev Inc NMC 991145 Pershing
SH 495 4/22/2008 Hycroft Res & Dev Inc NMC 991146 Pershing
SH 496 4/22/2008 Hycroft Res & Dev Inc NMC 991147 Pershing
SH 506 4/22/2008 Hycroft Res & Dev Inc NMC 991157 Pershing
SH 518 4/22/2008 Hycroft Res & Dev Inc NMC 991169 Pershing
SH 522 4/22/2008 Hycroft Res & Dev Inc NMC 991173 Pershing
SH 525 4/22/2008 Hycroft Res & Dev Inc NMC 991176 Pershing
SH 527 4/22/2008 Hycroft Res & Dev Inc NMC 991178 Pershing
SH 547 4/22/2008 Hycroft Res & Dev Inc NMC 991198 Pershing
SH 634 3/13/2010 Hycroft Res & Dev Inc NMC 1022825 Pershing
SH 635 3/13/2010 Hycroft Res & Dev Inc NMC 1022826 Pershing
SH 636 3/13/2010 Hycroft Res & Dev Inc NMC 1022827 Pershing
SH 637 3/13/2010 Hycroft Res & Dev Inc NMC 1022828 Pershing
SH 638 3/13/2010 Hycroft Res & Dev Inc NMC 1022829 Pershing
SH 639 3/13/2010 Hycroft Res & Dev Inc NMC 1022830 Pershing
SH 640 3/13/2010 Hycroft Res & Dev Inc NMC 1022831 Pershing
SH 641 3/13/2010 Hycroft Res & Dev Inc NMC 1022832 Pershing
SH 642 3/13/2010 Hycroft Res & Dev Inc NMC 1022833 Pershing
SH 643 3/13/2010 Hycroft Res & Dev Inc NMC 1022834 Pershing
SH 644 3/13/2010 Hycroft Res & Dev Inc NMC 1022835 Pershing
SH 645 3/13/2010 Hycroft Res & Dev Inc NMC 1022836 Pershing
SH 646 3/13/2010 Hycroft Res & Dev Inc NMC 1022837 Pershing
SH 647 3/13/2010 Hycroft Res & Dev Inc NMC 1022838 Pershing
SH 648 3/13/2010 Hycroft Res & Dev Inc NMC 1022839 Pershing
SH 649 3/13/2010 Hycroft Res & Dev Inc NMC 1022840 Pershing
SH 650 3/13/2010 Hycroft Res & Dev Inc NMC 1022841 Pershing
SH 651 3/13/2010 Hycroft Res & Dev Inc NMC 1022842 Pershing
WCD 1 3/22/2006 Hycroft Res & Dev Inc NMC 928826 Pershing
WCD 17 4/21/2006 Hycroft Res & Dev Inc NMC 928836 Pershing
WCD 18 4/21/2006 Hycroft Res & Dev Inc NMC 928837 Pershing
WCD 19 4/21/2006 Hycroft Res & Dev Inc NMC 928838 Pershing
WCD 2 3/22/2006 Hycroft Res & Dev Inc NMC 928827 Pershing
WCD 20 4/21/2006 Hycroft Res & Dev Inc NMC 928839 Pershing
WCD 21 4/21/2006 Hycroft Res & Dev Inc NMC 928840 Pershing
WCD 22 4/21/2006 Hycroft Res & Dev Inc NMC 928841 Pershing
WCD 23 4/21/2006 Hycroft Res & Dev Inc NMC 928842 Pershing
WCD 24 4/21/2006 Hycroft Res & Dev Inc NMC 928843 Pershing

 

Hycroft Mine Project

Page 346

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
WCD 25 4/21/2006 Hycroft Res & Dev Inc NMC 928844 Pershing
WCD 26 4/21/2006 Hycroft Res & Dev Inc NMC 928845 Pershing
WCD 3 3/22/2006 Hycroft Res & Dev Inc NMC 928828 Pershing
WCD 4 4/22/2006 Hycroft Res & Dev Inc NMC 928829 Pershing
WCX 10 9/8/2006 Hycroft Res & Dev Inc NMC 941262 Pershing
WCX 5 9/8/2006 Hycroft Res & Dev Inc NMC 941257 Pershing
WCX 6 9/8/2006 Hycroft Res & Dev Inc NMC 941258 Pershing
WCX 7 9/8/2006 Hycroft Res & Dev Inc NMC 941259 Pershing
WCX 8 9/8/2006 Hycroft Res & Dev Inc NMC 941260 Pershing
WCX 9 9/8/2006 Hycroft Res & Dev Inc NMC 941261 Pershing
WCX 34 9/8/2006 Hycroft Res & Dev Inc NMC 941263 Pershing
WCX 35 9/8/2006 Hycroft Res & Dev Inc NMC 941264 Pershing
WCX 36 9/8/2006 Hycroft Res & Dev Inc NMC 941265 Pershing
WCX 37 9/8/2006 Hycroft Res & Dev Inc NMC 941266 Pershing
WCX 38 9/8/2006 Hycroft Res & Dev Inc NMC 941267 Pershing
WCX 39 9/8/2006 Hycroft Res & Dev Inc NMC 941268 Pershing
WCX 40 9/8/2006 Hycroft Res & Dev Inc NMC 941269 Pershing
WCX 41 9/8/2006 Hycroft Res & Dev Inc NMC 941270 Pershing
WCX 42 9/8/2006 Hycroft Res & Dev Inc NMC 941271 Pershing
WCX 43 9/8/2006 Hycroft Res & Dev Inc NMC 941272 Pershing
WCX 44 9/8/2006 Hycroft Res & Dev Inc NMC 941273 Pershing
WCX 45 9/8/2006 Hycroft Res & Dev Inc NMC 941274 Pershing
WCX 46 9/8/2006 Hycroft Res & Dev Inc NMC 941275 Pershing
WCX 47 9/8/2006 Hycroft Res & Dev Inc NMC 941276 Pershing
WCX 48 9/8/2006 Hycroft Res & Dev Inc NMC 941277 Pershing
WCX 49 9/8/2006 Hycroft Res & Dev Inc NMC 941278 Pershing
WCX 50 9/8/2006 Hycroft Res & Dev Inc NMC 941279 Pershing
WCX 51 9/8/2006 Hycroft Res & Dev Inc NMC 941280 Pershing
WCX 52 9/8/2006 Hycroft Res & Dev Inc NMC 941281 Pershing
WCX 53 9/8/2006 Hycroft Res & Dev Inc NMC 941282 Pershing
WCX 54 9/8/2006 Hycroft Res & Dev Inc NMC 941283 Pershing
WCX 55 9/8/2006 Hycroft Res & Dev Inc NMC 941284 Pershing
WCX 56 9/8/2006 Hycroft Res & Dev Inc NMC 941285 Pershing
WCX 57 9/8/2006 Hycroft Res & Dev Inc NMC 941286 Pershing
WCX 58 9/8/2006 Hycroft Res & Dev Inc NMC 941287 Pershing
WRC 10 3/13/1995 Hycroft Res & Dev Inc NMC 714261 Pershing
WRC 11 3/13/1995 Hycroft Res & Dev Inc NMC 714262 Pershing
WRC 12 3/13/1995 Hycroft Res & Dev Inc NMC 714263 Pershing
WRC 13 3/13/1995 Hycroft Res & Dev Inc NMC 714264 Pershing
WRC 14 3/13/1995 Hycroft Res & Dev Inc NMC 714265 Pershing
WRC 15 3/13/1995 Hycroft Res & Dev Inc NMC 714266 Pershing
WRC 16 3/13/1995 Hycroft Res & Dev Inc NMC 714267 Pershing
WRC 17 3/13/1995 Hycroft Res & Dev Inc NMC 714268 Pershing
WRC 19 3/13/1995 Hycroft Res & Dev Inc NMC 714270 Pershing
WRC 1 3/13/1995 Hycroft Res & Dev Inc NMC 714252 Pershing
WRC 18 3/13/1995 Hycroft Res & Dev Inc NMC 714269 Pershing
WRC 2 3/13/1995 Hycroft Res & Dev Inc NMC 714253 Pershing
WRC 20 3/13/1995 Hycroft Res & Dev Inc NMC 714271 Pershing

 

Hycroft Mine Project

Page 347

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
WRC 21 3/13/1995 Hycroft Res & Dev Inc NMC 714272 Pershing
WRC 22 3/13/1995 Hycroft Res & Dev Inc NMC 714273 Pershing
WRC 23 3/13/1995 Hycroft Res & Dev Inc NMC 714274 Pershing
WRC 24 3/13/1995 Hycroft Res & Dev Inc NMC 714275 Pershing
WRC 25 3/13/1995 Hycroft Res & Dev Inc NMC 714276 Pershing
WRC 26 3/13/1995 Hycroft Res & Dev Inc NMC 714277 Pershing
WRC 27 3/13/1995 Hycroft Res & Dev Inc NMC 714278 Pershing
WRC 28 3/13/1995 Hycroft Res & Dev Inc NMC 714279 Pershing
WRC 29 3/13/1995 Hycroft Res & Dev Inc NMC 714280 Pershing
WRC 3 3/13/1995 Hycroft Res & Dev Inc NMC 714254 Pershing
WRC 30 3/13/1995 Hycroft Res & Dev Inc NMC 714281 Pershing
WRC 31 3/13/1995 Hycroft Res & Dev Inc NMC 714282 Pershing
WRC 32 3/14/1995 Hycroft Res & Dev Inc NMC 714283 Pershing
WRC 33 3/14/1995 Hycroft Res & Dev Inc NMC 714284 Pershing
WRC 34 3/14/1995 Hycroft Res & Dev Inc NMC 714285 Pershing
WRC 35 3/14/1995 Hycroft Res & Dev Inc NMC 714286 Pershing
WRC 36 3/14/1995 Hycroft Res & Dev Inc NMC 714287 Pershing
WRC 37 3/14/1995 Hycroft Res & Dev Inc NMC 714288 Pershing
WRC 38 3/14/1995 Hycroft Res & Dev Inc NMC 714289 Pershing
WRC 39 3/14/1995 Hycroft Res & Dev Inc NMC 714290 Pershing
WRC 4 3/13/1995 Hycroft Res & Dev Inc NMC 714255 Pershing
WRC 40 3/14/1995 Hycroft Res & Dev Inc NMC 714291 Pershing
WRC 41 3/14/1995 Hycroft Res & Dev Inc NMC 714292 Pershing
WRC 42 3/14/1995 Hycroft Res & Dev Inc NMC 714293 Pershing
WRC 43 3/14/1995 Hycroft Res & Dev Inc NMC 714294 Pershing
WRC 44 3/14/1995 Hycroft Res & Dev Inc NMC 714295 Pershing
WRC 45 3/14/1995 Hycroft Res & Dev Inc NMC 714296 Pershing
WRC 46 3/14/1995 Hycroft Res & Dev Inc NMC 714297 Pershing
WRC 47 3/14/1995 Hycroft Res & Dev Inc NMC 714298 Pershing
WRC 48 3/14/1995 Hycroft Res & Dev Inc NMC 714299 Pershing
WRC 49 3/14/1995 Hycroft Res & Dev Inc NMC 714300 Pershing
WRC 5 3/13/1995 Hycroft Res & Dev Inc NMC 714256 Pershing
WRC 50 3/14/1995 Hycroft Res & Dev Inc NMC 714301 Pershing
WRC 51 3/14/1995 Hycroft Res & Dev Inc NMC 714302 Pershing
WRC 52 3/14/1995 Hycroft Res & Dev Inc NMC 714303 Pershing
WRC 53 3/14/1995 Hycroft Res & Dev Inc NMC 714304 Pershing
WRC 54 3/14/1995 Hycroft Res & Dev Inc NMC 714305 Pershing
WRC 55 3/14/1995 Hycroft Res & Dev Inc NMC 714306 Pershing
WRC 56 3/14/1995 Hycroft Res & Dev Inc NMC 714307 Pershing
WRC 57 3/14/1995 Hycroft Res & Dev Inc NMC 714308 Pershing
WRC 58 3/14/1995 Hycroft Res & Dev Inc NMC 714309 Pershing
WRC 6 3/13/1995 Hycroft Res & Dev Inc NMC 714257 Pershing
WRC 60 3/14/1995 Hycroft Res & Dev Inc NMC 714311 Pershing
WRC 7 3/13/1995 Hycroft Res & Dev Inc NMC 714258 Pershing
WRC 8 3/13/1995 Hycroft Res & Dev Inc NMC 714259 Pershing
WRC 82 3/14/1995 Hycroft Res & Dev Inc NMC 714313 Pershing
WRC 84 3/14/1995 Hycroft Res & Dev Inc NMC 714315 Pershing
WRC 87 3/14/1995 Hycroft Res & Dev Inc NMC 714317 Pershing

 

Hycroft Mine Project

Page 348

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
WRC 88 3/14/1995 Hycroft Res & Dev Inc NMC 714318 Pershing
WRC 89 3/14/1995 Hycroft Res & Dev Inc NMC 714319 Pershing
WRC 9 3/13/1995 Hycroft Res & Dev Inc NMC 714260 Pershing
WRC 90 3/14/1995 Hycroft Res & Dev Inc NMC 714320 Pershing
WRC 91 3/14/1995 Hycroft Res & Dev Inc NMC 714321 Pershing
CKC #12 8/14/1987 Crofoot Daniel M NMC444109 Pershing/Humboldt
FG 226 9/5/2006 Hycroft Res & Dev Inc NMC 939259 Pershing/Humboldt
FG 275 9/1/2006 Hycroft Res & Dev Inc NMC 939296 Pershing/Humboldt
FG 324 9/1/2006 Hycroft Res & Dev Inc NMC 939337 Pershing/Humboldt
FG 377 9/1/2006 Hycroft Res & Dev Inc NMC 939382 Pershing/Humboldt
FG 433 9/1/2006 Hycroft Res & Dev Inc NMC 939438 Pershing/Humboldt
NC 132 8/14/2010 Hycroft Res & Dev Inc NMC1027970 Pershing/Humboldt
NC 17 8/14/2010 Hycroft Res & Dev Inc NMC1027855 Pershing/Humboldt
NC 170 8/14/2010 Hycroft Res & Dev Inc NMC1028008 Pershing/Humboldt
NC 205 8/14/2010 Hycroft Res & Dev Inc NMC1028043 Pershing/Humboldt
NC 240 8/14/2010 Hycroft Res & Dev Inc NMC1028078 Pershing/Humboldt
NC 274 8/14/2010 Hycroft Res & Dev Inc NMC1028112 Pershing/Humboldt
NC 306 8/14/2010 Hycroft Res & Dev Inc NMC1028144 Pershing/Humboldt
NC 50 8/14/2010 Hycroft Res & Dev Inc NMC1027888 Pershing/Humboldt
NC 91 8/14/2010 Hycroft Res & Dev Inc NMC1027929 Pershing/Humboldt
NFRA 12 11/7/2007 Victory Exploration Inc. NMC 977844 Pershing/Humboldt
NFRA 13 11/7/2007 Victory Exploration Inc. NMC 977845 Pershing/Humboldt
NFRA 14 11/7/2007 Victory Exploration Inc. NMC 977846 Pershing/Humboldt
NFRA 15 11/7/2007 Victory Exploration Inc. NMC 977847 Pershing/Humboldt
NFRA 23 11/7/2007 Victory Exploration Inc. NMC 977855 Pershing/Humboldt
NFRA 24 11/7/2007 Victory Exploration Inc. NMC 977856 Pershing/Humboldt
NFRA 4 11/7/2007 Victory Exploration Inc. NMC 977836 Pershing/Humboldt
NFRA 5 11/7/2007 Victory Exploration Inc. NMC 977837 Pershing/Humboldt
RFG #101 3/11/1989 Crofoot Daniel M NMC 546065 Pershing/Humboldt
RFG #103 3/11/1989 Crofoot Daniel M NMC 546066 Pershing/Humboldt
RFG #127 1/9/1980 Lewis Frank W NMC 141686 Pershing/Humboldt
RFG #129 1/9/1980 Lewis Frank W NMC 141687 Pershing/Humboldt
RFG #131 1/9/1980 Lewis Frank W NMC 141688 Pershing/Humboldt
RFG #132 1/9/1980 Lewis Frank W NMC 141689 Pershing/Humboldt
RFG #133 1/9/1980 Lewis Frank W NMC 141690 Pershing/Humboldt
RFG #134 1/9/1980 Lewis Frank W NMC 141691 Pershing/Humboldt
RFG #200A 12/28/1979 Lewis Frank W NMC 141725 Pershing/Humboldt
RFG #228 1/25/1980 Lewis Frank W NMC 141753 Pershing/Humboldt
RFG #230 1/25/1980 Lewis Frank W NMC 141757 Pershing/Humboldt
RFG #234 1/26/1980 Lewis Frank W NMC 141764 Pershing/Humboldt
RFG #235 1/26/1980 Lewis Frank W NMC 141766 Pershing/Humboldt
RFG #236 1/26/1980 Lewis Frank W NMC 141768 Pershing/Humboldt
RFG #237 1/30/1980 Lewis Frank W NMC 141770 Pershing/Humboldt
RFG #250 1/11/1980 Lewis Frank W NMC 141776 Pershing/Humboldt
RFG #252 1/11/1980 Lewis Frank W NMC 141778 Pershing/Humboldt
RFG #254 1/11/1980 Lewis Frank W NMC 141780 Pershing/Humboldt
RFG #257 1/11/1980 Hadi NMC 141783 Pershing/Humboldt
RFG #259 1/11/1980 Hadi NMC 141784 Pershing/Humboldt

 

Hycroft Mine Project

Page 349

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026

 

Unpatented Claim

Name

Location

Date

Claimant BLM Serial Number Filing County
RFG #261 1/11/1980 Hadi NMC 141785 Pershing/Humboldt
RFG #263 1/11/1980 Hadi NMC 141786 Pershing/Humboldt
RFG #99 3/11/1989 Crofoot Daniel M NMC 546064 Pershing/Humboldt
RFG 104 5/20/2006 Hycroft Res & Dev Inc NMC 932887 Pershing/Humboldt
RFG 105 5/20/2006 Hycroft Res & Dev Inc NMC 932888 Pershing/Humboldt
RFG 106 5/20/2006 Hycroft Res & Dev Inc NMC 932889 Pershing/Humboldt
RFG 108 5/20/2006 Hycroft Res & Dev Inc NMC 932891 Pershing/Humboldt
RFG 110 5/20/2006 Hycroft Res & Dev Inc NMC 932893 Pershing/Humboldt
RFG 112 5/20/2006 Hycroft Res & Dev Inc NMC 932895 Pershing/Humboldt
RFG 136 5/20/2006 Hycroft Res & Dev Inc NMC 932905 Pershing/Humboldt
RFG 138 5/20/2006 Hycroft Res & Dev Inc NMC 932906 Pershing/Humboldt
RFG 140 5/20/2006 Hycroft Res & Dev Inc NMC 932907 Pershing/Humboldt
RFG 256 5/20/2006 Hycroft Res & Dev Inc NMC 932911 Pershing/Humboldt
SH 348 4/21/2008 Hycroft Res & Dev Inc NMC 991000 Pershing/Humboldt
SH 349 4/21/2008 Hycroft Res & Dev Inc NMC 991001 Pershing/Humboldt
SH 329 4/22/2008 Hycroft Res & Dev Inc NMC 990981 Pershing/Humboldt
SH 330 4/22/2008 Hycroft Res & Dev Inc NMC 990982 Pershing/Humboldt
SH 331 4/22/2008 Hycroft Res & Dev Inc NMC 990983 Pershing/Humboldt
SH 332 4/22/2008 Hycroft Res & Dev Inc NMC 990984 Pershing/Humboldt
SH 333 4/22/2008 Hycroft Res & Dev Inc NMC 990985 Pershing/Humboldt
SH 353 4/21/2008 Hycroft Res & Dev Inc NMC 991005 Pershing/Humboldt
SH 354 4/21/2008 Hycroft Res & Dev Inc NMC 991006 Pershing/Humboldt
SH 355 4/21/2008 Hycroft Res & Dev Inc NMC 991007 Pershing/Humboldt
SH 356 4/21/2008 Hycroft Res & Dev Inc NMC 991008 Pershing/Humboldt
SH 357 4/21/2008 Hycroft Res & Dev Inc NMC 991009 Pershing/Humboldt
SH 371 4/21/2008 Hycroft Res & Dev Inc NMC 991023 Pershing/Humboldt
SH 372 4/21/2008 Hycroft Res & Dev Inc NMC 991024 Pershing/Humboldt
SH 382 4/21/2008 Hycroft Res & Dev Inc NMC 991034 Pershing/Humboldt
SH 383 4/21/2008 Hycroft Res & Dev Inc NMC 991035 Pershing/Humboldt
SH 384 4/21/2008 Hycroft Res & Dev Inc NMC 991036 Pershing/Humboldt
SH 385 4/21/2008 Hycroft Res & Dev Inc NMC 991037 Pershing/Humboldt
SH 407 4/21/2008 Hycroft Res & Dev Inc NMC 991059 Pershing/Humboldt
SH 408 4/21/2008 Hycroft Res & Dev Inc NMC 991060 Pershing/Humboldt
SH 409 4/21/2008 Hycroft Res & Dev Inc NMC 991061 Pershing/Humboldt
SH 410 4/21/2008 Hycroft Res & Dev Inc NMC 991062 Pershing/Humboldt
SH 411 4/21/2008 Hycroft Res & Dev Inc NMC 991063 Pershing/Humboldt
SH 431 4/21/2008 Hycroft Res & Dev Inc NMC 991083 Pershing/Humboldt
SH 432 4/21/2008 Hycroft Res & Dev Inc NMC 991084 Pershing/Humboldt
SH 433 4/21/2008 Hycroft Res & Dev Inc NMC 991085 Pershing/Humboldt
SH 434 4/21/2008 Hycroft Res & Dev Inc NMC 991086 Pershing/Humboldt

 

Hycroft Mine Project

Page 350

S-K 1300 Technical Report Summary and Initial Assessment with Economic Analysis

May 14, 2026